Home / Financial Firm (Unknown - Insurer) / Determination 338440
Determination 338440
Flood versus flash flood cover denial of home contents claim
Summary
The insured's home contents claim for flood water damage from the January 2011 Queensland floods was denied as flood. AFCA found the inundation was flash flood within 24 hours of heavy rain and ordered payment of $43,000 (50% of the contents sum insured) plus interest.
Inundation occurred within 24 hours of the heavy rainfall so the flash flood provision applied, and the PDS and certificate adequately informed the insured of the flood limitations under section 35 of the Insurance Contracts Act.
Issues
- Claim denial primary · upheld
“The inundation occurred, on the balance of probabilities, within the relevant 24 hour period ... so as to attract cover under the flash flood or stormwater runoff provisions”
- Failure to disclose secondary · not upheld
“the FSP has reasonably established that the relevant policy documentation was provided to the Applicant after inception of the policy in line with its obligations”
Subjects and remedies
natural disasterpay claimpay interest
Text of the determination
Case No: 338440 Determination Page 1 of 10
Case number: 338440
General Insurance - Domestic Insurance - Home Contents - FSP Decision -
Denial of claim
24 January 2014
Summary
Description
Claim under Home Contents Policy for water damage following the
inundation of the Applicant‟s property in Goodna Queensland, late evening
on 11 January 2011. The FSP has denied the claim as flood.
Basis of Determination
The Applicant relies on the “flash flood” provision in the policy to claim the
inundation occurred within 24 hours of commencement of the heavy
rainfall.
The Applicant‟s property was inundated at 8.00pm 11 January 2011. The
inundation occurred within the relevant 24 hour period.
Determination
The FSP is liable to meet the damage sustained in accordance with the
terms of the policy.
Background
1. The Applicant held a Home Contents Insurance Policy with the FSP covering
contents at his property in Goodna, Queensland, for a total sum insured of
$86,000 at the time of the loss.
2. On 15 January 2011, the Applicant lodged a claim under the policy due to
extensive water inundation of the home following severe weather events in
Queensland.
3. The FSP has denied the claim on the basis that the damage sustained was
due to „flood‟, which is excluded under the terms of the policy.
Determination
Case No: 338440 Determination Page 2 of 10
Summary of Applicant’s position
4. The Applicant refutes the FSP‟s position that it is not obliged to provide
indemnity for his loss arising from the inundation of his home by stormwater
runoff. He maintains:
Following inundation of the Applicant‟s home on 11 January 2011 a
representative of the FSP informed the Applicant on 13 January 2011
that he was covered for loss arising from the event „Flash flood‟ and he
would receive a payout equal to 50% of overall cover under the policy.
The Applicant could not remember whether the FSP provided him with
a Product Disclosure Statement (PDS) the previous year after inception
of the policy (2009). However, he is sure that one was not provided at
renewal of the policy in 2010.
The FSP‟s response to the Applicant‟s concer ns with respect to the
PDS are vague and it would seem even the FSP is not sure whether a
PDS was provided to him in line with its obligations.
The Applicant maintains he was provided with a copy of the PDS
attached to the FSP‟s submission to FOS. He is o f the opinion the
wording of the contract creates confusion for a reasonable person and
especially the definitions/wording of the terms and events of „Flood‟ as
well as „Flash flood‟ and „Stormwater Runoff ‟.
The Applicant maintains the insured property was first inundated at
approximately 8.00pm on 11 January 2011, this being within 24 hours
of rainfall and so he cannot believe how the FSP continues to deny him
indemnity under the claim.
5. The Applicant is seeking indemnity from the FSP in line with the terms of the
policy i.e. indemnity in an amount equal to 50% of the total sum insured
amount noted within the contract of insurance.
Summary of FSP’s position
6. The Applicant‟s property was not damaged by flash flood or stormwater
runoff, but by flood (as defined in the policy) because:
Its hydrological evidence shows that the proximate cause of the loss
was the rain which fell in the Wivenhoe Dam catchment from 9 January
2011 or earlier.
Releases from the dam caused the Brisbane and Bremer River levels
to rise and subsequently inundated the Applicant ‟ s residence. The
Applicant ‟ s property was therefore damaged by rain which fell more
than 24 hours earlier.
7. The Applicant was clearly informed of the limitations of cover relating to
flood, stormwater runoff and flash floods because:
Case No: 338440 Determination Page 3 of 10
He was provided with a PDS and certificate of insurance which clearly
state he was not covered for flood.
