Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim
amount
Determination
Case No: 350897 Determination Page 1 of 11
Case number : 350897 3 December 2014
1 Overview
1.1 Dispute
The Applicants lodged a claim under their home insurance policy with the
Financial Services Provider (FSP) for fire damage to their home in November
2011. The FSP accepted the Applicants’ claim and provided them with a cash
settlement totalling $335,933 for the building repairs.
However, the Applicants say that the cash settlement amount is not sufficient, as
the scope of works on which it is based does not include all of the required
repairs. The Applicants seek a further sum of $224,067 for the building repairs, as
well as an additional amount of approximately $130,000 as compensation for
costs incurred during the claim process.
1.2 Issues and key findings
Is the cash settlement for the building repairs sufficient?
The cash settlement amount does not include all of the additional damage
identified by the FSP’s building consultant as having arisen due to the fire and the
claim delays. The claim records do not suggest that the Applicants were
responsible for these delays.
What is an appropriate cash settlement amount?
The cash settlement amount should be increased by $35,000 to reflect the
additional damage to the building which has not been provided for to date.
Are the Applicants entitled to any additional amounts?
The Applicants are entitled to reimbursement of fees of $2,850 paid to their
building consultant (GC) as his report assisted in identifying additional damage to
the property. The Applicants are not entitled to any additional amounts.
1.3 Determination
This Determination is partly in favour of the Applicants.
The FSP is to pay the Applicants the amount of $37,850 in full and final
settlement of this dispute.
Case No: 350897 Determination Page 2 of 11
2 Reasons for Determination
2.1 Is the cash settlement for the building repairs sufficient?
Key issue in dispute concerns adequacy of additional variations to scope of
works
Since the FSP accepted liability for the Applicants’ claim on 23 February 2012,
the parties have been engaged in a protracted dispute about the scope of works
for the repair of the fire damage to the building.
The scope of works for the repairs was initially prepared by the FSP’s building
consultant (IC), following which the FSP obtained quotes from three builders to
undertake the works. However, the Applicants disputed the scope of works and
engaged their own building consultant (GC) who inspected the damage to the
property and advised that IC’s scope of works was inaccurate and out of date .
The Applicants then engaged a claims consultant (LM) to represent them. LM
appointed another building consultant (PM), who reviewed IC’s scope of works
and provided a lengthy and detailed analysis that identified a number of alleged
deficiencies. PM’s report prompted a simil arly detailed rebuttal from IC.
At one stage during this process, the FSP appointed the builder who had provided
the lowest quote (EC) to carry out the repairs. However, the repairs did not
proceed when the Applicants rejected the building contract put forward by EC and
sought to propose their own terms.
In early 2013, the Applicants engaged one of the other builders who had quoted
for the repairs (JL) to carry out the demolition works specified in IC’s scope of
works. Both parties were of the view that it would be easier to identify any
additional damage and assess any required variations to the scope of works once
the demolition works had been completed.
After carrying out the demolition works, JL identified additional variations to the
original scope of works with a total cost of $36,320. The FSP has accepted the
variations proposed by JL, less the costs ($500) for obtaining a hazardous
materials report, which the FSP considered was not required given JL had
confirmed that there was no asbestos present. The FSP also engaged IC to
prepare a further report identifying any additional works required.
During the course of the claim, the FSP has cash settled the Applicants for a total
of $335,933 for the cost of the building repairs. This amount is made up of:
the amount of $288,874 quoted by EC in April 2012, based on IC’s original
scope of works;
an amount of $9,787.80, reflecting the costs of ensuring that the works
complied with the requirements of applicable environmental sustainability
regulations (approved by the FSP in October 2012);
an amount of $1,452 for the cost of replacing anti-ponding boards and an
upstairs bathroom mirror (approved by the FSP in October 2012); and
an amount of $35,820, being the costs of the additional variations identified by
JL in May 2013.
Case No: 350897 Determination Page 3 of 11
The FSP says that the cash settlement amount fully discharges its obligations
under the policy. The FSP considers that it has in fact overpaid the Applicants by
$25,000 because the cash settlement amount includes allowances for works
which were not ultimately undertaken. However, the FSP has not sought to
recover this amount.
The Applicants disagree that the cash settlement amount of $335,933 paid to date
is sufficient to repair the property. They say that this amount should be increased
by a further $224,067 (such that the total amount paid would equal the building
sum insured of $560,000).
