Text of the determination
Case No: 343010 Determination Page 1 of 8
Case number: 343010
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
11 July 2014
Summary
Description
This dispute concerns a claim lodged by the Applicants under a strata title
insurance policy issued by the Financial Services Provider (FSP) for storm
damage to a shade sail and awning structure at their apartment. The
Applicants are dissatisfied with the FSP’s proposal to cash settle them for
the cost of repairing the shade sail, as they believe that any repairs
undertaken will be effective in the short term only. The Applicants also
seek reimbursement for cost incurred in carrying out repairs during the
course of this dispute, in order to prevent further damage.
Basis of Determination
Once it elected to repair the shade sail, the FSP was obliged to ensure
that any works undertaken were effective to restore the shade sail to the
condition it was in prior to the storm.
The available information establishes that the shade sail was only three
years old at the time of the storm and therefore could be expected to have
continued to function for a number of years before requiring replacement
as a result of ordinary wear and tear.
The FSP’s settlement offer did not satisfy its obligations under the policy
because it was based on proposed repairs which were unlikely to last for
more than two or three years, and therefore were not effective to restore
the shade sail to its prior condition.
Determination
The FSP is to either repair the shade sail to the condition it was in prior to
the storm (including a five year warranty of the repairs), replace the shade
sail in its entirety or cash settle the Applicants for the costs of doing so.
The FSP is to reimburse the Applicants for costs they incurred in carrying
out repairs to the shade sail in February 2014.
Determination
Case No: 343010 Determination Page 2 of 8
Background
1. In February 2013, the Applicants lodged a claim under the policy for damage
to the shade sail and awning structure on the outdoor patio of their unit, due
to high winds on 27 January 2013.
2. After assessing the damage, the FSP accepted the Applicants’ claim and
obtained quotes for the repair of the shade sail. The quotes indicated that
the shade sail was repairable but the repairs would only be successful for
around two to three years.
3. The Applicants refused to authorise the FSP’s repairer to complete the
repairs as they were concerned about what would happen if the repairs
failed. The FSP then offered to cash settle the Applicants for $2,904, being
the cost of the repairs to the shade sail based on the quote provided by the
FSP’s repairer.
4. In February 2014, the Applicants incurred costs of $3,317.60 for temporary
repairs to the shade sail.
Summary of Applicants ’ position
5. The Applicants’ preference is for the shade sail to be repaired rather than
replaced due to the inconvenience associated with replacing the entire
structure. However, they are concerned about the FSP’s proposal to repair
the shade sail, given that the repairs are not expected to last for more than a
few years.
6. The Applicants are also dissatisfied with the FSP’s proposal to cash settle
them for the cost of the repairs, as this would result in the FSP having no
liability in the event that the repairs fail.
7. The Applicants want the FSP to agree that, if the attempted repairs are
unsuccessful or fail shortly after completion, then it will cover the costs of
rectifying the repairs or replacing the shade sail.
8. The Applicants say that they incurred costs to repair the shade sail in
February 2014 so as to prevent the existing damage worsening during the
storm season. However, by 1 April 2014, these repairs had already begun to
fail.
Summary of FSP’s position
9. The FSP says that:
under the terms of the App licants’ policy, it is entitled to determine how
to settle their claim;
Case No: 343010 Determination Page 3 of 8
it is not obliged to replace the shade sail, given that it is over ten years
old and the policy does not provide cover for loss or damage due to
wear and tear or gradual deterioration;
it chose to authorise repairs rather than replace the shade sail, as the
repairers’ quotes indicated that the shade sail could be repaired; and
when the Applicants indicated that they were unhappy with the
proposed repairs, it decided that the best approach was to cash settle
the claim instead.
10. The FSP says that it should not be liable for the repairs carried out by the
Applicants in February 2014 as it was not made aware of these repairs and
did not authorise them.
Issues
11. Whether the cash settlement amount of $2,904 offered by the FSP for the
damage to the shade sail complies with its obligations under the policy.
Reasons for decision
12. I am satisfied that an exchange of material information has taken place
between the parties and that each party has had the opportunity to address
any issues raised by the other.
13. The FSP has accepted liability for the damage to the shade sail and the
awning structure. However, the FSP and the Applicants disagree as to the
manner in which the claim should be settled.
14. The FSP has offered to cash settle the Applicants for of $3,738.24 in relation
to the damage to the timber awning structure, which the Applicants have not
disputed. However, the Applicants dispute the amount of the cash settlement
of $2,904 offered in relation to the damage to the shade sail membrane.
Proposed repairs to shade sail structure
15. After the Applicants lodged their claim, the FSP appointed a loss adjuster
(“E”) to inspect the damage. E reported that:
a section of the timber facade running around the area of the shade sail
had split;
a seam in the corner of the shade sail had come apart; and
the perspex sheeting attached to the timber framework surrounding the
shade sail had been pulled through the screw fixing points.
16. The FSP obtained quotes for the repair of the shade sail from two builders
as follows:
Case No: 343010 Determination Page 4 of 8
the first builder (“R”) provided a quote for $8,380.07 for the removal,
repair and replacement of the shade sail. R also provided a quote for
$26,042.25 for the complete replacement of the shade sail; and
the second builder (“T”) provided a quote for $2,904 (including GST) for
the repair of the shade sail.
