Text of the determination
Determination
General Insurance - Small Business/Farm Insurance - Commercial Property - Service -
Delay in Claim Handling
Determination
Case No: 348168 Determination Page 1 of 8
Case number : 348168 6 January 2015
1 Overview
1.1 Dispute
The Applicants lodged a claim under their business insurance policy with the
Financial Services Provider (FSP) for damage caused by Cyclone Yasi in
February 2011.
The FSP accepted the claim and attempted to agree an approved scope of works
and obtain quotations for repairs from the Applicants. When agreement could not
be reached, the FSP cash settled the claim for $48,883.90 in April 2013.
The Applicants say that the FSP (and its assessor) unnecessarily delayed their
claim and refused to arrange a builder to complete the necessary repairs. The
Applicants seek a review of their claim and payment for loss of rent suffered as a
result of the delays.
1.2 Issues and key findings
Did the FSP unreasonably delay settlement of the claim?
While the final settlement could have been made sooner, the evidence does not
establish that the FSP unreasonably delayed the progress of the claim.
Is the cash settlement paid by the FSP appropriate?
The FSP acted reasonably in cash settling the Applicants for the cost of the
repairs when it was unable to finalise the scope of works. The cash settlement
paid adequately covers most of the claim related repairs. However, the FSP is
required to pay the Applicants an additional amount of $6,603, which includes an
allowance for any additional costs and any general increase in costs.
Are the Applicants entitled to compensation?
As the FSP did not unreasonably delay the claim, the Applicants are not entitled
to compensation for loss of rent or non-financial loss.
1.3 Determination
This Determination is substantially in favour of the FSP.
The FSP is to pay the Applicants an additional amount of $6,603 in full and final
settlement of their claim. The Applicants are not entitled to any further payment.
Case No: 348168 Determination Page 2 of 8
2 Reasons for Determination
2.1 Did the FSP unreasonably delay settlement of the claim?
Neither party was solely to blame for the repair delays
A timeline of the key events which occurred during the claim process is set out in
section 3.2 below.
Having carefully reviewed the claim history, the Panel considers that there were a
number of factors which contributed to the extensive delays which arose during
the course of the claim.
Following the initial assessment of the property in September 2011, the FSP’s
assessor (C) sought further information from the Applicants and their builder (AP)
who had provided a quotation for the repairs.
The Panel accepts that it was reasonable for C to seek further information in
relation to the quote provided by the Applicants’ builde r (AP), so that the claim
could be settled in its entirety.
Nevertheless, the Panel considers that, with the benefit of hindsight, the FSP
could have authorised some elements of the repairs earlier, given that only certain
aspects of the quotation required clarification and in light of the widespread
damage caused by Cyclone Yasi.
However, at the time, the FSP and its assessor could reasonably have expected
that the outstanding issues would be resolved within a relatively short period of
time, rather than remaining unresolved for almost two years.
The Panel also acknowledges that C made genuine attempts to resolve the
outstanding issues and accepts that his attempts to do so were somewhat
hamstrung by delays and difficulties in contacting the Applicants. While the
Applicants were reportedly dealing with health issues and other Cyclone Yasi-
related matters, as a consequence there were extended periods of time during
which little or no progress was made in relation to their claim.
The available information i ndicates that the Applicants were also in contact with
their insurance broker and communications were variously directed between the
Applicants, their broker, various contractors and the assessor (C). This
undoubtedly further confused the lines of communication.
The FSP says that it was willing to have one of its authorised builders complete
the necessary repairs but the Applicants wanted to use a local contractor. When,
no agreement had been reached after two years, the FSP finally cash settled the
Applicants for $48,883.90 for the assessed costs of the remaining repairs, despite
the fact that the Applicants had not provided a signed release.
The Panel has considered the Applicants’ submissions that the FSP’s assessor
has been untruthful. However, having reviewed the copies of phone records,
contact letters and reports, the Panel is satisfied, on balance, that C made
genuine attempts to try and resolve the Applicants’ claim, including by repeatedly
Case No: 348168 Determination Page 3 of 8
seeking to make contact with them and obtain further information about the
outstanding issues.
In the Panel’s view, when taken as a whole, the FSP and its assessor managed
the claim appropriately. For the reasons outlined above, the Panel does not
consider that the bulk of the delays in settling the claim are primarily attributable
to the FSP.
Accordingly, the FSP is not liable for any losses suffered by the Applicants as a
result of these delays (including any additional damage to the property resulting
from the delay in commencing repairs).
2.2 Is the cash settlement paid by the FSP appropriate?
FSP acted reasonably in deciding to cash settle the claim
It appears that the FSP initially sought to arrange for the repair of the Applicants’
property in accordance with the terms of the policy, which provides for the repair
of the damaged property to its condition when new. However, when the FSP was
unable to finalise the scope of works for the repairs, it elected to cash settle the
Applicants for the cost of the repairs instead.
