Determination 352784
Storm damage repairs not completed, adequacy of cash settlement offers and temporary accommodation
Summary
The applicant's storm-damaged home was not reinstated after more than two years of repair attempts and cash settlement disputes. AFCA ordered $20,600 for floors, $8,305 for paintwork and $4,000 temporary accommodation, plus $1,500 non-financial loss and interest, and refused ceiling insulation and utility costs.
Once the insurer has elected to repair and started the work, it cannot unilaterally cash settle the balance, and any cash offer must be fair and reasonably sufficient to complete the works.
Issues
- Repairs or contractors primary · upheld
“after more than two years, the FSP has not yet returned the property to its pre-loss condition”
- Claim amount dispute secondary · upheld
“the FSP has not satisfactorily shown that its offers for painting works and kitchen repairs were reasonably adequate”
- Claim denial secondary · not upheld
“the FSP is entitled to deny the claim for ceiling insulation as the Applicant did not show storm damage”
- Delay secondary · upheld
“the FSP's actions caused an unusual amount of time to resolve the claim”
Subjects and remedies
home or building damagenatural disasterpay claimpay compensationpay interestpay non financial loss
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - Service - Service Quality
Determination
Case No: 352784 Determination Page 1 of 8
Case number : 352784 22 May 2015
1 Overview
1.1 Dispute
The Applicant’s claim for storm damage to her property was accepted by the
Financial Services Provider (FSP).
The FSP’s authorised repairer (T) failed to return the property to its pre -loss
condition after several repair attempts, so the FSP offered to cash settle the
Applicant $33,772 for the rectification repairs.
The Applicant seeks $37,966 for the remaining works, plus the following
additional items:
water damage to ceiling insulation
gas and electricity bills for temporary accommodation.
1.2 Issues and key findings
Can the FSP cash settle the remaining repair works?
The FSP elected to repair and has in fact carried out repair works to the
Applicant’s property. Therefore, the FSP is not unilaterally entitled to cash settle
the remaining repair works, unless the Applicant agrees with this course of action,
which the Applicant has done in this dispute.
Is the FSP’s offer adequate to complete remaining repairs?
The evidence does not support the FSP’s position that the offer to meet the cost
of the paintwork, is adequate.
Is the Applicant entitled to cover for ceiling insulation?
The Applicant has not shown that the ceiling insulation was storm damaged.
Is the FSP’s $1,400 offer for t emporary accommodation, adequate?
The FSP is to pay the Applicant $4,000, to meet the costs of additional temporary
accommodation.
Is the Applicant entitled to gas and electricity costs?
The Applicant is not entitled to indemnity for gas and electricity costs because:
these are her living expenses, which she would incur whether she lives in her
own home or in temporary accommodation
Case No: 352784 Determination Page 2 of 8
the policy does not cover living expenses.
Should the FSP pay compensation for the way it handled the claim?
The FSP should pay the Applicant compensation for non-financial loss because:
it failed to reinstate her property for more than two years
it has subjected her to significant delays and inconvenience.
1.3 Determination
This Determination is partly in favour of the Applicant.
The FSP is to pay the Applicant within 7 days of receipt of this Determination:
$20,600 for the floor damage
$8,305 for the paintworks
$4,000 for temporary accommodation
$1,500 compensation for non-financial loss
interest on the above amounts (save for the amount of compensation for non-
financial loss), at the statutory rate from 21 February 2014 , (referral to this
Service) until payment has been satisfied.
The Applicant is to provide the FSP with:
a sample of the original benchtop. If it is in fact granite, the FSP must settle
this portion of the claim based on the Applicant’s quote of $13,365 (together
with interest as above).
The FSP must meet all payable losses under the policy within 7 days of
acceptance of this Determination by the Applicant.
Case No: 352784 Determination Page 3 of 8
2 Reasons for Determination
2.1 Can FSP cash settle the remaining repair works?
FOS has previously determined that insurers cannot unilaterally cash settle the
cost to complete repairs to damaged insured property, after the FSP has made an
election to repair the damage. This is particularly the case when the FSP has
actually commenced the repair.
There is no dispute the FSP elected to repair the Applicant’s property and had in
fact carried out the repair, albeit incomplete. In the circumstances, the FSP is now
not entitled to unilaterally cash settle the remaining repair works to reinstate the
property, unless the Applicant agrees with this course of action, which the
Applicant has done in this dispute.
2.2 Is the FSP’s offer adequate to carry out repairs for all damage?
Cash settlement must be sufficient to complete remaining work
Where an insurer offers a cash settlement for the repair of damaged insured
property, FOS has previously determined that the amount offered must be fair and
reasonably sufficient to enable an Applicant to complete the relevant repair.
