Home / Financial Firm (Unknown - Insurer) / Determination 350658

Determination 350658

Explosion damage claim settlement, asbestos remediation delays and claim management

FirmFinancial Firm (Unknown - Insurer)
Decided2015-01-08
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$89,888
Non-financial loss$3,000
Amount claimed$412,000
SourceAFCA PDF

Summary

The Applicant's home and contents were damaged in an explosion, and the FSP's contractors failed to fully remediate asbestos contamination. AFCA ordered the FSP to complete or cash settle the remaining works and contents, pay temporary accommodation, $3,000 non-financial loss and up to $3,000 legal costs.

The FSP is obliged to complete or cash settle repairs once it elected to restore the property, and it is liable for the delay and distress caused by its contractors' inadequate remediation.

Issues

Subjects and remedies

health or medicalpay claimpay compensationpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building – Home Contents - Service - Service Quality Determination Case No: 350658 Determination Page 1 of 7 Case number : 350658 12 December 2014 1 Overview 1.1 Dispute The Applicant lodged a claim under her home insurance policy with the Financial Services Provider (FSP) for damage to her home and contents caused by an explosion at her neighbour’s property on 14 June 2013. The FSP accepted the Applicant’s claim and made arrangements for repairs to her property, which have been partially completed. However, a dispute has arisen during the course of the repairs. The Applicant wants her claim to be settled by payment of the total sum insured for the building and contents. She says that the asbestos decontamination works at the property have not been properly carried out by the FSP’s contractors. She also seeks compensation for financial and non-financial losses suffered due to the manner in which the FSP has handled her claim. 1.2 Issues and key findings How should the claim be settled? The Applicant may elect to have the FSP complete the remaining works required to restore the property to its pre-loss condition, or cash settle her for the cost of doing so. The Applicant is not entitled to settlement on a total loss basis as the damage to her home and contents caused by the explosion is less than the sums insured. Is the Applicant entitled to compensation? The Applicant is entitled to compensation for non-financial loss suffered as a res ult of the failure by the FSP’s contractors to decontaminate the property. She is also entitled to partial reimbursement of her legal costs. 1.3 Determination This Determination is partly in favour of the Applicant. The FSP is to complete the necessary works t o restore the Applicant’s property to its condition prior to the explosion or cash settle the Applicant for the cost of doing so (at her election), in accordance with sections 2.1 and 3.2 below. The FSP is to pay the Applicant compensation of $3,000 for non-financial loss and up to $3,000 for legal costs, in accordance with section 2.2 below. Case No: 350658 Determination Page 2 of 7 2 Reasons for Determination 2.1 How should the claim be settled? Available information does not establish total loss Under the terms of the Applicant’s policy, the FSP is only obliged to settle her building claim on a total loss basis if the damage caused to her home by the explosion is such that the building cannot be repaired, or it would be uneconomical for the FSP to undertake repairs (given the building sum insured of $379,000). The Applicant has raised specific concerns about the adequacy of the scope of works approved by the FSP for the building repairs. These issues are considered in more detail below. However, having carefully reviewed the available information, the Panel is satisfied that the damage caused to the Applicant’s home by the explosion can be safely and economically repaired for an amount which is considerably less than the building sum insured. The Applicant says that the FSP should pay her the building sum insured due to the delay in finalising her claim and based on medical advice that it would be preferable for her to sell her home rather than endure further delays while the repairs are finalised. However, under the terms of her policy, the FSP is not obliged to settle the Applicant’s building claim on a total loss basis where the damage to the property can be safely and economically repaired. In these circumstances, the FSP is obliged to either repair the damage or cash settle the Applicant for the cost of the repairs. The FSP has acknowledged that some of the Applicant’s contents items have been damaged as a result of the explosion. Under the terms of the policy, the FSP is required to arrange for the replacement of these items or cash settle her for the replacement cost. However, there is no information to suggest that the value of the damaged contents items is equal to or greater than the contents sum insured of $33,000 and therefore the FSP is not obliged to settle the contents claim on a total loss basis. The FSP’s liability is to be determined by identifying the specific contents items which have been damaged as a result of the explosion, in accordance wi th the process set out below. Applicant may choose to have repairs completed or accept cash settlement In accordance with its obligations under the policy, the FSP elected to settle the Applicant’s building claim by arranging for the repair of the damage to her property. Once the FSP decided to settle the claim in this manner, it was obliged to complete the repairs (regardless of any additional complications which arose during the repair process). After the Applicant sought payment of the total sum insured, the FSP offered to cash settle her for the cost of the additional works required (together with certain Case No: 350658 Determination Page 3 of 7 other amounts), in an attempt to resolve the dispute. However the Applicant and the FSP were unable to agree on the settlement amount. Given the FSP’s initial election to restore the property, the Applicant is entitled to