Denial of storm damage to brick piers and hallway tiles based on prior excavation and washing away exclusion
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of
claim
Determination
Case No: 341701 Determination Page 1 of 10
Case number : 341701 3 December 2014
1 Overview
1.1 Dispute
The Applicants lodged a claim under their home business insurance policy with
the Financial Services Provider (FSP) for damage to their property caused by
storms on or around January 2012.
The FSP accepted the Applicants ’ claim but denied liability for damage to the
brick piers in the sub-floor area (and resulting internal damage) on the basis that
this damage was not caused by the storm but by prior excavation works.
The Applicants dispute the FSP’s denial of liability and seek compensation for
financial losses incurred during the course of the dispute.
1.2 Issues and key findings
Is the FSP liable for the disputed damage?
The available information establishes that, on the balance of probabilities, the
disputed damage was caused by the effects of stormwater run-off which washed
away the soil around the brick piers. The FSP has not established that extensive
excavation works were conducted in the sub-floor area prior to the storm. As the
storm was the proximate cause of the damage, the exclusion for washing away
does not apply.
Are the Applicants entitled to any additional payments?
The Applicants are entitled to reimbursement of costs incurred in obtaining reports
from their engineer and surveyor, as these assisted in identifying the cause of the
damage. However, they are not entitled to reimbursement for legal costs or
compensation for loss of income.
1.3 Determination
This Determination is in favour of the Applicants.
The FSP is to pay the Applicants the amount of $6,530.21 (plus interest in
accordance with section 2.1 below) and to reimburse the Applicants for the
reasonable cost of repairing the hallway tiles, subject to the Applicants providing
an appropriate receipt. The FSP is to pay the Applicants a further amount of
$1,546 as reimbursement of professional costs.
Case No: 341701 Determination Page 2 of 10
2 Reasons for Determination
2.1 Is the FSP liable for the disputed damage?
Application of policy depends on cause of damage
The Applicants’ policy is a defined events policy which provides cover for damage
caused by one or more of the events listed in the policy (which include “storm,
rain or flood”) , subject to the exclusions and condition set out in the policy.
The policy contains an exclusion for “ landslide, subsidence, erosion, undermining,
washing away, or slippage ”.
The Applicants say that the disputed damage was caused by stormwater run-off
through the sub-floor area during the storms on or around 25 January 2012, which
eroded the soil around the brick piers, resulting in movement of the piers and
cracking damage to the floor tiles above. They have provided a report from their
engineer (CR) which supports their position.
The FSP does not dispute that there has been movement of the piers in the sub-
floor area. However, the FSP says that this movement was not caused by
stormwater run-off, but occurred as a result of extensive excavation works
undertaken in the sub-floor area prior to the storm, which destabilised the brick
pier. The FSP has also referred to the effects of ongoing subterranean water entry
over a prolonged period of time.
Alternatively, the FSP says that if it is accepted that the damage was caused by
stormwater run-off, then it is entitled to rely on the exclusion for washing away of
soil to deny the Applicants’ claim.
Available information establishes significant stormwater run-off occurred
The available information establishes that the Applicants’ property was affected
by significant stormwater run-off during the storm on 25 January 2012.
The FSP’s assessor (RM) who inspected the property on 6 February 2012 noted
that the area underneath the house clearly showed the path of the run-off. RM
noted that the property was subject to a steep slope from the rear to the front.
RM also reported that there was damage to the timber boundary fence at the
property, which the Applicants told him had occurred when stormwater run-off
from the rear of the property flowed down around the fence, washing out the soil
and exposing the concrete footings.
The FSP accepted the Applicants’ claim for stormwater damage to the boundary
fence. Accordingly, it appears that the FSP accepted that the extent of the
stormwater run-off resulting from the storms in January 2012 was sufficient to
wash away a significant amount of soil from this area.
Case No: 341701 Determination Page 3 of 10
There is conflicting information about the nature and timing of excavation
works in the sub-floor area
The FSP disputes the conclusions of th e Applicants’ engineer that the damage to
the sub-floor was caused by stormwater run-off. The FSP relies on a report
provided by its building consultant (DC) which states that the disputed damage to
the brick piers was caused by extensive excavation works carried out in the sub-
floor area, which destablised the brick piers.
DC’s conclusion that extensive excavation works had been undertaken at some
time in the past appears to have been based on the current state of the sub floor
area, as compared with the information shown in the site plans prepared when the
house was built approximately 15 years earlier. DC advised that, prior to the
excavation works, the footings would have been adequate (assuming the house
had been constructed in accordance with the site plans).
