Storm damage claim: adequacy of settlement offer and delays

FirmFinancial Firm (Unknown - Insurer)
Decided2015-02-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$880
Non-financial loss$2,000
Amount claimed—
SourceAFCA PDF

Summary

The applicant's storm claim for internal and external damage was disputed in part, and the claim handling was delayed. AFCA ordered a revised scope of works with cash settlement, $2,000 for non-financial loss and $880 for an engineer's report.

Storm cover extends to subsidence occurring immediately after a storm, and unusual delay and claims handling causing a significant impact on peace of mind justify non-financial loss compensation under the Terms of Reference.

Issues

Subjects and remedies

home or building damagemental healthnatural disasterpay claimpay compensationpay non financial lossreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim Amount Determination Case No: 340647 Determination Page 1 of 15 Case number : 340647 3 February 2015 1 Overview 1.1 Dispute The Applicant‟s claim follows damage to his home by storm on 26 January 2013. The FSP accepted liability for the internal damage and partial liability for external damage. The Applicant has disputed the FSP‟s decision and in addition seeks payment for non- financial loss due to the FSP‟s poor claims handling process and the delays associated with his claim. 1.2 Issues and key findings Is the FSP’s offer to settle the Applicant’s claim for the internal damage reasonable? The offer to settle the internal damage claim is not reasonable because:  the offer does not take into account the likely additional costs incurred in rectifying damage to the ceiling as an asbestos ceiling. Is the FSP ’s limited offer to cover external damage reasonable? The FSP‟s limited offer for external damage is not reasonable because:  on the balance of probabilities that the damage to the foundations was caused during the event  the offer to settle does not include cost of rectification of the damage to the foundations. Is the Applicant entitled to compensation for non-financial loss? The Applicant is entitled to compensation for non-financial loss because:  there were considerable delays in the claims process and handling  as a result of the delays, there was an unusual degree of inconvenience and time taken resulting in the Applicant‟s loss of enjoyment or peace of mind. 1.3 Determination This Determination is substantially in favour of the Applicant. The FSP is to obtain a further Scope of Works including the costs of removing and replacing the asbestos ceiling area damaged as a result of the storm, rectifying the damaged foundations and repairing the damaged brick work . Case No: 340647 Determination Page 2 of 15 The FSP is entitled to cash settle the Applicant‟s claim in line with the revised Scope of Works. The FSP is to pay the Applicant the sum of $2,000 pursuant to paragraph 9.3 of the Terms of Reference for non-financial loss. The FSP is to pay the Applicant the sum of $880 pursuant to paragraph 9.4 of the Terms of Reference to cover the costs of engineer E‟s report. Case No: 340647 Determination Page 3 of 15 2 Reasons for Determination There has been a full exchange of material between the parties and each party has had the opportunity of addressing the issues that arise from the material exchanged. This Determination is based on what is fair in all the circumstances having regard to the information exchanged, relevant legal principles, terms of the policy, good industry practise, and where appropriate, prior Determinations. The Policy provides general cover for storm damage including subsidence if it occurs immediately as a result of a storm The general exclusions relating to cover note that subsidence and landslip are excluded unless it happens immediately as a result of a storm. This is consistent with the cover provided under storm cover. It is noted that the Policy does not cover loss or damage “arising” from the settling, shrinkage or expansion in buildings, foundations, walls or pavements. This exclusion must be applied in context of the actual cover and proximate cause. That is, if the loss or damage arises in and of itself from settling, shrinkage or expansion of the footings then it would not be covered. However, if the storm is the proximate cause of subsidence resulting in damage to the footings it would be covered under the Policy. 2.1 Is the FSP’s offer to meet the costs of the internal damage adequate? The FSP‟s offer to meet the costs of the internal damage does not adequately provide for the costs to either repair or replace the asbestos sheeting. Engineer R referred to the plaster board ceilings being sound and not displaying any noticeable loss of strength. Engineer R considered if asbestos was present in the ceilings, it would only be an issue if removal was necessary. It is now agreed between the parties that the ceiling sheets in the kitchen, lounge room and passage way are asbestos sheeting. There is an indication in the report from engineer R that there was some cracking identified along the joints and storm damage to the panels. Engineer R believed the panels could be dried out and painted, but it is unclear given his assessment that the panels were plaster board that he would make such an assessment in the understanding that the panels were asbestos. The quotations provided by the Applicant do not clearly identify that the ceiling sheets have been compromised. In my view, it is fair in the circumstances that in the event that the ceiling sheets have been damaged, that it would be necessary to remove the s heeting. In my view, it is reasonable for a cautious approach to be taken to the material which is hazardous and which may well have been damaged by the storm. Case No: 340647 Determination Page 4 of 15 In the circumstances, the parties should obtain a report form a mutually agreeable asbestos expert as to the condition of the ceilings. In the event that the expert determines that the asbestos ceiling panels have been damaged, then the FSP should meet the cost to remove and replace the ceilings with appropriate ceiling sheets prior to repainting. 