Home / Financial Firm (Unknown - Insurer) / Determination 333209

Determination 333209

Inadequate roof repairs and water damage claim

FirmFinancial Firm (Unknown - Insurer)
Decided2014-10-10
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$14,000
Non-financial loss—
Amount claimed$35,840
SourceAFCA PDF

Summary

A landlord claimed $35,840 for water damage to a rental property, blaming the insurer's inadequate 2008 hail roof repairs and failure to advise of an insufficient roof pitch. AFCA found the insurer liable for the rectification of the earlier repairs and related damage, but not the pre-existing pitch defect or damage from the landlord's delay, and ordered a $14,000 contribution with no interest.

The insurer is responsible for its repairer's failure to advise of the roof pitch and resulting damage, but the pre-existing pitch defect and the applicant's failure to mitigate limit its liability to a partial contribution.

Issues

Subjects and remedies

home or building damagepay claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - Service - Service quality Determination Case No 123456 Report type Page 2 of 2 Case number: 333209 11 September 2014 1 Overview 1.1 Dispute In 2012, the Applicant lodged a claim under his home insurance policy with the Financial Services Provider (FSP) for water damage to his rental property. The Applicant said that the damage occurred because the FSP failed to properly repair his roof following an earlier claim relating to a hailstorm in December 2007. The Applicant wants the FSP to pay for the costs of replacing the roof and repairing all of the internal damage to his property, which he estimates to be $35,840. 1.2 Issues and key findings Were the earlier repairs undertaken by the FSP sufficient? The FSP has acknowledged that there were issues with the earlier repairs which required rectification. In addition, the FSP and its repairer failed to advise the Applicant of the insufficient pitch of the roof when the replacement roofing tiles were installed in 2008. Is the FSP responsible for the repair costs? The FSP is not responsible for the costs of addressing the insufficient pitch of the roof, as this was caused by faulty workmanship and pre -existed the hail storm. However, the FSP is responsible for the rectification of the earlier repairs and for the additional damage which has arisen as a result of its failure to advise the Applicant about the insufficient pitch of the roof. However, the Applicant is responsible for the additional damage caused by his failure to appropriately progress his claim and/or take action to mitigate any further damage. 1.3 Determination This Determination is partly in favour of the Applicant. The FSP is pay the Applicant an amount of $14,000 as its contribution to the repair costs. No interest is payable on this amount. Case No: 333209 Determination Page 2 of 6 2 Reasons for Determination 2.1 Were the earlier repairs undertaken by the FSP sufficient? Repairs undertaken in 2008 were inadequate The Applicant says that the FSP’s repairer (R) failed to properly repair his ro of following hail damage in 2008. In particular, he says that R did not replace the damaged sarking (foil insulation material) which has resulted in the roof leaking constantly since 2008, causing further internal damage. It is not clear from the available information whether sarking was present prior to the repairs in 2008 and/or whether the FSP’s repairer (R) installed new sarking during the repair process. In this respect, I note that:  the repair of the hail damage in 2008 involved the replaceme nt of approximately 150 roof tiles and the repointing of the ridge capping. The itemised quote for the repairs does not include any reference to sarking;  the roofer (RR), who was appointed by the FSP to inspect the property in 2012, considered that the absence of sarking under most of the tiles at the back of the house had exacerbated the current issues with the roof (but was not the primary cause);  the builder (S), who was appointed by the FSP to inspect the property in 2013, confirmed that sarking was present and provided a photograph showing sarking under one roof tile; and  the Applicant’s builder (MB) has advised that the FSP’s repairer installed the replacement tiles over the existing sarking but that this was not done correctly. MB also says that the 2008 repairs did not comply with applicable building requirements because the repairer did not install an anti-ponding device. Accordingly, it is difficult to establish with any certainty whether the 2008 repairs were inadequate in relation to sarking and to what extent the possible lack of sarking has contributed to the current issues with the roof. It is also not clear whether the installation of the replacement roofing tiles was carried out correctly. While the FSP’s roofer (RR) noted certain potentia l issues with the manner in which the tiles were installed, its builder (S) confirmed that they