Home / Financial Firm (Unknown - Insurer) / Determination 345975

Determination 345975

Dispute over cash settlement for water damage and kitchen bench top

FirmFinancial Firm (Unknown - Insurer)
Decided2014-12-19
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed for water damage to his home and a kitchen bench top and sought compensation for claim handling. The FSP had cash settled the claim for $10,287 in total and AFCA found it had met its policy obligations.

The policy allows the FSP to cash settle, the cash settlement covered the quoted repairs, and the bench top damage was not shown to be caused by the leaking pipe.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building – Home Contents - FSP Decision - Claim Amount Determination Case No: 345975 Determination Page 1 of 6 Case number : 345975 1 6 December 2014 1 Overview 1.1 Dispute The Applicant lodged a claim with the Financial Services Provider (FSP) for water damage sustained to his home as a result of a leaking pipe on the 7 April 2013. Although the FSP accepted the claim, the dispute has arisen as to the extent of the damage sustained and the FSP’s claim handling . The Applicant seeks payment of the costs of replacing his kitchen bench tops and compensation. 1.2 Issues and key findings Is the FSP liable for the Applicant’s bench top ? The FSP is not liable to meet the cost of repair to the bench top because there is no evidence the bench top was damaged due to the leaking pipe. Has the FSP met its obligations under the terms of the policy? The FSP has met its obligations under the terms of the policy because :  the policy provides that the FSP may repair, replace or cash settle the Applicant’s claim  the FSP has provided cash settlement to the Applicant with respect to the damage sustained. Should the Applicant be awarded compensation? The Applicant has not established entitlement to compensation pursuant to paragraph 9.3 of the Terms of Reference in support. 1.3 Determination This Determination is in favour of the FSP. The FSP has met its liability in accordance with the terms and conditions of the policy. The Applicant has not established an entitlement to compensation pursuant to paragraph 9.3 of the Terms of Reference. Case No 345975 Determination Page 2 of 6 2 Reasons for Determination There has been a full exchange of material between the parties and each party has had an opportunity to address the issues that arise from the material exchanged. This Determination follows consideration of all of the material exchanged and is based on what is fair in all the circumstances having regard to relevant legal principles, terms of the policy, good industry practice and prior Determinations where relevant. 2.1 Is the FSP liable to meet costs of replacing the Applicant’s bench top? The FSP is not liable to meet the cost of replacing the Applicant’s bench top The Applicant lodged his claim against the FSP on 7 April 2013 because of water damage due to a leaking pipe. The Applicant previously lodged a claim for water damage as a result of a leaking pipe on 18 January 2013 which had been settled by the FSP. In lodging the second claim, the Applicant included items such as the kitchen floor tiles and a lambs wool carpet that had been settled from the previous claim on 18 January 2013. The FSP accepted liability with respect to the damage sustained as a result of the leaking pipe on 7 April 2013. Various attempts were made to settle the dispute. The FSP ultimately paid the Applicant the sum of $5,230.30 (on top of the $5,056.70 payment rejected by the Applicant), which incorporates a number of quotes obtained by the Applicant (plasterer, electrician, painter, builder and accommodation). The FSP also allowed for kitchen cupboards and carpentry work. The Applicant maintains however, that the FSP should be liable to meet the cost of replacing or repairing the kitchen bench top. The Applicant contends that it was damaged as a result of the leaking pipe. The Applicant provided a brief letter from a kitchen building company (KE) in relation to the bench top. KE said the bench top was warped due to the water damaged cupboard beneath it. However, the building company utilised by the FSP (UBS) negated this by providing an explanation of why this is not the situation. I have considered both explanations. KE has not explained how water from the leaking pipe would have caused the bench top to warp. UBS has provided an explanation as to why the damage to the bench top was not due to the water from the leaking pipe. Case No 345975 Determination Page 3 of 6 In my view it is unlikely that the bench top was warped due to the water damage to the cupboards beneath it. I prefer the opinion of UBS. I accept that the bench top was not damaged as a consequence of the leaking pipe. The FSP is not liable to meet the Applicants for the cost of repair or replacement of the kitchen bench top. 2.2 Has the FSP fulfilled its obligations toward the Applicant with respect to his claim? The FSP has met its liability under the terms of the policy The policy provisions allow for the FSP to cash settle a claim, if it elects to do so. The FSP chose to cash settle the claim. The FSP has paid an additional amount of $5,230.30 on top of $5,056.70 paid to resolve this dispute. This additional amount takes the total payment to $10,287, which includes UBS’s outline of the repair work required (email dated 29 August 2013), in addition to the various quotes obtained by the Applicant. The Applicant has made a number of comments abo ut the condition of his kitchen. However, without documents in support, these comments do not establish the FSP’s payments fall short of what is require d to repair the Applicant’s home following the water leakage in April 2013. The cash settlement is sufficient to cover the quoted repair work. In the circumstances, without evidence of further damage, the cash settlement meets the FSP’s liability under the policy. 