In particular, the Applicants say that:
based on a report prepared by their building consultant (PM) dated 1 May
2013 , JL’s assessment of the additional variations to the scope of works is
incomplete;
the quotations on which the FSP has based the cash settlement significantly
underestimate the actual cost of the repairs; and
the cash settlement does not take into account the additional works required
as a result of the further deterioration of the property during the course of the
claim.
IC’s further report identifies additional fire damage
After reviewing the additional variations proposed by JL as set out in his letter
dated 16 May 2013, the FSP appointed IC to carry out a further inspection of the
property in order to identify:
any additional works required to the building as a direct result of the fire;
any additional works which had become necessary due to progressive
deterioration of the property as a result of the protracted delay in resolving the
claim; and
any aspects of the above works which were already included within the scope
of works.
IC prepared a report dated 19 June 2013 which set out his conclusions in relation
to each of the above matters.
There are aspects of IC’s report which are not entirely clear, particularly the extent
to which he took into account the additional variations proposed by JL in
identifying any further works required. Accordingly, it is necessary to carefully
consider each of the additional items identified by IC to determine whether or not
they have been accounted for in the cash settlement paid to date.
The Panel has reviewed each of the additional items of damage which IC
identified as having been caused by the fire and comments as follows:
Item Panel comments
Mirror within the level 3
bathroom
This item was not identified in IC’s original scope of
works, but was included as part of the additional
settlement amount approved by the FSP in October
2012 . Accordingly, no additional allowance is
required.
Case No: 350897 Determination Page 4 of 11
Item Panel comments
Four floor joists on level 3 The additional v ariations proposed by JL include the
replacement of three joists on level 2 and two joists
on level 3, at a total cost of $2,070. Accordingly,
allowance should be made for the replacement of two
further floor joists (at a cost of approximately $8 0 0).
Lev el 3 floor linings The replacement of the l evel 3 floor linings was not
included in IC’s original scope of works (which
assumed that the floor linings could be retained and
restored). However, the replacement of the l evel 3
timber flooring has been includ ed in the additional
variations proposed by JL. Accordingly, no further
allowance is required.
Level 2 floor linings IC report specifies that the replacement of the l evel 2
floor linings as an additional item of damage. This
item was not identified in JL’s additional variations
nor was it specifically identified in IC’s original scope
of works (although the scope does refer to the
sanding and polishing of “new timber f loor linings”).
Accordingly, it is unclear whether the cash settlement
takes this item into account.
In these circumstances, the Panel considers that an
additional allowance should be made for the
replacement of the l evel 2 floor linings. Given the
areas o f l evel 2 which had timber flooring and the
e stimated cost of replacing the l evel 3 floor linings,
the Panel considers that an additional allowance of
$8,2 00 is appropriate.
In determining this amount, the Panel has taken into
account that the original sc ope of works included the
sanding and polishing of the floor linings for both
l evels 2 and 3.
FSP should be liable for additional damage arising from claim delays
In his report dated 19 June 2013, IC identified additional damage to the building
which had arisen as a result of the protracted delays in resolving the claim.
The FSP says that it should not be liable for the costs of repairing this damage as
the claim delays were caused by the Applicants . In particular, the FSP says that
the Applicants failed to provide information requested by the FSP for the purposes
of investigating the claim and refused to enter into a contract with the FSP’s
appointed builder (EC) so that repairs could commence.
IC’s report con firms that it was not possible to effectively cover the building to
prevent further damage until after the demolition works had been completed. IC
states that therefore the delay in carrying out the demolition works resulted in
considerable additional water damage as a result of the building remaining
exposed to the elements.
Case No: 350897 Determination Page 5 of 11
The Applicant’s builder (GC) who inspected the property in April 2012 noted that,
by that time, the property had already sustained extensive additional water
damage as a result of not having been protected from the elements.
In these circumstances, the Panel considers that it is reasonable to assume that
the initial delay of approximately five months between the date of the fire and
GC ’ s inspection was sufficient in itself to cause the additional damage identified
by IC in his report.
Having reviewed the claim history, the Panel does not consider that the
Applicants were responsible for the five month delay during this period.
The available information establishes that there was an initial delay of
approximately three months while the FSP investigated the claim, before
accepting liability in late February 2012.
The FSP requested extensive information from the Applicants for the purposes of
its investigations including telephone and financial records and travel details for
the Applicants and their two children, and receipts for repairs to the property.