Accordingly, if the Applicant is now prepared to accept a cash settlement for the
remaining works, the FSP must show that its offer is fair and reasonably sufficient
to complete such works.
Apart from the $20,600 offer for the floor repairs, the FSP has not satisfactorily
shown that its offers for painting works and kitchen repairs were reasonably
adequate to complete the relevant works.
$20,600 offer for floor is fair and reasonable
The Applicant seeks $600 more (ie. $21,200) for the floor repairs because:
her original quote did not include the cost to remove, store and replace her
furniture
the FSP’s delay in settl ing the matter has resulted in increased cost to replace
the floor.
However, the FSP’s $20,600 offer includes work to repair the floor at the rear
section of the home, although the Applicant’s so n concedes it was not damaged
by the claimed event. The son had informed the case manager overseeing this
dispute (during a conversation on 11 March 2015), that this damage resulted from
insufficient door sills and poor surface drainage. The cost to repair the floor at this
section of the home would likely exceed the additional $600 the Applicant seeks.
Accordingly, I do not consider it fair in all the circumstances to revise the FSP’s
$20,600 offer any further.
Case No: 352784 Determination Page 4 of 8
FSP’s paintwork quote does not cover all wor k required
The FSP has not responded to the Applicant’s assertions that its $5,072 offer:
only allowed for one coat of paint when the common practice is to re-sand the
walls and apply two coats of sealer and paint
does not address the oval feature which T never repaired
did not include the living room pillars
does not address the damage paint on the pillar bases which T damaged.
In the absence of evidence to the contrary, I accept the Applicant’s assertions on
these matters.
The Applicant has provided an alternative quote of $8,305, which includes the
repair of these additional matters. As the FSP has failed to reinstate the property
for more than 2 years, I consider it fair in all the circumstances to accept this
quote to bring finality to the matter.
Applicant to prove kitchen benchtop is granite
The Applicant’s rejection of the FSP’s $8,100 offer , to reinstate the kitchen, is
based on her belief her benchtop is made of granite. The FSP’s offer is for Caesar
stone.
I understand remnants of the original benchtop are still available for inspection. I
consider it fair in all the circumstances that the Applicant provides the FSP with a
sample of the original benchtop. If it is in fact granite, the FSP must settle this
portion of the claim based on the Appli cant’s quote of $13,365.
In the event the benchtop is demonstrated to be Caesar stone, the FSP is entitled
to settle this aspect of the claim for $8,100.
2.3 Is Applicant entitled to cover for ceiling insulation?
Insufficient evidence ceiling insulation was damaged by storm
The law requires the Applicant to show that the storm damaged the ceiling
insulation. Save for merely making the suggestion, the Applicant has not provided
sufficient evidence to support her claim.
In the absence of evidence to support thi s aspect of the Applicant’s claim, the
FSP is entitled to deny the claim for ceiling insulation.
2.4 Is FSP’s offer for t emporary accommodation adequate?
There is no dispute the Applicant will need temporary accommodation when the
property’s floor is being rep laced.
The FSP allowed two weeks temporary accommodation at $700 per week. The
Applicant believes the offer is inadequate because:
it unlikely caters for a residence suitable for four adults and a puppy
her repairer estimated repairs could take more than three weeks, depending
on weather conditions.
Case No: 352784 Determination Page 5 of 8
For these reasons, the Applicant believes one month ’s temporary accommodation
at a rate between $1,125 and $2,170 per week is more appropriate.
It is difficult to estimate the length and the total cost of temporary accommodation
required based on the available information. Rental rates fluctuate depending on
availability and season. The Applicant also has a pet, which is likely to reduce the
number of rental properties available to her.
I also understand that given the limited period, the Applicant may experience
difficulty in finding a suitable location. Taking all these matters into account, doing
what is fair in the circumstances and being conscious of the need to bring this
matter to a close, the FSP is to pay the Applicant $4,000 for temporary
accommodation, based on an allowance of $1,000 per week for four weeks.
2.5 Is the Applicant entitled to gas and electricity costs?
Policy does not cover living expenses
The Applicant is not entitled to indemnity for gas and electricity consumption,
whilst in temporary accommodation. Such costs are part of her living expenses,
whether she lives in her home or in temporary accommodation. The policy does
not cover living expenses.
2.6 Should the FSP pay compensation for the way it handled the
claim?
FOS may award compensation for non-financial loss
FOS can award the Applicant compensation (capped at $3,000) for non-financial
loss where the FSP has:
taken an unusual amount of time to resolve her claim
subjected her to unusual physical inconvenience
unusually interfered with her expectation of enjoyment or peace of mind.
FSP failed to reinstate property for more than two years
It is plain that the FSP has not yet, after more than two years, returned the
property to its pre-loss condition, despite having had numerous inspections and
opportunities to complete repair.