17. The first builder (R) was unable to guarantee the repairs to the shade sail,
while the second builder (T) indicated that the repairs would be successful
for a period of two to three years only. T commented that:
he did not recommend removing the sail in order to fix it (as proposed
by R), as this risked damaging the surface of the sail, given the
estimated age of the sail membrane and the somewhat complicated
repair method suggested. Instead, he proposed applying fabric patches
to both sides of the membrane; and
while the repair may last longer than two to three years, the top coating
of the sail membrane deteriorates and therefore it was difficult to
predict whether the patches applied to the top side would adhere
properly. However, the bottom side of the sail was considered to be
okay and would also be patched.
18. The Applicants say that they have been told by other repairers that repairs to
the shade sail would last no longer than twelve months and that it should be
replaced.
Settlement obligations
Terms of policy
19. The strata title policy provides cover for accidental loss or damage to the
insured property, subject to the conditions and exclusions set out in the
policy.
20. Among other things, the policy excludes cover for loss or damage caused by
“lack of maintenance ..., Wear, Tear, fading, gradual corrosion or gradual
deterioration”. For the purposes of the policy, the expression “Wear, Tear” is
defined to in clude “damage or a reduction in value through age, ordinary
use”.
21. In settling a claim under the policy, the FSP may choose to either replace or
repair the damaged item or pay the insured the amount it would cost to
repair or replace the damaged item.
22. Accordingly, in accordance with the terms of the policy, the FSP was entitled
to decide to repair the shade sail and to seek quotations from qualified
repairers to undertake this work.
23. However, in order to comply with its obligations under the policy, the FSP
must ensure that the works undertaken are effective to “repair” the shade
sail.
Case No: 343010 Determination Page 5 of 8
24. The expression “repair” is not defined for the purposes of the policy and
therefore takes its usual and ordinary meaning, being “to restore to a good or
sound condition” (as pe r the Macquarie Dictionary Online). Given the
commercial intention of the policy, this requires restoring the shade sail to
the condition it was in prior to the storm damage.
Effectiveness of repairs
25. The issue in dispute is essentially whether the repairs proposed by the
FSP’s preferred repairer (T) are effective to satisfy the FSP’s obligations
under the policy, in circumstances where T has acknowledged that the
repairs may fail within two to three years.
26. The FSP says that the repairs proposed by T are sufficient to fix the storm
damage and restore the shade sail to the condition it was in prior to the
storm. The FSP says that it is not required to replace the shade sail, as it
was not new and had already deteriorated when the damage occurred.
27. While the FSP acknowledges that it would be obliged to replace the shade
sail in the event that it could not be repaired, it considers that this obligation
does not arise as the shade sail can be effectively repaired.
28. The FSP’s position is based in part on its under standing that the shade sail
was at least ten years old at the time of the storm. The FSP’s view is based
on the age of the sail as estimated by an employee of the repairer (T) who
was apparently involved in installing the shade sail and remembered that this
had occurred while the sail manufacturer was located at its previous
premises (and therefore must have occurred at least ten years previously).
29. The Applicants dispute T’s statement that the shade sail was at least ten
years old when the damage occurred. They say that they bought their unit
approximately two years ago and the shade sail was installed by the
previous owner, who lived at the property for three years. Accordingly, the
Applicants say that the shade sail was installed between 2008 and 2010 and
was therefore no more than five years old when the damage occurred.
30. In support of their position, the Applicants have provided a letter from a
building inspector dated 18 March 2010 which confirms completion of the
approval process for “structures” at t he Applicants’ unit. The FSP says that it
is not clear that this letter refers to the installation of the shade sail.
However, I consider that the fact that the letter is addressed to the director of
the building company which provided the quote for replacement of the shade
sail in June 2013 provides a reasonable basis for concluding that it relates to
the shade sail.
31. The Applicants have also provided copies of plans dated February 2008 for
renovations to the rear of their unit, which include the installation of the
shade sail.
32. I consider that the approval letter and plans provided by the Applicants
provides strong support for their position that the shade sail was no more
Case No: 343010 Determination Page 6 of 8
than five years old at the time the damage occurred. In this regard, I am
inclined to give more weight to the documentary information provided by the
Applicants than to the unsubstantiated recollections of T’s employee
regarding events which occurred some years previously.
33. In my view, the available information establishes that, on the bala nce of
probabilities, the shade sail was installed in or around March 2010 and was
therefore no more than three years old at the time of the storm.
34. There is limited information available regarding the expected life span of the
shade sail in circumstances where it was exposed to ordinary wear and tear
only, and did not suffer storm damage. The Applicants say that the shade
sail is of commercial quality and have estimated that it would ordinarily have
a life span of approximately 20 years, but have not provided any
independent information to support this.
35. Based on publicly available information regarding the anticipated lifespan of
sails constructed from the same fabric, I am satisfied that the ordinary life
span of the shade sail would have been significantly longer than the three
year period for which it had been installed at the time of the storm. In my
view, the likely life span of the shade sail would have been at least ten years.