have been installed in accordance with industry standards. Having said that, the FSP has acknowledged during discussions with the FOS Case Manager that there were issues with the repairs which required rectification. Nevertheless, the expert reports obtained by the FSP indicate that the absence of sarking (and/or the way in which the replacement tiles were installed) was not the primary cause of the current damage. Both the FSP’s builder (S) and roofer (RR) concluded that the current issues with the roof were primarily due to the fact that the roof did not meet the minimum pitch requirements for terracotta roofing tiles. The insufficient pitch of the roof allowed storm water to build up on the terracotta tiles and back over into the roof cavity Case No: 333209 Determination Page 3 of 6 below, causing internal damage. The Applicant’s builder (MB) agrees with S and RR that the pitch of the roof was insufficient. The 2008 repairs did not involve any repairs to the timber roof frame supporting the tiles and therefore there is no information to suggest that the insufficient pitch of the roof was caused by these repairs. On this basis, the FSP says that it is not responsible for any issues caused by the insufficient pitch, as this was a design fault which existed prior to the hail damage in 2008. I accept that the FSP was not required to rectify the insufficient pitch when it carried out the repairs in 2008. This issue was not caused by the hailstorm and also falls within the policy exclusion for faulty workmanship. However, I consider that good industry practice required the FSP’s repairer to advise the Applicant that the roof had insufficient pitch at the time he replaced the roof tiles, so that the Applicant could take appropriate steps to rectify the issue at his own expense. In my view, it is reasonable to expect the FSP’s repairer to have identified this issue given that:  each of the builders (S, RR and MB) who has subsequently inspected the roof has clearly identified the insufficient pitch as a significant issue; and  the relatively flat pitch of the lower part of the roof is obvious to the naked eye and could quickly and easily be verified with a digital level. The FSP is generally responsible for the actions of its contractors. The failure of the FSP and its repairer to advise the Applicant of the insufficient pitch of the roof (possibly exacerbated by inadequate installation of the sarking and roof tiles) has caused further leaks and water damage to th e Applicant’s property. In these circumstances, the FSP is responsible for any further damage which has occurred as a result. 2.2 Is the FSP responsible for the repair costs? FSP is not responsible for entire cost of roof repairs The available information establishes that the insufficient pitch of the roof was an issue which pre-existed the hailstorm in 2008. Accordingly, even if the FSP had advised the Applicant of this issue at the time, he would still have been responsible for bearing the costs of rectifying this issue. The FSP’s liability (then and now) would be limited to addressing any issues with the replacement of the hail-damaged roof tiles and related items. FSP is not responsible for entire cost of repairing internal damage The Applicant says that he first became aware of the leaking roof when he was advised by his tenant of the problem approximately six months after the repairs were completed. He says that the FSP failed to take any action to address the issue, until he followed up again in 2012. The FSP has confirmed that it has no record of the Applicant raising any concerns about the roof repairs before 14 September 2012, when it commenced Case No: 333209 Determination Page 4 of 6 investigating the issue. The FSP says that it should not be held responsible for the additional water damage to the property caused by the delay of several years in the Applicant reporting the issue. Even I were to accept that the Applicant first notified the FSP of the leaking roof in 2008/09, I consider that he has failed to act reasonably to follow up his claim and/or mitigate his loss during the intervening period of more than three years. Given the nature of the issue, it was to be expected that a failure to take action would result in further internal damage to the property during periods of heavy rainfall. Accordingly, the FSP should not be required to pay for the entire cost of repairing the internal damage to the property. Nevertheless, the FSP has denied liability for all of the repair costs in circumstances where it should be liable for at least some of these costs and did not offer the Applicant a cash settlement until after he lodged his dispute with FOS. In these circumstances, the FSP should be responsible for some of the additional damage to the property which has occurred during this period. FSP is responsible for part of the repair costs only The Applicant seeks payment of $35,840 based on a quote provided by his builder (MB). However, in addition to the repair of the internal water damage, this quote includes the complete replacement of the existing terracotta roof with a metal roof (for which the FSP is not liable). The Applicant was asked to obtain a breakdown showing the cost of each item included in MB’s quote but has been unable to do so. The FSP has acknowledged that the need for rectification of the repairs to the roof tiles and has estimated the cost of these works as $10,164. The FSP has also offered to pay the Applicant an additional amount of $2,018 (presumably for the repair of internal water damage resulting from the issues with the roof). Given the limited information available, it is difficult to determine the appropriate apportionment of costs between the Applicant and the FSP. In the circumstances, I consider that it is fair that the FSP be required to contribute $14,000 to the cost of the repairs. In arriving at this figure, I have had regard to the extent of internal damage to the property which is likely to have been sustained prior to the Applicant becoming aware of the problem in 2008/2009 (and which should be borne by the FSP). The FSP’s contribution also takes into account any interest to which the Applicant may be entitled. Case No: 333209 Determination Page 5 of 6 3 Supporting information 3.1 Experts’ reports Report Key points FSP’s builder (S B ) Report – 24 September 2012 (incorporates roofer’s comments)  There was water damage to the plaster ceiling and the cove cornice in the rear bedroom, which would need to be completely replaced.  The tenant confirmed that this damage was already present when she moved into the property approximately three yea rs earlier.  Based on RR’s report (see below), the water entry has occurred because the back skillion is under pitched, as a result of faulty workmanship. FSP’s roofer (RR) Report – 22 September 2012  Terracotta roof tiles (brand W) had been used to replace damaged tiles (C brand) throughout the roof following the hail storm several years earlier.  The large tiled roof area at the rear of the property had a long rafter below the minimum pitch required f or terracotta roof tiles. Due to the pitch being too flat on most of the back of the house, storm water is building up on the terracotta tiles and backing over into the roof cavity below, causing the leak.  There is no sarking on the majority of the back of the house, thus accentuating the problem of the flat pitch.  In a couple of area on the eastern side of the roof, the gap between the roof tiles had been pointed over in an attempt to stop stormwater entry.  A possible cause of the problem is that the roof tiles have slipped off the tile batten.  The back skillion roof needs to be sheeted with an appropriate metal roof and the terracotta tiles removed as they are not designed to handle storm water unde r a minimum of 17 degrees pitch (as compared to the curre nt pitch of 12.7 degrees). FSP’s builder (S) Report and s cope of works – 5 March 2013  The damage to the rear bedroom ceiling is consistent with water entry through the roof cavity.  The terracotta roof tiles were in fair condition (with no cracks apparent) , although sections of the roof were loosely fitted and cracks were apparent in the roof capping tile mortar bedding. The tiles were a mixture of old and newer tiles. There was sarking to the underside of the tiles.  The pitch of the roof above the rear be droom was between 13.7 and 13.2 degrees, which did not comply with the manufacturer’s minimum pitch requirement of 15º for tiled roofs with sarking.  The damage to the rear bedroom ceiling lining is the result of the under pitched roof which allowed water to seep through the gaps between the roof tiles . Case No: 333209 Determination Page 6 of 6 Report Key points  Although the roof does not comply with minimum pitch requirements, the replacement terracotta roof tiles had been installed in accordance with current industry standards and practices.  T he repair of the roof would require the removal and disposal of the terracotta roofing tiles on the southern end of the roof area and the removal and disposal of the timber roofing frame.  A new timber roofing frame would need to be installed with rafters allowing for a minimum pitch of 15 degrees in accordance with the applicable Australian Standard , and new terracotta tiles installed . Applicant’s builder (MB) Report – 9 June 2014  Australian Standard 2050 (Installation of roof tiles) applies to roof pitches of 15 de grees or greater.  Therefore, roof tiles should not have been installed to a pitch lower than 15 degrees. The Applicant should have received some consultation on how to remedy the situation at the time of the damage to his roof.  In 2008, the Building Code r equired an anti - ponding device / board to be used on roofs with a pitch of less than 20 degrees where sarking is installed.  The FSP’s failure to replace the sarking in 2008 breached the Building Code.