FOS has previously determined that its PDS clearly informed
policyholders of the relevant limitations with respect to flood,
stormwater runoff and flash flood damage.
8. It is not required to pay interest on the Applicant‟s claim (if payable) for any
period prior to the Determination because:
It had not acted unreasonably for purposes of Section 57 of the Act.
It is entitled to a reduction on the interest payable to account for delays
that were not its fault.
The Applicant took 30 months to dispute the denial of their claim.
9. The FSP relies on the following policy provisions:
Page 3 of the Certificate of Insurance (COI)
“ What optional covers are included and not included
Contents
...
Flood and storm surge not included”
Pages 10-12 of the PDS
“ Words / terms with special meanings
Word / term Meaning
...
Flood Rising water which enters your home as a result of it
running off or overflowing from any origin or cause.
This policy does not cover flood unless we have
agreed and it is shown on your certificate of insurance.
Flash flood and
stormwater runoff
A sudden flood caused by heavy rain that fell no more
than 24 hours prior to the flash flood or stormwater
runoff .
...
Storm A violent disturbance of the atmosphere associated
with strong winds including a cyclone, lightening,
heavy rain, hail or snow, but not continuous bad
weather by itself.
...
Pages 17-18 of the PDS
“ Insured events you are covered for
Damage caused by weather...
Case No: 338440 Determination Page 4 of 10
What is covered What is not covered
Storm Loss or damage:
caused by rain, hail or snow
after it has reached the
ground...
...
Flash flood and stormwater runoff
A sudden flood caused by heavy rain
that fell no more than 24 hours prior to
the flash flood or stormwater runoff
Loss or damage caused:
by flood...
...
Page 32 of the PDS
“ Your contents
The most we will pay you for contents claims
What is covered What is not covered
Flash flood and stormwater runoff
We will pay up to 50% of your contents
sum insured or $25,000, whichever is
higher , but not exceeding your contents
sum insured.
...
...”
Issues
10. Whether the FSP has provided the Applicant with the PDS prior to the loss in
line with its obligations set out in the Insurance Contracts Act 1984 (the Act).
11. Whether the Applicant‟s loss was caused by rain or stormwater runoff, flash
flood and/or flood (as defined in the policy).
12. Whether the FSP is required to pay interest and if so, is it entitled to a
reduction in the amount payable.
Reasons for decision
13. Due to the nature and complexity of the dispute, it has been directly referred
to the Panel for Determination in accordance with the Operational Guidelines
to the FOS Terms of Reference.
Case No: 338440 Determination Page 5 of 10
14. The Panel consists of an Ombudsman and two Panel members with
extensive experience in the insurance industry and consumer claims.
15. The Panel is satisfied that the material has been exchanged and the parties
have had the opportunity to respond to the issues raised.
16. The Panel having reviewed the submissions of the parties is satisfied the
parties do not dispute the following:
The Applicant held a home contents policy o f insurance for loss or
damage arising from the listed insured events at the time of loss.
“Flash flood and stormwater runoff ” is listed as one of the insured
events for which the policy provides indemnity. Whilst, the loss or
damage arising from the event „flood‟ is excluded from cover under the
policy.
The Applicant‟s home was initially inundated at 8.00pm or thereabouts
on the evening of 11 January 2011 which continued to rise to higher
levels within the home until 4.00am on 12 January 2012 and reaching
peak levels later in the day.
The inundation of the property has resulted in significant damage/loss
of the insured contents.
The policy, if a claim is accepted by the FSP, limits its obligation to
provide indemnity for loss arising from the event of flash flood and
stormwater runoff to $25,000 or 50% of the contents sum insured,
whichever is higher.
Provision of PDS
17. Section 35 of the Act imposes the obligation on the insurer to clearly inform
the insured in writing before the contract is entered into. However, Section
69(2) of the Act provides that if it was not reasonably practicable for the
information to be so given orally or in writing at policy inception, the
information shall be deemed to have been given if it is given in writing 14
days after the day on which the contract was entered into.
18. The Panel has also reviewed the FSP‟s documentary evidence in respect to
providing the Applicant with the PDS and is satisfied the FSP has reasonably
established that the relevant policy documentation was provided to the
Applicant after inception of the policy in line with its obligations under the
Act. Further, that the FSP is not obliged to provide a copy of the policy
wording at each policy renewal unless there has been any change(s) to the
policy of which the policyholder needs to be made aware. It is not asserted
by either party that policy changes had occurred.
