Home / Financial Firm (Unknown - Insurer) / Determination 341278

Determination 341278

Denial of loss of rent claim after hot water system leak damage

FirmFinancial Firm (Unknown - Insurer)
Decided2014-07-11
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The Applicant claimed loss of rent after water damage from a hot water system, arguing the property was not fit to rent while repairs were pending. AFCA found the policy requires the property to be uninhabitable, which it was not, so the FSP was entitled to deny the claim.

The policy wording is clear that loss of rent is payable only where the rental property is uninhabitable, not merely unfit for tenancy.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim-Exclusion/ condition Determination Case No: 341278 Recommendation Page 1 of 5 Case number : 341278 9 July 2014 1 Overview 1.1 Dispute The Applicant lodged a claim with the Financial Services Provider (FSP) for damage sustained to his investment property and lost rent. The FSP accepted the claim was one to which the policy responds in relation to the resultant damage caused by water leaking from a hot water system. However, the FSP denied the claim for loss of rent as the property remained habitable. The Applicant seeks a review of the FSP's decision to deny the claim for the loss of rent as the property was not in a fit state to be rented out until repairs were completed. Conclusions in Recommendation The case manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination The FSP accepted the Recommendation but it was rejected by the Applicant. Further submissions After the Recommendation was rejected, the Applicant made a further submission. He essentially restates his position and says: “if the insurance policy did not acknowledge the laws of QLD for renting houses, then the policy is not fit for purpose and should not have been sold.” He also says that: “After the loss adjustor “C”... attended the site to inspect, it was not until circa 20 April some 5 months after the damage that the builder (T) advised the loss adjustor “C” that they could not carry out the work and that other work needed to be completed (an email dated 22 April 2013 is attached). It is further noted that not only is no evidence in that communication that the builder (T) was able or willing to work with tenants, but he states that he is unable to complete the work until other works are completed. The property was therefore totally uninhabitable and the required work would now not be carried out by our insurers. This is why the insurers offered me a cash settlement, which we used to contribute to the costs of repairs by a local register ed builder.” Case No: 341278 Determination Page 2 of 5 The FSP made no further submissions after the Recommendation. 1.2 Issues and key findings Was the FSP entitled to deny the claim for loss of rent? The FSP was entitled to deny the claim for loss of rent because:  the condition of the property did not render it uninhabitable  the policy requires the property to be uninhabitable, not unfit for tenancy, for loss of rent to be payable  the property was not unfit for tenants because of the conduct of the FSP Determination This Determination is in favour of the FSP. The FSP is entitled to deny the Applicant's claim for loss of rent. Case No: 341278 Determination Page 3 of 5 2 Reasons for Decision As the Applicant rejected the Recommendation the dispute is referred to me for Determination. I have decided the dispute on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I have carefully considered the case manager’s Recommendation, together with the Applicant’s further submission. I am satisfied that the case manager’s Recommendation contains an accurate summary of the background to thi s dispute, the parties’ positions, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. I agree with the case manager’s reasons for the Recommendation and the recommended outcome. The Applicant’s post-Recommendation submission does not advance the Applicant’s case or aff ect the outcome as he essentially restates his position which I do not accept for the reasons stated. I have considered the further information, but it does not change my view that the case manager’s Recommendation was correct. 2.1 Was the FSP entitled to deny the claim for loss of rent ? The policy terms are clear and unambiguous - the policy requires the property to be uninhabitable before the loss of rent benefit is payable The FSP was entitled to deny the claim for loss of rent as although the property sustained water damage, which event is covered under the terms of the policy, in order to claim lost rent the Applicant must show the rental property is uninhabitable. The Applicant says the property was un-tenantable but I do not accept that this is the relevant test. The policy is clear and unambiguous in this regard. For loss of rent to be paid, the property must be uninhabitable. The Applicant says the policy is not fit for the purpose. I ha ve carefully considered the renewal letter dated 26 July 2012 and the policy itself. I am satisfied that the policy clearly explains the cover provided and its limitations. The Applicant does not dispute he received the policy so I am satisfied that he received it before the loss. I also note that the letter dated 26 July 2012 specifically directs the Applicant to read the policy to “confirm (your) revised cover meets your insurance needs.” Case No: 341278 Determination Page 4 of 5 It is accepted insurance law that the onus rest with the policyholder to ensure the policy purchased meet their needs and that the policy must be read in its entirety to gain a complete understanding of the cover. In all the circumstances I am satisfied that the Applicant was or should have been well aware of the policy terms and limitations. The damage sustained to the property did not render it uninhabitable I have carefully considered the material provided about the state of the property. I am satisfied that the HWS leaked and damaged the property but I am not satisfied that the damage was to such an extent that the property was uninhabitable. The replacement of the HWS was never the responsibility of the FSP. The policy makes this clear. The photographs taken by the assessor show the limited damage to the property. The FSP acted promptly. It arranged for the property to be assessed and the assessor arranged for the builder T to commence repairs within a short time after the claim was made. Both the assessor and T say the property was habitable. I accept that the HWS could be replaced before the other repairs were done and that the hot water would only be off for a short time. And, in any event, as the extract from the policy as set out below shows, the replacement of the HWS was not the responsibility of the FSP. The property was not uninhabitable because of delays by the FSP After the Recommendation, the Applicant submits that the property was uninhabitable because of the delays by T. I accept that T said he would not commence work until other non claim works were done. In