Maladministration in lending - progress payments advanced without required building contract and council approval
Text of the determination
Determination
Credit - Consumer Credit - Construction Loans - FSP Decision - Maladministration in
lending
Case number : 338310 8 April 201 5
1 Overview
1.1 Dispute
This dispute concerns a home loan for $352,342 (the home loan) which the
Financial Service Provider (FSP) provided to the Applicant in July 2011. The
home loan was secured by a first registered mortgage over land in Queensland.
It was intended that the home loan be used to purchase land, a kit home to be
constructed on the land and the construction of that kit home.
The home loan was used to purchase land for $159,000 and to purchase a kit
home in December 2011. Due to unforeseen factors, the funds from the home
loan were not sufficient for the Applicant to construct the kit home on the land.
The Applicant applied to the FSP for additional funds to construct the kit home.
Although the FSP was prepared to approve further funding it was unable to obtain
Lenders Mortgage Insurance (LMI) to proceed with the additional loan.
The Applicant says that the FSP should not have provided the home loan without
being aware of the costs to erect the kit home and being prepared to fund its
construction. The kit home is currently stored on the land and the Applicant has
continued to meet his repayment obligations under the home loan. The Applicant
has recently taken steps to mitigate his losses associated with the home loan by
selling the land and taking reasonable steps to sell the kit home.
1.2 Issues and key findings
Should the FSP have granted the home loan to the Applicant in July 2011?
It was reasonable for the FSP to advance funds for the purchase of the land but it
was unreasonable for the FSP to advance the progress payments for the
purchase of the kit home without a building contract and council approval being in
place. The advance of the progress payments for the purchase of the kit home
was in breach of the FSP’s own policies and industry practice.
Has the FSP’s conduct caused the Applicant to suffer loss ?
The Applicant has suffered a loss as a result of the advance of the progress
payments for the purchase of the kit home in the form of the holding and disposal
costs for the kit home only. Before the progress payments were advanced the
Applicant had already entered into a contract with a third party to purchase the kit
Case No: 338310 Determination Page 2 of 11
home so his liability to the kit home supplier arose before his liability for the
progress payments to the FSP.
The Applicant has alleged that the FSP misled him into believing that it was
appropriate for him to sign the kit home contract with the third party. However the
balance of information in this dispute does not adequately support that claim.
But for the FSP’s advance of the progress payments for the purchase of the kit
home to the Applicant I am satisfied on the balance of probabilities that –
the Applicant would still have been liable to the third party for the purchase
price of the kit home inclusive of the transport and delivery component of that
purchase price, as the purchase price was “all inclusive” (that is , I am satisfied
that the Applicant would have been liable for the all-inclusive price irrespective
of whether the kit home was delivered or not – and irrespective of whether the
Applicant advised the third party that he could not honour the contract before
the third party ordered any materials and started to suffer any loss or not);
the Applicant would not have been liable for the substantiated and reasonable
holding costs (set out in section 2.3 of this Determination) associated with the
kit home and interest on the progress draws used for the purchase of the kit
home
the Applicant (given his circumstances, commitments, the purpose of the
funds sought, the economic climate at the time and the fact that the FSP held
a first ranking mortgage over the land with a high loan to value ratio) would not
have been able to source funds from an alternative financier to honour his
obligations under his kit home contract with the third party.
Consequently, the Applicant’s financial loss arising from the FSP’s conduct is the
sum of his substantiated holding costs and interest on the inappropriate
drawdowns as set out in section 2.3 of this Determination. The FSP’s conduct in
funding the progress payments without meeting its own requirements has also
caused the Applicant undue stress and inconvenience for which the FSP is to pay
him $2,000 in non-financial compensation.