Accordingly, there was some delay while the Applicants sought this information
from third party service providers, which was most likely exacerbated by the
Christmas/New Year holiday period.
However, the FSP was also unable to complete its investigations until it received
reports from the police and fire brigade in relation to the fire. The claim records
indicate that this information was not received until at least late January 2012 and
the FSP’s investigator did not provide his report until 13 February 2012. The FSP
did not advise the Applicants of the outcome of its investigation until on or around
27 February 2012.
After the FSP accepted liability for the claim, there was a further period of
approximately two months while the FSP obtained a scope of works and three
quotations for the building repairs. There is no information to suggest that the
Applicants were in any way responsible fo r the time taken to complete this
process.
For the reasons outlined above, the Panel considers that the FSP should be
responsible for the cost of repairing any additional damage which occurred during
the five month period between November 2011 and April 2012. Given the views
expressed by the Applicants’ building consultant (GC) in April 2012, it is
reasonable to assume that the bulk of the additional damage to the building had
already occurred during this period.
Cash settlement should be increased to cover damage resulting from delays
The Panel has reviewed each of the items which IC identified as additional
damage resulting from the delays and comments as follows:
Item Panel comments
All the timber wall frameworks
and associated bracing and
wall - tie el ements
The replacement of the timber wall frameworks for
levels 2 and 3 (to the extent not included in IC’s
orig i nal scope of works) were included in the
Case No: 350897 Determination Page 6 of 11
Item Panel comments
additional variations proposed by JL , at a cost of
$23,6 50 .
However, the replacement of the level 1 wall
frameworks were not included in JL’s additional
variations or IC’s original scope of works (which
assumed that the level 1 wall frameworks remained
undamaged).
Accordingly, the Panel considers that an additional
allowance should be made for the replac ement of the
level 1 wall frameworks. Given the estimated cost of
replacing the level 2 and level 3 wall frameworks, the
Panel considers that an additional allowance of
$10,000 is appropriate.
Wall linings, tiles,
waterproofing, fixtures and
fittings in the level 1 laundry
and adjoining bathroom
These items were not included in the original scope
of works as it appears that they were not damaged by
the fire. However, neither were they included in JL’s
additional variations.
Accordingly, the Panel conside rs that an additional
allowance should be made for these items. In the
circumstances, the Panel considers that an additional
allowance of $10,000 is appropriate.
Level 1 doors Most of the doors on level 1 were considered to be
salvageable following the fi re and therefore were not
included in IC’s original scope of works. However,
neither were they included in JL’s additional
variations.
Accordingly, the Panel considers that an additional
allowance should be made for these items. In the
circumstances, the P anel considers that an additional
allowance of $1,000 is appropriate.
The Panel is comfortable that the above analysis takes into account the extent to
which each of the items identified were already allowed for in the cash settlement
paid by the FSP (whi ch the FSP has referred to as a “credit”). Accordingly, no
further adjustment on this basis is required.
Items identified in PM’s report have largely been accounted for
In his report dated 1 May 2013, PM identified 33 separate items which he
described as major variations to the original scope of works prepared by IC .
Having carefully reviewed each of these items, the Panel is comfortable that the
bulk of them have been allowed for in the cash settlement amount paid by the
FSP (or the additional allowances outlined above) or do not justify any additional
allowance being made.
The Panel notes that both IC and JL have provided a detailed and reasonable
explanation of how many of the items identified by PM were adequately
addressed in IC’s original scope of wo rks. Further items (such as the replacement
Case No: 350897 Determination Page 7 of 11
of the timber wall frameworks) were addressed in the additional variations
proposed by JL.
The Panel is satisfied that the information provided by PM In relation to the bulk of
the remaining items is not sufficient to establish the need for any further variations
to the scope of works.
For example, PM has referred to the need for the replacement of all of the existing
brickwork due to the potentially corrosive effects of effluent due to the fire.
However, IC and JL have confirmed that the original scope of works provided for
cleaning of the brickwork, consistent with industry practice. PM has not provided
any further information (such as test results) to support his position that the
brickwork needs to be replaced because it is infused with thiols (organosulfur
compounds).
In the circumstances, the Panel is not satisfied that a specific additional allowance
should be made for any of the items identified in PM’s report.
Available information does not establish quotations provided are inaccurate
The Applicants say that the builders’ quotations relied upon by the FSP for the
purpose of determining the cash settlement amount significantly underestimate
the cost of the repairs. In support of their position, the Applicants have provided a
quotation provided by their building consultant (GC) for $554,533 and a quotation
provided by a second builder (B) for $570,596.