Accordingly, had the shade sail not suffered storm damage, it is likely that it
would have continued to function for a significant period of time before
requiring replacement as a result of ordinary wear and tear.
36. In these circumstances, I do not consider that the FSP’s proposed approach
to repairing the shade sail is sufficient to comply with its obligations under
the policy, given that the repairs proposed repairs are expected to last for
two to three years only (at best). The FSP’s approach effectively provides for
the temporary repair of the shade sail, rather than restoring it to the condition
it was in prior to the storm.
37. The FSP says that requiring it to take responsibility for further repairs in the
event that the initial repairs fail (or requiring it to replace the shade sail) is
equivalent to requiring it to indemnify the Applicants for damage to the shade
sail caused by wear and tear.
38. I do not accept that this is the case. In the event that the FSP is required to
repair the shade sail following the failure of the initial repairs, this obligation
would only arise because the original repairs to the storm damage were
ineffective and required rectification, in order for the FSP to satisfy its
obligations under the policy. In this scenario, both the original and
subsequent repairs would be directed towards repairing the damage caused
by the storm (which is covered under the policy), not repairing other damage
caused by wear and tear (which is excluded under the policy).
39. For the reasons outlined above, I consider that, under the terms of the
policy, the FSP is obliged to repair the shade sail to the condition it was in
prior to the storm – that is, so that the damage caused by the storm will not
reduce the anticipated life span of the shade sail in the ordinary course.
Case No: 343010 Determination Page 7 of 8
40. During the course of this dispute, the Applicants advised that they had
undertaken repairs to the shade sail themselves, in order to prevent the
existing damage being exacerbated during the upcoming storm season.
These repairs were undertaken in late February 2014 and by early April
2014 had already shown signs of failing.
41. The Applicants have provided a copy of an invoice for $3,317.60 (including
GST) for these repairs, which confirms that they were undertaken by the
FSP’s preferred repair (T). Given that the cost of these repairs is similar to
the earlier quote provided by T to the FSP, it is reasonable to assume that
the scope of works was also similar. The fact that these repairs are already
failing tends to indicate that the repair method adopted by T is ineffective to
permanently repair the storm damage.
42. Throughout the course of this dispute, the Applicants have indicated that
they are comfortable with the shade sail being repaired (rather than
replaced), provided that the repairs will be effective for a reasonable period
of time.
43. In the circumstances, I consider that the FSP should be given the
opportunity to arrange for the rectification of the repairs carried out by T to
the reasonable satisfaction of the Applicants, subject to the FSP (or the
repairer) warranting the repairs for a period of five years.
44. However, in the event that rectification repairs are undertaken and prove
unsuccessful (or if the FSP elects not to undertake rectification repairs), then
the FSP should be required to replace the shade sail or cash settle the
Applicants for the cost of doing so.
45. Given that I have found that the settlement offer made by the FSP was
inadequate, I consider that the Applicants acted reasonably in rejecting it on
the basis that they were concerned about the potential short-term failure of
the proposed repairs. In these circumstances, I consider that the FSP should
be required to pay interest on any cash settlement ultimately paid to the
Applicants.
Cost of repairs carried out to date
46. The FSP says that it should not be liable for the repairs carried out by the
Applicants in February 2014 as it was not aware of these repairs and did not
authorise them.
47. The policy states that the FSP’s approval is required before any repairs are
undertaken, other than emergency repairs of less than $2,000 which are
undertaken to minimise further loss.
48. I accept that the Applicants did not obtain the FSP’s consent before
undertaking the repairs. However, I am satisfied that they acted in good faith
when they arranged for the repairs to be carried out, so as to minimise the
risk of further damage during the storm season.
Case No: 343010 Determination Page 8 of 8
49. Further, I do not consider that the Applicants’ actions materially
disadvantaged the FSP, in circumstances where the repairs were carried out
by the FSP’s preferred repairer, and the costs incurred in doing so did n ot
significantly exceed the amount which would have been incurred by the FSP
had it carried out the repairs itself (or cash settled the Applicants for the cost
of the repairs).
50. Accordingly, I consider that the FSP should reimburse the Applicants for the
amount of $3,317.60 incurred in carrying out repairs to the shade sail in
February 2014.
Determination
51. On the basis of the available information I determine that:
within 28 days of the Applicants accepting this Determination, the FSP
should:
i. arrange for the rectification of the repairs carried out by T to the
reasonable satisfaction of the Applicants, subject to the repairer
(or the FSP) warranting the repairs for a period of five years; or
ii. replace the shade sail or cash settle the Applicants for the cost of
doing so;
in the event that the FSP elects to undertake rectification repairs and
such repairs are unsuccessful, then the FSP is to replace the shade
sail or cash settle the Applicants for the cost of doing so;
the FSP is to pay interest on any cash settlement paid to the Applicants
in respect of the shade sail, at the interest rate applicable under section
57 of the Insurance Contracts Act 1984 (Cth), calculated from the date
of 18 December 2013 until the date of payment; and
the FSP is to reimburse the Applicants for the amount of $3,317.60
incurred in carrying out repairs to the shade sail in February 2014.