have her building claim settled on this basis. Alternatively, it is open to her to choose to be cash settled for the cost of the necessary works. In either case, the extent of the FSP’s liability is to be determined as set out below - for ease of reference, a summary is included in section 3.2 . Scope of asbestos remediation works is appropriate The remaining works required to restore the property to its condition prior to the explosion comprise:  additional remediation works to address asbestos contamination; and  repair of the damage to the building itself. The FSP has provided a quotation for $46,090 from an asbestos remediation contractor (E) for additional works to address asbestos contamination at the property. E’s quote is based on a comprehensive asbestos remediation plan prepared following a detailed inspection of the site and testing of air and soil samples. The proposed remediation works include:  detailed cleaning of the interior of the house (including HEPA vacuuming) and the disposal of any items contaminated by asbestos  the removal of any asbestos fragments from the soil around the house  the disposal of asbestos contaminated soil and other items at a licensed waste facility  the supply and installation of top soil at the site. E was appointed by the FSP at the Applicant’s request, after she raised concerns about the adequacy of the initial asbestos remediation works carried out by the original contractor (PC) appointed by the FSP. In a report prepared in February 2014, E concluded that the property remained unfit for residential use due to the ongoing presence of asbestos. Due to the nature and location of the materials identified, E concluded that the asbestos at the property had most likely originated from the explosion. The Panel is satisfied that E’s proposed remediation plan is appropriate to address the continuing asbestos contamination at the property. The Panel notes that, while the tests conducted by E (and the FSP’s previous contractors) did not identify any contamination to the interior of the house, E’s scope of works includes a comprehensive clean of the interior as a precautionary measure, which should address the Applicant’s concerns in this r egard. The Panel notes that E’s remediation plan contemplates the possibility that additional works may be required to fully remediate the property. The Panel considers that the FSP should be liable for any additional works which E confirms are reasonably required. Case No: 350658 Determination Page 4 of 7 Scope of building works includes bulk of repairs required The FSP has provided a quotation for $25,547.50 from its builder (A) for the necessary repairs to the property, which is based on a scope of works prepared by the FSP’s consulting engineer (HB). The Panel has reviewed HB’s scope of works and considers that it includes the bulk of the repairs required to repair the damage to the property resulting from the explosion. The Panel is satisfied that, in finalising the scope of works, HB has adequately addressed all of the specific issues raised by the Applicant during the course of this dispute, other than the minor additional damage to the property resulting from some of the windows not being properly covered after the glass was blown out during the explosion. In this regard, the Panel notes that:  the FSP has acknowledged that it did not take prompt action to secure the windows in order to prevent further damage  when the FSP’s engineer (HB) attended the property in January 2014 he confirmed that the floorboards in the bathroom and the laundry had sustained water damage as a result of the windows being left uncovered  it is not clear that HB’s final scope of works provides for the repair of this damage  the FSP should be required to arrange for the repair of this damage or, in the event of a cash settlement, should be required to pay an additional amount of $1,500. Based on the available information, the Panel is satisfied that the additional items of damage identified by the Applicant (such as the movement damage to the bedroom floor) were not caused by the explosion. The Panel notes that the Applicant has not provided any independent information to rebut the findings of the FSP’s contractors in this regard. The FSP obtained quotes for the necessary repairs from two builders and also offered the Applicant the opportunity to provide a quote from her preferred builder. In these circumstances, the Panel is satisfied that the quote provided by A reasonably reflects the cost of carrying out the building repairs. FSP is liable for damaged contents items The FSP acknowledges that it is liable for the replacement of the carpets at the property and has provided a quote for $13,750 for this item. The FSP has also agreed to replace a fridge which the Applicant ad vised has been damaged. The FSP has previously settled the Applicant for other contents items which were damaged as a result of the explosion. The Applicant has not provided any independent information which establishes that the amount quoted by the FSP for the replacement of the carpets is insufficient. Accordingly, the FSP should arrange for the replacement of the carpets and the fridge, or pay the Applicant the replacement cost. The FSP is also liable for the Case No: 350658 Determination Page 5 of 7 replacement of any additional contents items which E identifies as being contaminated with asbestos, during the course of the remediation works. Settlement should include payment for temporary accommodation Based on the report prepared by E in February 2014, it appears that the steps undertaken by t he FSP’s original asbestos remediation contractor (P) in December 2013 were inadequate to fully address the contamination of the soil at the property. Further, it appears that the second contractor (S) appointed by the FSP failed to identify the ongoing pr esence of asbestos (possibly because S’s tests were confined to the interior and exterior of the house itself). The Applicant has raised a number of concerns about the actions of the FSP’s contractors in this