Case No: 338440 Determination Page 6 of 10
Clearly Inform
19. The Panel notes that a number of issues raised in this dispute are identical
to issues that have been extensively considered in a number of previous
Determinations in respect of this FSP and its policy (available on the FOS
website). As these issues have been determined before, the Panel does not
consider it expedient to engage with them at length and instead proposes to
address them summarily at the outset.
20. It is well established that a fair reading of Section 35(2) of the Act requires
that the language of a policy relating to any relevant exclusion or limitation
be clear and unambiguous so that a person of average intelligence and
understanding would be capable (on reading the policy) of finding and
understanding the extent of the exclusion or limitation.
21. In this dispute, the policy is relevantly indexed and cross referenced. The
definitions of flood, flash flood and stormwater runoff are clear. The Panel is
satisfied that on reading the policy, a person of average intelligence and
education would have little difficulty in understanding the nature and extent
of the exclusions and limitations.
22. In the circumstances, the Panel is satisfied the FSP has met its obligation to
clearly inform the Applicant of the relevant exclusion and limitations in line
with Section 35 of the Act.
Proximate cause of damage
23. Having carefully reviewed the material exchanged, the Panel does not
consider it is strictly necessary to determine whether the Applicant‟s home
was initially inundated by localised stormwater runoff or flash flood. The
Applicant‟s entitlement to indemnity would be the same irrespective of
whether the loss was caused by localised stormwater runoff or flash flood, so
long as it arose within 24 hours of the heavy rainfall.
24. In order for the Applicant to be entitled to cover for flash flood, the following
elements must be established:
there was a sudden flood;
there was heavy rain that occurred within 24 hours prior to that flood;
the sudden flood was caused by that heavy rain.
25. The FSP in the Notice of Response dated 12 November 2013 relied upon its
attachments „Reference document for disputes relating to Queensland
Floods 2011‟ dated 28 August 2012 which includes the following
documentation:
a) Reference document. This is a general reference document that covers
the various arguments made by the FSP in relation to the issues arising
from the various disputes. Not all of the issues arising or referred to in
the reference document are relevant to the current dispute.
Case No: 338440 Determination Page 7 of 10
b) Letter dated 6 November 2013 from “WT” attaching key conclusions
sheet of the Applicant‟s property.
c) WT report investigation of January 2011 inundation event Brisbane –
March 2011.
d) General statement from hydrologist SC, dated 7 June 2012.
e) Certificate of Insurance.
f) PDS.
g) Site specific statement by hydrologist SC, dated 7 November 2013.
h) Loss Adjusters Report dated 15 March 2011.
Assessor’s Report dated 19 February 2011
The insured property was inspected by the FSP‟s assessor on 2 February
2011.
The assessor placed a reserve for the damage at $87,764.50 which
reasonably would be considered a total loss of the insured contents.
Hydrologist “SC’s” Report dated 6 November 2013 and Key Conclusions
statement
Normal Brisbane River level RL 1.7m AHD.
Minimum Land Level (insured property) RL 11.6m AHD.
Maximum Land Level (insured property) RL 12.1m AHD.
Approximate benchmark level RL 11.6m AHD (Slab on Ground unit).
Approximate time Brisbane River reached the approximate benchmark
level: 8.18pm on 11 January 2011.
Time effect of W4 release first reached the vicinity of the property was
12.50pm on 11 January 2011.
W4 releases from the Wivenhoe Dam commenced at 8.00am 11 January
2011.
The property is 82.2km from Wivenhoe Dam (measured along the
Brisbane River).
The approximate level at 4.00am on 12 January 2011 would have been
14.6m AHD this being 3m above benchmark level.
26. The evidence of the parties is reasonably consistent with respect to the
timing of the initial inundation although differs with regards to the source of
water that resulted in the initial inundation of the property. Further, the
parties acknowledge that the level of inundation continued to rise within the
insured home through the early hours of 12 January 2011, reaching its peak
of 5.1m above the benchmark level late in the afternoon the same day.
27. The parties only differ with respect to the cause of the inundation, with the
Applicant claiming it was flash flood and therefore covered under the policy
Case No: 338440 Determination Page 8 of 10
whilst the FSP claims it was floodwater from the rising level of the Brisbane
River which would be excluded from cover.
28. FOS has determined in other disputes, following consideration of all material
exchanged, that the heavy rainfall commencing around 4.00am on 11
January 2011 was a proximate or effective cause of the inundation of the
properties downstream from the Wivenhoe Dam.
29. Although each dispute is determined on its merits and in this dispute,
detailed further submissions have been made by the parties, the Panel is not
satisfied that the evidence in this dispute substantially changes the position
adopted in earlier Determinations in this regard.
