Home / Financial Firm (Unknown - Insurer) / Determination 353041

Determination 353041

Water ingress claim refused for inherent defects; handling of solicitors and loss adjuster and delays

FirmFinancial Firm (Unknown - Insurer)
Decided2014-10-08
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$500
Amount claimed—
SourceAFCA PDF

Summary

The applicant's water ingress claim was refused because the damage was caused by excluded inherent defects, and the FSP's earlier $6,939.42 cash settlement did not bind it for later damage. AFCA awarded $500 for non-financial loss due to the FSP's claim handling.

Expert evidence established excluded inherent defects as the cause, while the FSP's solicitor engagement and loss adjuster appointment caused an unusual degree of inconvenience warranting non-financial loss compensation.

Issues

Subjects and remedies

home or building damagepay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance – Home Building - Service – Delay in claim handling Determination Case No: 353041 Determination Page 1 of 9 Case number : 353041 2 October 2014 1 Overview 1.1 Dispute The Applicant lodged a water damage claim on 31 December 2007, under her home insurance policy with the Financial Services Provider (FSP). The damage was to the downstairs basement accommodation area where the carpet was exceptionally wet, the timber cladding of the walls bowed out and a power point was exposed. Upon investigating the claim, the FSP considered the cause was due to building and drainage defects, predominantly caused by her neighbour who built the property when subdividing the land. Therefore, it declined to rectify these issues but accepted liability for the resultant water damage. The claim became protracted. The FSP ultimately attempted to cash settle the resultant water damage for $6,939.42 , on or around 3 January 2013. The Applicant has since stated there is continued damage and is seeking the FSP to investigate the cause and pursue her neighbour. In particular, she believes her current situation is due to the FSP’s negligence in the manner it has handled the claim, including the fact it initially engaged solicitors to assist her and then withdrew their assistance. 1.2 Issues and key findings Does the FSP have any further liability towards the Applicant’s water ingress claim? The FSP has no further liability because the available evidence establishes the damage was caused by an event excluded by the policy, namely inherent defects as described by exclusion clause 1g of the policy. Therefore, the FSP was not liable for any of the damage, including the resultant damage it accepted. It follows it is also not liable for any additional damage that may have resulted, due to either the defects not being addressed or the resultant damage not being repaired. Did the FSP’s decision to en gage solicitors entitle the Applicant to any remedy? It does not because:  the FSP was not liable to provide this assistance under the policy, and  the Applicant cannot establish any prejudice as a result of the FSP’s decision to engage solicitors and withdraw them. Case No: 353041 Determination Page 2 of 9 Did the FSP’s handling of the claim warrant an award of compensation for non-financial loss under paragraph 9.3(b) of the Terms of Reference? The FSP should pay $500 for non-financial loss because:  the Applicant experienced an unusual degree of inconvenience as a result of the FSP’s decision to engage solicitors and then withdraw same; and  the engagement of the latest loss adjuster contributed to the Applicant’s negative experience. This was due to the FSP’s failure to properly brief him and the loss adjuster coming to different conclusions as to how the defects should be rectified compared to the adjusters and experts previously engaged. 1.3 Determination This Determination is substantively in favour of the FSP. I determine the dispute should be fully and finally resolved in the following manner:  The FSP is not liable to pay any further amount towards the Applicant’s claim.  The FSP is to pay $500 towards the Applicant for non-financial loss pursuant to paragraph 9.3(b) of the Terms of Reference. Case No: 353041 Determination Page 3 of 9 2 Reasons for Determination 2.1 Does the FSP have any further liability towards the Applicant’s water ingress claim? The Applicant must establish an insured event caused the loss It is accepted insurance law that the Applicant has the onus to establish, on the balance of probability that the policy responds to her loss. In a policy that only responds when certain events have occurred (i.e. insured events), the policyholder must generally establish that the insured event was the cause of the loss. Only if the Applicant establishes that the loss arose from an event covered by the terms of the policy, is the FSP required to establish, on the balance of probability that the loss is subject to an exclusion within the policy. Based on the available expert evidence, the damage was caused by factors excluded under the policy (inherent defects) The substantive expert opinions have been provided by the FSP. These experts are an engineer (HCE) and a plumber (SS). In essence, their conclusions were that water was penetrating the damaged area due to a lack of waterproofing of the