2.2 Is the FSP’s offer to cover the external damage reasonable? The FSP is liable to meet the cost of repair to the brick works The FSP agreed to pay for the external brick work given the evidence of SS and BB with both engineers suggesting the pooling of water was an active cause of the damage. Engineer R and Engineer E‟s reports both indicate that between 4 to 5 square meters of brick should be rebuilt. Engineer R indicated that there was too much rotation for the wall to be patched and it appears Engineer E‟s report is in agreement. Both Engineer R and Engineer E have provided diagrams regarding the remedial works. Engineer E has provided the measurements for both portions of the wall which extend from the corner of dwelling where the damage has appeared whereas Engineer R has only provided for one side of the wall. Engineer E recommends that the existing damaged brickwork should be removed and replaced along the rear and side walls, up to a point where no further storm damage is evident. In my view, the report of engineer E is to be preferred. I am satisfied that as the policy includes cover to meet the current building regulations in building a home, that any quotation for repair of the brick work should ensure that the repairs are consistent with current building regulations. The FSP should obtain a Scope of Works and quotations to complete the rectification works to the external brick works in accordance with the recommendations of engineer E. The damage to the footings and foundation is covered under the terms of the policy The damage to the footings and foundation is on the balance of probabilities covered under the terms of the policy. Both Engineer R and Engineer E have indicated the footing and slab system was built in accordance with normal practice at the time of construction. Further, both note that the building stood for 35 years without damage which suggests its construction was sound. Whilst the policy excludes loss or damage associated with faulty workmanship, there is no evidence that the construction of the footings and foundation was faulty at the time of construction. It follows that the FSP has not established the application of the exclusion relating to faulty workmanship. Case No: 340647 Determination Page 5 of 15 Engineer R has indicated that the footing is inherently weak particularly due to downward subsidence at the corners because it was not reinforced with any top reinforcing steel. Engineer R believed the slab movement had developed over a period of time but it was reasonable to accept that the infiltration of ground water (via overland flow and heavy rain) near the back left hand corner of the house was one of the initiating factors leading to movement/damage. Further minor settlement to the sewer trench bedding materials occurred due to the ingress of water, causing localised and minor reduction in support where sewer trench passes beneath the corner of the footing. In a later report Engineer R notes the relative movement does not indicate a failure of the footings. The comment regarding minor strengthening work to the footings was not an essential part of the repair work to reinstate the item. Engineer E generally concurred with Engineer R‟s report, however he considered that in order to restore the property to a pre-existing condition to a satisfactory engineering standard that it was not just prudent but necessary to strengthen the western corner‟s foundations. I accept based on both reports that whilst there was some movement in the footings prior to the January 2013 storm that the inundation of the property as a result of the storm was an initiating factor leading to movement and damage to the footings and foundations. The policy provides cover for subsidence occurring immediately after a storm. Based on the information available, I am satisfied that the damage to the foundations occurred immediately after the storm. Accordingly, I am satisfied based that the FSP is liable to meet the cost of repair of the footings and foundations and to ensure that the footings and foundations meet current building regulations. That is the circumstance in the current dispute. Is the FSP’s offer for the other external damage reasonable? The FSP‟s offer to cover the other external damage including the costs of the pipe vent in the sum of $528, the glazing in the sum of $390.01 and the cost of the external door repair is reasonable. 