Misstated construction finance amount and refinance delays

FirmFinancial Firm (Unknown - Credit)
Decided2015-03-19
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$2,250
Amount claimed—
SourceAFCA PDF

Summary

The borrower alleged the FSP misled him about construction finance when refinancing loans, delayed settlement and withheld final funds. AFCA found the FSP's $530,000 email was incorrect and one refinance was unreasonably delayed, and awarded $2,250 for non-financial loss, rejecting the other financial claims.

Misleading conduct requires reliance and detriment, so compensation reflects the loss caused rather than making the representation true, and unreasonable settlement delay attracts non-financial loss compensation.

Issues

Subjects and remedies

pay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 340744 Determination Page 1 of 1 Determination Case No: 340744 Determination Page 1 of 17 Case number : 340744 6 March 201 5 1 Overview 1.1 Dispute The FSP refinanced the Applicant’s loans held with three other financial services providers and advanced additional funds to finance the construction of a home on the V property. The Applicant says that, to encourage him to refinance his existing loans, the FSP misrepresented to him that it would lend him $590,000 for the construction of V property - but then advanced less. He says that the FSP then mismanaged the loans by delaying the advance of finance, withholding the final advance and failing to apply the interest rate discount it had offered to resolve his concerns. 1.2 Issues and key findings Did the FSP mislead the Applicant about the finance it would provide to construct a home on the V property? The FSP slightly overstated the net amount it would adva nce for the construction; however, this overstatement was not substantial in the context of the construction project. The FSP should have detected an error in the total refinance liabilities when it settled the loans, but failed to do so and consequently contributed to the Applicant’s stress and anxiety. I have awarded the Applicant $1,500 in non- financial loss compensation in this regard (for his stress and angst). Did the FSP unreasonably delay releasing finance? Under its finance offers accepted by the Applicant in February 2010, the FSP had agreed to advance a net amount of $435,000. It advanced most of these funds by the end of March 2010, but it delayed arranging the refinance of one loan by 12 weeks - which is outside what is considered to be consistent with usual industry practice. I accept that the FSP’s delay caused the Applicant to suffer stress. I have awarded non-financial loss compensation for the FSP’s contribution to the Applicant’s stress of $750. The Applicant appears to have overlooked $96,000 of redraw funds available to him but the information available in this dispute does not support a finding that the FSP caused that oversight. The FSP withheld a final payment of $5,000 but was entitled to do so under the standard terms and conditions applying to the loan. The FSP provided inaccurate Case No: 340744 Determination Page 2 of 17 information to the Applicant about this, but the Applicant did not suffer financial loss as a result. Did the FSP mislead the Applicant about the interest rate discount? The information available does not establish that the FSP misled the Applicant about the interest rate discount. 1.3 Determination This Determination is substantially in favour of the FSP. Should the Applicant accept this Determination within 30 days off its date (above), within a further 14 days of that acceptance, the FSP must pay him a total compensation amount of $2,250 (for the non-financial loss suffered by the Applicant). Case No: 340744 Determination Page 3 of 17 2 Reasons for Determination 2.1 Did the FSP mislead the Applicant about the finance it would provide to construct a home on the V property? The Applicant says that the FSP represented that it would loan him $590,000 for the construction of V property. The Applicant says that the FSP made the representation verbally. The FSP manager no longer works with the FSP and has not provided information in relation to this dispute. Broadly, to succeed in a claim for misleading conduct the Applicant must be able to show that:  the FSP made a statement or engaged in conduct that was false or misleading (misrepresentation),  the Applicant relied on that misrepresentation to change their position, and  the Applicant suffered detriment as a consequence. The information available does not establish that there was a misrepresentation about a loan amount of $590,000 The application for finance involved 6 loans from the FSP to allow the Applicant to access equity across 6 properties to support the finance of the construction. The V Property (where the construction was to occur) was vacant land and the FSP valued it on that basis for its loan to asset valuation ratios. A history of the loan application is set out in Section 3.3 of this Determination. The FSP offered the Applicant finance of $1.438 million which, after the refinance of the Applicant’s existing liabilities listed on the loan application, would leave about $520,000 for construction. The Applicant signed a building contract for $529,000 after receiving the FSP’s offers and an email from the FSP confirming an unconditional approval of $530,000. Based on this history, it seems likely that the Applicant and FSP had discussions about higher borrowings because the banker initially in November 2009, entered