Home / Financial Firm (Unknown - Insurer) / Determination 335232
Determination 335232
Adequacy of building settlement after cyclone damage
Summary
Landlords whose property was damaged by ex-tropical Cyclone Oswald disputed the FSP's building settlement and claims handling. AFCA found the settlement adequate on the disputed items but ordered ten weeks of lost rent, $1,500 non-financial loss and statutory interest.
The scope of works already covered the disputed items, but the claim was handled inadequately and the rent allowance should have run from when the FSP released repair funds.
Issues
- Claim amount dispute primary · not upheld
“The FSP's cash settlement offer for the building repairs adequately discharges its liability under the terms of the policy.”
- Poor claim handling secondary · upheld
“The original loss adjuster did not manage the claim or the issues raised by the Applicants in a timely or expedient manner.”
- Delay secondary · upheld
“A final scope and settlement offer were not finalised until July 2014, some eighteen months after the loss occurred.”
Subjects and remedies
home or building damagenatural disasterpay compensationpay interestpay non financial loss
Text of the determination
Determination
General Insurance - Domestic Insurance - Home Building - Service - Delay in Claim
Handling - Claim Amount
Determination
Case No: 335232 Determination Page 1 of 8
Case number: 335232 7 October 2014
1 Overview
1.1 Dispute
The Applicants hold residential landlord and home building policies underwritten
by the Financial Services Provider (FSP). The insured property was damaged by
ex-tropical Cyclone Oswald and a claim was lodged with the FSP for the damage
sustained.
The FSP accepted the claim and settled the loss by way of a cash payment for
the building repairs and forfeited rental income. The Applicants remain dissatisfied
with the amount offered in settlement by the FSP and the manner in which the
claim was handled by the FSP.
1.2 Issues and key findings
Has the FSP’s final offer of settlement fulfilled its obligations under the
terms of the policy?
In relation to the issues the subject matter of this Determination, the FSP has
fulfilled its obligations to the Applicants under the policy because the scope of the
works upon which the settlement offer was based included the disputed items.
However the FSP is to pay an additional ten weeks loss of rent because the
FSP‟s claims management was inadequate .
Are the Applicants entitled to compensation for the manner in which the
FSP managed their claim?
The policies exclude claims for financial consequential loss so the FSP is no t
obliged to pay this compensation.
The FSP is obliged to pay the Applicants $1,500 compensation for non-financial
loss because of inadequate and tardy claims handling.
The FSP is also to pay statutory interest on the building settlement sums from
1 September 2013 until the various dates of payment.
Interest is also to be paid on the additional ten weeks lost rent from the date of the
settlement offer made on 23 July 2014 until payment.
Case No: 335232 Determination Page 2 of 8
1.3 Determination
This Determination is partially in favour of the Applicants.
Should the Applicants accept the Determination the FSP is to pay the Applicants
an additional payment representing ten weeks of lost rent
interest on the building settlement funds from 1 September 2013 until the
various dates of payment
interest on the ten weeks lost rent from 23 July 2014 until payment
$1,500 compensation for the manner in which the FSP managed the claim.
Case No: 335232 Determination Page 3 of 8
2 Reasons for Determination
2.1 Does the FSP’s final cash settlement offer fulfil its obligations
pursuant to the terms of the policy?
The Determination deals with limited items in dispute
Since this matter came before the Service, a number of the issues disputed by the
parties have resolved. Accordingly, no further consideration will be given to those
issues in this Determination.
This Determination deals with the remaining items still in dispute which were set
out in the correspondence between the Case Manager and the parties in August
2014 and responded to by the FSP in its final Notice of Response namely:
Refitting windows and doors
Mould remediation
Loss of rent
Compensation
Other issues have been raised more recently but this Determination does not deal
with those issues while the parties are still in dialogue and negotiation regarding
those issues.
The FSP’s cash settlement o ffer for the building repairs adequately
discharges its liability under the terms of the policy
The FSP engaged a structural engineer N to review various issues raised by the
Applicants and after a further scope of works was prepared a selective tender was
conducted. Builders A and B submitted tenders.
A senior quantity surveyor R reviewed the tenders and as a result of that
consultation the FSP offered and paid the Applicants a combined total of
$213,657.84 in settlement for the building repairs. The offer was based on
material which included a number of PC (prime cost) allowances including $4,500
for the heating system in the house and $20,000 for mould investigation and
remediation works.
The Applicants agreed to accept this sum in settlement of the building repairs
although at the time and latterly raised issue with items they say are not included
in the scope of works upon which the offer was based.
The scope of works upon which the settlement offer was based includes the
items in dispute
Having consid ered the documentation that culminated in R‟s report dated 4 July
2014, I am satisfied that the scope of works included an allowance for the heating
system. An allowance of $4,500 for this item is clearly set out on the final page of
the report.