DC was unable to provide any more specific indication as to when the excavation
works he referred to had been carried out. In his report, DC says that the
Applicants had advised him that the works were undertaken by the previous
owner some time before they purchased the property two and a half years ago.
However, the Applicants have denied that they mentioned any such excavation
works to DC. They say that the only excavation works they are aware of at the
property are minor works which they carried out with a shovel after the storm in
January 2012, when they installed a temporary retaining wall in an attempt to
prevent any further damage.
It is possible that there was a misunderstanding between DC and the Applicants
during the discussion about the excavation works – for example, the Applicants
may have thought DC was referring to the initial excavation works carried out
when the house was built or, conversely, it is possible that DC misinterpreted a
comment by the Applicants about the temporary works they had carried out after
the storm. In these circumstances, it is inappropriate to place too much weight on
DC’s comments in this regard (particularly given the Applicants’ later statements).
It is also unclear as to what visual observations DC relied on in concluding that
extensive excavation works had been carried out prior to the storm. DC’s report
does not contain any photographs of the excavated area, which may have
provided further support for his views.
DC has subsequently stated that, based on his recollections of the site inspection,
the temporary retaining wall had been installed at the time the excavation works
were carried out, given the materials used and the fact that the brick piers would
have experienced major movement if they remained unsupported.
However, DC’s statement is inconsistent with the Applicants’ advice that they
installed the retaining wall after the storm (which is also supported by the report of
their engineer (CR)). Further, based on the condition of the retaining wall as
shown in photographs taken by CR in July 2012, it appears to have been installed
relatively recently.
Case No: 341701 Determination Page 4 of 10
In light of the issues identified above, I am not satisfied that the available
information establishes that extensive excavation works were undertaken in the
sub-floor area prior to the storm.
Damage was caused by stormwater run-off
The available information establishes that, on the balance of probabilities, the
damage to the sub-floor area (and the resulting damage to the hallway tiles) was
caused by the effects of stormwater run-off in January 2012, which washed away
the soil around the brick piers.
This explanation is supported by the findings of the Applicants’ engineer and is
consistent with the observations of the FSP’s assessor, as wel l as those of the
Applicants themselves. It is also consistent with the manner in which the damage
to the boundary fence occurred, which the FSP has not disputed.
While the FSP’s building consultant has attributed the damage to the effects of
prior excavation works, there is insufficient information available to establish that
extensive excavation of the sub-floor area was carried out prior to the storm.
Further, neither the FSP’s building consultant (DC) nor the Applicants’ engineer
(CR) has referred to any signs of past movement damage or prior repairs (either
to the brick piers themselves or the interior of the home), which might be expected
had the piers been subject to the effects of destabilising excavation works over a
period of several years. No such evidence is apparent from the photographs
provided.
Washing away exclusion does not apply
The policy states that the FSP “will not cover …. washing away”.
Given the terms in which this exclusion is expressed and the context in which it
appears, I consider that the exclusion should be interpreted narrowly, such that it
only applies to exclude cover where the washing away of soil is a proximate
cause of the claimed damage (ie a real, effective or predominant cause).
In the present case, the proximate cause of the disputed damage was stormwater
run-off, which is an insured event under the policy. In these circumstances, the
exclusion does not apply.
This is consistent with the FSP’s approach to the Applicants’ claim for damage to
the boundary fence, in respect of which it did not seek to rely on the washing
away exclusion.
FSP is to cash settle Applicants for disputed damage
For the reasons outlined above, the FSP is liable for the Applicants’ claim for th e
damage to the brick piers and the hallway floor tiles.
Both the FSP’s building consultant and the Applicants’ engineer have suggested
that the Applicants’ property is susceptible to ongoing movement damage due to
the features of the property, at least in the absence of improved drainage
Case No: 341701 Determination Page 5 of 10
systems. As noted abo ve, the FSP’s building consultant considers that the
ongoing issues may be more serious.
The Applicants have provided a quote for $6,530.21 from their builder (W) to carry
out the works recommended by the Applicants’ engineer. In the circumstances, I
consider that it is appropriate that the FSP cash settle the Applicants for the
amount of the quote, plus interest calculated in accordance with section 57 of the
Insurance Contracts Act 1984, from 21 June 2013 (being the date of W’s quote)
until the payment date.
The FSP should also indemnify the Applicants for the reasonable cost of repairing
the damage to the hallway tiles, subject to the Applicants providing an appropriate
invoice. The FSP is not required to pay interest on this amount.
