Determination 350073

Quantum of loss of rent payable after Cyclone Yasi damage to a strata unit, with legal fees and delay compensation sought

FirmFinancial Firm (Unknown - Insurer)
Decided2015-02-23
ProductGeneral Insurance · Strata
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed$17,680
SourceAFCA PDF

Summary

A strata unit owner claimed 104 weeks of loss of rent ($17,680) after Cyclone Yasi damage, plus legal fees and delay compensation. AFCA ordered the FSP to pay 9 months' loss of rent with interest under section 57 of the Insurance Contracts Act, and refused the legal costs and compensation.

The policy covers loss of rent, the original repair offer was inadequate and the policy limits such claims to 12 months, so AFCA allowed a fair additional period, while the delays were largely normal for a catastrophe claim and no legal costs were shown to be necessary.

Issues

Subjects and remedies

natural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Residential Strata Title - Service - Service Quality Determination Case No: 350073 Determination Page 1 of 8 Case number: 350073 11 February 2015 1 Overview 1.1 Dispute The Applicant is an owner of a unit insured under an ISR policy insuring a body corporate residential strata complex. On 2 February 2011 the complex in which the Applicant’s unit is located sustained substantial damage as a result of Cyclone Yasi. The Applicant requested a loss of rent payment for the time taken until his unit was repaired. He requests a total of 104 weeks for loss of rent totalling $17,680. The Financial Services Provider (FSP) has included a partial settlement of this amount to the insured (the body corporate) and has declined to offer any further settlement to the Applicant. The Applicant remains dissatisfied with the settlement offered. In addition to his loss of rent, he also seeks settlement for his legal fees and compensation for the delays in settling his claim. 1.2 Issues and key findings Does the FSP have to pay an additional settlement to the Applicant for loss of rent? The FSP is required t o pay the equivalent of a total of 9 month’s loss of rent for the Applicant’s claim. Does the FSP have to contribute to the Applicant’s legal costs? The FSP does not have to contribute to the Applicant’s legal costs as there is no evidence to support the A pplicant’s need for legal services in respect of the claim or dispute. Does the FSP have to pay compensation to the Applicant? The FSP does not have to pay compensation to the Applicant. 1.3 Determination This Determination is partially in favour of the Applicant. The FSP is to contribute a total of 9 months’ rent for the Applicant’s loss of rent claim, pursuant to policy terms and conditions. Case No: 350073 Determination Page 2 of 8 The FSP is to also pay interest on this sum, in accordance with section 57 of the Insurance Contracts Act 1984 (Cth) (the Act) from the time its original settlement to the insured for this aspect of the claim was made, up until the date of settlement. The FSP is not required to pay any of the Applicant’s legal costs. The FSP is not required to pay compensation to the Applicant. Case No: 350073 Determination Page 3 of 8 2 Reasons for Determination 2.1 Does the FSP have to pay an additional settlement to the Applicant for loss of rent? Factors not considered by the FSP which would impact the loss of rent claim The FSP does not dispute the policy provides cover for loss of rent. It has previously provided a settlement to its insured for this aspect of the claim which was returned by the insured. The insured does not accept how the settlement amount was calculated. The settlement was based on the advice of the FSP’s a ssessor (CR). Whilst the policy provides cover for loss of rent, due to the nature of the claim and other non- claim related damage, a commercial offer of settlement was made by the FSP. Therefore, there is no exact calculation of what portion of this settlement was for the Applicant. CR has indicated in the settlement offer made to the insured the following:  the Applicant’s unit was one of only a few units within the whole complex which suffered damage wholly attributable to the claim event  the Applicant’s unit was subject to a private rental agreement  an estimated timeframe to complete roof repairs to the building which housed the Applicant’s unit (and which was wholly damaged by the claim event) was one month  a commercial offer covering a six month period was made. It is noted the property damage portion of the claim was not finalised until over two years after the claim event. The FSP denies it caused any delays during the claims process. The following provides a brief timeline of events, relevant to the delays experienced throughout the claim:  2 February 2011 – Cyclone Yasi damages the property  15 February 2011 – CR inspects the damaged property  13 April 2011 – CR’s first report is received by the FSP  24 June 2011 – first settlement offer is made to the insured for roof repairs  26 July 2011 – FSP receives the Applicant’s email notifying it of his loss of rent claim from the date of loss (this email was received by CR on 18 July 2011)  2 August 2011 – a meeting is held between the insured, CR and other interested parties regarding roof repairs to a couple of the units, including the Applicant’s unit, due to the insured’s concerns over the settlement offered. The FSP agrees, as a result of this meeting, to appoint an engineer to address the insured’s concerns.  