west boundary wall. This lack of waterproofing was due to a number of factors identified by SS in the report dated 4 June 2008. This report accompanied HCE’s report dated 6 June 2008. The reasoning and conclusions of both reports is logical, plausible and consistent with the evidence available. For instance, water testing was done on various areas whereby water penetration was identified. The tests conducted led to the conclusion of inadequate waterproofing. In addition, the Applicant has not provided any contradictory expert evidence. Although she is seeking further investigation to be undertaken as a result of additional water ingress and developments since the original assessment was concluded, there is no evidence to indicate HCE’s and SS’s conclusions , as to the cause of the water penetration, are incorrect. As a result, I am satisfied that the damage that led to the claim on 31 December 2007, was caused directly or indirectly by inherent defects, faulty design, structural defects or poor workmanship. This falls within the following policy exclusion clause: “ 1. The policy does not cover loss, liability, injury or damage: … g. Inherent defects caused directly or indirectly through inherent defects, faulty design, structural defects or poor workmanship.” Case No: 353041 Determination Page 4 of 9 The FSP’s decision to accept the resultant damage led to the Applicant receiving a benefit beyond that allowed under the policy Despite the cause of the damage being clearly excluded, the FSP elected to accept liability for the resultant damage. It did so on the basis it accepted the Applicant was unaware of the defects. The policy does not specifically provide such an exception. Therefore, the FSP’s decision resulted in the Applicant receiving a benefit beyond that allowed under the terms of the policy, namely a cash payment in the sum of $6,939.42. Further, the Applicant has not provided any evidence to refute that the amount fairly reflected the scope of the damage sustained. On the other hand, given that the FSP had decided, seemingly with legal advice, to accept that aspect of the claim and given the circumstances of this dispute, it would not be appropriate or fair that the FSP seek reimbursement of the settlement amount. Having said that, I do note that there is no suggestion or indication that the FSP intended to seek reimbursement. The point is made, simply for clarity. There is insufficient evidence to establish that any additional damage that may have occurred is covered by the policy The Applicant has not provided any evidence to establish the extent of the new damage or the likely cause for that new damage. If the cause of the additional damage is due to similar reasons that occurred previously, then such damage is excluded under the policy for reasons already explained. Further, the fact the FSP elected to accept the resultant damage from the first incident does not bind the FSP for any additional damage that occurred. There is no principle that would support such a finding, particularly given the absence of the FSP providing any assurance or representation in that regard. Therefore, I do not accept the Applicant has provided sufficient evidence to establish that the FSP has any responsibility to indemnify her for additional water damage that may have occurred since the cash settlement was made. 2.2 Did the FSP’s decision to engage solicitors entitle the Applicant to any remedy under the policy? Even accepting the FSP did engage solicitors to pursue the neighbour, this does not assist the Applicant One of the substantive matters raised by the Applicant was the FSP’s decision to engage solicitors for this claim and then inexplicably withdraw its instructions to those solicitors. In particular, the Applicant believed the engagement of the solicitors was to pursue the neighbour for the rectification of the defects identified. The FSP has refuted this. Case No: 353041 Determination Page 5 of 9 However, even if I was to accept the Applicant’s position on this point, I do not believe it assists her position for the following reasons: The FSP had no liability under the policy to provide this benefit First, the FSP had no liability under the policy to engage solicitors to pursue the neighbour on the Applicant’s behalf. Although the Applicant has referred to a policy additional benefit set out under “Removal of debris, professional fees and extra costs”, these benefits are only payable when they relate directly to the damaged part of the building. It would not extend to the Applicant engaging solicitors to seek recovery for losses excluded by the policy. The FSP could withdraw its solicitors support in circumstances when it was not a benefit under the policy and the Applicant sustained no monetary loss as a result of this decision Second, even if the FSP did decide to engage solicitors to support the Applicant, there is nothing to refute the fact it could withdraw that support in circumstances when it had no liability under the policy to offer such assistance and its withdrawal did not prejudice the Applicant’s rights. In this regard, I note the Applicant believed the solicitors were engaged to handle the conduct of the litigation in or around June 2009. By 24 December 2009, the solicitor who was