loan amounts that were significantly in excess of the final amount offered and appear to be based on 80% of the Applican t’s estimated values of the propert ies. The loan amounts were adjusted down after valuations for the security properties came in below these estimates. Further, it is evident that the Applicant planned to spend more than even the $530,000 mentioned in the email - because the original building contract excluded a number of basic components of the building such as plumbing, electrical work, doors, cabinetry, fencing, heating, air conditioning, painting etc. (noted as being completed by the owner) - and which the Applicant estimated would cost $60,000. The contract was also only to lock up stage and there was a swimming pool planned according to the planning permit. Case No: 340744 Determination Page 4 of 17 It is not apparent that the Applicant had access to other funds and it seems possible and likely that the Applicant and FSP had discussions about further advances once building had commenced. This could have involved revaluation of the V property and possibly other of the security properties to allow access to any additional equity- and, in fact this is what transpired in a fresh application for further funds in mid-2010. The relevant banker has left the bank - and so has not provided his account of events - and in those circumstances and in fairness to the Applicant, I have considered what information the Applicant was able to supply to support his claim. FOS is not a court and I cannot rely solely on the Applicant’s statement. The information available to me does not establish that the FSP had offered finance or guaranteed future finance to the Applicant in excess of the $1.438 million in the loan offers or the $530,000 in the email. In other words, on the basis of the available information and on the balance of probabilities - I am not satisfied the Applicant was misled by the FSP that loan funds of $590,000 would be made available. The FSP represented it would lend $530,000 for the construction The FSP represented to the Applicant that it would lend $530,000 towards the construction according to the email of 11 February 2010 (quoted in Section 3.3) and I accept that the Applicant relied on this when he signed a building contract for $529,000. The information in the email, however, was incorrect. Ultimately, the FSP’s offer of $1.438 million left only about $435,000 available for construction. There were two reasons for the difference between $530,000 and $435,000 ($95,000):  The Applicant had disclosed total liabilities of $917,439 in the application and, based on the loan offer, this left about $520,000 for the construction. So this was an error of $10,000.  When the FSP finally refinanced the Applicant’s liabilities, it paid out $1,001,579, so $84,000 more than was disclosed in the application. This is because the application did not include the Applicant’s investment home loan (account number ending **6508 for $71,000) and the Applicant’s line of credit (account number ending **7099) had increased by about $9,000. It is clear that t he FSP’s representation was incorrect , but it was only responsible for $10,000 of the incorrect information. The most substantial part of the error (90% of the difference) was as a result of the incorrect liability information in the application and the increased line of credit. The FSP is not responsible for the errors on the application form It is the responsibility of the Applicant to provide correct and fulsome information about his existing liabilities – given that he would reasonably understand that the FSP would be relying upon that information. Case No: 340744 Determination Page 5 of 17 The Applicant says the application only had room for 4 loans but he had disclosed all 5 loans to the FSP banker and had provided loan statements. The application form allowed the Applicant to list more than 4 loans later on the same page and in my view, it is more likely than not that the loan was omitted as a result of the Applicant’s oversight. Statements, however, may have highlighted an error. Under its policies, the FSP is required to obtain 6 months of s tatements for refinance liabilities. In this case, it has provided FOS with statements for two of the C bank loans but no statements for the other loans. Even so, the FSP’s obligation to obtain statements would have been limited to the loans listed on the application and the Applicant has not provided documentation which allows me to conclude he provided the FSP with the statements for the missing loan account. This means I cannot conclude that the FSP should have detected the missing loan account at that stage. The FSP should have become aware of the discrepancy when arranging settlement The FSP issued discharge forms for the V and P properties signed by the Applicant on 11 January 2010. The FSP has not provided any documentation showing what A Bank said in response or when it responded - but it is more likely than not that A Bank responded listing all three loans - including the missing loan of $71,000 and the increased balance of the line of credit. At settlement, the FSP paid out two loans – the line of credit ($229,046 compared to $220,507 on the application) and the missing loan with account number ending ** 6508 ($71,413). This second loan was on the FSP disbursement schedule and on the settlement statement but not on the application or on the settlement instructions. There is no documentation to explain what transpired at settlement , although it may be explained by the later FSP notes that say there was an issue with the spelling of the Applicant’s name on one title. Even so, had the FSP checked the account numbers and amounts against the original application, it may have noticed the discrepancy. In my view, the FSP should have done so rather than risk paying out a debt it was not authorised to repay: That is, the FSP should have checked with the Applicant. Notwithstanding this, the discrepancy came about because of the Applicant’s error originally and he was in the best position to realise the error given the liabilities were his - including the escalated line of credit balance. The Applicant should have taken the appropriate and prudent step of reviewing the loan offers against his existing liabilities. Consequently, it is reasonable for both the FSP and the Applicant share responsibility for the fact that the discrepancy was not noticed and the consequences of that. Case No: 340744 Determination Page 6 of 17 The FSP is liable to pay compensation of $1,500 The Applicant says that if he was aware of the reduced amount available, he would have taken an offer of $500,000 from A Bank or scaled back the construction. The bulk of the difference in the amount should have become apparent to the FSP later in February 2010 at settlement but this was after the building contract had been signed. The Applicant has not provided documentation to show that there was an offer from A Bank so - consequently I cannot conclude that he would have been able to stay with A Bank and access that finance. It may have been possible that the Applicant could have scaled back construction – although I note that there was the existing building contract in place. The Applicant ultimately realised the discrepancy in about June/July 2010, and the FSP approved additional finance in excess of even the original amount (of $590,000 that the Applicant thought he was receiving by the end of July 2010). So this mitigated the difference in finance. It is difficult to assess what would have been different for the Applicant if the FSP had alerted him to his errors in February 2010. This difficulty arises primarily because the build was always to cost substantially more than the original building contract - and so it is difficult to separate out what financial impact this - versus the impact of the discrepancy and its consequences - had on the construction timeframes. FOS does not provide a service where it can undertake a fore nsic investigation of a building contract. I do accept, however, that the FSP’s conduct (through its part in failing to alert the Applicant to the discrepancy) contributed to a highly stressful period for the Applicant in June/July 2010: However, as discussed above, the FSP was not wholly responsible for that stress for the reasons I have discussed above. In my view, in the circumstances it is appropriate for the FSP to compensate the Applicant for the FSP’s role in causing that stress by paying him non-financial loss compensation of $1,500. 2.2 Did the FSP unreasonably delay releasing finance? In addition to the shortfall as a result of higher than disclosed liabilities, the Applicant did not access some redraw funds - and there was a delay in one refinance settlement. There were also further loan applications assessed in mid- 2010, in respect to which some funds were advanced in July 2010 but a further loan was not advanced until September 2010. The final drawing of $5,000 has not yet been advanced. Case No: 340744 Determination Page 7 of 17 The Applicant did not access redraw funds available in loan account **700 There was about $98,000 available as redraw in loan account ending **700 which the Applicant did not access until the loan was refinanced into a consolidated loan in July 2010. The Applicant says that he did not know about these redraw funds but the statements issued to the Applicant over the period from drawdown in March 2010, showed the available funds. When each of the loans were drawn, the FSP paid some of the loan proceeds into the operating account when drawn whilst other proceeds were retained as redraw funds. This makes sense given the progressive-draw nature of the funds required by the Applicant: I note that the FSP did not control the disbursement of these funds – and so wa s not responsible for the Applicant’s oversight. There was redraw available under the loans for $49,000 and $77,000 which the Applicant accessed in May 2010. However, on 8 July 2010, the Applicant wrote to the FSP saying: “Could you pl ease call at your earliest convenience. There seems to be money not shown in our accounts I think this is about 280K. Can you please call ASAP to discuss as payments are due and not enough money in account. Also will need to look at refinance as at lockup be end of next week.” At this stage it is reasonable to expect that the FSP may have become aware of the undrawn funds and potentially the Applicant’s oversight - but this was overtaken by the need for finance above and beyond the redraw amount. The FSP commenced an application on 14 July 2010 and advanced additional funds of $100,000 beyond the available redraw on 23 July 2010. The FSP could have told the Applicant about the available redraw up to 2 weeks before making the new funds available, so allowing earlier payment to the builder to be made, however at the same time, given the Applicant’s urgency, it would be reasonable to expect that he would be checking his own statements and have detected the existence