Having reviewed the claim history, the Panel is satisfied that, in the circumstances
of the present case, it was reasonable for the FSP to depart from its initial
decision to repair the damage to the Applicants’ property and offer them a cash
settlement instead.
Cash settlement amount should be increased
The Applicants’ policy provides that claims for property damage are to be settled
based on the cost of reinstating the property at the time the damage occurred.
The FSP has cash settled the Applicants for a total amount of $48,883.90 for the
repairs to the property (including $10,450 for the replacement of the air
conditioners and $2,859.82 for electrical repairs).
As set out in C’s letter dated 14 December 2014, t he remainder of the cash
settlement amount ($30,034.07) was based on quotations provided by the
Applicants ’ repairers (AP and TC) for the building repairs, reduced by allowances
for the repair of the skylights, the repair and repainting of the side wall and the
replacement of the car park door.
The Panel has carefully reviewed the available information, including the various
scopes of works and quotations provided, the re port of the Applicants’ engineer (I)
and C’s comments on I’s report .
Having done so, the Panel is satisfied that the FSP was not liable for issues such
as the moisture in the northern wall of the property, as the available information
does not establish that this was caused by Cyclone Yasi.
However, the Panel considers that the cash settlement amount is inadequate as it
excludes any allowance for the repair of the skylights, on the basis that this was
not included in I’s report. However, given that this i tem was included in C’s scope
Case No: 348168 Determination Page 4 of 8
of works dated 7 October 2011, the Panel considers that the FSP should be liable
for the costs of repairing the skylights (being $1,603, based on A P’s quotation ).
Further, the Panel considers that the cash settlement does not provide for the
replacement of the water damaged carpet in the front reception area, which was
identified in C’s scope of works. While AP’s quote includes a provisional
allowance of $800 for the cost of replacing the damaged carpet, AP subsequently
confirmed to C that this reference was a mistake and his quotation did not include
any allowance for carpet.
The Applicants have provided a copy of a quotation for $3,030 (excluding GST)
for replacement carpets. However, the Panel notes that this quotation covers the
cost of replacing carpet in the hallway, stairs and rear entry of the building as well
as the carpet in the front reception area. Accordingly, the quotation provided by
the Applicants exceeds the FSP’s liability for the damage to the carpet.
The Panel considers that, in the interests of finalising the claim, it is appropriate
that the FSP be required to pay the Applicants an additional amount of $6,603,
made up of:
an additional amount of $1,603 for the skylights; plus
a further amount $5,000 for the cost of replacing the carpet in the front
reception area, and to allow for any other minor costs that arise during the
repair of the property and any general increase in costs.
In arriving at this additional amount, the Panel has taken into account the delays
experienced during the claim process. In light of this, the FSP is not required to
pay interest on the additional amount.
2.3 Are the Applicants entitled to compensation?
Applicants are not entitled to compensation for loss of rent
The Applicants say that the FSP should be required to compensate them for loss
of rent as the property was ready to be rented out when it was damaged by
Cyclone Yasi and therefore they have suffered financial losses as a result of the
delay in settling their claim.
FOS does not have jurisdiction to consider the Applicants’ claim for loss of rent in
the context of the business interruption cover provided under their policy.
Accordingly, the Applicants are only entitled to compensation for loss of rent if
they have been unable to rent the property due to the FSP and its assessor
having unreasonably delayed the progress of their claim.
For the reasons outlined above, the Panel does not accept that the bulk of the
delays experienced during the claim process are primarily attributable to the FSP.
In the Panel’s view, the Applicants ’ own actions contributed significantly to these
delays.
Further, the Panel is not satisfied that the Applicants have attempted to mitigate
their loss, by taking all reasonable steps to progress the claim as quickly as
possible and restore the property to its pre-loss condition so that it can be rented
Case No: 348168 Determination Page 5 of 8
out. It appears that repairs were not commenced until at least mid-2014, despite
the Applicants having received a substantial cash settlement in April 2013.
In these circumstances, the FSP is not required to compensate the Applicants for
loss of rent.
Applicants are not entitled to compensation for non-financial loss
Under section 9.3(b) of the FOS Terms of Reference, compensation for non-
financial loss may be awarded where an applicant suffers an unusual degree or
extent of physical inconvenience, time taken to resolve the situation or
interference with their expectation of enjoyment or peace of mind.
In the present case, the Panel acknowledges that the ongoing nature of the claim
has undoubtedly been a source of significant stress and frustration for the
Applicants.
However, for the reasons outlined above, the Panel is satisfied that the delays
experienced during the claim process were not primarily attributable to the
inaction of the FSP or its assessor (C).