However, the fact that other builders have quoted significantly higher amounts for
the repairs does not of itself establish that the quotations obtained by the FSP
were inadequate.
The FSP obtained quotes from three builders, who each quoted a very similar
amount (with the difference between the highest and lowest quotes being less
than 2% of the total costs). Further, the quotes were obtained on the basis that
the builders would be prepared to undertake the repairs for the quoted amount.
The only reason t his did not occur was because the Applicants and the FSP’s
appointed builder (EC) were unable to agree on the terms of the contract for the
repairs.
In these circumstances, the Panel does not consider that the information provided
by the Applicants is sufficient to establish that the quotations on which the FSP
based the cash settlement amount were inadequate.
2.2 What is an appropriate cash settlement amount?
Policy requires FSP to pay reasonable cost of repairs
Under the terms of the Applicants’ policy , the FSP is required to repair their
house, or to pay them the reasonable cost of the repairs. While the FSP originally
elected to repair the house, it subsequently provided a cash settlement, due to the
Applicants’ dissatisfaction with the terms of the buildin g contract offered.
The Applicants have advised that the property has since been sold. In these
circumstances, the only appropriate remedy is to require the FSP to increase the
Case No: 350897 Determination Page 8 of 11
cash settlement amount to reflect the additional items identified above which have
not been included in the cash settlement paid to date. The total additional
allowance for these items is $30,000.
In the circumstances, the Panel considers that, it is appropriate to allow an
additional amount of $5,000 (approximately 15%) as a buffer, in the event that
any of the amounts estimated by the Panel are insufficient and/or to cover any
other minor items which have been omitted from the original scope of works or
JL’s additional variations.
The Panel is satisfied that the resulting increase of $35,000 to the settlement
amount of $335,933 is fair in all the circumstances. In arriving at this amount, the
Panel has taken into account the delays experienced during the course of the
claim. Accordingly, the FSP is not required to pay interest on this amount.
2.3 Are the Applicants entitled to any additional amounts?
Applicants seek reimbursement of significant additional costs
The Applicants seek reimbursement of various costs incurred during the claim
process. Although the Applicants’ dispute form re fers to a total of $126,840 in
costs, it appears the correct figure is $129,683.97 (being the total of the individual
items listed below).
Item Amount
Demolition costs charged by JL $ 26,000
Variation costs charged by JL $ 22,847
GC ’s fees (inspection and quotation) $ 2,850
LM ’s fees (3 invoices) $ 19,192.80
PM ’s fees $ 6,114.17
Rent - November 2012 to July 2013 $ 33,240
Rent – Further 9 months $ 19,240
Pool cleaner (maintenance) $ 200
TOTAL $ 129,683.97
Cash settlement amount includes demolition and variation costs
The demolition costs of $26,000 and the variation costs of $22,847 which the
Applicants have referred to are not consistent with the documentary information
provided.
The Applicants have provided a copy of an agreement with JL dated 12 March
2013 which provides for the demolition works to be undertaken at a cost of
$22,847 (which is the amount the Applicants have referred to as a variation). It is
not clear where the amount of $26,000 has been derived from.
Case No: 350897 Determination Page 9 of 11
In any event, the Panel is satisfied that the cash settlement amount paid by the
FSP included the costs of undertaking the demolitions works. The cash settlement
amount was based on EC’s quotation which had been prepared based on ICs
original scope of works, which included the demolition works later carried out by
JL.
As outlined above, the cash settlement amount paid to date included an amount
of $35,820 in respect of the additional variations proposed by JL and approved by
the FSP in May 2013.
Accordingly, the Applicants are not entitled to any further payment for demolition
and variation costs.
Policy requires FSP’s approval before professional fees are incurred
The Applicants’ policy entitles them to reimbursement of reasonable fees paid to
architects, engineers and surveyors, where necessary to rebuild their home
following an insured event.
However, it is a condition of the policy that the FSP agree to any such fees before
they are incurred.
The Applicants did not obtain the FSP’s consent prior to engaging G C, LM or PM.
Further, the fees were paid for the purpose of disputing the FSP’s settlement of
the Applicants’ claim, rather than for the purpose of rebuilding the property.
In these circumstances, the FSP is not obliged under the terms of the policy to
reimburse the Applicants for the fees incurred.
