Home / Financial Firm (Unknown - Insurer) / Determination 332339

Determination 332339

Storm damage claim denied in part and delayed assessment

FirmFinancial Firm (Unknown - Insurer)
Decided2014-02-05
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$5,224
Non-financial loss—
Amount claimed$40,000
SourceAFCA PDF

Summary

Owners of a holiday house claimed for storm-related structural and ceiling damage that the FSP partly denied and assessed slowly. AFCA ordered a cash settlement of $5,224.45 for the ceiling damage, 65% of the structural repair cost (to be quantified by contractors), and interest on the ceiling amount; the applicants bear the other 35% and no non-financial loss was awarded.

Both insurer and insured had obligations to progress the claim, so liability for progressive structural damage was apportioned between them, with the insurer's delay and the insureds' failure to mitigate loss both weighed.

Issues

Subjects and remedies

home or building damagepay claimpay interestreassess claim

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 332339 Determination Page 1 of 15 Case number: 332339 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 08 January 2014 Summary Description  This dispute concerns a claim by the Applicants for storm damage to their holiday house, following the collapse of the living room ceiling. The FSP denied the claim on the basis that the damage was caused by various factors excluded under the policy. The Applicants say that the FSP failed to assess their claim for almost two years, during which period the property sustained further damage. Basis of Determination  The FSP failed to comply with its obligations to promptly assess the Applicants‟ claim. However, the Applicants also contributed to the delay in their claim being assessed and failed to take reasonable steps to mitigate their loss. Determination  The FSP should contribute 65% of the costs of repairing the structural damage to the Applicants‟ property. The Applicants are to contribute the remaining 35% towards the cost of repairs.  The FSP is not liable for the remainder of the disputed items of damage, on the basis that these are either excluded under the policy or could have been prevented had the Applicants taken reasonable steps to mitigate their loss. Background 1. The Applicants held a home building and contents insurance policy with the FSP which provided cover for their holiday house. Determination Case No: 332339 Determination Page 2 of 15 2. On 30 November 2010, the Applicants lodged a claim under the policy after the living room ceiling of the property collapsed as a result of stormwater entering through the tiled floor of the upstairs balcony. 3. The FSP initially declined the Applicants‟ claim on the basis that the damage was caused by various factors excluded under the policy, including a known structural defect. 4. After a further review, the FSP accepted the Applicants‟ claim for the initial damage to the living room ceiling and offered to cash settle them for $5,224.45 for the cost of repairing this damage. However, the FSP maintained its decision to deny the Applicants‟ claim for the remaining damage, including damage to the balcony and structural beam. 5. The Applicants are dissatisfied with the FSP‟s settlement offer and seek indemnity for the entire amount of their loss. The Applicants are also seeking compensation for non- financial loss suffered as a result of the FSP‟s handling of their claim. Summary of Applicants ’ position 6. The Applicants say that the damage to their property was ca used by a single storm event and was not due to ongoing maintenance issues (as alleged by the FSP). The Applicants say that the damage was caused when:  a single storm came crashing into the balcony sliding door, as result of which water made its way down to the underside of the balcony saturating the structural beam and eventually causing it to deflect. This caused the balcony to fall towards the home; and  from then onwards, even during normal periods of rainfall, the rain was directed into the already damaged area which resulted in the structure being affected, the beam rotting and the walls sinking. 7. Accordingly, the Applicants say that they are entitled to indemnity under the policy for all of the claimed damage (estimated at over $40,000). The Applicants want the FSP to authorise the repairs necessary to restore their home to the condition it was in prior to the storm in 2010 or cash settle them for the cost of the repairs. 8. The Applicants are also dissatisfied with the manner in which the FSP has handled their claim. In particular, the Applicants say that:  the FSP unreasonably delayed the appointment of an assessor and/or a builder, which resulted in additional damage to their home;  the assessor ultimately appointed by the FSP was biased, took into account irrelevant matters and made negative comments about the Applicants;  the FSP sent claim-related correspondence to the wrong address; and  the FSP generally delayed and mismanaged the handling of their claim. Case No: 332339 Determination Page 3 of 15 9. The Applicants say that the FSP„s handling of the claims process has caused them unnecessary stress and has adversely affected the health of the male Applicant. Summary of FSP’s position 10. The FSP relies on the reports of its assessor and its engineer in support of its decision to deny liability for the damage claimed by the Applicants (other than the initial damage to the living room ceiling). The FSP says that its consultants‟ reports establish that the claimed damage was caused by factors which are excluded under the policy (such as wear and tear, gradual deterioration and a known structural defect). The FSP notes that the Applicants have not provided any evidence to dispute the findings of its consultants. 