3 August 2011 – the engineer’s schedule an inspection date of 4 September 2011 Case No: 350073 Determination Page 4 of 8  16 September 2011 – engineer’s report is received and a request is made to the insured and other parties to attend another meeting to discuss the increase quotation for repairs and the next steps to progress the claim  4 October 2011 – the insured provides an alternative quotation for repairs. The original offer advised of contributions required by the insured to the overall cost of repairs for non-claim related repairs. It was th e FSP’s intention to authorise repairs to its nominated builder (PD). PD provided advice it would not be able to start the repairs until 18 July 2011. The insured provided a formal response to the FSP’s offer on 18 July 2011. The Panel is satisfied the timeframe to respond to the offer is not unreasonable given the issues raised by the insured, the size of the complex of units and the extent of damage to same. A meeting between the associated parties was suggested by the project manager and this was agreed to by all parties with the meeting date set for 2 August 2011. The FSP was not provided with an update of this meeting until 8 September 2011. The report notes the items discussed and what action was still required including awaiting firm costs for some of the common area repairs required. It also notes the main delay in authorising repairs was the insured being able to raise relevant funds to attend to the non-claim related repairs. Essentially, these repairs had to be made concurrently with the claim related repairs. Even if the insured was able to raise the necessary funds to contribute to the cost of repairs, it is clear other items were still outstanding at this time and therefore, repairs could still not proceed. It appears the update regarding costs was not received by the FSP until around 16 September 2011. The insured then advised the FSP on 26 September 2011 that whilst PD was the preferred repairer an alternative quotation was being obtained. The quotation was received by the FSP on 4 October 2011. The FSP was therefore, not realistically in a position to offer settlement or authorise repairs until this date, some eight months after the event. However, on receipt of the quotation from the insured, it referred all available information to the project manager for review with a request to agree on a contractor and commence repairs. This was emailed to the insured and project manager on 7 October 2011. It would appear ultimate authority to proceed with repairs was given around 25 October 2011. The difficulty faced by the FSP with respect to the overall repair program was the non-claim related repairs. These repairs related solely to roof damage. Whilst the FSP contributed 20% to these costs, the majority of claim related damage was internal to the buildings. As such, the roof damage had to be repaired prior to any internal work being completed. From the above summary, it is clear the original offer made to the insured for repairs to the roof, was not made until over four months after the event. It is clear the original offer was inadequate given the negotiations, further quoting and subsequent authority for a higher amount was given on 25 October 2011, almost Case No: 350073 Determination Page 5 of 8 nine months after the event. FSP file notes indicate repairs had started by 14 November 2011. CR su ggests the repairs to the Applicant’s unit, including the roof, should take only one month. However there is no advice as to whether the unit would have been tenantable or even accessible at this time, given the extensive nature of repairs being undertaken across the complex. Simply having the unit repaired does not necessarily render it tenantable if a tenant cannot access the unit because of other site repairs. Additionally, there is no indication as to when, during the course of the proposed repairs to t he entire complex, the repairs to the building housing the Applicant’s unit would have commenced. The Financial Ombudsman Service (FOS) through its experience with disputes relating to catastrophe claims, is aware there are often long delays between the event and repairs commencing. There are a number of factors which contribute to this, namely:  the extensive amount of damage sustained over a widespread area  the availability, or lack thereof, of repairers and/or materials  the occurrence of other weather events within the area which prohibit the progression of repairs (ie: during the “wet season” between October and April each year). On reviewing CR’s advice regarding settlement of the loss of rent aspect of the claim, no consideration appears to have been given to the above factors. Clearly, the FSP’s focus was on achieving an agreed settlement with the insured in respect of the substantive claim. It is unfortunate for the Applicant that settlement of the insured’s claim took precedence, however this was i n fact a commercial transaction which was being properly pursued by the insured and the FSP. The Panel is however mindful that this left the Applicant somewhat exposed to the commercial negotiations and unable to progress his own claim. The FSP ultimately allowed the Applicant 6 months loss of rent, being the maximum likely repair period