2.2 Are the Applicants entitled to any additional payments?
Applicants are entitled to partial compensation for professional costs
incurred
Under paragraph 9.4 of the FOS Terms of Reference, FOS may require a
financial services provider to contribute to legal or other professional costs
incurred by an applicant in the course of their dispute. A financial services
provider will generally not be required to contribute more than $3,000 unless
exceptional circumstances apply.
The Applicants seek reimbursement for legal costs of $2,531 and engineer’s and
surveyor’s fees totalling $1,546, which they say they have incurred for the
purposes of progressing their dispute.
It was reasonable for the Applicants to obtain reports from an engineer and a
surveyor in order to r ebut the findings of the FSP’s building consultant. These
reports have also assisted in identifying the cause of the disputed damage.
Accordingly, the FSP is required to reimburse the Applicants for the cost of these
reports.
However, I am not satisfied that the nature of the legal issues raised in this
dispute required the Applicants to obtain legal advice. FOS provides a service that
is free for applicants and it is generally unnecessary for either party to be legally
represented. If an applicant chooses to be represented, they will usually have to
cover their legal fees themselves.
In the present case, the dispute revolved primarily around the cause of the
damage to the Applicants’ property. In these circumstances, legal advice is
unlikely to add significant substantive value. Further, the Applicants have not
provided any independent information (eg invoices) to substantiate the costs
incurred.
Applicants are not entitled to compensation for lost income
The Applicants seek compensation of $31,000 for income lost during the course
of the claim. They say that they have lost income as a result of the time devoted
Case No: 341701 Determination Page 6 of 10
to pursuing their claim, and that the female Applicant has been unable to carry on
her naturopath business at the property because the FSP advised that it would
not provide cover until the brick piers were repaired.
The Applicants did not have business interruption cover under their policy.
Accordingly, this aspect of their claim should be considered as a claim for
compensation for consequential financial loss, for which FOS is able to award
compensation of up to $3,000.
While the terms of the Applicants’ policy exclude cover for consequential loss of
any kind, this does not necessarily preclude the award of compensation for losses
which arise as a con sequence of the FSP’s handling of the Applicants’ claim,
rather than as a result of the insured event itself.
However, FOS generally only awards compensation for financial losses where an
applicant can show that they have actually incurred the amount claim ed or can
provide detailed inform ation substantiating a loss of opportunity. Compensation is not
generally awarded for the notional value of lost time expended in the course of
pursuing a dispute. Further, FOS expects an applicant to take reasonable steps to
minimise consequential loss.
In the circumstances, I am not satisfied that the information provided by the
Applicants is sufficient to justify an award of compensation for consequential financial
loss in the present case.
Case No: 341701 Determination Page 7 of 10
3 Supporting information
3.1 FOS approach to this dispute
As advised to the parties, the Financial Ombudsman Service (FOS) has
considered it appropriate to expedite the dispute in accordance with the
Operational Guidelines to the FOS Terms of Reference. Accordingly, this dispute
has not been the subject of a Recommendation and has proceeded directly to
Determination.
There has been a full exchange of all material information relied on for the
purposes of this Determination and each party has had the opportunity to address
any issues raised by the other. All of the material provided by the parties has
been reviewed for the purposes of this Determination.
While the parties have raised numerous issues in their submissions, for the
purposes of this Determination, commentary has been restricted to only those
issues which are considered to be directly relevant to the outcome.
This dispute has been decided on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions.
3.2 Terms of policy
Subject Terms
Storm We will pay for loss of or damage to your home, contents or both
caused by storm, rain or flood.
Exclusions – home
building
We will not cover: …
landslide, subsidence, erosion, undermining, washing away,
or slippage
General exclusions These are the policy exclusions which apply to all sections of
y o ur policy, unless otherwise specified.
We will not cover: …
Consequential loss
consequential loss of any kind including loss by delay,
confiscation or detention by customs or other lawful authority,
loss of market, lack of performance, loss of contract or
depreciation in the value of land and stock.
This does not apply to [section of policy which provides cover for
business interruption].
…
Existing damage
any existing dama ge which happens before this cover starts or
which arises from an event before the period of insurance cover
starts.
Case No: 341701 Determination Page 8 of 10
3.3 Report
Record Key points
FSP’s assessor (RM )
Report - 9 February
2012
The building is a two storey structure which is cut into the land
due to the steep slope of the site. It is two stories at the front
and a single storey at the rear. The building has been built on
brick piers.