1.3 Determination
This Determination is partially in favour of the Applicant. Should the Applicant
accept this Determination within 30 days of its date;
within a further 14 days of that acceptance, the FSP must in accordance with
section 2.3 of this Determination -
o split the Applicant’s home loan into interest and non -interest bearing
components backdated to 17 February 2015 as follows:
Revised Interest Bearing Debt $129,615.50
Revised Non-Interest Bearing Debt $93,623.39 (calculated as
$107,474.00 minus holding costs of $11,850.61 and non financial
loss compensation of $2,000)
Case No: 338310 Determination Page 3 of 11
Revised Total Debt $223,238.89
The FSP is liable to reimburse all substantiated holding costs and sale costs
associated with the kit home going forward (or absorb those costs should the
kit home be surrendered to it) until the kit home is sold in accordance with this
Determination.
within a further 4 months of his acceptance of this Determination the Applicant
is to –
o sell the land or surrender the land to the FSP for sale as a mortgagee in
possession, with the sale proceeds applied in reduction of the interest
bearing component of the home loan, with any surplus funds after that
reduction applied to the non-interest bearing component of the home
loan, and
o sell the kit home for market price and apply the sale proceeds in
reduction of the non-interest bearing component of the home loan, or
surrender the kit home to the FSP within that timeframe (for sale by the
FSP within a further 3 months for market price) - with the sale proceeds
applied in reduction of the non-interest bearing component of the home
loan
Both parties to this dispute have acknowledged that after the sale of the kit home
and the land, and the application of the reductions required by this Determination,
the Applicant will be left with a shortfall or residual unsecured debt of an as yet
unquantifiable amount (but expected to be in the lower range of the tens of
thousands). It is anticipated that all (if not almost all) of the residual shortfall debt
after the sale of the land will be from the interest free component of the
Applicant’s home loan. To the extent that the residual debt is in part or whole
from the interest free component of the Applicant’s home loan it is to remain
interest free until the Applicant has repaid it in full.
The Applicant has requested that the FSP waive his shortfall debt after the sale of
the land and kit home - or that FOS compel that waiver. As explained to the
Applicant, in circumstances such as these FOS cannot require the waiver of the
shortfall as FOS has found that the Applicant would have been liable for the
purchase price of the kit home absent the FSP’s behaviour. The FSP has
indicated that it is unwilling to waive the shortfall.
After the sale of the land and the kit home, the parties should work together to
agree upon a repayment plan for the unsecured shortfall debt that will see that
debt repaid in a reasonable period of time without causing undue hardship or
financial difficulty to the Applicant and his pregnant partner.
In the event the Applicant does not accept this Determination then the FSP is not
required to make any payment or reduction, and the Applicant will remain liable
for the full balance of the home loan.
Case No: 338310 Determination Page 4 of 11
2 Reasons for Determination
2.1 Should the FSP have granted the home loan to the Applicant in
July 2011?
It was appropriate for the FSP to fund the land purchase
The home loan offered by the FSP was a construction loan for $352,342.31 based
on the following application of funds:
Purchase land $159.000
Kit home purchase $104,524
Construction $ 97,318
$360,842
Less deposit $ 8,500
$352,342
In July 2011, prior to offering the home loan to the Applicant the FSP:
Completed a needs analysis of the Applicant.
Obtained documentation and information to support the finance request – that
is a copy of the land contract, kit home purchase price and estimated cost to
supply and build the kit home.
Received the loan application from the Applicant and assessed his capacity to
repay the loan.
Obtained its estimated “on completion” valuation and LMI approval.
To assist in my consideration of the FSP’s assessment and approval of the home
loan, I obtained the view of the Banking Specialist (the specialist). The specialist
has had extensive experience in the banking and financial services industry and
regularly provides FOS with advice about banking and financial services practice
and procedure and what constitutes good and standard industry practice.
The sp ecialist reviewed the FSP’s credit contract, the Applicant’s application and
supporting documents in respect of the home loan and relevant FSP policies and
advised that in his opinion:
The FSP engaged in responsible lending when it provided the home loan and
the proposed loan was not unsuitable.
Good industry practice did not require the Applicant to provide the FSP with
council approved plans and a fixed building contract at the time of making the
loan offer.
It was appropriate for the FSP to fund the land purchase of $159,000 under
the home loan offer.
Case No: 338310 Determination Page 5 of 11
2.2 Should the FSP have advanced progress payments for the
purchase of the kit home in 2011?
The funds to purchase the kit home were progress payments under a
construction home loan
The parties agree the home loan was to purchase land and construct the
Applicant’s home.