30. The evidence supports the view that the flooding downstream of the
Wivenhoe Dam is attributable to the particularly intense rainfall over the dam
that commenced at approximately 4.00am on 11 January 2011. This rainfall
event caused a sharp rise in the dam‟s level, ultimately leading the dam‟s
operating engineers to move from a W3 release strategy to adopt a W4
release strategy from 8.00am on 11 January 2011.
31. The Panel is satisfied having considered all of the evidence presented and in
particular, the further submissions and hydrology reports provided by the
FSP, that it was the heavy rainfall commencing at approximately 4.00am on
11 January 2011 that was the proximate, that is, the effective or dominant
cause, of the inundation of the A pplicant‟s property.
32. The FSP‟s own hydrology indicates that rising Brisbane River water levels
were likely to have caused an inundation of the Applicant‟s property above
benchmark level (slab on ground) at or about 8.18pm on 11 January 2011
reaching a level of 3m above benchmark level by 4.00am on 12 January
2011.
33. In the Panel‟s view, the inundation of the Applicant‟s home occurred, on the
balance of probabilities, within the relevant 24 hour period of the
commencement of the heavy rainfall so as to attract cover under the flash
flood or stormwater runoff provisions of the policy.
Coverage
34. Coverage under the policy in respect of flash flood is limited to 50% of the
contents sum insured or $25,000, whichever is higher. The Certificate of
Insurance for the relevant period shows a contents sum insured of $86,000.
35. The FSP has provided a site report from its appointed loss adjuster „F‟. The
assessor has placed a total reserve on the loss at $87,764.50 in terms of
contents loss which reasonably indicates a total loss of insured contents
arising from the inundation. The report does not provide an itemised list of
the loss assessed/identified or the estimated cost for each item.
36. Whilst it is evident that the inundation of the Applicant‟s home had led to
significant loss of contents (possibly total loss), the available information is
Case No: 338440 Determination Page 9 of 10
insufficient for the Panel to form a definite view as to the extent of the loss
and the FSP‟s obligations under the policy. In saying that, it is reasonably
evident the loss amounts to higher than $25,000 and given the time already
elapsed since the event and resultant loss, the Panel is of the opinion
settlement equal to 50% of the total contents sum insured is reasonable
under the circumstances. Accordingly, the FSP is required to make pa yment
of $43,000 to the Applicant within 21 days of the Applicant‟s acceptance of
the Determination.
37. The Panel has also considered the question of interest.
38. The FSP maintains that it did not act unreasonably in this dispute and
therefore interest is not payable. Alternatively if some period of interest is to
be awarded, it should be reduced to account for the substantial delays
through the course of the process which were not the FSP‟s fault.
39. Section 57 of the Insurance Contracts Act 1984 (the Act) requires interest be
paid when it becomes “unreasonable for the insurer to have withheld
payment”. An examination of relevant case law indicates that most probably,
interest will be awarded from either when an insurer first emphatically denied
liability or disputed a matter, or from when in the normal course of events the
claim should have been paid if liability had not been disputed.
40. In this dispute, the Panel accepts that the FSP was entitled to withhold
payment of the settlement monies until such time as it had properly
investigated the dispute and made its decision as to liability.
41. The decision on interest is not based on whether the insurer has genuine or
reasonable grounds to deny a claim, but looks at the day from which it was
unreasonable to withhold payment.
42. The FSP made its decision to deny the claim after receiving relevant
assessment reports, hydrology reports and other information. The FSP was
aware of the terms of its policy and aware of the relevant provisions under
which liability might arise and chose to deny the claim having reviewed those
relevant provisions and the evidence available to it.
43. In the Panel‟s view, at that point the FSP had made its decision on the claim
and it is appropriate that from that time interest be paid unless it can be
established that the Applicant had withheld information from the FSP that
would have led to an alteration of its decision.
44. Accordingly, the Panel determines that it is appropriate that the FSP in this
dispute pay interest from the day upon which the FSP determined to deny
liability of the Applicant‟s claim, until payment of the claim.
Case No: 338440 Determination Page 10 of 10
Determination
45. The Panel determines the FSP meet its liability in accordance with the terms
of the policy, the FSP is to pay the Applicant $43,000 (50% of the home
contents sum insured).
46. Insofar as the FSP is to cash settle the claim, the FSP is to pay interest from
28 October 2011(being the date of the FSP‟s final decision letter) to date of
payment of the claim, in accordance with Section 57 of the Act.