The Applicants say the scope of works does not include the replacement of
external French doors in the sum of $17,235.00 and painting the ceiling with
Case No: 335232 Determination Page 4 of 8
mould retardant paint for $3,957. They have provided quotations in these
amounts and seek payment from the FSP.
Having reviewed the documentation carefully I accept that the scope of works
allowed for reuse of existing doors where possible, with all existing doors, frames,
etc., to be sanded and repainted or re-stained and adjusted to ensure normal
operation.
Further, the Applicants have not provided any compelling independent evidence
to support the contention that the doors are not reusable and require replacement.
On the basis of the material provided, I am not satisfied that the Applicants‟ claim
is made out at this time. However, should the Applicants provide further
information to the FSP in support of their position after the work is completed and
the work is done to the doors as contemplated by the scope of works, the FSP is
obliged to consider this further information and determine its liability.
Review of the quotation from builder “B” shows that it includes an allowance for
two coats of Dulux paint for the all timber surfaces requiring repainting.
The Applicants‟ quotation does not specify which „ceiling‟ r equires repainting and
review of the B quotation and the scope of works show an allowance has been
included for repainting the ceiling of several of the rooms.
On balance, I am satisfied that this item is allowed for in the B quotation and the
amount subsequently offered in settlement by the FSP. On this basis, I do not
accept on the material provided, that the Applicants have established they are
entitled to additional funds for painting the ceilings.
The Applicants have not demonstrated they are entitled to additional
payments for the mould remediation
The initial scope of works allowed for mould remediation and this aspect was
quoted and included by B, who tendered the winning quote, in the amount of
$20,000 (plus $4,000 builder‟s margin).
However, thi s was a PC allowance and included in the FSP‟s cash settlement
offer on a bona fide basis so as not to delay settlement of the claim.
A PC allowance is simply an estimate or „best guess‟ of what that particular
component will cost. It does not reflect the actual costs that will be incurred.
Whilst this issue was on foot, the FSP engaged mould remediation specialists “W”
to inspect the property and provide a costed estimate for the works required. W
provided a firm quote of $8,976 for the works required. It is this amount the FSP
has offered in settlement.
W has further stated that in the event that the mould treatment proposed is
insufficient to remove all mould at the premises, W will undertake further works at
no additional cost. A clearance certificate will be provided at completion.
W‟s quotation has been reviewed by consulting engineer “N” who was satisfied
the scope was sufficient to remediate the home of mould and properly restore it to
Case No: 335232 Determination Page 5 of 8
its pre- loss condition. W‟s quotation includes remediation to bo th walls and
ceilings.
The Applicants have not provided any persuasive independent expert evidence to
say that either the scope proposed by W is insufficient or that the amount offered
by the FSP does not adequately reflect the costs to treat the mould at the
premises nor have they demonstrated they are entitled to additional funds for this
work. Further the Applicants have not provided any persuasive independent
expert evidence supporting their assertion that W‟s quotation only includes mould
remediation to the ceilings only and excludes the walls.
The Applicants further say they have already incurred costs of approximately
$20,000 in mould remediation to the walls, for which the FSP has not reimbursed
them. This was undertaken prior to the W inspection. However, the Applicants
have not provided any evidence to support their assertion that they incurred these
expenses. Therefore, no further consideration can be given to the matter.
Accordingly, on the information provided, and for the reasons stated I am satisfied
that the FSP‟s offer for the mould remediation is fair in the circumstances and
adequately discharges their liability under the terms of the policy.
The FSP has not adequately compensated the Applicants for loss of rent
The FSP‟s policy provides an additional benefit for payment of up to a maximum
allowance of 365 days loss of rental income. The FSP has paid the maximum
entitlement and in recognition that the scope was not finalised and funds not
remitted for the repair of the building until December 2013/January 2014, has
allowed a further 16 weeks of rental payments to cover the period when the
property is being repaired. This settlement was based on the estimate provided by
B, of there being a 12-16 week timeframe for the repairs.
The Applicants have not provided any evidence to suggest the repair will take
longer than 16 weeks and accordingly it is accepted that this timeframe is
reasonable.
However, it is fair in all the circumstances that the allowance should have been
calculated from the time the FSP made the funds for repair available, being
December 2013, as it is clear that even if the Applicants wanted to, they could not
begin the repair process without the funds necessary to do so.
Further, it is of note that when the initial scope was prepared by the loss adjuster
and quotations sought from builders in April 2013, the FSP did not remit those
funds to enable works to begin although the FSP has promptly and regularly
remitted periodic payments for the forfeited rental income.
Although the Applicants disputed the amount offered, there is no dispute that, at a
minimum, the FSP was liable to pay the amount established at that time as the
FSP‟s liability under the policy terms. What was in dispute was whether this
amount was sufficient to discharge its obligations under the policy.