The loan contract provides that for a construction loan the FSP may lend the loan
amount in a series of advances provided certain requirements are first met. These
requirements include the provision of a signed building contract, council approved
building plans and appropriate insurance policy.
The FSP says the additional information (council approval, builder’s contract and
insurance etc), required under the loan contract and its internal policy was
required to provide funding for the construction of the kit home but not required for
the purchase of the materials to construct a structure.
The loan agreement does not distinguish between the funding of a kit home and
funding of building materials to construct a new home.
The FSP agreed to fund the construction of the Applicant’s home and knew the
Applicant intended to build a kit home as recorded in the loan application.
Following settlement of the land purchase in August 2011, the FSP advanced
funds to pay for the kit (building materials) for construction of the Applicant’s
home.
The FSP permitted progress draws of:
Date Action Amount
27 September 2011 Building consultancy fee $2,950
27 September 2011 Deposit on kit home $ 8,500
1 December 2011 Remaining cost of kit home $96,024
Total $107,474
The loan funds advanced to the Applicant and used to purchase the kit home
were progress payments under the home loan
It was not appropriate for the FSP to permit progress payments
Before approval of the home loan, the FSP received an email dated 25 July 2011,
from the kit home supplier to Mr C of the FSP. The email includes “an indicative
estimate” to buy and build the kit home of $195,000 to $210,000.
The FSP relied on this email when it assessed and approved the Applicant’s loan
application. The FSP’s home loan offer included the k it home purchase for
$104,524 and construction for $97,318 being a total of $201,842.
It is our specialist’s view that if the kit home could be constructed within the
original estimates of $97,318, it was reasonable for the FSP to exercise its
Case No: 338310 Determination Page 6 of 11
commercial discretion to permit the progress draws under the home loan to
purchase the kit, on the basis that the payments made were a cost that would be
incurred in the overall funding of the loan.
Neither party has provided a building quote within the original estimate. The FSP
says that the Applicant’s original builder could not complete construction of the kit
home because he went out of business. However there is no information to
support this statement.
The Applicant says there was no agreement that the kit home supplier would also
supply a builder. The Applicant says he was unable to source a local builder
prepared to construct the kit home within the original estimate of $97,318, as most
quotes were between $250,000 and $300,000. In August 2012, the Applicant
obtained a lower quote from a builder referred to him by the kit home supplier of
$257,900.
Both parties agree that no building contract or council approval was obtained
before the FSP funded the progress payments. Accordingly it appears the FSP
did not satisfy itself that the kit home could be constructed within the original
estimate.
It is our specialist’s view that good industry practice and the FSP’s C onsumer
Lending General Conditions Part B, clause 2, applied to the home loan so that
progress draws should not have been allowed:
without the FSP first obtaining council approved plans and a building contract
from the Applicant,
until it was satisfied that the total building project could be completed within
the remaining loan funds of $193,342.
As the FSP did not take the steps set out above, it was not reasonable or
responsible for the FSP to approve progress draws amounting to $107,474. I note
however that as the FSP is not the Applicant’s fiduciary, therefore it was not the
FSP’s role to secure a builder to build the kit home within the ori ginal estimate.
2.3 Has the FSP’s conduct caused the Applicant to suffer loss ?
The Applicant had a debt obligation before the progress payments were
made
On 23 September 2011, following approval of the home loan and land purchase
the Applicant agreed to purchase the 15.2 meter square kit home for $85,002. On
27 September 2011, the Applicant paid a deposit for the kit home using home
loan funds. From 23 September 2011, the Applicant was liable to the kit home
supplier for the price of the kit home.
On 16 November 2011, the Applicant and kit home supplier agreed to some
variations to the kit home at an additional cost of $19,522, bringing the total cost
of the kit home to $104,524. On 1 December 2011, the Applicant paid the balance
of $96,024 to the supplier of the kit home using home loan funds and took delivery
of the kit.
Case No: 338310 Determination Page 7 of 11
By signing the home loan offer with the FSP, on 5 August 2011, the Applicant
agreed to be bound by those terms. It is irrelevant whether or not the Applicant
read the document before signing it. Under Part B, clause 2.2 it is a requirement
for a construction loan that a signed building contract and approved council plans
be received by the FSP prior to the provision of funds for the construction of the
kit home.