11. The FSP acknowledges the Applicants‟ concerns in relation to the handling of their claim and the delays involved. However, it says that:  shortly after lodging their claim, the Applicants advised that they had appointed two builders to inspect the damage and quote on the necessary repairs;  at no time, did the Applicants notify it of any ongoing water entry issues or additional damage; and  to some extent, the delays in the claims handling process resulted from delays in the Applicants providing necessary information. Issues 12. Whether the Applicants are entitled to indemnity for the whole of the claimed damage to their property. 13. Whether the Applicants are entitled to compensation for non-financial loss as a result of the FSP‟s handling of their claim. Reasons for decision 14. As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the circumstances of the dispute. Accordingly, this dispute has not been the subject of a Recommendation and has proceeded directly to Determination. 15. I am satisfied that there has been an exchange of material information between the parties and that each party has had an opportunity to address any issues raised therein. Case No: 332339 Determination Page 4 of 15 16. The primary issues in dispute between the parties relate to the cause of the damage to the Applic ants‟ property, and the manner in which the FSP has handled their claim. Chronology of the claim 17. The claims records provided by the FSP reflect that:  when the male Applicant lodged the claim on 30 November 2010, he advised that part of the ceiling in the living room had collapsed due to extensive rain and a possible leak in the roof. The male Applicant subsequently advised the FSP that he had cleaned up and taken photographs of the damage;  on 1 December 2010, the FSP advised the Applicants that it did not have a preferred builder in the area. The Applicants agreed to arrange for two builders to attend the property and prepare a report on the cause of the damage and quote on the repairs required, which they would provide to the FSP;  on 4 January 2011, the male Applicant confirmed to the FSP that two builders had attended the property and would provide quotes;  on 4 April 2011, when the FSP called the male Applicant to follow up in relation to the quotes, he advised that he was having trouble arranging for a builder to attend but wanted the claim to be kept open;  on 2 May 2011, the FSP sent a letter to the Applicants advising that the claim would be closed if the builders‟ reports and photographs of the damage were not received within 14 days. This letter was mistakenly sent to the address of the insured property, rather than to the Applicants‟ recorded mailing address. When no response was received, the claim was closed in June 2011;  the male Applicant contacted the FSP on 23 March 2012 to advise that he had previously sent documents relating to the claim to a post office box, but would now fax them to the FSP;  on 13 April 2012, the male Applicant faxed the FSP a quote for $5,478 from a tiler for replacing the upstairs balcony tiles and installing a waterproof membrane, and a quote for $39,437.20 from a builder (“RH”) for repairing the damage to the upstairs flooring, structural beam and living room ceiling;  on 15 May 2012, the male Applicant contacted the FSP to follow up on his fax and the FSP explained that a further quote was required (which it appears had been inadvertently omitted from the original fax). The Applicants subsequently provided a further quote for $42,789 (excluding tiling) from a second builder (“WS”) which was not itemised;  on 28 May 2012, the FSP called the male Applicant to advise that it could either send a builder to inspect the property or arrange for a desk top assessment based on photographs of the damage. The male Applicant confirmed that he would prefer a desk top assessment, as he Case No: 332339 Determination Page 5 of 15 wanted to use local builders and would like the claim resolved quickly. The FSP confirmed that it also required a detailed scope of works from the second builder (WS);  on 22 August 2012, the male Applicant called the FSP to follow up the claim and advised that he had sent the documents requested. When the FSP advised that it had not received these documents, the male Applicant agreed to resend them;  on 19 October 2012, the male Applicant called again to advise that he had sent the documents, but the FSP advised that it had still not received them;  on 25 October 2012, the male Applicant sent the FSP a more detailed quote from WS. After reviewing the quotes, the FSP advised that an onsite assessment by an internal assessor and a structural engineer would be required;  on 1 November 2012, the FSP‟s assessor, builder and engineer inspected the property and identified significant structural damage requiring immediate make safe repairs;  on 26 November 2012, the male Applicant, advised the FSP‟s assessor that in January 2011 he had received a written quotation for $69,000 from one of the builders