of the redrawn funds. I do not accept that there was any transfer of responsibility to the FSP for the Applicant’s failure to access these redraw funds. The FSP unreasonably delayed refinancing loan **5908 $28,000 of the loan funds approved by the FSP were not available until after mid May 2010 because of the delay with the final A Bank loan. The Applicant says that he signed the loan contracts in January 2010 but the FSP delayed 6 to 9 months in providing the loan funds. Section 3.3 of the Determination sets out the dates on which the loan contracts were signed and funding was released. From 10 February 2010 when the final Case No: 340744 Determination Page 8 of 17 contract was signed, settlement and funding of the relevant accounts occurred as follows:  account **655 (an unencumbered property) was financed within 1 week.  account **567 (an unencumbered property) was financed within 2 weeks.  account **463 (refinance) was financed within 2 weeks  account **727 (refinance) was financed within 5 weeks  account **700 (refi nance) was financed within 7 weeks, and  account **698 (refinance) was financed within 18 weeks. When FOS investigates claims of delayed refinancing we will consider whether the circumstances show that the refinancing was effected within a reasonable timeframe having regard to industry practice and the complexity of the refinancing. I conferred with the FOS Banking Industry Adviser regarding this dispute and his view is that settlement of financing of this nature involving discharging banks would usually occur within six weeks. For unencumbered properties, if the security arrangement are straightforward, the finance would be available earlier than this. Loan accounts **655, **567, **463 and **727 all fell within the “standard time frame expected” according to the FOS Banking Industry Advise r’s advice . Consequently, I am satisfied that there was no unreasonable delay in the settlement and finding of these loans. In relation to account **700, the FSP’s client contact notes indicate the involvement of a broker who created delays in obtaining responses from the discharging bank and there was a general lack of urgency from the discharging bank. It is apparent from the notes, however, that the FSP’s staff monitored the situation closely with continual attempts to obtain what was required for settlement and did not cause the one week excessive delay. The FSP says that the settlement associated with loan account **698 was delayed due to how the Applicant was described on the certificate of title and there was a further two weeks delay with the discharging bank (A Bank). The problem with the Applicant’s name, however, was first identified on 16 February 2010 but not actioned by the FSP until 20 May 2010 when the change of name forms were sent to the Applicant (see more detailed chronology in section 3.4 of this Determination). According to the FSP’s client contact notes 14 weeks passed with the settlement documents not being actioned. The FSP manager stated in the notes on 9 April 2010, that the “file has stopped” . Once the change of name forms were sent to the Applicant, they were returned and settlement was arranged within four weeks, in accordance with usual industry practice. In light of the factors identified above, it is my view that the delay in financing account **698 beyond the standard 6 week period was unreasonable to the extent Case No: 340744 Determination Page 9 of 17 of 12 weeks of the delay and the loan should have settled by about mid-March 2010 rather than mid June 2010. The FSP is liable to pay the Applicant $750 non-financial loss compensation In Section 3.4 of this Determination, I have compared the A Bank rate to the FSP rate. According to the A Bank statements and the history of the A Bank investment home loan rate, the Applicant was paying 0.7% below the standard variable rate. The comparison shows that the Applicant did not suffer any interest rate detriment as a result of the delay because the A bank rate was lower than the FSP rate. Given the relatively small amount of funds available from this refinance, I cannot calculate what different position the Applicant would have been in had he had these funds, although I do accept that the general lack of funds contributed to the Applicant’s overall stress and anxiety. In my view, therefore, the FSP should compensate the Applicant for $750 for this delay. There were no further unreasonable delays The FSP started the loan application for the additional approximate $100,000 on 14 July 2010 and the second loan application - it appears for a further approximate $300,000 - on 19 July 2010. The first application was approved and drawn by 23 July 2010 and the second (loan **132) was drawn on 17 September 2010 - releasing surplus funds of $250,000. It is apparent from the second loan that it was a construction loan and the FSP controlled the drawings. The application notes show that there were a number of valuations and a change in the amount. The time taken with this second application reflected the complexity of the fact that the Applicant was building a property for a cost more than the a vailable loan funds, and more than even the $530,000 the FSP had represented in its original email. The new application was a construction loan - which is more complex to assess - and required the FSP to control progressive payments. Based on my review, there was no inappropriate or unreasonable delay by the FSP in relation to this application. The FSP did not unreasonably