2.3 Is the Applicant entitled to compensation for non-financial loss? Paragraph 9.3 of the Terms of Reference provide that the Service may determine to award compensation for non-financial loss in limited circumstances, to a maximum of $3,000. It is necessary for awarding compensation to be satisfied that the Applicant has suffered an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant‟s expect ation of enjoyment or peace of mind. Case No: 340647 Determination Page 6 of 15 It is accepted that an insurer is entitled to investigate a claim appropriately and that in some circumstances, delays will occur, in particular, where there are significant weather events resulting in a large influx of claims. That is the circumstances in the current dispute. Although the FSP notified the Applicant on 20 March 2013 of its decision to partially decline the claim, it is clear from the information exchanged that the FSP had not completed its investigations at that time. The Applicant disputed the FSP‟s decision to partially decline the claim in July 2013. The review was not completed until February 2014. At that time, the FSP agreed to pay for some internal damage as well as the cracked brick work and to waive an excess. The delays were associated with the failure to obtain an engineering report or to in fact arrange for an engineering report until October 2013. This is eight months after the original claim. The Applicant provided a psychological report that makes it abundantly clear that the claims process and interaction with the FSP has significantly impacted on his peace of mind. He has suffered symptoms of anxiety and depression which the psychologist has directly linked to the claims handling process. The FSP has not provided any evidence to dispute this. I am satisfied based on the information exchanged that the delay in the claim process and the claims handling has had a significant impact on the Applicant‟s mental health. Given the nature of the impact, I am satisfied that the Applicant is entitled to an award of $2,000 under the Terms of Reference for non-financial loss. Other matters The Applicant has complained that he was not provided proper access to the claim file. It would appear based on the information exchanged that he did not receive the file in its entirety at first instance which may in part be due to a miscommunication between the Applicant and the FSP. The FSP has provided information that it believed the A pplicant‟s request contained in a letter dated 7 January 2013 was a request for the relevant information to be exchanged. The FSP has apologised to that for any misunderstanding. The issues with respect to the exchange of information are issues which more appropriately are dealt with by the Code Compliance Committee. Whilst the delays and claims handling is relevant in terms of consideration as to the Applicant‟s entitlement to compensation for non -financial loss, it is not appropriate as part of this Determination to determine whether there has been a breach of the relevant industry code of conduct. Case No: 340647 Determination Page 7 of 15 Is the Applicant entitled to reasonable costs of obtaining an expert opinion? Paragraph 9.4 of the Terms of Reference provides that the Service may determine that the FSP contribute to professional costs by the Applicant in the course of the dispute. In determining whether the FSP should contribute to an Applicant‟s costs, it is appropriate to take into account the complexity of the dispute, whether the Applicant reasonably needed the advice and whether the advice assisted in the resolution of the dispute. I am satisfied that the report of engineer E has been of significant assistance in helping resolve this dispute and in the circumstances, I am satisfied the FSP should meet the costs of the report in the sum of $880 inclusive of GST. Case No: 340647 Determination Page 8 of 15 3 Supporting information 3.1 Relevant Policy Wording “Storm … Covered - violent wind, cyclone or tornado - rain, thunderstorm, hail or snow - landslide or subsidenc e that happens immediately as a result of storm … Meeting building regulations .. Covered under Buildings Insurance - The costs to meet current building regulations to repair or rebuild the part of your home that was damaged. Not covered - Costs to meet building regulations: - that were already in place when your home was built, renovated or altered - for undamaged parts of your home – for example, installing insulation in ceilings that were not damaged … Exclusions for all cover These exclusions apply to all cover under your policy What we don‟t cover Loss, damage, injury or death arising from: … Subsidence or landslide unless it happens immediately as a result of: .. - a storm or flood .. - the settling, shrinkage or expansion in buildings, foundations, walls or pavements. … Maintaining and occupying your home We don‟t cover loss, damage, injury or death arising from:  Faulty design or workmanship” 3.2 Relevant Terms of Reference “9.3 Other compensation a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for consequential financial loss or damage up to a maximum amount of $3,000 per claim made in the Dispute ... b) Subject to paragraph 9.3c) and paragraph 9.7, FOS may decide that the Financial Services Provider Compensate the Applicant for non-financial loss but only where: (i) An unusual degree or extent of physical inconvenience, time taken to resolve the situation or interfe rence with the Applicant‟s expectation of enjoyment or peace of mind has occurred; or (ii) In the case of a Dispute pertaining to an individual‟s privacy rights – injury has occurred to the Applicant‟s feelings or humiliation has been suffered by the Applicant. The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation for: (i) Consequential financial loss; or (ii) Non-financial loss, Case No: 340647 Determination Page 9 of 15 In a Dispute arising as a result of a claim on a General Insurance Policy that e xpressly excludes such liability ... 9.6 Other types of damages Punitive, exemplary or aggravated damages may not be awarded.” 3.3 Claim Description provided on 26 January 2013 “Stormwater damage to foundations and walls and cracking of glass of windows and possibly concrete flooring.” 