Determination 341861
Additional Cyclone Yasi damage (roof battens, electrical work) claim refused beyond FSP's accepted settlement
Summary
The applicant sought further cyclone damage costs for roof battens and electrical work after the FSP settled the original claim. AFCA found he had not established the roof damage was caused by Cyclone Yasi and found the FSP's $4,653.33 electrical settlement reasonable.
The applicant bears the onus of proving the additional damage arose from the insured event, and the contemporaneous engineer's report of no batten lift was preferred over later reports prepared years after the cyclone.
Issues
- Claim denial primary · not upheld
“I am not satisfied that the Applicant has met his onus to establish that the additional damage is related to the insured event of Cyclone Yasi.”
- Claim amount dispute secondary · not upheld
“I am satisfied that the FSP's acceptance of the claim for the rewiring... for the reduced amount of $4,653.33, is reasonable in the circumstances.”
Subjects and remedies
home or building damagenatural disasterno remedy
Text of the determination
Case No: 341861 Determination Page 1 of 5
Case number: 341861
General Insurance - Domestic Insurance - Home Building - Extent of Damage
due to Insured Event - Service
7 October 2014
Background
1. The Applicant holds a home building insurance policy with the Financial
Services Provider (FSP), which was current at the time of the loss. Cyclone
Yasi caused damage to the Applicant’s home and as a result, he lodged a
claim with the FSP on 3 February 2011.
2. The FSP accepted and settled the claim in accordance with the scope of
works a nd paid the Applicant’s preferred builder, based on his quote.
3. While carrying out the repairs, the builder said there was additional damage
due to the cyclone. The Applicant claimed for additional repair costs.
However, the FSP does not agree there was any additional damage due to
the cyclone. The Applicant wants the Service to review the FSP’s decision.
4. The dispute was considered by a Case Manager of the Service who issued a
Recommendation. In that Recommendation, the Case Manager determined
the dispute in favour of the FSP on the grounds that he was not satisfied that
the Applicant had established that the additional damage claimed was as a
result of the insured event.
5. The Recommendation was not accepted by the Applicant. Pursuant to
paragraph 8.5 c) of the Terms of Reference of the Service, the Applicant
requested that the dispute proceed to Determination.
Summary of Applicant’s p osition
6. The Applicant maintains that the additional damage to the roof is as a result
of Cyclone Yasi and not shrinkage as alleged by the FSP.
7. Further, the claimed electrical work also relates to Cyclone Yasi and should
be attended to under the terms and conditions of the policy.
Summary of FSP’ s position
8. The FSP maintains that it has provided coverage for the loss and damage
arising from the insured event and that the Applicant has not provided
Determination
Case No: 341861 Determination Page 2 of 5
sufficient evidence to establish that the claimed additional damage relates to
the insured event.
9. Further, the FSP maintains that it has been prejudiced by the actions of the
Applicant, first in refusing to allow the FSP’s experts access to further
assess the insured property and second by completing the electrical work
prior to the FSP’s experts having the opportunity to assess the loss and
damage claimed.
10. The FSP says that most of the additional items for which the Applicant is
now claiming resulted from wear and tear and this is excluded from cover. In
this respect, the FSP is relying on the following policy provision:
“ Section A – Home Cover
What you are not insured for
Under Section A – Home Cover, we will not pay for:
…
2. loss of or damage to your property caused by:
…
f. wear, tear, rust, corrosion, depreciation, gradual deterioration, mildew,
mould, dampness of atmosphere or variations in temperature;
…”
Issue
11. Whether the Applicant has established that the additional damage to his
home is covered under the terms and conditions of the policy.
Reasons for Decision
12. I have reviewed all of the material provided by the parties, together with the
reports which have been included within their respective submissions.
13. The Recommendation of the Case Manager has not been accepted by the
Applicant and as such, this matter will proceed to Determination in
accordance with the Terms of Reference of the Service.
“8.5 Dispute is resolved on the basis of the Recommendation.
c) If, within 30 days of receiving the Recommendation, either:
(i) The Financial Services Provider does not accept the
Recommendation in relation to the Dispute; or
(ii) Either party requests FOS to proceed from a Recommendation
to a Determination.
FOS will proceed to a Determination by either an Ombudsman or by
a FOS Panel (as the Chief Ombudsman or his or her delegate
decides is appropriate). Before the Determination is made, the
parties will be given a reasonable opportunity to make submissions,
Case No: 341861 Determination Page 3 of 5
and provide any further information, in response to the
Recommendation.”
14. Subsequent to the Case Manager’s Recommendation , both parties have
provided further submissions and reports and I have considered all of the
material as part of this Determination.
15. The law is clear in that the Applicant carries the onus to show that he has
suffered a loss which is covered under the terms and conditions of the
policy.
16. The Applicant says that he suffered a loss in that there was damage to this
home and the FSP accepted the Applicant’s loss and made payment to the
Applicant in respect to the necessary repair.
17. The Applicant says that during the course of the repairs, he was advised of
additional damage as a result of Cyclone Yasi and he now seeks for the cost
in respect to the additional damage to be met by the FSP, under the terms
and conditions of the policy.