The Applicants had advised that during the storms on 25
January 2012, stormwater runoff from the rear of the pr operty
flowed down the timber boundary fence adjacent to the
council walkway, washing out the soil and exposing the
concrete footings. The water had seeped through the ground
under the house exposing the dirt around the internal brick
piers.
There was also cracking to ceramic tiles in the hallway, which
the Applicants believed was not present prior to the storm , as
well as cracking to the concrete driveway where the water had
entered under the house.
He considered the proximate cause of the loss to be
consi stent with the Applicants’ description.
The area under the house clearly shows the path of the runoff.
A building consultant will be appointed to determine the fully
extent of the damage (if any) to the property due to the
stormwater runoff.
FSP’s building
consultant ( D C )
First r eport - 10 March
2012
The site has an extreme slope from the rear down to the front.
There was cracking to the hallway tiles and minor cracking to
the lounge room tiles in the south - eastern corner.
The sub - floor area below the hallway consisted of the garage
and a void area under the house.
His inspection of the garage revealed that one of the
laminated floor beams supporting the floor joists had deflected
by approximately 10mm, resulting in the cracking to the
hallway tiles .
His i nspection of the sub - floor area revealed that extensive
excavation works had been undertaken, causing instability to
the pier supports. The Applicants had advised that these
works were carried out by the previous owner and they were
not aware of th em when they purchase d the property around
two and a half years earlier.
There was extensive water ru n - through to the sub - floor area,
which was likely to be ongoing due to the slope of the block
and the retaining walls to the rear of the property.
The App licants had advised that they had installed a drainage
system to the rear retaining wall in an attempt to limit the
water unde r the house, but subterranean water penetration
was still being experienced during extreme weather
conditions.
Differential moveme nt of the foundations was occurring,
resulting in some packing of bearers between the piers. Most
of the piers required new foundations belo w the excavated
Case No: 341701 Determination Page 9 of 10
Record Key points
area to stabilis e and reduce any further movement.
T he cracking to the hallway tiles was the result of the
deflection of the laminated beam to the garage and the
differential mo vement of the sub - floor piers , due to inadequate
foundations as the result of the past excavation works.
Applicant s ’ engineer
( CR )
Report – October 2012
(as updated in May
2013 )
He had inspected the property on 23 February 2012 and
again on 6 May 2013.
Based on the soil profile of the sub - floor , he believed that it
had been adversely affected by excessive water run - off
coming through the subfloor area during the storm on 25
January 2012 .
Two of the sub floor brick piers had been adversely affected
by the water run - off. A third pier had become unstable since
his original inspection in February 2012.
The footings under the brick piers had not been affected by
the water run - off. The movement of the timber floor was within
normal limits.
Some temporary shoring had been installed to support the
sub - floor soil but this should be replaced with a 600 mm high
structural timber sleeper retaining wall. The drainage in the
rear yard shoul d also be improved.
FSP’s building
consultant ( DC )
Response to CR’s report
- 27 November 2013
He agreed with CR’s observations but noted that CR’s report
did not re fer to the fact that excavation works had been
carried out before the Applicants purchased the property, or
that the excavation works had affected the foundations of the
piers.
This should have been identified in the pre - purchase report .
In his opinion, the movement of the piers was the direct result
of the excavation works and ongoing subter ranean water
entry, which was long - term as indicated by the fact that the
previous owner had installed retaining walls and the additional
drainage installed by the Applicants had not stopped the water
entry .
FSP’s building
consultant ( DC )
Further response – 2
May 2014
He has reviewed the site plans provided by the Applicants.
He commented in his earlier report that the Applicants’ pre -
purchase inspection report should have identified this as the
footing for the piers has been structurally compromis ed and
well exceed the Australian Standards in relation to the zone of
influence.
The plans clearly identify the cut line and item 1 of the
engineering details specifies that the footings are to be at
least 450mmm from the batter toe.
The information on th e plans supplied would comply with the
requirements for the zone of influence
The excavation works have clearly exposed the footings,
resulting in inevitable movement.
His previous report and site notes do not address in detail
whether the retaining walls were installed before or after the
Case No: 341701 Determination Page 10 of 10
Record Key points
storm.
Based on his recollection of the site, and reviewing his
photographs, the retaining wall materials appeared to be
consistent with the time of excavation, otherwise major
movement would have occurred to the footing s as they were
unsupported (as shown in the engineer’s plan).
It is obvious that excavation works have been carried out as
the retaining walls in situ are not structurally adequate.
The presence of e xposed footings also confirm s that
excavation works have been carried out as these do not
comply with the engineer’s details on the plans .
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.