3.4 Expert Reports and other relevant material/reports Report provider and date Relevant information Assessment report dated 28 February 2013  Storm conditions resulted in rainwater entering the home through flashing and tile clips. The roof is generally well maintained and the insured would not have been aware of any defect prior to the event as there is no evidence of damage pre - dating the incident.  The cycloni c wind ha impacted on the front roof plane of the property causing the internal linings to crack and the fixings supporting the ceiling linings to pop.  There are structural issues to the external eastern wall and this is the result of unstable ground. The assessor could not confirm whether the damage is consistent with the claimed event. Assessment report dated 21 June 2013 from “B”  B‟s inspection suggested that there was no storm created opening but there was evidence of minor cracking to the corner of so me roof tiles. The ridge did not look to have been re - pointed since the dwelling was constructed. Further, there was no sarking under the tiles. There was also internal damage to the plaster and to the laundry door.  There were structural issues noted to th e external eastern wall of the dwelling which appeared to be the result of unstable ground affecting the load bearing walls of the dwelling from an unknown cause.  An investigation into the main and dwelling drain lines determined no damage to these lines.  At the time of purchasing the property the Applicant noted signs of cracking to the rear door and adjacent window and corner. However, the cracking worsened after the storm.  B opined that the damage to the ceiling and broken laundry door were consistent wi th the storm event. However B believed the cracking to the plaster joint was from natural building movement rather than storm. Further, the cracking to the brickwork was considered to be the result of subsidence although B does confirm that “it is possible that heavy rain may have contributed to it. Case No: 340647 Determination Page 10 of 15 Report dated 31 July 2013 from B  In addition to the damaged kitchen/dining and lounge ceilings, the external laundry door is broken and the bedroom adjacent to the laundry has a cracked glass panel which the Ap plicant indicates is due to subsiding brickwork during or shortly after storm.  There is no sarking under the roof tiles but this was not a BCA requirement as the roof pitch is greater than 16 degrees.  The roof tiles were in good condition for the age of the property although some cracking of the pointing to the ridge and hip capping was noted. This did not contribute to the water ingress during the storm event. B believes the water ingress was due to rain driven under the tiles by strong winds.  The sewer lines were undamaged.  During the storm event large volumes of water flowed through and settled near the corner of the home.  An inspection of the bedroom adjacent to the subsided brickwork did not show any signs of stress to the internal walls or ceiling sh eets or mouldings. It is assumed that the construction is an infill slab and the concrete foundation has broken or subsided and the slab is cantilevered on fill.  B recommends the engagement of a suitably qualified Engineer to undertake a full investigation .  B confirms the damage is consistent with the recorded incident. Report dated 21 March 2013 from property inspector “C”  Settlement has occurred at the rear south corner of the building. A visual appraisal is that the footing edge of the slab has settle d approximately 20 - 30mm and caused rotational cracking in the brick veneer and displacement around a window frame. There is some evidence of prior repairs to cracking.  C opined that the damage to the building is a result of subsidence of founding within t he sewer trench backfill. The subsidence may be the result of broken pipework, or leaching of backfill soils during recent storms and flooding events.  C recommended that the sewer lines be checked for breakages or leaks including the house drains. Letter dated 27 September 2013 from “SS”  SS has been to the insured property a number of times and can state the damage in the form of cracked and displaced bricks between the back door and the corner of the house extending around the corner and a long the first part of the back wall appeared after the storm in January 2013.  The damage appears to have resulted from subsidence at the time the locale had significant rain and flooding. Letter dated 5 December 2013 from the previous owner of the residence  AW purchased the property in 1982 or 1983.  At the time of purchasing the property he noted a crack existing in the wall which was repaired by the previous Case No: 340647 Determination Page 11 of 15 “AW” owner.  A plumber who worked on the home informed AW that the crack was “nothing to worry about”. Reques t for personal information  The Applicant signed a form requesting access to his personal information on 8 January 2014. This document was sent to the FSP on 9 January 2014 by email with a request for reinstatement due to damage caused by destructive testi ng. Engineering Report dated 10 February 2014 by “R”  The footing and slab system was built in accordance with normal practice for the time of construction.  It would be expected that this type of footing would rotate outwards causing cracking as the slab i s not connected to the footing.  The slab system can deflect vertically out of alignment due to soil moisture effects because it does not contain internal strengthening beams.  