withhold the final progressive payment The Applicant says that the FSP withheld the final drawing of $5,000 because it required a certificate of completion when the FSP previously informed him that it would be provided based on an occupancy certificate. In February 2011, the FSP agreed to pay the remaining funds available from the loan save for $5,000 which its internal notes say would be released for “ CTC [cost to complete] of NIL ”. The FSP provided a temporary overdraft limit of $5,000 on the Applicant’s account to cover additional costs. The FSP offered, as resolution of the FOS Case No: 340744 Determination Page 10 of 17 dispute, to refund interest for a maximum of 2 years or until it was paid out, whichever earlier. The Applicant did not accept the offer. The FSP says it refunded $91.28 of the $384.72 interest charged. Clause 4 of the standard terms and conditions includes: “(c) Final Inspection When the construction or renovation is complete, we will arrange a final inspection by a licensed valuer.” Under the terms and conditions, progress payments are payable based on an invoice and a progress inspection (at the FSP’s discretion) but as an owner builder, the Applicant is to provide a: “...report from a recognised independ ent professional with each progress payment request ...[which]... must address the points outlined below...  Provide an estimate of the work required to complete the project. If that amount is more than the undrawn loan available to complete the project, then we may require you to pay a further contribution from your own funds before you draw any of your loans...” In a file note faxed internally by the banker in mid October 2010, the banker wrote: The banker dealing with the relationship left the bank in November 2010 and in an email notifying the Applicant of this dated 2 November 2010, he included the comment: “...Your project is on track now. The process is that you will use the funds now available to get the home to certificate of occupancy stage... Please fax the certificate of occupancy to [FSP] when to hand, with a letter confirming home is complete and requesting the remaining funds be made available to you. She will confirm completion with a final inspection of the property. The loan should then revert to a normal home loan with redraw, so you can access the additional funds easily...” The occupancy certificate issued on 29 January 2011. There was a lack of clarity in relation to the certificate of occupancy and the certificate of completion, which appears to have misled the Applicant about access to the final $5,000. Even if misled, the remedy for misleading conduct is not to make any misrepresentation come true; rather we consider what position the Applicant would have been in but for the misrepresentation. But for the alleged misrepresentation, the Applicant would otherwise have had to source the funds Case No: 340744 Determination Page 11 of 17 and the FSP provided the funds through the temporary overdraft. Consequently, I cannot conclude that the Applicant has suffered any loss as a resu lt of the FSP’s conduct in this regard. The offer made by the FSP to refund interest was in the form of a resolution offer that the Applicant did not accept, so the FSP is not obliged to refund any additional interest. Case No: 340744 Determination Page 12 of 17 2.3 Did the FSP mislead the Applicant about the interest rate discount? The Applicant says that as part of the agreement to transfer his investment loans across to the FSP, the FSP agreed to discount the applicable interest rate by 1%. The Applicant believed this 1% discount was in addition t o the FSP’s existing discount of 0.7%. The documentation provided by the FSP shows it approved an increased discount of 0.3% to take the total discount to 1%. Neither party has provided documentation to show that the FSP approved a total discount of 1.7% or advised the Applicant of this discount. I accept that the Applicant may have been under a misapprehension that the discount was higher, but the information available in this dispute does not establish that this misapprehension was caused by the FSP. F urther, even if the explanation provided by the FSP was unclear and contributed to any misapprehension, again, even if misled, the remedy is not to make any representation come true, the question is – what loss was suffered in reliance upon the misrepresentation. The Applicant says that but for the alleged misrepresentation about the rate discount, he may have compromised his spending - but, based on the available information, I cannot establish this and so I cannot conclude he has suffered any loss as a result of his misapprehension. In summary therefore, I am not satisfied on the basis of the information available in this dispute - that there was a representation by the FSP that it would provide a discount of 1.7%: However, even if it could be shown that there was any confusion caused by FSP about the size of the discount, no loss has been established. Case No: 340744 Determination Page 13 of 17 3 Supporting information 3.1 FOS Approach Expedited Determination This dispute has not been the subject of a FOS Recommendation. Due to its nature, it was appropriate to proceed directly to a Determination in line with the Operational Guidelines to the FOS Terms of References. There has been a full exchange of material between the parties, and each party has had the chance to address any issues raised by the other. Assessment of disputes FOS is not a court of law. This means that FOS is not able to take evidence on oath. When presented with differing accounts of what occurred in a scenario, FOS will decide what was most likely to have occurred on the balance of probabilities, taking into account available contemporaneous documentation. Non-financial loss compensation FOS will only award compensation for non-financial loss where there has been an unusual degree or extent of inconvenience. Applicants are expected to:  be moderately robust in dealing with unexpected problems, and  take reasonable steps to reduce inconvenience. 