However, the Applicants have had the benefit of most of the settlement funds
since December 2013 but do not appear they have made sufficient effort since
Case No: 335232 Determination Page 6 of 8
that time to commence repairs nor to mitigate their exposure to forfeited rental
income. They did not engage a builder to commence works on the property until
May 2014; some several months after the bulk of the funds were made available
to them to do so.
That the Applicants continued to dispute the cash settleme nt amount for the
repairs did not prohibit them from commencing works in an effort to mitigate their
loss of rent.
After considering all the material and allowing for the traditionally quiet holiday
period immediately following the payment of the first cash settlement and time for
the Applicants to make appropriate arrangements, I consider that it is fair in all the
circumstances that the FSP pay an additional ten weeks loss of rent to the
Applicants.
2.2 Are the Applicants entitled to compensation for the manner in
which the FSP managed their claim?
The policies exclude claims for financial consequential loss
The Applicants remain dissatisfied with the level of service they received from the
FSP throughout the management of the claim and the timeframe taken to resolve
the situation.
The FSP‟s policies specifically exclude consequential loss from the terms of
cover. On this basis, this Service is unable to consider an award of compensation
for consequential financial loss pursuant to its Terms of Reference (the Terms).
The Applicants are entitled to compensation for the manner in which the
FSP handled the claim as the initial claims management was inadequate
The Service is able to award compensation for non-financial loss pursuant to the
Terms if it is established that the conduct of the FSP caused the Applicants an
unusual degree of inconvenience or time taken to resolve the situation.
I am satisfied that the policy term is not sufficiently specific to prevent such an
award.
The simple passage of time is not a sufficient trigger for this award of
compensation. However review of the material provided shows the original loss
adjuster did not manage the claim or the issues raised by the Applicants in a
timely or expedient manner and greatly contributed to the delays experienced in
bringing this claim to a conclusion in an acceptable timeframe.
The FSP‟s email to th e loss adjuster of 24 June 2013 shows the FSP itself was
unhappy with the loss adjuster‟s carriage of the claim. However, it did not take
over conduct of the matter itself in an effort to speed things up and only requested
a new loss adjuster be appointed in August 2013.
Matters progressed in a smoother and more expedient manner from that point,
although it is of note that a final scope and settlement offer were not finalised until
July 2014, some eighteen months after the loss occurred. It is also noted that the
Case No: 335232 Determination Page 7 of 8
original offer to the Applicants was significantly less than the final offer which is
suggestive of a serious deficiency in the initial handling of the claim.
Although the Applicants have also contributed to the delay in resolving the claim
and the fact of their residing outside Australia has not assisted matters, I am
satisfied that the overall claim timeframe could have been substantially reduced
through more effective management of the claim on the part of the FSP.
The FSP has offered the Applicants the sum of $1,500 in recognition of the delays
experienced in bringing the matter to conclusion.
On the material provided and for the reasons stated I am satisfied that this
amount is fair in all the circumstances.
The Applicants are also entitled to interest
Pursuant to Section 57 of the Insurance Contracts Act 1984 (the Act), an insured
is entitled to interest on a settlement from the point it became unreasonable for
the insurer to withhold payment.
For a claim and loss of this magnitude, it is reasonable to expect the FSP should
have been in a position to make an encompassing and realistic offer of settlement
within about six months of the date of the loss.
Accordingly, after considering all the material provided I am also satisfied that it is
fair in all the circumstances that the FSP pay the Applicants interest at the
statutory rate on the settlement funds for the building repairs from 1 September
2013 until the various dates of payment.
Interest is also to be paid on the additional ten weeks lost rent from the date of the
settlement offer made on 23 July 2014 until payment.
3 Supporting information
3.1 FOS approach to this dispute
A full exchange of the relevant information has taken place between the
respective parties and each party has had the opportunity of addressing any
issues raised.
All of the provided material has been reviewed and considered. The parties have
raised numerous issues in their submissions to the Service. For the purpose of
this Determination, commentary is restricted to only those issues considered
relevant to the outcome.
3.2 Policy documents
The relevant extracts from the Policies are set out in the FSP‟s Notices of
Response.
Case No: 335232 Determination Page 8 of 8
3.3 Terms of Reference
“9.3 Other compensation
a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for consequential
financial loss or damage up to a maximum amount of $3,000 per claim made
in the Dispute.
b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the
Financial Services Provider compensate the Applicant for non-financial loss
but only where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant‟s expectation of
enjoyment or peace of mind has occurred; or
(ii) in the case of a Dispute pertaining to an individual‟s privacy rights -
injury has occurred to the Applicant‟s feelings or humiliation has been
suffered by the Applicant.
The maximum amount of compensation for non-financial loss will be $3,000
per claim made in the Dispute.
c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation
for:
(i) consequential financial loss; or
(ii) non-financial loss,
in a Dispute arising as a result of a claim on a General Insurance Policy that
expressly excludes such liability.