The Applicant is significantly inconvenienced by FSP’s failure to reinstate
property
I have no doubt the long drawn affair significantly inconvenienced the Applicant
and interfered with her expectation of enjoyment of her home and peace of mind.
Despite her misgivings, I note that the Applicant remained very patient and
cooperative throughout the whole claim process.
In the circumstances, I consider it is fair in all the circumstances that FOS award a
payment of $1,500, as reasonable compensation for delays and inconvenience
suffered by the Applicant during the claims process .
Case No: 352784 Determination Page 6 of 8
3 Supporting information
3.1 Relevant Policy Provisions
How we settle your building claim
We will choose to settle your claim for loss or damage to your home…in one of the following
ways:
1. Arrange for repairer, builders or suppliers to repair or rebuild your home.
2. Pay you the reas onable cost to repair or rebuild your home.
3.2 The Applicant’s chronology
Date Action
December 2011 S torm occurred and caused extensive damage to the
property .
April 2012 The FSP commissioned its preferred repairer to
commence repairs .
July 2012 The Applicant advised the FSP via email that she
was dissatisfied with quality of repairs by the FSP’s
repairer (T) .
July 2012 T he floor was re - sanded and re - polish ed .
The FSP also agreed to complete other wor ks that
had not been completed .
November 2012 S econd repair attempt was carried out by the FSP’s
repairer, but it failed to return property to a
satisfactory condition.
T he Applicant’s flooring expert (B) inspected the
floor and recommended replacement , believing the
floor is unlikely to withstand a fo urth sanding and
polish.
December 2012 Parties agreed to make a final repair attempt, subject
to the works being supervised by the Asses s or P
and T’s building supervisor .
January 2013 The Applicant informed the FSP the floor and other
damage have not been properly repaired .
The FSP engaged another flooring expert a nd a
representative from Caesarstone to provide reports
for the floor and kitchen benchtop .
The FSP provided the Applicant with another scope
of works for painting .
The FSP advised the Applic ant the bench - top has
been repaired, but the Applicant did not accept the
work was acceptable .
The Applicant received report from flooring company
and again raised concerns about the floor with the
FSP .
April 2013 Applicant received Caesarstone’s report .
Case No: 352784 Determination Page 7 of 8
May 2013 T he parties met again to address the Applicant’s
concerns .
June 2013 T he FSP engaged another floor expert (C) to inspect
and provide report for the floor .
Assessor P informed the Applicant no further work
on the floor was to be carried out as it was waiting
for a second report .
P also stated that the cupping on the floor was a
result of ina dequate surface drainage issue .
A quote was received from T for the kitchen bench -
top, including removal and refitting of plumbing and
bench - top for $5,100 ( including GST) .
The FSP offered a cash payment of $3,072 for the
paintworks, but the Applicant rejected the offer .
August 2013 T he Applicant received the FSP’s final decis ion letter
dated 22 August 2013 .
November 2013 T he Applicant provided the FSP with quotes to
rectify all the damage.
T he FSP informed the Applicant the matter will be
finalized by the end of that week , but the parties
failed to reach agreement .
October 2013 Before the claim could be finalised the flashing which
was affixed to the roof gables was blown off by
heavy winds .
A report was commissioned as the new damage was
treated as a separate claim.
November 2013 Inspection r eport received, stating that the flashing
may possibly h ave been reinstalled.
This part of the roof was an area which consisted of
new tiles, leading to the presumption that the
flashing would have been originally removed to
install the new tiles.
T he Applicant informed the FSP she noticed fresh
water stain ma rks on the ceiling of the bar room; the
same areas damaged in 2011 .
December 2013 T he FSP advised the Applicant that it was
considering making a cash settlement offer for the
floor and therefore will c ommission another floor
report .
Following the floor i nspection , the FSP’s floor expert
confirmed there was still serviceable wood to
withstand another sanding and that destructive tests
would be required to ascertain if the moisture
resulted from an external source or resulted from the
a bsence of an appropri ate sealer .
T he parties engaged in negotiation with the view to
increase the cash settlement offers for the
paintworks and kitchen bench - top .
Case No: 352784 Determination Page 8 of 8
January 2014 The FSP obtain ed two quotes to reinstate the floor .
The FSP ’s new builder (AJ) provided a new scope of
work for reinstatement of the floor and to repaint the
walls .
The FSP made an offer to cash settle the claim .
The Applicant:
- rejected the cash offer for the painting and kitchen
benchtop
- does not agree the new damage to the flashing
and ceiling stain constitute a new claim
- accepted the cash settlement for the floor, but she
also requested paym ent for temporary
accommodation.
The FSP agreed to pay $1,400 for temporary
accommodation .
February 2014 Parties failed to reach an agreement on the final
cash settlement offer.
The Applicant lodged a dispute with FOS.