18. I am satisfied that it is the Applicant who carries the onus to establish that
the additional damage arises from the insured eve nt and is covered by the
terms and conditions of the policy.
19. In respect to the roof of the home, there is significant disagreement between
the parties as to the cause for the separation of the roof battens, from the
supporting rafters.
20. On the one hand, the Applicant says that the cause of this problem was the
Cyclone winds, whereas on the other hand, the FSP maintains that the
problem is related to timber shrinkage and/or poor construction techniques.
21. Within the Recommendation, the Case Manager was not satisfied that the
Applicant had established that the problem was related to Cyclone Yasi. This
conclusion was based upon the Case Manager’s consideration of the
numerous reports and submissions made by the respective parties.
22. Subsequent to the Case Manager’s Recommendation, the Applicant has
provided a further report from the structural engineer, which provides a
detailed analysis and numerous calculations in respect to the separation of
the battens.
23. The structural engineer reinspected the property on 11 April 2014, for the
purposes of the provision of the report.
24. The structural engineer concludes that there were too many examples of
batten separation of varying degrees of separation, combined with consistent
depths along the length of individual battens that make the cause of the
separation most likely to be due to uplift wind pressures from a major wind
event and that Cyclone Yasi is the most recent wind event to fit this
category.
Case No: 341861 Determination Page 4 of 5
25. The Applicant has also provided a further report from a builder to the effect
that the shrinkage of any timber is likely to have occurred at a much earlier
date.
26. I note that the report from the builder, on two occasions refers to Cyclone
Larry (March 2006) and makes no reference to Cyclone Yasi. Further, the
builder does not reach a conclusion that the problem was caused by the
insured event of Cyclone Yasi, but rather, simply that any shrinking of the
timber had stopped some time earlier.
27. On the other hand, the structural engineer is of the view that the only
explanation for the random lifting of roof battens, between post Cyclone
Larry and the present time, was the major wind event of Cyclone Yasi.
28. However, the structural engineer’s further report does not take into account
the FSP’s alternate submission of poor construction techniqu es.
29. I have difficulty with both the structural engineer and the builder’s reports to
the extent that they both reach their conclusions, at least partly on the basis
“it must have been” Cyclone Yasi. This, in my view, is quite different from
saying, “It was Cyclone Yasi.”
30. I am satisfied that there were other potential causes for the batten lift,
including poor construction which have not been adequately discounted.
31. Further and most significantly, I am not satisfied that the Applicant’s
structural engineer and builder, account for the comments of the Applicant’s
original engineer, who inspected the property only three months after
Cyclone Yasi.
32. The original engineer inspected the Applicant’s premises with the specific
purpose of assessing the impact, loss and damage of the high and
damaging winds from Cyclone Yasi.
33. At that time, the Applicant’s original engineer confirmed that the roof
sheeting was inspected and appeared sound and that the frame appeared
structurally sound.
34. There was no reference to batten lifting at that time. The first reference to
batten lifting occurs in excess of two years after Cyclone Yasi.
35. Having considered all of the available evidence and including the further
reports from the structural engineer and builder, which were obtained by the
Applicant, specifically to explain the cause of the additional damage, I am
not satisfied that the Applicant has met his onus to establish that the
additional damage is related to the insured event of Cyclone Yasi.
36. The expert evidence contemporaneous in time to the insured event, the
report from the Applicant’s original engineer, confirms no batten lift.
37. I am satisfied that the report from the Applicant’s original engineer, prepared
within 3 months of the insured event, is to be preferred to the reports from
Case No: 341861 Determination Page 5 of 5
the Applicant’s subsequent engineer, prepared 32 and 40 months
respectively, post the insured event.
38. In respect to the second issue of the electrical work which is claimed by the
Applicant, I note that the Applicant has provided a report from an electrical
contractor which again relates to an inspection which occurred in excess of
two years after the date of the insured event, Cyclone Yasi.
39. It is difficult to understand how the property was inspected by engineers and
builders at a time reasonably proximate to the insured event, yet neither the
original structural engineer nor the original builder makes any reference to a
need for electrical work. It is only more than two years after Cyclone Yasi
that the Applicant has obtained a report seeking to replace substantial parts
of the electrical cabling to the property.
40. In this regard, I also note that the builder who engaged the electrician to
attend in 2013, advised that the electrical wiring was the old rubber wire
which would not meet the relevant statutory code.
41. This suggests that the wiring was old and in any event in need of updating.
42. Further, I note that the electrical work was completed prior to the FSP having
the opportunity to consider the claim for the electrical work.
43. Given my concerns regarding the delay in reaching a conclusion that the
electrical work was needed to be carried out and given the builder’s
commentary in respect to the age and compliance of the wiring, I am
satisfied that the FSP’s acceptance of the claim for the rewiring and the
replacement of the main switchboard for the reduced amount of $4,653.33,
is reasonable in the circumstances.
Determination
44. I determine that save for the settlement amount of $4,653.33, for the rewiring
and the replacement of the main switchboard, the FSP has otherwise met its
obligations in respect to the Applicant’s claim for loss and damage arising
from the insured event of Cyclone Yasi.