In September 2011, without first obtaining a signed building contract and
approved council plans, the Applicant proceeded to enter an agreement with a
third party for the supply of the kit home , without knowing if the construction funds
would be provided. From that date on the Applicant had an obligation to pay the
supplier regardless of the actions of the FSP.
The progress payment of $96,024, drawn on 1 December 2011, satisfied the
remainder of the debt obligation that the Applicant had incurred to the kit home
supplier on 23 September 2011.
The available information does not establish that Applicant was misled into
entering the kit home contract
As set out above, before the progress payments were advanced the Applicant
entered a contract with a third party to purchase the kit home so that his liability to
the kit home supplier arose before his liability for the progress payments to the
FSP. The Applicant has stated that he received assurances from the FSP’s
employee that it was “ok to sign the contract” and that he relied to his detrim ent
upon those assurances. Neither party has been able to provide any corroborative
information to show what if any representations were made by the F SP’s
employee concerning the kit home contract. Consequently I cannot find that the
Applicant was misled into signing the kit home contract.
The Applicant’s non -financial loss
At the time the FSP funded the progress payments, which I have said was not
appropriate, if it had instead required the Applicant to provide council approved
plans and a building contract then the Applicant would have appreciated the steps
he was required to take to facilitate the construction of his home.
The FSP’s conduct in funding the progress payments without meeting its own
requirements caused the Applicant undue stress and inconvenience due to the
prolonged nature of his predicament, for which the FSP is to pay him $2,000
compensation to be deducted from the balance owing on the home loan.
What is the Applicant’s loss?
As noted earlier in this Determination, absent the FS P’s approval of the
drawdowns to pay for the kit home, the Applicant would still have been liable for
the contract price of the kit home. Consequently his financial losses as a result of
the FSP’s inappropriate approval of the progress payments for the ki t home are
comprised of the holding costs he incurred as a result of him being able to use the
drawn funds to complete his purchase of the kit home – to the extent that those
Case No: 338310 Determination Page 8 of 11
costs can be substantiated plus the interest that he has paid on the progress
draws used to pay for the kit home (as set out below).
To model the Applicant's debt, the FOS Banking Specialist (the Specialist) has
reconstructed the facility as though the inappropriately approved progress
drawdowns were not drawn. Using this method the Specialist has calculated that
the Applicant is entitled to an interest adjustment of $21,885.90 as at 17 February
2014 and has a revised debt of $237,089.50 with $129,615.50 being interest
bearing in nature and $107,474.00 non-interest bearing.
Calculations of interest due to the Applicant
Actual Interest Accrued as at 17.02.2015 = $51,130.81
Less: Reconstructed Interest Accrued as at 17.02.2015 $(29,244.91)
Interest Adjustment Due Applicant = $21,885.90
Holding costs
The Applicant has submitted receipts and a claim for costs to FOS including
indirect consequential losses (of a nature that FOS would generally not require be
refunded) associated with the Applicant’s mitigation steps, and legal advice. As
FOS is a free dispute resolution service that does not require Applicants to obtain
lawyers, as a matter of policy, FOS will only require the refund of an Applicant’s
legal costs in exceptional cases (generally involving extremely complex matters).
This dispute in my view does not fall within that category of exceptional cases.
Accepted holding costs submitted by the Applicant within FOS guidelines are as
follows
Pest and mitigation treatment costs relating to the kit home $732.80
Any marketing and sale costs relating to kit home – $0
Insurance relating to kit home as stored $1,277.00
Container hire $9,840.91
These holding costs to date are to be deducted from the non-interest bearing
component of the Applicant’s loan.
The holding costs associated with the storage, sale (if applicable), transport or
delivery (if sold) and insurance until the kit home is sold or surrendered to the
FSP are to be paid (by reimbursal to the Applicant upon the submission of
invoices) by the FSP. If the kit home is surrendered to the FSP the FSP must
absorb all holding and sale costs associated with the kit home after surrender.