handling the file had discussed the matter with the Applicant whereby the Applicant first became aware that the solicitor would not be proceeding with the matter. This was confirmed in correspondence from the FSP dated 24 February 2010 (but apparently received by the Applicant on 15 March 2010). Even accepting it was 9 months between the time the Applicant first became aware the solicitors were engaged and the time they were withdrawn, I am not satisfied the Applicant is able to establish any prejudice by the withdrawal of this assistance, beyond the inconvenience such a process would have entailed. For instance, there is no monetary loss she has sustained. Further, she has not been able to identify any right she had against the neighbour which was prejudiced by this delay. Although the Applicant has provided submissions this has occurred, she has not been able to specify how this occurred and on the face of it, I am not satisfied this delay could have had such an effect. The Applicant has also referred to the fact the withdrawal of solicitors was a failure to act in utmost good faith. Even if that was the case, it does not entitle her to the remedy sought due to her inability to establish any loss or prejudice by this failure. Therefore, the Applicant is not entitled to any remedy with respect to her insurance claim as a result of the FSP’s decision to withdraw its solicitors’ assistance. Case No: 353041 Determination Page 6 of 9 2.3 Does the FSP’s handling of the claim warrant compensation for non-financial loss under paragraph 9.3(b) of the Terms of Reference? The Applicant experienced an unusual degree of inconvenience as a result of the FSP’s decision to engage solicitors and then withdraw those solicitors I did not accept the engagement of the solicitors gave rise to any entitlements with respect to the Applicant’s claim. However, I d o accept that the confusion and delays experienced in this regard were such that the Applicant suffered an unusual degree of physical inconvenience, time taken to resolve the situation and/or interference with her peace of mind. Although the FSP states the solicitors were only engaged to advise them as to indemnity and how the policy should respond, the available information lends greater support to the Applicant’s positio n. This is due to the following: First, there is no indication the FSP’s position rega rding liability was in any doubt. The only expert opinions available to the FSP supported its position. As a result, the FSP accepted liability for the resultant damage, but not for the cause. Further, the Applicant did not appear to be disputing this. Instead, the issues that arose were the difficulties the Applicant was experiencing with the neighbour, in rectifying the defects, to enable the resultant damage to be repaired. Second and of most substance, is the fact the FSP’s materials lend greater support to the Applicant’s position. This is evident from the following:  The FSP’s 10 th loss adjuster report dated 18 June 2009 – The adjuster recommended that solicitors be engaged to enforce the neighbour’s compliance. Shortly afterwards, solicitors were engaged.  The FSP ’ s file note dated 19 June 2009, which stated the following: “Approval of appointment of solicitors in this regard – [Law firm name], due to the necessity to have T P repairs done prior to insured;’s rectification works – TP is not complying.”  A claim note dated 3 August 2012, where the file was reviewed by SL. This stated the following of relevance: “… TP did not repair the damage for a long time and we even appointe d Sols [Law firm name] to pursue TP.” Therefore, when considering the whole of the available evidence, I am satisfied the engagement of solicitors was more consistent with the argument that they were to assist the Applicant to pursue the neighbour for the rectification of the identified defects. The engagement of the latest loss adjuster contributed to the Applicant’s negative experience There has been at least one other instance where the FSP’s claims handling has contributed to the Applicant’s negative ex perience. This was the latest appointment of the loss adjuster (BP), where I note the following: Case No: 353041 Determination Page 7 of 9  BP did not appear to be properly briefed as he acknowledged in his report that he was not aware the Applicant had been cash settled for the resultant damage.  B P indicated the rectification was within the Applicant’s control to address. This was contradictory to the advice and information she had been receiving from the FSP prior to this. The Applicant has raised other serious allegations about BP ’ s conduct, particularly when he came to inspect the damage. However, I am not satisfied that these allegations are established in the absence of more evidence in support, such as a witness statement. The substantive delays were not caused by the FSP The Applicant has also stated that all of the delays were due to the FSP’s claims handling. However, I am not satisfied by this. There have been instances when the FSP was awaiting the outcome of the Applicant’s pursuit against the builder. For instance, prior to the solicitors being engaged in June 2009, one and a half years had passed whilst the FSP awaited the outcome of the Applicant’s pursuit. Following the withdrawal of the solicitors, the FSP then sought to cash settle the resultant damage in an effort to resolve this long outstanding matter. It appeared that from this point until a cash settlement was provided, substantive delays were experienced. These were predominantly due to the following:  The Applicant’s inability to obtain building quotes. The re was a substantive period of time that lapsed whilst the FSP awaited provision of this.  