Home / Financial Firm (Unknown - Credit) / Determination 335320

Determination 335320

Financial difficulty assistance for business loans in arrears

FirmFinancial Firm (Unknown - Credit)
Decided2014-09-22
ProductCredit · Business lending
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

Small business applicants in arrears on business loans complained about the FSP's financial difficulty assistance. AFCA found the FSP did not fully meet its obligations in 2011 and 2012, but its overall response was appropriate, ordered no compensation, and held that it cannot vary business facilities.

The FSP's response was reasonable given the time allowed to sell security, and AFCA has no power to vary business facilities that are not regulated by the National Credit Code.

Issues

Subjects and remedies

financial hardshipsmall businessno remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Business Finance - Business Loans - Financial Difficulty - FSP failure to respond to request for assistance Determination Case No: 335320 Determination Page 1 of 4 Case number : 335320 2 2 August 2014 1 Overview 1.1 Dispute The dispute concerns the financial difficulty the Applicants have been experiencing in meeting repayments to various business facilities held with their Financial Services Provider (FSP). As at 11 August 2014, the status of the facilities was as follows: Loan Balance Arrears Business Loan A $288,983.64 $71,787.29 Business Loan B $327,990.54 $54,679.73 Business Account $15,716.94 Full debt payable Business Overdraft $17,406,02 Nil – under its limit The business facilities are secured by three properties, two of which are residential, and one of which is a rural property. 1.2 Issues and key findings Did the FSP assist the Applicants with their financial difficulty? The FSP did not fully meet its obligations to give genuine consideration to the Applicants ’ requests for financial difficulty assistance from April 2011 to October 2012, because it did not ask the Applicants to provide financial information. However, the FSP did otherwise respond appropriately to the Applicants’ financial difficulty. Do I have power to vary any of the facilities? As the facilities are all for business purposes and are not regulated by the National Credit Code, I do not have the power to vary any of the facilities. 1.3 Determination This Determination is substantially in favour of the FSP.  The Applicants are not entitled to any compensation.  I do not have the power to vary any of the business facilities.  Once the file is closed, the FSP is entitled to rely on its contractual rights to recover the outstanding debts. Case No: 335320 Determination Page 2 of 4 2 Reasons for Determination 2.1 Did the FSP assist the Applicant s with their financial difficulty? An FSP should genuinely consider a business ’s requests for fi nancial difficulty assistance An FSP has an obligation to assist a small business in financial difficulty. Whether an FSP is able to provide ongoing assistance will be substantially influenced by the ability of the small business to demonstrate its ongoing viability. If the small business is unable to do so, based on reasonably tested information, then I would not expect an FSP to accept further risk. I expect small businesses to work with their FSP and to propose a realistic plan to repay the debt within a reasonable timeframe. If the business is unable to service the repayments to the loan, it may be that the most appropriate assistance is for the FSP to provide a reasonable time to refinance , sell assets to reduce the debt, or work with the business to achieve an orderly winding up of the business. The FSP did not fully meet its obligations to the Applicants in 2011 There are gaps in the information provided by the parties. However, it is apparent that the Applicants were experiencing difficulties from at least 11 April 2011. During a telephone discussion between the parties on that date, the Applicants explained that problems had arisen due to:  a poor harvest from their vineyard business in 2009  added financial strain caused by purchasing a recycling business  delays in receiving income from debtors  problems trying to sell one of the residential properties. The Applicants also advised that a sum of $100,000 was due and payable to a third party under the vendor finance agreement for the purchase of their recycling business, and requested the FSP to consider providing additional finance to meet this debt. The FSP declined to provide any further lending. The FSP’s decision to decline the Applicants’ request for further lending was a commercial one which I am unable to review. However, the FSP was under an obligation to genuinely consider the Applicant s’ situation, with a view to seeing what, if any, assistance (other than additional lending) it might reasonably be able to provide. The FSP did not fully meet its obligations, because although it was apparent at the time of the Applicants’ request for additional funds that their businesses were experiencing financial difficulties, the FSP does not appear to have requested the Applicants to provide information that would assist it to assess the ongoing viability of the business until much later, in October 2012. Case No: 335320 Determination Page 3 of 4 I consider below whether the Applicants are entitled to any compensation as a result of the FSP’s failure to request information about the Applicants’ business at an earlier stage. The Applicants are not entitled to any compensation During the period April 2011 to October 2012, the Applicants’ main proposal for remedying the arrears was to sell one of the security properties. Throughout this time, the FSP did not take action to try to recover the debts. It also refrained from charging any default interest to the facilities until April 2012, a full year after the Applicants first experienced financial difficulty. From April 2012, the FSP has been charging default interest on the Business Cheque and Overdraft facilities only, and not on the Business Loans. In my view, given that the Applicants had indicated that they intended to clear the arrears and reduce their debts through the sale of a security property, it was reasonable for the FSP to allow them time to do this. Although the FSP did not ask for detailed information about the Applicants’ financial circumstances until October 2012, it had effectively allowed the Applicants a period of at least a year without recovery action or default interest to try to sell the security property. Even though the property has not yet been sold, I consider the period allowed by the FSP to be more than reasonable in the circumstances. As the FSP’s response was appropriate, the Applicants are not entitled to any compensation. The FSP has met its obligations from October 2012 onwards In October 2012, the Applicants requested that the FSP consider allowing them to retain some of the sale proceeds from the expected sale of the security property to pay other creditors. The Applicants proposed to reduce the arrears on their facilities by an amount of $75,000. The FSP gave genuine consideration to the A pplicant’s situation at this time, as it:  Requested that the Applicants provide details of the financial position of the business, including a profit and loss statement, balance sheet, cash flow forecast, and tax returns.  Specified a timeframe for the Applicants to provide the information, namely, 31 October 2012, with an extension provided to 21 January 2013.  Assessed the information provided in January 2013. The financial information showed that the business was operating at a loss, and had been doing so for the previous two years. Based on this information, it was apparent to the FSP that the Applicants no longer had the capacity to service the debts.  Thereafter, the FSP attempted to contact the Applicants on numerous occasions to discuss options, but with little success. From June 2013 onwards, the FSP has proposed that the debt be repaid in full, either through selling one or both of the residential properties, or refinancing the debt. This was an appropriate response given the length of time that the facilities have been in default and given that the Applicants ’ financial difficulty appears to be longer term. The Applicants have not provided any alternative realistic proposals to repay the debt. They have not sold the residential property to reduce the debt despite the Case No: 335320 Determination Page 4 of 4 property having now been on the market in excess of four years. In August 2013, the Applicants were considering sourcing funds from a third party to expand the business by purchasing industrial land, which would have potentially increased their overall debt position and made it even more difficult for them to meet their existing obligations. In addition, since the lodgement of the dispute, the Applicants have made a number of requests seeking for the FSP to restructure the facilities and provide them with additional finance. More recently, the Applicants have indicated that they are exploring the possibility of refinancing the facilities to another financial institution. It is unclear whether they will be successful in doing this. In the absence of a refinance, selling one or both of the security properties would appear to be the only realistic way of repaying the debt. 2.2 Do I have the power to vary any of the facilities? While I have the power to vary certain types of credit contract, this only applies to facilities which are regulated under the National Credit Code. This power does not extend to commercial or business facilities. I have reviewed each of the facility contracts and I am satisfied they were granted primarily for business purposes. As such the credit contract is not regulated under the National Credit Code. This means that I do not have the power to vary any of the facilities. Once the dispute is closed, the FSP will be entitled to enforce its rights under the facility contracts.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.