Home / Financial Firm (Unknown - Insurer) / Determination 350658
Determination 350658
Explosion damage claim settlement, asbestos remediation delays and claim management
Summary
The Applicant's home and contents were damaged in an explosion, and the FSP's contractors failed to fully remediate asbestos contamination. AFCA ordered the FSP to complete or cash settle the remaining works and contents, pay temporary accommodation, $3,000 non-financial loss and up to $3,000 legal costs.
The FSP is obliged to complete or cash settle repairs once it elected to restore the property, and it is liable for the delay and distress caused by its contractors' inadequate remediation.
Issues
- Repairs or contractors primary · upheld
“The failure of the FSP's contractors to carry out appropriate remediation works exacerbated the stress and inconvenience suffered by the Applicant.”
- Claim amount dispute secondary · not upheld
“The Applicant is not entitled to settlement on a total loss basis as the damage is less than the sums insured.”
- Poor claim handling secondary · upheld
“The FSP's failure to adequately address the Applicant's concerns caused her to lose confidence in the FSP's management of the claim.”
- Delay secondary · upheld
“Failure to remediate the property for more than eight months after the explosion significantly delayed the claim process.”
Subjects and remedies
health or medicalpay claimpay compensationpay non financial lossrepair or rectify
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building – Home Contents - Service -
Service Quality
Determination
Case No: 350658 Determination Page 1 of 7
Case number : 350658 12 December 2014
1 Overview
1.1 Dispute
The Applicant lodged a claim under her home insurance policy with the Financial
Services Provider (FSP) for damage to her home and contents caused by an
explosion at her neighbour’s property on 14 June 2013.
The FSP accepted the Applicant’s claim and made arrangements for repairs to
her property, which have been partially completed. However, a dispute has arisen
during the course of the repairs.
The Applicant wants her claim to be settled by payment of the total sum insured
for the building and contents. She says that the asbestos decontamination works
at the property have not been properly carried out by the FSP’s contractors. She
also seeks compensation for financial and non-financial losses suffered due to the
manner in which the FSP has handled her claim.
1.2 Issues and key findings
How should the claim be settled?
The Applicant may elect to have the FSP complete the remaining works required
to restore the property to its pre-loss condition, or cash settle her for the cost of
doing so. The Applicant is not entitled to settlement on a total loss basis as the
damage to her home and contents caused by the explosion is less than the sums
insured.
Is the Applicant entitled to compensation?
The Applicant is entitled to compensation for non-financial loss suffered as a
res ult of the failure by the FSP’s contractors to decontaminate the property. She is
also entitled to partial reimbursement of her legal costs.
1.3 Determination
This Determination is partly in favour of the Applicant.
The FSP is to complete the necessary works t o restore the Applicant’s property to
its condition prior to the explosion or cash settle the Applicant for the cost of doing
so (at her election), in accordance with sections 2.1 and 3.2 below. The FSP is to
pay the Applicant compensation of $3,000 for non-financial loss and up to $3,000
for legal costs, in accordance with section 2.2 below.
Case No: 350658 Determination Page 2 of 7
2 Reasons for Determination
2.1 How should the claim be settled?
Available information does not establish total loss
Under the terms of the Applicant’s policy, the FSP is only obliged to settle her
building claim on a total loss basis if the damage caused to her home by the
explosion is such that the building cannot be repaired, or it would be
uneconomical for the FSP to undertake repairs (given the building sum insured of
$379,000).
The Applicant has raised specific concerns about the adequacy of the scope of
works approved by the FSP for the building repairs. These issues are considered
in more detail below. However, having carefully reviewed the available
information, the Panel is satisfied that the damage caused to the Applicant’s
home by the explosion can be safely and economically repaired for an amount
which is considerably less than the building sum insured.
The Applicant says that the FSP should pay her the building sum insured due to
the delay in finalising her claim and based on medical advice that it would be
preferable for her to sell her home rather than endure further delays while the
repairs are finalised.
However, under the terms of her policy, the FSP is not obliged to settle the
Applicant’s building claim on a total loss basis where the damage to the property
can be safely and economically repaired. In these circumstances, the FSP is
obliged to either repair the damage or cash settle the Applicant for the cost of the
repairs.
The FSP has acknowledged that some of the Applicant’s contents items have
been damaged as a result of the explosion. Under the terms of the policy, the
FSP is required to arrange for the replacement of these items or cash settle her
for the replacement cost.
However, there is no information to suggest that the value of the damaged
contents items is equal to or greater than the contents sum insured of $33,000
and therefore the FSP is not obliged to settle the contents claim on a total loss
basis. The FSP’s liability is to be determined by identifying the specific contents
items which have been damaged as a result of the explosion, in accordance wi th
the process set out below.