who initially attended the property. However, he had not sent this to the FSP as he believed the amount to be excessive;  following receipt of the assessor‟s report, the FSP de clined the Applicants‟ claim on the basis that the claimed damage had been caused by wear and tear, gradual deterioration and a structural defect that the Applicants should reasonably have known about, and therefore fell within exclusions under the policy;  after the Applicants disputed the denial, the decision was reviewed by the FSP‟s Internal Dispute Resolution (IDR) department which advised the Applicants on 18 December 2012 that the initial decision had been upheld;  on 17 July 2013, the Applicant‟s broker emailed the FSP to advise that the Applicants remained unhappy with the denial of their claim, following which a dispute was lodged with FOS; and  in October 2013, the FSP advised that it was willing to cash settle the Applicants for the initial water damage to the living room ceiling, and offered a cash settlement of $5,224.45 based on a quote provided by the FSP‟s builder. 18. The Applicants say that the FSP‟s claim records are not a true outline of events and omit certain facts. In particular, the Applicants say that they provided photographs and documents to the FSP on several occasions, and also advised the FSP that they were concerned about continuing structural damage to their property. However, the Applicants have not been able to provide any independent evidence (such as copies of correspondence or contemporaneous notes of telephone conversations) to support their position Case No: 332339 Determination Page 6 of 15 in this regard. In the absence of any such information, I am prepared to accept the FSP‟s contemporaneous claim records as prov iding a reasonably accurate reflection of the claims handling process. Damage to property Terms of policy 19. The Applicants‟ policy provides cover for damage caused by certain specified insured events, including “d amage caused by rain, wind, hail and storm”, which is covered under the insured event of “Storm and flood”. 20. However, this is subject to a number of general exclusions, including exclusions for:  damage caused by a defect, structural fault or design fault that the insured knew about (or should reasonably have known about) and did not fix before the damage occurred;  damage c aused by, or as a result of, the insured‟s failure to take reasonable care of the building and contents, keep the building and contents in good condition and well maintained and/or fix faults and defects as soon as he or she became aware of them; and  damage caused by wear, tear, rust, fading, gradual deterioration, mould, rising damp, mildew, action of light, atmospheric or climatic conditions, corrosion or rot, unless this is covered under certain other insured events (including the insured event of storm). Claimed damage 21. The FSP has accepted liability for the initial damage to the living room ceiling notified by the Applicants when they lodged their claim, and has offered to cash settle them for $5,224.45. However, the Applicants also seek indemnity for the following additional damage:  rotting of the structural beam above the living room;  water damage to the carpet, tiles and couches in the living room;  damage to the upstairs windows as a result of the movement of the structural beam; and  damage to the balcony (including the tiles). Available information regarding cause of damage 22. As noted above, the FSP‟s internal assessor (“CV”) inspected the property on 1 November 2012, in the company of an engineer (“WG”) and a builder. In his report dated 21 November 2012, CV states that: Case No: 332339 Determination Page 7 of 15  the male Applicant had confirmed to him that there was no sign of damage prior to 30 November 2010 and that the damage had occurred as described when he lodged the claim;  there was severe structural weakening in the ground level living room where a significant timber beam had rotted from long term water damage and had deteriorated so much that the engineer considered it to be dangerous and ordered make safe works;  there was also damage in a bathroom adjacent to the living room due to the sagging of building elements connected to the damaged beam, and the upstairs bedroom floor was found to be spongy in the vicinity of the structural beam;  the balcony outside the upstairs bedroom sloped towards the building, when it should have sloped away. It was also apparent from looking under one of the tiles that there was no waterproof membrane underneath them. This explained the water entry and the resulting damage;  the male Applicant had advised him that the tiles were laid around four years earlier. He initially said they had been laid by a tiler from Melbourne, but later advised that the work had been done by “a mate of mate” of his son with no invoice provided; and  on the date of the inspection, the beam and floor were wet from recent water entry and an armchair and floor rug were wet and damaged due to having been left within reach of the entering water. 