The Applicant disputing which experts the FSP ought to engage to review the matter. For instance, she disputed the engagement of one expert (S) as she was concerned they would not fairly assess the claim. Her concern arose after she reviewed their website.  The Applicant being overseas for over 3 months. Therefore, I am not satisfied these delays were caused by the FSP. Further, a fair period of time passed between the cash settlement and the Applicant restarting this claim. Based on the Applicant’s own correspondence, this was 7 months, although according to the FSP’s claim notes, it was closer to 10 months (January 2013 to November 2013). This cannot be attributed to the FSP. Following her restarting the claim, the FSP engaged BP to assess the matter. For reasons already explained, I am satisfied this engagement did contribute to the Applicant’s negative claims experience. An award of $500 is appropriate and fair in all the circumstances Under paragraph 9.3(b)(i) of the Terms of Reference, I am empowered to award compensation up to $3,000 for non-financial loss. However, I note that this Case No: 353041 Determination Page 8 of 9 provision of the Terms of Reference is to be used sparingly as it is meant to encompass extreme situations. In this context and although I accept the Applicant has suffered an unusual degree of inconvenience, time taken to resolve the situation and/or interference with her peace of mind, I consider the following factors mitigate against a substantive amount being awarded:  The substantive part of the delays not being attributed to the FSP.  The Applicant receiving a benefit under the policy she was technically not entitled to by payment of the resultant damage. Given all of the above and exercising my discretion under clause 9.3(b)(i) of the Terms of Reference, I am of the opinion that compensation in the amount of $500 is fair in all of the circumstances. 3 Supporting information 3.1 Expert Evidence Record Key points FSP’s expert ( SS ) Report 6 Feb 2008  Water has entered through the brick wall clad in timber paneling.  Inspection along the foundation line of the walls revealed the foundation line on the eastern side appears dry whilst the foundation line along the north is showing signs of wate r or dampness.  The natural fall of the land in the adjoining allotment is towards the south east.  It is our opinion that water run - off in the adjoining allotment is damming up behind the brick wall/foundations and is being directed towards the decking are a of the insured’s dwelling.  There appears to be an old earthenware drain running to the council pit located in the south west corner of the adjoining allotment. It is possible that if this is an old drain and it has not been sealed, water may have backed up into this drain during storm conditions. FSP’s expert (HCE ) Report 6 Jun 2008  Water ingress is occurring due to the lack of waterproofing of the west boundary wall.  Testing of the west wall showed water ingress occurring at the junction of the new retaining wall, from cracks above the original door and window head, and possibly from within the cavity. This last factor is due to inadequate sealing of the 50mm diameter pipe penetration below the timber decking.  Therefore the flooding of the storage room has resulted from water ingress due to inadequate waterproofing of the west wall. Case No: 353041 Determination Page 9 of 9 FSP’s expert (SS) Report 4 Jun 2008  Identified a number of issues that are contributing to the water entry into the basement area.  First , the brick retaining wall divid ing the Applicant’s property with the adjoining one is not correctly sealed and is permitting water entry.  An attempt to waterproof the wall was done by painting. However there is no effective seal between the red brick retaining wall and the cream brick dividing wall and there is no waterproofing of the cream brick dividing wall in between the end of the retaining wall. Further, “foama fill” and a black expansion joint material has been applied that does not provide a waterproof seal.  Second , cracks are e vident in the cement mortar brick courses where the opening for the glass doors were bricked up. Hose testing of the wall resulted in water penetration.  Third , a 50mm drain located through the timber decking is flowing in the unsealed wall on the eastern s ide and finding its way into the basement. This method of discharge is questionable as water off one property should not be discharging into another.  Fourth , the location of an agricultural drain in a small garden bed is questionable. 3.2 Paragraph 9.3(b)(i) of the Terms of Reference “Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non-financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred;”

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.