The footing is inherently weak particularly due to downward subsidence at the cor ners because it has not been reinforced with any top reinforcing steel.  The floor measurements suggest the overall slab movements have developed progressively over a very long period of time.  In relation to the brickwork damage occurring so soon after Janu ary 2013 R states the following:  The brick work is in good condition.  The soil type is not subject to large movement due to moisture variation.  It is reasonable to accept that the infiltration of ground water (via overland flow and heavy rain) near the back left hand corner of the house was one of the initiating factors leading to movement/damage.  It is probable that minor settlement to the sewer trench bedding materials occurred due to the ingress of water, causing localised and minor reduction in supp ort where sewer trench passes beneath the corner of the footing.  In order for subsidence to have occurred some or all of the following issues would need to have contributed:  The construction of the footings over a sewer.  The extreme weather conditions whic h resulted in ground saturation and caused previously poorly compacted trench backfill to subside.  There is no obvious sign of settlement at the surface. R concludes that the footing and slab system must therefore have been a significant contributory fact or.  The building has moved marginally but the damage exceeds what would ordinarily be expected. The lateral rotation of the brickwork is to major for patching the brickwork. It will require demolishment and rebuilding. This remedial action would place the building back to its pre - existing condition but R recommends strengthening this corner of the home to avoid any issues created by the close proximity of the Council Case No: 340647 Determination Page 12 of 15 sewer pipe.  The vertical crack in the brickwork below the window jambs on the rear wall of the building are minor in nature and can be repaired if this is considered appropriate. The cracking has occurred over time and is probably due to the lack of any control jointing.  The roofing is at a pitch at which sisilation is not required to prevent w ater ingress. The water was most likely driven under the tiles due to high winds.  The plasterboard roof sheeting is sound and does not display any noticeable loss of strength, sagging or similar. R opines the joints could be dried out and repair work simpl y involve painting of the ceiling.  R does not agree that the removal of the ceilings in the kitchen, lounge room and passageway is warranted to repair the affected rooms. Builder Assessment Report dated 28 February 2014 by “A”  A provides a costing/scope of works based on the report of engineer “R”.  A states that the damage sustained as a result of tropical cyclone Oswald includes the plasterboard ceilings to the kitchen, dining and lounge rooms, broken glass to the laundry door and bedroom 3 window and cracking to external brickwork.  A opines that the effective cause of damage to the insured residence are weather factors associated with the cyclone.  The assessed amount for building works was $6,256 . Engineering Report by R 2 June 2014  R denies accurate measurements were not taken of the brick work, that 2/3rds of the ramp needs to be removed or that there is no accurate scope of works in regard to the requirement to replace brickwork.  The ceilings do not need to be removed as the material is sound and has not lost strength. If asbestos was present in the ceiling sheeting such a presence would only be an issue if removal was necessary. Further temporary accommodation is not required for the painting of ceilings.  R accepts that the kitchen, lounge and hallway ceilings need to be repainted to provide uniform finish after localized repairs. However there is no need to paint walls or remove cornices.  R accepted in its report dated 10 February 2014 it was reasonable to accept infilt ration of ground water near the back left hand corner of the house was one of the initiating factors but there was no suggestion of ongoing settlement.  R accepted that the isolated damage at the back left hand corner of the house is storm damage requiring replacement of around 4 - 5 square meters of brickwork. The relative movement does not indicate a failure of the footings. The comment regarding minor strengthening work to the footings was not an essential Case No: 340647 Determination Page 13 of 15 part of the repair work to reinstate the item.  Eve n if the building occurred over the sewer lines, it has had no damage for 35 years since construction which indicates it has not been an issue.  Any footing movements would be minor in nature. The brickwork will be replaced and the footings can be reused.  R confirms the causes of the cracking have occurred over a long time, and it is not disputed that the crack occurred after the cyclone. Repairs would involve installing a brick control joint because no structural damage has occurred.  R did not consider so il tests were required in the circumstances.  The gap between brickwork and window is not a defect as it is not a „crack‟. Remedial work would include touch up painting inside and provision of a minor aluminium cover strip between the window and bricks.  R i s not aware of building costs in the Applicant‟s locale and would have no basis to claim the costs should be higher because of the locale. Doctor’s Report 11 July 2014  The Applicant has been regularly seeing a psychologist since January 2014 with ongoing review and support.  The Applicant has commenced medication for psychological distress. Engineering Report by “E” 24 July 2014  E noted cracking to the brickwork in various locations around the western corner of the house.  