Applicants are entitled to partial reimbursement of fees only
Under paragraph 9.4 of the FOS Terms of Reference, FOS may require a
financial services provider to contribute to legal or other professional costs
incurred by an applicant in the course of their dispute. A financial services
provider will generally not be required to contribute more than $3,000 unless
exceptional circumstances apply.
In the present circumstances, the Panel is satisfied that it was reasonable for the
Applicants to obtain a report from their building consultant (GC) in April 2012 for
the purpose of disputing the initial cash settlement offered by the FSP. GC
identified that significant further damage had occurred as a result of the property
remaining exposed to the elements. In circumstances where the Panel has found
that the FSP is liable for this damage, it is appropriate that the FSP be required to
reimburse the Applicants for GC’s fees (totalling $ 2,850).
However, the Panel is not satisfied that it was necessary or appropriate for the
Applicants to engage a claims manager (LM) to handle their claim. The nature of
the FSP’s internal dispute resolution (IDR) process (and the FOS process) is such
that it is generally unnecessary for app licants’ claims to be professionally
managed. While the Applicants themselves were unable to speak English, they
had the assistance of their son and daughter who represented them during the
claim process.
Case No: 350897 Determination Page 10 of 11
In these circumstances, the Applicants are not ent itled to reimbursement of LM’s
expenses.
The Panel considers that PM’s involvement was of little to no value in progressing
the Applicants’ claim and appears in some respects to have escalated the current
dispute.
The extensive report prepared by PM in August 2012 outlined a large number of
issues which had already been dealt with in IC’s scope of works. PM also
identified a number of other matters which were already governed by applicable
statutory requirements and therefore did not need to be specifically addressed in
IC’s scope of works, or which were unnecessary in the context of repairs to a
residential property.
In these circumstances, the Applicants are not entitled to reimbursement of PM’s
expenses.
Applicants are not entitled to compensation for rental costs
The rental costs claimed by the Applicants are in addition to the 12 months ’ worth
of temporary accommodation benefits paid by the FSP, which is the maximum
benefit available under the policy. This period expired in November 2012.
As outlined above, the Panel considers that the FSP was responsible for the five
month delay in progressing the Applicants’ claim between November 2011 and
April 2012. However, the Panel is not satisfied that the FSP is responsible for any
further delays following this period (during which the additional rental costs were
incurred).
These further delays occurred due to the Applicants’ reluctance to sign the
building contract which would have allowed the FSP’s builder (EC) to commence
the works in or around May 2012. The contract estimated that the works would
take approximately 13 to 15 weeks. Accordingly, they should have been
completed by November 2012 (even allowing time for any additional variations
which were identified during the course of the works).
The Panel accepts that the Applicants’ reluctance to sign the building contract
proposed by the FSP’s builder (EC) was partly driven by concerns about the
adequacy of IC’s scope of works (which the Panel has found were partly justified).
However, the Panel co nsiders that the Applicants’ behaviour were also based on
their concern that the FSP would not accept liability for any further variation works
which were identified as required during the repair process.
The Panel is not satisfied that the approach taken by the Applicants was
reasonable, in circumstances where the FSP had explained that, under applicable
legislation, the works could not commence until they signed the building contract.
Further, the FSP had recognised (based on IC’s scope of works) that fur ther
works might be required in the event that the preliminary demolition works
revealed further fire damage to the building.
The Applicants also had the comfort of the lifetime guarantee of the works
provided by the FSP, in accordance with the terms of th e Applicants’ policy.
Case No: 350897 Determination Page 11 of 11
In addition, the Panel notes that the alternative contractual terms offered by the
Applicants were clearly inappropriate in the context of the works required. The
terms of the Applicants’ contract required, among other things, the appointment of
a superintendent and project manager (at the builder’s cost)
In the circumstances, the Panel considers that the FSP is not responsible for the
further delays which occurred after April 2012 . Accordingly, the FSP is not
required to compensate the Applicants for additional rental costs incurred during
this period.
Applicants are not entitled to compensation for pool maintenance costs
The costs of maintaining the swimming pool at the property is a cost associated
with ordinary home maintenance, rather than a cost arising from the fire or the
FSP’s management of the Applicants’ claim. Accordingly, the Applicants are not
entitled to compensation for this amount.
3 Supporting information
3.1 FOS approach to this Determination
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it been referred directly to a Panel for Determination, in line
with the Operational Guidelines to the FOS Terms of Reference . The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.