including some margin of 2 months. However this has left the Applicant well short of his period of vacancy. On the face of it, 6 months loss of rent would be an adequate time in which to have repairs completed, but in any event, even were this expected to take much longer (and in this instance up to 2 years) the policy limits such claims to 12 months. Having considered all of the above, the Panel intends to exercise its remit to do what is fair in all the circumstances and allow an additional period of 3 months loss of rent. That is, 3 months in addition to the 6 months offered by the FSP. There is no evidence to support the Applicant’s need for legal services The Applicant refers to legal fees he has incurred and is still incurring , however he has not provided any evidence of these costs. Despite this, the Panel has considered his request for a refund of his costs. Case No: 350073 Determination Page 6 of 8 The Applicant has not provided any evidence of why he needed to engage the services of a solicitor. Whilst it is understood he experienced difficulties throughout the claims experience for a variety of reasons, he has not provided any evidence of what legal action was taken by his representative to assist his case. As such, the FSP does not have to contribute to the Applicant’s legal fees. The Applicant has not suffered an unusual degree of physical inconvenience There is no doubt the settlement of this claim was protracted for a number of reasons. However, it would appear the majority of the delays experienced in the claims process would either be considered normal industry standards given the magnitude of the event, or as a result of negotiations between the FSP and its insured. As such, the Panel does not consider a payment of compensation is appropriate in these circumstances. Case No: 350073 Determination Page 7 of 8 3 Supporting information 3.1 FSP’s file notes The following file notes are relevant to establishing the timeline of events detailed in the Determination:  03/02/2011 – report of claim event made by insured  13/04/2011 – CR’s 1 st report is received  16/05/2011 – scope of works received  24/06/2011 – settlement letter sent to insured  18/07/2011 – response provided by insured to settlement offer and detailing concerns/issues for further discussion  26/07/2011 – confirmation of email received from insured detailing Applicant’s claim for contents items. File note does not mention email also contains Applicant’s request for loss of rent  02/08/2011 – confirmation of meeting being held on this day at 2pm  08/09/2011 – CR’s 4 th assessment report is received detailing items requiring follow up/further information  16/09/2011 – updated costs and engineering report received and sent to insured  27/09/2011 – insured representative advises an alternative quotation is being sought  04/10/2011 – alternative quotation received from insured  07/10/2011 – second quotation provided by insured  25/10/2011 – FSP provides its authority to insured with respect to claim related repairs  14/11/2011 – insured confirms the name of builder appointed to conduct the non- claim related repairs and confirms contact will be made with FSP’s builder to progress claim related repairs 3.2 Expert reports The FSP relies upon advice received from CR regarding the calculation of the Applicant’s loss of rent claim. The following extracts are from that advice, dated 19 December 2013. “The estimated timeframe to rectify the total scope of work according to the original estimator’s timeframe is four months. However, we are of the understanding that not all o f the damages arose from Ins ured causes. Specifically the bulk of the repair in relation to the roofing damages which were mostly attributed to inappropriate repair and maintenance than direct damage from the Cyclone. The only building which had units sust aining damage as a direct result of the cyclone related to damages to Units [Applicant’s unit and others]. Therefore, we can only consider BI losses flowing from units [Applicant’s unit and others] as Insurable losses. Based on the estimator’s schedule t he timeframe estimated for rectifying all of the damages to the 12 buildings will require fourt h months. Even if we accept that a reasonable time to agree a arrangement with contractor and potential delay is 6 months the repair time for one building out of 12 should not take more than one month.” (sic) Our commercial settlement offer is primarily made on the following basis: Case No: 350073 Determination Page 8 of 8 - We are of the opinion that the maximum time allowed for the entire repair should not exceed 6 months; - That the most time consuming aspect of the repair relates to the roofing repair of which only units [the Applicant’s unit and others] are covered; - … - We believe only losses flowing from Units [the Applicant’s unit and others] are insured. Estimated time to repair damages to the building is approximately one month. We are willing to consider accepting 20% of the losses flowing from the next 5 months, thereby allowing a total interruption period of 6 months. (sic)” 3.3 Other issues The Applicant has raised other issues during the course of this dispute which were not raised in his original dispute application. These additional issues have therefore not been considered when issuing this Determination.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.