I note that the Applicant has entered into a contract of sale with a purchaser for
the land and that accordingly the kit home (in its storage container) will need to be
moved off the land before settlement later this month (should settlement proceed
as planned). The FSP must reimburse the Applicant for the costs he incurs in
arranging the transport and new storage arrangements for the kit home should the
sale of the land proceed – within 7 days of the Applicant’s presentation of invoices
or receipts for those expenses.
Case No: 338310 Determination Page 9 of 11
Debt Structure should the Applicant accept this Determination
Revised Interest Bearing Debt as at 17 February 2015 = $129,615.50
Revised Non-Interest Bearing Debt as at 17 February 2015 = $107,474.00 minus
holding costs of $11,850.61 and non-financial loss compensation of $2,000 =
$93,623.39
Revised Total Debt as at 17 February 2015 = $223,238.89
Case No: 338310 Determination Page 10 of 11
3 Supporting information
3.1 Terms and Conditions
FSP’s Consumer Lending General Conditions (current at July 2011)
Part A: All Loans
Clause 53 “Meaning of words”
“construction loan means a loan where the Schedule stipulates that the purpose of your
loan is, or includes, the construction of a r esidential dwelling..”
Part B: Home Loans
Clause 2 “Our additional requirements if you have a construction loan”
Clause 2.1 “How we lend the loan amount for a construction loan”
“If we have a construction loan, we may lend the loan amount in a series of advances.”
Clause 2.2 “Requirements before the first loan advance under a construction
loan”
“We need not make the first loan advance unless the following requirements .....are all
satisfied:
......
(b) we have received:
(i) a copy of the fully signed building contract;
(ii) a copy of the building plans approved by the local authority;
(iii) a full set of the specifications signed by you and your builder;
....
(vi) an adequate and appropriate insurance policy in your name for the period of
construction for the contract price of the building work;
......”
3.2 FSP internal policy
Home Loan Policy (current at July 2011)
Clause 2.5.3 “Building, renovating or extending” of the FSP’s Home Loan Policy
which applied in July 2011 provides
“If the purpose of the credit application is to fund building, renovations or an extension,
we require a copy of singed ‘ Building Contract’ (for NSW, a copy of the signed and dated
contract must be provided on exchange).
This contract must include all special conditions and all attachments, and must be dated
and signed by all parties.
In addition, we require:
details of building costs and council approved plans
a copy of builders insurance coverage, and
a copy of Insurance Policy and [FSP] noted as an ‘interested party’.”
Case No: 338310 Determination Page 11 of 11
4 Other matters
4.1 Maladministration in lending and the appropriateness of the
FSP’s approval of the home loan as a whole
The Applicant has alleged that the FSP engaged in maladministration in lending in
advancing the home loan, citing an inappropriate loan to value ratio and the fact
that his deposit was substantially comprised of his first home owners grant. As
discussed with the Applicant and discussed earlier in this Determination, having
sought advice from FOS’ in -house expert Banking Specialist, I am satisfied that
the Applicant could service the home loan without substantial hardship, that the
initial loan approval was within the FSP’s lending policy and that the FSP did not
engage in maladministration in lending in approving it. With respect to the loan to
value ratio accepted by the FSP, this is a commercial risk decision by the FSP
and a decision not capable of review by FOS.
4.2 Unenforceable penalties under the kit home contract and the
components of the kit home price
It was a term of the agreement between the Applicant and supplier that the
Applicant would pay interest on any amount that remained outstanding to the
supplier at an escalating penalty interest rate plus additional penalty costs. Having
reviewed the contract as a whole and sought advice, I am not persuaded that
these penalty clauses for non-payment would be enforceable at law under the so
called Australian Consumer Law (set out in the Competition and Consumer Act
2010 (Cth)), should the Applicant have been sued for non-payment of the
purchase price by the kit home supplier. Consequently I am satisfied that the
extent of the Applicant’s liability under the kit home contract with the supplier
would have been the all-inclusive purchase price.
I note that the Applicant has contended that he should not be held liable for the
components of the purchase price that relate to the transport and delivery of the
kit home to the land. Having considered the contract as a whole it is my view that
irrespective of whether the Applicant completed the contract or not, he would
have been liable for the all-inclusive price.