fact, for this reason the FSP cash settled the claim. I do not accept on the material provided by the Applicant that T only advised he would not carry out the work until “circa 20 April”. The email provided dated 22 April 2013 is not persuasive evidence of that. Rather although it talks of advice from T to the Applicant about what other repairs had to be done, it is an email written to the assessor mainly to address the question asked about the replacement of the HWS after the resultant damage had bee n completed. On the information provided and for the reasons stated the FSP is not obliged to pay the claim for lost rent. 3 Supporting information 3.1 Policy wording Additional benefits We will cover We won't cover Loss of rent (continued) When:  loss or damage to your buildings occurs as result of an event as listed in this Policy If your rental property is habitable and you can safely gain access to your rental property. Case No: 341278 Determination Page 5 of 5 Event We will cover We w on’t cover Water or liquid damage Loss or damage cause by water or liquid escaping from:  A fixed pipe or an object attached to a pipe, fixed gutter, fixed tank or a drain ... ... Cost of repairing the item from which the water or liquid escaped. 3.2 The assessor’s (C) reports , letters and emails. I note the following from the material provided:  the tenants left the property on or about 23 November 2012  in an exit inspection at that time it was noted the HWS leaked  the claim was made 7 February 2013  C attended to inspect the premises on 11 February with T a builder  C took photographs of the damaged floor and vanity and HWS  C provided a report dated 18 February 2013 in which she advised the FSP to accept the claim for the resultant damage  C noted damage to the back portion of the property - flooring and the laundry/bathroom area, vanity and the cupboards where the HWS was kept  C knew the insured wanted to re- lease the properly and so attended with T to ensure repairs could commence promptly  T provided a quote for $9,419.33 to do repairs in the bathroom and toilet  C authorised T to commence the works  The HWS could be installed prior to the resultant repairs being undertaken and T did not advise the insured otherwise  In any event the HWS was not covered and was not work T quoted to do  The hot water would have been turned off for only a short time  The property was habitable when assessed and would have been habitable during the repairs  T was not to commence repairs until certain other maintenance items were done by the insured – this did not include the HWS as its replacement was not covered under the policy  Because of this, a cash settlement was recommended and all the work was done by the insured using the cash settlement  C noted there was another bathroom in the house that could be used during repairs Recommendation General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim - Exclusion/Condition Recommendation Case No: 341278 Recommendation Page 1 of 3 Case number : 341278 20 May 2014 4 Overview 4.1 Dispute Financial Ombudsman Service The Applicant lodged a claim with the Financial Services Provider (FSP) for damage sustained to his investment property. The FSP accepted the claim was one to which the policy responds in relation to the resultant damage caused by water leaking from a hot water system. However, the FSP denied the claim for loss of rent as the property remained habitable. The Applicant seeks a review of the FSP's decision to deny the claim for the loss of rent as the property was not in a fit state to be rented out until repairs were completed. 4.2 Issue and key findings Was the FSP entitled to deny the claim for loss of rent? The FSP was entitled to deny the claim fo r loss of rent because:  the condition of the property did not render it uninhabitable  the policy requires the property to be uninhabitable, not unfit for tenancy, for loss of rent to be payable. 4.3 Recommendation This Recommendation is in favour of the FSP. The FSP is entitled to deny the Applicant's claim for loss of rent. Case No: 341278 Recommendation Page 2 of 3 5 Reasons for Recommendation 5.1 Was the FSP entitled to deny the claim for loss of rent ? When lodging a claim for consideration, the onus lies with the Applicant to demonstrate, on the balance of probabilities, the loss claimed is as a result of an event insured against under the policy. This is called a prima facie claim. Only once this has been established, does the onus transfer to the FSP to show, on the balance of probabilities, some or all of the loss claimed falls within an exclusion of the policy or is somehow otherwise not covered. As it is not in dispute the Applicant's property sustained water damage, which is covered under the terms of the policy, he has been able to establish a prima facie claim. The damage sustained to the property does not render it uninhabitable The damage to the Applicant's property was first noticed during an exit inspection by the managing agent on 23 November 2012. A claim was lodged with the FSP on 7 February 2013. Following lodgement of the claim, the FSP appointed a loss adjuster (C) to attend the Applicant's property and report on the extent and cause of the damage. C was satisfied the loss was one to which the policy responds. When C attended the Applicant's property, she was accompanied by a builder (T) who provided a scope of works. The Applicant asserts T informed him the hot water system could not be installed until such times the resultant damage had been attended to. C sought clarification from T who denied such advice had been given to the Applicant. The Applicant has not provided any independent evidence to suggest this would be the case. Whilst accepting there may have been inconvenience to any tenant, in that the hot water supply would have to be disconnected for a short period of time on the day the replacement system was installed, this in itself does not render the entire property uninhabitable. T was prepared to work with any tenant to reduce any inconvenience to him/her. The policy requires the property to be uninhabitable before the loss of rent benefit is payable The Applicant argues the property was not legally tenantable, and therefore uninhabitable for tenants, under Queensland residential tenancy legislation. The Applicant has not provided any evidence of this. The policy wording is clear and unambiguous in that the property must be rendered uninhabitable, ie, unfit for human habitation, before loss of rent is payable. As detailed above, the property was not uninhabitable and therefo re, the FSP was entitled to deny the Applicant's claim for loss of rent. Case No: 341278 Recommendation Page 3 of 3 6 Supporting information 6.1 Policy wording Additional benefits We will cover We won't cover Loss of rent (continued) When:  loss or damage to your buildings occurs as result of an event as listed in this Policy If your rental property is habitable and you can safely gain access to your rental property.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.