Home / Financial Firm (Unknown - Insurer) / Determination 346308

Determination 346308

Amount paid to repair malicious contractor damage and loss of rent claim

FirmFinancial Firm (Unknown - Insurer)
Decided2014-12-17
ProductGeneral Insurance · Landlord
OutcomeFor the complainant in part
Amount awarded$4,912
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

After a contractor damaged newly installed stumps at a rental property, the FSP accepted the claim but relied on its lowest repair quote. AFCA found that quote unreasonable, ordered an additional $4,911.67 for repairs plus statutory interest, and rejected the loss of rent claim.

A settlement cannot rely on a repair quote from a provider not prepared to perform the work, and loss of rent is payable only where the FSP agrees the property cannot be occupied.

Issues

Subjects and remedies

home or building damagepay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim Amount Determination Case No: 346308 Determination Page 1 of 6 Case number : 346308 8 Decemb er 2014 1 Overview 1.1 Dispute The Applicant held a landlord insurance policy with the Financial Services Provider (FSP). On 5 December 2012 the Applicant lodged a claim with the FSP for malicious damage to the property caused by a disgruntled contractor on 26 November 2012. The Applicant’s contractor had destroyed newly installed stumps with a sledgehammer. The FSP accepted the Applicant’s claim for replacement of the damaged stumps and rectification of resultant damage to internal parts of the property. A dispute has arisen over the amount paid to the Applicant by the FSP for repairs to the internal parts of the home and for loss of rent. This dispute has not been the subject of a Financial Ombudsman Service (FOS) Recommendation. Due to its nature, it was appropriate to proceed directly to a Determination in line with the Operational Guidelines to the FOS Terms of Reference. 1.2 Issues and key findings Was the amount paid by the FSP to repair the internal damage fair and reasonable? The amount paid by the FSP to repair the internal damage was not fair and reasonable because:  The FSP should not have relied on a quote from a provider who was not prepared to undertake the work. Is the FSP liable for loss of rent until the repairs are completed? The FSP is not liable for loss of rent until the repairs are completed because:  The policy only covers loss of rent for the period the FSP agrees the property cannot be lived in and for the reasonable time it should take to repair the property. Case No: 346308 Determination Page 2 of 6 1.3 Determination This Determination is partly in favour of the Applicant and partly in favour of the FSP. The FSP is required to pay the Applicant an additional $4,911.67 for repairs plus interest at the statutory rate from 17 December 2013 to the date payment is made in accordance with Section 57 of the Insurance Contracts Act (1984) . The FSP is not required to make any further payments to the Applicant in regard to loss of rent. Case No: 346308 Determination Page 3 of 6 2 Reasons for Determination I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties. There has been a full exchange of all documents relied on to make this Determination and each party has had the opportunity to address any issues raised by the other. 2.1 Was the amount paid by the FSP to repair the internal damage fair and reasonable? A number of different quotes were obtained The following quotes were obtained by the parties for the works: Date Provider Quote 3/9/13 CP (App) $25,300 6/12/13 IB (FSP) $16,841.71 6/3/14 JPF (FSP) $10,560 Undated BBS (FSP) $22,503.36 Initially the FSP cash settled the claim based on the lowest quote. It later increased the cash settlement to $16,636.69 based on the average of its three quotes. The Applicant considers the quote in the sum of $10,560 should not be used at all given the works cannot be completed for this sum and that his quote in the sum of $25,300 should be substituted instead. A provider must be prepared to undertake the work The FSP’s policy allows it to determine how a claim will be settled. It can decide whether to arrange for the property to be repaired or pay the reasonable cost for the work to be performed instead. It is not reasonable to include in a settlement offer a quote for works where the provider is not prepared to, or able to, undertake the works. Particularly when the quote is more than $6,000 less than the next comparable quote and more than $10,000 less than a third. Accordingly, the FSP should not have calculated the repair settlement using the lowest quote. Allowing the Applicant’s quote ($25,300) in place of the FSP’s lowest quote brings about an average of $21,548.36. In these circumstances I find that the FSP is required to pay the Applicant an additional $4,911.67 plus interest for the internal repairs. Case No: 346308 Determination Page 4 of 6 2.2 Is the Applicant entitled to loss of rent until the repairs are completed? The property was tenanted at the time of the loss The policy conditions for loss of rent during repairs state there must be a rental agreement in place that states the terms of the rental period and the amount of rent/bond the tenant needs to pay. The FSP has argued the Applicant has not been able to establish a rental agreement was in place at the time of the loss, however, the evidence indicates otherwise. The Applicant has provided a copy of the rental agreement in place for the period 1 November 2012 - 30 November 2012 indicating a monthly rent of $3,378.27 and bond of $4,518. He has also provided a Statutory Declaration to say the property was tenanted until 30 November 2012. The date of loss was 26 November 2012. The Applicant has therefore established the property was tenanted at the time of the loss (albeit with a pre-determined tenancy end date of 30 November 2012, four days after the damage was caused). The FSP must agree the property cannot be lived in The Applicant says the internal damage at the property has made it un-tenantable and it will remain so until all the necessary repairs have been completed. Accordingly, he considers he should be entitled to loss of rent from the date the damage occurred until the date the repairs are completed in full. In support, the Applicant has provided a letter from his Property Manager stating the property was advertised for rent on 5 December 2012 across four websites and, although there were several enquiries, prospective tenants were discouraged due to the damage to the property. However, the policy only covers loss of rent when the FSP agrees the property cannot be lived in and for the reasonable time the FSP considers it should take to repair. The property could be occupied There is no evidence to show the FSP at any time agreed the property could no t be lived in. A property will generally need to have sustained significant damage in order for it to satisfy this test. It is not sufficient that the property is not in a fit state to be re-tenanted - it must be unable to be occupied because, for example, it is unsound or unsafe. The evidence indicates the damage to the property was cosmetic in nature and did not affect the overall safety. Despite considering the Applicant did not have an entitlement, the FSP paid him an amount of $17,134 for loss of rent due to the delay in reaching an agreement over settlement for the repairs. This equates to approximately five months rental, which seems more than adequate given the evidence indicates the repairs to the premises were only cosmetic in nature. Case No: 346308 Determination Page 5 of 6 The Applicant failed to mitigate his loss Where a claim arises under the policy, the Applicant is required to take all reasonable and responsible precautions to prevent further loss in relation to his property, and to minimise the amount of the claim. The Applicant also has a duty at law to mitigate his loss. The Applicant received the sum of $16,636 to complete the internal repairs. Whilst the Applicant has established the work more than likely could not have been completed for the sum paid by the FSP, there is no e vidence to indicate the property could not at least have been repaired to an extent that would allow it to be re-tenanted. The Applicant has therefore failed to mitigate his loss. Accordingly, the FSP is not liable to make any further payments to the Applicant for loss of rent. Case No: 346308 Determination Page 6 of 6 3 Supporting information 3.1 Key documents  FSP’s Product Disclosure Statement  Scope of works inspection report (S) 22/2/13 (FSP)  Quote (CP) 3/9/13 $25,300 (Applicant)  Quote (IB) 6/12/13 $16,841.71 (FSP)  Quote (JPF) 6/3/14 $10,560 (FSP)  BBS Estimator Budget (undated) $22,503.36 (FSP)  Fourth extension of residential tenancy agreement 20/10/10 (App licant)  Fifth extension of residential tenancy agreement 24/9/12 (Applicant)  Bank statements August, September and October 2012 (Applicant)  Letter from Property Manager 16/7/13 (Applicant)