2.3 Should the Applicant be awarded compensation? The Applicant is not entitled to compensation pursuant to paragraph 9.3 of the Terms of Reference. The Applicant is seeking compensation because of the FSP’s handling of the claim. The Service’s T erms of Reference (TOR) provide that compensation may be awarded to an Applicant for a non-financial loss to a maximum of $3,000. The TOR states that compensation will only apply where there has been an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred. The Applicant has indicated that the claim process has caused him stress and that, since the damage has not yet been repaired, his health has deteriorated. The Applicant has provided a brief note from his doctor, however there is no proof of a link between the Applicant’s health and the environment in his home. The FSP arranged for a company (SA ) to test the Applicant’s home for possib le air contamination. SA asked a laboratory to test the samples taken from the Applicant’s home and concluded there was no evidence of mould spore growth detected. Case No 345975 Determination Page 4 of 6 Based on the information exchanged there is no evidence to establish the leaking pipe caused air contamination or mould growth within the property. Whilst there were some delays in the resolution of the claim the Applicant is expected to be moderately robust and bear a normal degree of inconvenience when problems do arise. The majority of the issues that have caused delay arise from the Applicant’s dispute as to the extent of the damage suffered. I am not satisfied that the Applicant has established that due to the FSP’s conduct there was an unusual degree of physical inconvenience or time taken to resolve the situation. Case No 345975 Determination Page 5 of 6 3 Supporting information 3.1 Policy provisions “ How we settle your buildings claim We will choose to settle your claim for loss or damage to your home or 'other cover' in one of the following ways: 1. Arrange for repairers, builders or suppliers to repair or rebuild your home. If you agree, we can arrange for our preferred repairers, suppliers or builders to repair or rebuild your home. 2. Pay you the reasonable cost to repair or rebuild your home. We can choose to: ► pay you ► pay your nominated repairer, supplier or builder, or ► provide you with store credits from one of our nominated suppliers. For example, we may pay you directly when: ► you decide not to repair or rebuild your home, or ►you don’t start repairing or rebuilding your home within 6 months from when the damage takes place, or within any longer period we agreed to in writing. 3.2 Service ’s Terms of Reference Paragraph 9.3b) of the TOR states that: “Subject to paragraph 9.3c) [where a general insurance policy expressly excludes such liability] and paragraph 9.7 [cap on maximum value of remedy], [the Service] may decide that the Financial Services Provider compensate the Applicant for non-financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred; … … The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. ” 3.3 Expert Evidence Record Key points FSP’s expert – Building company (UBS ) Report dated 5 June 2014  There is / was no swelling of the bench top to the wall between the bathroom (where the leak was) and the kitchen where the disputed bench top is.  Before UBS removed the cupboards of the bench top to repair the wall, UBS noted – o there was no silicone or other seal between the bench top and the sink Case No 345975 Determination Page 6 of 6 o Applicant was renovating the kitchen – thus no wall tiles  UBS negated Applicant’s contention the floor had risen causing a noticeable lip between the sink and bench top – If the floor had risen, both the sink and cupboard would rise together as they sit on the same floor. Applicant’s expert – Kitchen Builders (KE ) Report dated 4 July 2014  KE has 3 0 years in the kitchen trade rep airing and replacing damaged cupboards .  It is necessary for the bench top to be replaced because it is warped as the result of having been lifted up at one end by the water damaged cupboard below .  The laminex bench top cannot be reused by screwing it down . FSP’s expert – specialised cleaning company (SA) Report dated 20 August 20 13  SA inspected kitchen cupboard framework and bench top regarding treatment for mould contamination and the repair method undertaken by UBS.  Five tape lift samples taken from cupboard, timber underside of bench top – no evidence of any visible microbial growth, nor was there evidence of any water damage or swelling. FSP’s expert – laboratory company (AAL) Report dated 20 August 2013  Analysed five tape lift specimens.  No evidence of mould spore growth. Information relied upon  UBS email dated 29 August 2013  FSP letter dated 10 June 2014  Applicant’s doctor’s letter dated 30 November 2013 .

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.