The eave was out of alignment at the western corner of the home.  There was a sewer located in close proximate to the western corner of the home.  E generally concurs with the content of R‟s report. However in order to restore the property to pre - existing condition to a satisfactory enginee ring standard it is not only prudent but completely necessary to strengthen the western corner‟s foundations.  Further, E recommends that the existing damaged brickwork should be removed and replaced along the rear and side walls, up to a point where no fu rther indication of the storm damage is evident. E has attached designs to illustrate the works to be done.  E notes that the construction methodology used on the insured premise was likely a common and acceptable practice at the time of construction. Howev er, due to the time that has elapsed it is difficult to comment on the workmanship – but the fact it has stood 39 years without a single crack suggests a high standard of workmanship.  The drawings provide dimensions suggesting the rear of the property shou ld have 4.9m of brick work repaired and the side should have 5.15m of brick work repaired. Further, that strip footing should extend 1m past existing brickwork that is replaced.  The cost of the Report was $880 (GST inclusive). Case No: 340647 Determination Page 14 of 15 Psychologist Report 4 September 2014  The psychologist notes the Applicant was referred by his doctor for treatment of anxiety and stress management. The psychologist states “…This was a direct psychological consequence form the continuation of an insurance claim for damage to h is property resultant of the January 2013 floods.  The Applicant has been a patient for 12 months.  The Applicant‟s symptoms include restlessness, irritability, depressed mood, frustration and anger regarding the insurance claim, excessive financial worries due to need for repairs, sleep disturbance, loss of interest in food and low energy levels.  Testing revealed his anxiety and stress within the extremely severe range and depression severe range. The symptoms are consistent with the DSM - IV diagnostic criter ia of mixed anxiety and depressed mood.  The psychologist notes that the symptoms were precipitated significantly by the management of the claim for damages to his home. The symptoms are likely to occur with his insurance claim being equitably resolved.  The Applicant has no previous psychiatric history. Laboratory Report  Confirms that the material is asbestos . Council Policy for Building Over Sewers Issue date: 31 October 2011  Generally the Council states it is undesirable for a building to be located ove r a sewer line and that construction of such is avoided if at all possible. Pre - purchase inspection report  The pre - purchase inspection report indicates “crack in brick” to the external of the home but does not suggest large cracking and structural instab ility.  The Applicant ‟ s submissions indicate the property was purchased on 5 April 2000. Undated letter from Plumber “PB”  PB attended the property on 27 November 2012 to provide a quotation to re - gutter the property and a discussion ensued with the Applicant regarding placement of rainwater tanks. In particular, PB discussed whether to place the rainwater tanks to the rear left or rear right hand side of the house.  PB notes that he would definitely have noticed damage to the rear wall if it had exist ed at the time of preparing this quotation.  PB states that there was “definitely no cracking in the walls in November 2012 as we looked at both rear walls for a fair time while discussing the guttering and the positioning of rain water tanks.” 3.5 Quotations for Repair Quotation Provider and Date Amount and scope of works Plumbing Quotation 9 February 2014  Removal of vent pipe and installation of a new PVC pipe to be painted the same colour .  Works would cost $490 (GST inclusive) . Case No: 340647 Determination Page 15 of 15 Plumbing Quotation 28 February 2014  Replacement of vent pipe in 10mm PVC including painting.  Works cost $528 (GST inclusive) . Asbestos Removal Company 31 March 2014  The scope of works was to remove ceiling sheets in lounge and dining/kitchen.  Remove insulation batts from ceili ng cavity .  Remove kitchen cabinets for decontamination .  The works do not include re - plastering or re - installation of cabinets .  The works would cost $3,520 (GST inclusive) . Asbestos Removal Quotation 7 April 2014  The removal of asbestos material and insulation batts .  Saf ety works.  Installation of plaster sheeting together with painting .  Replace external door using hardware and paint .  The quotation costs $14,292 (GST inclusive) . Plastering company 30 June 2014  Remove and replace 75mm cornice around ki tchen cupboards.  The works would cost $220 (GST inclusive) . Building Company “M” 27 August 2014  To underpin storm settlement damage as suggested by E‟s drawings is $21,719 (GST inclusive) .  Remove and replace storm damaged asbestos ceilings would be $18,75 7 (GST inclusive). Bricklaying company 5 September 2014  The scope of works includes pulling down existing damaged wall to copper pipe and removing from site, tooth out the existing wall and relay with similar bricks not straight vertical control joint.  The cost of these works would be $3,270 (GST inclusive) provided there is no touching of the concrete path way. Glazing Company 12 September 2014  Re - glaze window and laundry door panel .  Cost of works would be $390.01 .

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.