regard. However, the Panel considers that it is unnecessary to reach a view on these issues for the purposes of this Determination. It is sufficient to note that the failure of the FSP’s contractors to successfully remediate the property for more than eight months after the explosion has significantl y delayed the claim process. Further, it is clear that the FSP’s failure to adequately address the Applicant’s concerns about the remediation process (which have been substantiated by E’s findings) has caused the Applicant to lose confidence in the FSP’s m anagement of the claim as a whole. This further delayed the preparation of a scope of works for the building repairs. Due to the delay in resolving this dispute, the Applicant has exhausted her entitlement to temporary accommodation benefits under the policy and has been required to fund the cost of rental accommodation herself. The Panel considers that these additional costs are directly attributable to the actions of the FSP and its contractors in failing to adequately carry out the initial asbestos remediation works. Accordingly, the Panel considers that the FSP should be required to reimburse the Applicant for temporary accommodation expenses incurred from the date benefits were last paid (being on or around 6 September 2014) until the date on which the Applicant accepts this Determination, subject to the provision of appropriate receipts. The FSP should also fund the cost of temporary accommodation for the Applicant and her son for a period of up to 60 days following the date the Applicant accepts this Determination. Given the estimates provided, this should allow sufficient time for the asbestos remediation works and building repairs to be completed. 2.2 Is the Applicant entitled to compensation? Applicant is entitled to compensation for non-financial loss Under paragraph 9.3(b) of the Terms of Reference, FOS can award compensation where an applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with their expectation of enjoyment or piece of mind. The Applicant has provided medical reports confirming that she has suffered a significant degree of stress in connection with her claim. The Applicant says that, Case No: 350658 Determination Page 6 of 7 due to the delay in resolving the claim, she and her son have been required to relocate on several occasions which has been particularly stressful during her son’s final year of school. The Panel acknowledges that the circumstances which gave rise to the Applicant’s claim were inherently stressful. However, the Panel considers that the stress and inconvenience suffered by the Applicant has been exacerbated by the failure of the FSP’s contractors to carry out appropriate remediation works. This is particularly critical in the case of a contaminant such as asbestos, which naturally triggers a high level of concern among property owners. In the circumstances, the Panel considers that an award of compensation for non- financial loss in the amount of $3,000 is appropriate. Applicant is entitled to partial reimbursement of legal costs Under section 9.4 of the Terms of Reference, FOS can require a financial services provider to reimburse legal costs incurred by an applicant in the course of their dispute. However, FOS will generally not require a financial services provider to reimburse legal costs of more than $3,000. The Applicant did not engage legal representation until after she had spent a number of months trying to resolve her concerns directly with the FSP. It appears that the Applicant engaged a solicitor because she was sufferi ng from high levels of stress and therefore was no longer able to effectively represent herself. In the circumstances, the Panel considers that the Applicant’s actions were not unreasonable and were driven by the delays in resolving her claim and her perception that the FSP was not listening to her concerns about ongoing asbestos contamination. In these circumstances, the Panel considers that the FSP should be required to reimburse the Applicant’s legal costs (of up to $3,000), subject to the Applicant providing appropriate evidence of the costs incurred. Case No: 350658 Determination Page 7 of 7 3 Supporting information 3.1 FOS approach to dispute This dispute has not been the subject of a FOS Recommendation. Due to the nature of the dispute, it has been referred directly to a Panel for Determination, in line with the Operational Guidelines to the FOS Terms of Reference. The Panel consists of an Ombudsman and two representatives with consumer and insurance experience. The Panel has decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. The parties have made extensive submissions and provided voluminous materials. All material information relied on for the purposes of this Determination has been exchanged between the parties, and each party has had the opportunity to address any issues raised by the other. The Panel has reviewed and considered all of the material provided by the parties. While the parties have raised a number of issues in their submissions, for the purposes of this Determination the Panel has restricted its commentary to those issues which it considers directly relevant to the outcome only. The Applicant has been represented by her solicitor during the course of this dispute. For the purposes of this Determination, submissions made by the Applicant’s solicitor have been treated as having been made by the Applicant herself. 3.2 Basis for settlement Item Amount Asbestos remediation works (per E’s scope of works) (plus any additional works reasonably required) $46,090.00 [TBD] Building repairs (per HB’s scope of works) (plus repair of laundry and bathroom floorboards) $25,547.50 $1,500 Carpet replacement $13,750.00 Fridge plus any additional contents items identified by E [TBD] Temporary accommodation from on or around 7 September 2014 to the date which is 60 days after the date the Applicant accepts this Determination [TBD] Note : In addition, compensation is payable in accordance with section 2.2 above.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.