Applicant may choose to have repairs completed or accept cash settlement
In accordance with its obligations under the policy, the FSP elected to settle the
Applicant’s building claim by arranging for the repair of the damage to her
property. Once the FSP decided to settle the claim in this manner, it was obliged
to complete the repairs (regardless of any additional complications which arose
during the repair process).
After the Applicant sought payment of the total sum insured, the FSP offered to
cash settle her for the cost of the additional works required (together with certain
Case No: 350658 Determination Page 3 of 7
other amounts), in an attempt to resolve the dispute. However the Applicant and
the FSP were unable to agree on the settlement amount.
Given the FSP’s initial election to restore the property, the Applicant is entitled to
have her building claim settled on this basis. Alternatively, it is open to her to
choose to be cash settled for the cost of the necessary works. In either case, the
extent of the FSP’s liability is to be determined as set out below - for ease of
reference, a summary is included in section 3.2 .
Scope of asbestos remediation works is appropriate
The remaining works required to restore the property to its condition prior to the
explosion comprise:
additional remediation works to address asbestos contamination; and
repair of the damage to the building itself.
The FSP has provided a quotation for $46,090 from an asbestos remediation
contractor (E) for additional works to address asbestos contamination at the
property. E’s quote is based on a comprehensive asbestos remediation plan
prepared following a detailed inspection of the site and testing of air and soil
samples. The proposed remediation works include:
detailed cleaning of the interior of the house (including HEPA vacuuming) and
the disposal of any items contaminated by asbestos
the removal of any asbestos fragments from the soil around the house
the disposal of asbestos contaminated soil and other items at a licensed
waste facility
the supply and installation of top soil at the site.
E was appointed by the FSP at the Applicant’s request, after she raised concerns
about the adequacy of the initial asbestos remediation works carried out by the
original contractor (PC) appointed by the FSP. In a report prepared in February
2014, E concluded that the property remained unfit for residential use due to the
ongoing presence of asbestos. Due to the nature and location of the materials
identified, E concluded that the asbestos at the property had most likely originated
from the explosion.
The Panel is satisfied that E’s proposed remediation plan is appropriate to
address the continuing asbestos contamination at the property. The Panel notes
that, while the tests conducted by E (and the FSP’s previous contractors) did not
identify any contamination to the interior of the house, E’s scope of works includes
a comprehensive clean of the interior as a precautionary measure, which should
address the Applicant’s concerns in this r egard.
The Panel notes that E’s remediation plan contemplates the possibility that
additional works may be required to fully remediate the property. The Panel
considers that the FSP should be liable for any additional works which E confirms
are reasonably required.
Case No: 350658 Determination Page 4 of 7
Scope of building works includes bulk of repairs required
The FSP has provided a quotation for $25,547.50 from its builder (A) for the
necessary repairs to the property, which is based on a scope of works prepared
by the FSP’s consulting engineer (HB).
The Panel has reviewed HB’s scope of works and considers that it includes the
bulk of the repairs required to repair the damage to the property resulting from the
explosion.
The Panel is satisfied that, in finalising the scope of works, HB has adequately
addressed all of the specific issues raised by the Applicant during the course of
this dispute, other than the minor additional damage to the property resulting from
some of the windows not being properly covered after the glass was blown out
during the explosion. In this regard, the Panel notes that:
the FSP has acknowledged that it did not take prompt action to secure the
windows in order to prevent further damage
when the FSP’s engineer (HB) attended the property in January 2014 he
confirmed that the floorboards in the bathroom and the laundry had sustained
water damage as a result of the windows being left uncovered
it is not clear that HB’s final scope of works provides for the repair of this
damage
the FSP should be required to arrange for the repair of this damage or, in the
event of a cash settlement, should be required to pay an additional amount of
$1,500.
Based on the available information, the Panel is satisfied that the additional items
of damage identified by the Applicant (such as the movement damage to the
bedroom floor) were not caused by the explosion. The Panel notes that the
Applicant has not provided any independent information to rebut the findings of
the FSP’s contractors in this regard.
The FSP obtained quotes for the necessary repairs from two builders and also
offered the Applicant the opportunity to provide a quote from her preferred builder.
In these circumstances, the Panel is satisfied that the quote provided by A
reasonably reflects the cost of carrying out the building repairs.
FSP is liable for damaged contents items
The FSP acknowledges that it is liable for the replacement of the carpets at the
property and has provided a quote for $13,750 for this item. The FSP has also
agreed to replace a fridge which the Applicant ad vised has been damaged. The
FSP has previously settled the Applicant for other contents items which were
damaged as a result of the explosion.
The Applicant has not provided any independent information which establishes
that the amount quoted by the FSP for the replacement of the carpets is
insufficient.
Accordingly, the FSP should arrange for the replacement of the carpets and the
fridge, or pay the Applicant the replacement cost. The FSP is also liable for the
Case No: 350658 Determination Page 5 of 7
replacement of any additional contents items which E identifies as being
contaminated with asbestos, during the course of the remediation works.