In these circumstances, the Applicants are not entitled to compensation for non-
financial loss.
Case No: 348168 Determination Page 6 of 8
3 Supporting information
3.1 FOS approach to dispute
This dispute has not been the subject of a FOS Recommendation. Due to the
nature of the dispute, it has been referred directly to a Panel for Determination, in
line with the Operational Guidelines to the FOS Terms of Reference. The Panel
consists of an Ombudsman and two representatives with consumer and insurance
experience.
The Panel has decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous Financial Ombudsman
Service (FOS) decisions.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other.
The Panel has reviewed and considered all of the material provided by the
parties. While the parties have raised a number of issues in their submissions, for
the purposes of this Determination the Panel has restricted its commentary to
those issues which it considers directly relevant to the outcome only.
3.2 Timeline of key events
Date Event
2 February 2011 Cyclone Yasi damage s the Applicants’ property .
March 2011 The Applicants say that at this time they tried to lodge a
claim with the FSP , but the FSP would not allow them to do
so o ver the phone .
Between April and
July 2011
The Applicant s lodge their claim with the FSP (the date of
lodgement is disputed).
July – September
2011
The FSP’s assessor (C) tries to arrange an assessment of
the property with the Applicants , reportedly calling and
sending letters.
A letter from C dated 11 August 2011 refers to a telephone
conversation with the Applicants on 27 July 2011 , following
which the y were to call C back . A letter from C dated 30
August 2011 refers to further attempts to contact the
Applicants .
The Applicants say they no longer use d the post office box
address to which C sent the letters and therefore they di d
not receive them . They say C should have tried to contact
them by email.
A n a ssessment of the property takes place on 15
September 2011 .
7 October 2011 C’s report to FSP provides scope of works and details of
three quotations for repairs obtained by the Applicants ,
Case No: 348168 Determination Page 7 of 8
Date Event
including a quote from AP for $40,096 for the building
repairs .
C requests a breakdown of costs from AP and a second
quotation from another builder ( D ) to validate the quote
provided by AP .
October 2011 -
February 2012
C receives a breakdown of costs from AP but seeks further
clarification in relation to some of the repairs.
In November 2011, the FSP writes to the Applicants
advising that it has authorised the replacement of the air
conditioning units but is still seeking further information
from AP .
There are delays in the Applicants providing the second
quotation requested by C , reportedly due to an illness in
the family .
C advises the FSP that it has emailed the Applicants
offering to arrange for a second quotation but they have
responded advising that they will provide the quotation
shortly.
March 2012 – July
2012
O n 14 March 2012, C writes to the Applicants advising that
unless the outstanding quotation s are received within 14
days, the claim wil l be closed.
The Applicants provide some additional quotations for
repairs which omit some of the items in C’s scope of works
and include other items not contained in C’s scope of
works.
C undertakes a further inspection of the property and
appoints an e ngineer to provide a report to clarify the
scope of works in relation to the front awning, roof and
skylights. C recommends a cash settlement due to the
Applicants’ failure to co - operate .
The Applicants provide a quotation from another repairer
(BW) for $115,623.20, which includes repairs that were not
included in C’s scope of works.
The FSP’s engineer (N) reportedly advises C that it has
tried contacting the Applicants three times to arrange an
inspection but the Applicants have advised that they do no t
want NCE to attend and will arrange their own engineering
report.
August – September
2012
C requests a copy of the Applicants’ engineering report .
November 2012 The FSP arranges m ake safe repairs for the awning at the
property.
C discusses the claim with the Applicants and the
Applicants reportedly agree to contact AP to check whether
the 2011 quotation is still valid . C emails the Applicants
outlining the issues which still require clarification.
C reviews the report provided by the Applicants’ engineer
(I) and advises that it does not change the scope of works
Case No: 348168 Determination Page 8 of 8
Date Event
in any significant way .
C proposes a cash settlement of $ 48,883.90 based on the
quotations obtained to date, including the quotation
provided by AP for the building repairs .
December 2012 –
April 2013
C sends details of the proposed settlement and a release
document to the Applicants (but acknowledge receiving the
settlement offer) .
C reportedly follows up the Applicants by email for their
response to the settlement off er.
C advises the FSP that the Applicants advised during a
telephone conversation that they had signed and returned
the release document. However, the signed release is not
received by C .
In March 2013 , the Applicants advise C that they will not
accept the settlement offer .
On 15 April 2013 the FSP cash settles the Applicants for
$48,883.90 for the outstanding repairs .
29 October 2014 The Applicants advise the FOS Case Manager that the
repairs are currently in progress.
The Applicants also advise that, at the time of the loss in
February 2011 , the property was ready to be rented out.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.