3.2 Documents relevant to this decision In considering this dispute, I have taken into account all relevant information from the FSP and the Applicant, including the:  FSP’s contact client file notes  loan documentation, and  account statements. Case No: 340744 Determination Page 14 of 17 3.3 Loan details A review of the history of this loan application shows the following: Date Event Sept 2009 The FSP took applications for finance from the Applicant to finance six loans over six properties. There were a number of applications because each loan was to be matched against one property. In the application, the Applicant listed four existing loans w ith A Bank with a total debt outstanding of $917,439. The FSP originally entered total lending of $1.762 million . It seems this may have been determined on the basis of 80% of the estimated value of the properties. Late 2009/early 2010 The FSP conducted property valuations and as a number of the properties were valued below the original estimates, the FSP amended the application amounts down to total lending of $1.438 million . Based on the existing liabilities in the application, this w ould leave a net $520,561 available for the construction. Jan 2010 The FSP issued loan offers dated 18 November 2009 (for total finance of $1.438 million . 11 Jan 2010 The Applicant signed accepting all offers excluding the offer for $336,000. 10 Feb 2010 The Applicant signed accepting the final offer. 11 February 2010 The FSP sent an email to the Applicant “ This email confirms our recent discussions, I am pleased to confirm that your loan application for $530,000 is unconditionally approved. Thank you for completing the loan mortgage documentation.” 24 Feb 2010 The Applicant signed the building contract for $529,000 The loan application records that the Applicant had four existing loans at the time he lodged his application with the FSP. The liabilities listed totalled $917,439; The FSP approved the following loans relevant to this dispute: Loan offer Signed contract Account Number ending Contract Amount Security 18 Nov 09 11 Jan 10 **727 $280,000 S property 18 Nov 09 11 Jan 10 **700 $296,000 M property 18 Nov 09 11 Jan 10 **655 $49,000 T property 18 Nov 09 10 Feb 10 **698 $336,000 B property Case No: 340744 Determination Page 15 of 17 18 Nov 09 11 Jan 10 **567 $77,000 SR property 18 Nov 09 11 Jan 10 **463 $400,000 V property Total $1,438,000 When settling with A Bank, the FSP paid out the following amounts and disbursed the funds as follows: Financial Services Provider Refinance Amount Date paid/drawn Loan Account Available redraw Transferred to acc **767 B Bank $197,490 19 March 10 **727 $81,426 C Bank $196,359 30 March 10 **700 $98,626 A Bank 1 **7099 $229,046 25 Feb 10 ** 463 $99,301 A Bank 2 ** 6508 $71,413 25 Feb 10 **463 New Security SR property 24 Feb 10 ** 567 $76,902 New Security T property 16 Feb 10 ** 655 $49,000 A Bank **5908 $307,622 15 June 10 ** 698 $28,078 Totals $1,001,579 $126,704 $306,531 Subsequently the FSP provided additional finance as follows, part of which refinanced 3 of the existing loans and releasing additional funds of about $430,000 to the Applicant (including the $96,000 available undrawn in loan account **700): Account Amount Drawn Proceeds **276 $360,000 23 July 10 Paid out loan ** 698 ($308,377) ** 359 $344,000 23 July 10 Paid out Loan **700 ($205,173) **132 $650,000 17 Sept 10 Paid out Loan **463 ($401,662) Total $1,354,000 Case No: 340744 Determination Page 16 of 17 3.4 Settlement chronology Based on the FSP’s client contact notes, the events relevant to the settlement of account ** 698 are as follows: Date Event 10 Feb 2010 The loan contract is signed. 16 Feb 2010 The requirement to change the Applicant’s name on the certificate of title is raised by a FSP officer – some discussion ensues as to whether or not it is required – it is agreed that a change is required. 26 March 2010 The FSP manager requests that the change of name forms be sent to him. 9 April 2010 The FSP manager writes “this file has stopped”. He requests documents are sent to him. 19 May 2010 The FSP manager writes: “I have been asking for change of name forms since March!!! Please forward change of name forms and request SL M to rest on these docs. This should have settled already.” 20 May 2010 The change of name forms are prepared and emailed. 31 May 2010 Approval is required within FSP to extend the loan approval as the original offer has expired. The FSP manager writes: “This seems to be a comedy of errors and the interim loan docs have expired. [Discharging bank] are ready to settle and clients are most annoyed...” 1 June 2010 The FSP contacts the discharging bank to arrange settlement. 15 June 2010 Settlement is completed. Case No: 340744 Determination Page 17 of 17 Interest Rates FSP and A bank: Date FSP Int rate A Bank Int Rate 15 March 2010 6.31% 6.16% 9 April 2010 6.56% 6.41% 7 May 2010 6.81% 6.66%

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.