Settlement should include payment for temporary accommodation
Based on the report prepared by E in February 2014, it appears that the steps
undertaken by t he FSP’s original asbestos remediation contractor (P) in
December 2013 were inadequate to fully address the contamination of the soil at
the property. Further, it appears that the second contractor (S) appointed by the
FSP failed to identify the ongoing pr esence of asbestos (possibly because S’s
tests were confined to the interior and exterior of the house itself).
The Applicant has raised a number of concerns about the actions of the FSP’s
contractors in this regard. However, the Panel considers that it is unnecessary to
reach a view on these issues for the purposes of this Determination.
It is sufficient to note that the failure of the FSP’s contractors to successfully
remediate the property for more than eight months after the explosion has
significantl y delayed the claim process. Further, it is clear that the FSP’s failure to
adequately address the Applicant’s concerns about the remediation process
(which have been substantiated by E’s findings) has caused the Applicant to lose
confidence in the FSP’s m anagement of the claim as a whole. This further
delayed the preparation of a scope of works for the building repairs.
Due to the delay in resolving this dispute, the Applicant has exhausted her
entitlement to temporary accommodation benefits under the policy and has been
required to fund the cost of rental accommodation herself.
The Panel considers that these additional costs are directly attributable to the
actions of the FSP and its contractors in failing to adequately carry out the initial
asbestos remediation works. Accordingly, the Panel considers that the FSP
should be required to reimburse the Applicant for temporary accommodation
expenses incurred from the date benefits were last paid (being on or around 6
September 2014) until the date on which the Applicant accepts this
Determination, subject to the provision of appropriate receipts.
The FSP should also fund the cost of temporary accommodation for the Applicant
and her son for a period of up to 60 days following the date the Applicant accepts
this Determination. Given the estimates provided, this should allow sufficient time
for the asbestos remediation works and building repairs to be completed.
2.2 Is the Applicant entitled to compensation?
Applicant is entitled to compensation for non-financial loss
Under paragraph 9.3(b) of the Terms of Reference, FOS can award
compensation where an applicant has suffered an unusual degree or extent of
physical inconvenience, time taken to resolve the situation or interference with
their expectation of enjoyment or piece of mind.
The Applicant has provided medical reports confirming that she has suffered a
significant degree of stress in connection with her claim. The Applicant says that,
Case No: 350658 Determination Page 6 of 7
due to the delay in resolving the claim, she and her son have been required to
relocate on several occasions which has been particularly stressful during her
son’s final year of school.
The Panel acknowledges that the circumstances which gave rise to the
Applicant’s claim were inherently stressful. However, the Panel considers that the
stress and inconvenience suffered by the Applicant has been exacerbated by the
failure of the FSP’s contractors to carry out appropriate remediation works. This is
particularly critical in the case of a contaminant such as asbestos, which naturally
triggers a high level of concern among property owners.
In the circumstances, the Panel considers that an award of compensation for non-
financial loss in the amount of $3,000 is appropriate.
Applicant is entitled to partial reimbursement of legal costs
Under section 9.4 of the Terms of Reference, FOS can require a financial
services provider to reimburse legal costs incurred by an applicant in the course
of their dispute. However, FOS will generally not require a financial services
provider to reimburse legal costs of more than $3,000.
The Applicant did not engage legal representation until after she had spent a
number of months trying to resolve her concerns directly with the FSP. It appears
that the Applicant engaged a solicitor because she was sufferi ng from high levels
of stress and therefore was no longer able to effectively represent herself.
In the circumstances, the Panel considers that the Applicant’s actions were not
unreasonable and were driven by the delays in resolving her claim and her
perception that the FSP was not listening to her concerns about ongoing asbestos
contamination.
In these circumstances, the Panel considers that the FSP should be required to
reimburse the Applicant’s legal costs (of up to $3,000), subject to the Applicant
providing appropriate evidence of the costs incurred.
Case No: 350658 Determination Page 7 of 7
3 Supporting information
3.1 FOS approach to dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions.
The parties have made extensive submissions and provided voluminous
materials. All material information relied on for the purposes of this Determination
has been exchanged between the parties, and each party has had the opportunity
to address any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.
The Applicant has been represented by her solicitor during the course of this
dispute. For the purposes of this Determination, submissions made by the
Applicant’s solicitor have been treated as having been made by the Applicant
herself.
3.2 Basis for settlement
Item Amount
Asbestos remediation works (per E’s scope of works)
(plus any additional works reasonably required)
$46,090.00
[TBD]
Building repairs (per HB’s scope of works)
(plus repair of laundry and bathroom floorboards)
$25,547.50
$1,500
Carpet replacement $13,750.00
Fridge plus any additional contents items identified by E [TBD]
Temporary accommodation from on or around 7 September
2014 to the date which is 60 days after the date the Applicant
accepts this Determination
[TBD]
Note : In addition, compensation is payable in accordance with section 2.2 above.