23. The report provided by the structural engineer (WG) and included with the assessor‟s report states that:  the living room floor was wet from recent rain and the ceiling over part of the room had no plasterboard lining remaining, exposing the insulation batts;  the structural beam above the living room had deflected by approximately 300mm. The beam appeared to be made of timber (covered in plaster board) and was found to be soft when probed with a screwdriver, which was likely due to water rot;  the floor of the upper bedroom appeared to be bouncy, but the under- floor structure was inaccessible and therefore its condition could not be determined;  the balcony floor was constructed out of timber floor joists with fibre cement sheet, overlaid by ceramic tiles. When loose tiles were lifted, it was apparent that a waterproof membrane had not been laid over the fibre cement sheet;  the slope of the balcony towards the building appeared to be due to the excessive deflection of the timber beam underneath. The window header had also moved in a similar manner; and Case No: 332339 Determination Page 8 of 15  it appeared that no repairs had been undertaken since the initial damage in November 2010, and the underlying source of the damage had not been addressed. 24. Based on his observations and his discussions with the male Applicant, WG concluded that:  it was apparent that wind driven rain had over time saturated the floor of the upstairs balcony and, with no slope away from the building and no water proof membrane, the water had entered the ceiling space underneath, causing the ceiling to become saturated;  it was likely that water had entered over a period of time gradually causing the rotting of the structural beam and possibly the floor joist of the upstairs bedroom; and  the primary cause of water entering the living room ceiling was as a direct result of the poor construction of the upper floor balcony, in particular the tiles being laid with no definite fall away from the building and without a waterproof membrane underneath. 25. The FSP has provided a copy of a subsequent letter from the engineer (WG) dated 27 September 2013 in which he stated that:  it was highly unlikely that water entering as a result of a one off storm event caused the collapse of the ceiling and the additional rotting damage; and  when he inspected the property on 1 November 2012, no remedial repair works had been attempted nor had any protection barriers been put in place to prevent ongoing water entry; and  if remedial works had been carried out in a timely manner, then the timber floor beam would have been structurally sound and only cosmetic repairs would have been required. 26. The Applicants say that the damage to their property arose from a single storm event which resulted in water entering under the tiles of the upstairs balcony and saturating the structural beam. They say that this caused the beam to deflect which resulted in the balcony sloping towards the building, meaning that any further rainfall was directed into the damaged area causing further water rot. 27. The Applicants have provided information from the Bureau of Meteorology in relation to rainfall levels during 2011. However, this information shows rainfall levels for the whole of Australia, and does not provide any specific information about rainfall in the area where the Applicant‟s property is located. Further, the Applicants have not provided any expert evidence which supports their explanation of how the damage occurred or which contradicts the findings of the FSP‟s consultants regarding the cause of the damage. Case No: 332339 Determination Page 9 of 15 Analysis regarding cause of damage 28. There is an onus on an insured to establish on the balance of probabilities that a claim fits the definition of an insured event. This is known as a prima facie claim. Should this onus be discharged, it is then the responsibility of the insurer to establish that, on the balance of probabilities, the claim falls within an exclusion under the policy or it is otherwise entitled to deny liability for the claim. 29. The FSP‟s engineer determined that the primary cause of the damage to the Applicants‟ property was rainwater entering underneath the balcony tiles, due to the inadequate construction of the balcony and, in particular, the tiles being laid with no definite fall away from the building and without a waterproof membrane underneath. 30. I am satisfied that the FSP‟s engineer is appropriately qualified to report on the cause of the damage, and that his report provides a logical explanation of how the damage occurred. The Applicants have not provided any expert evidence which disputes the findings of the FSP‟s engineer and therefo re I am satisfied that the primary cause of the damage to the Applicants‟ property was the inadequate construction of the balcony. 31. The FSP initially sought to deny the whole of the Applicants‟ claim on various grounds, including under the exclusion for damage caused by a structural or design fault that the Applicants knew about (or should reasonably have known about) and did not fix before the damage occurred. The FSP said that the male Applicant (as a builder) should reasonably have known about the absence of a waterproof membrane, and/or should have become aware that water was leaking through the balcony tiles and the ceiling, and undertaken appropriate repairs before the claimed damage arose. 32. The FSP has subsequently accepted liability for the damage to the living room ceiling which the Applicants initially reported when they lodged their claim in November 2010. I consider that it is appropriate for the FSP to accept liability in this regard, as there is insufficient evidence to suggest either that the Applicants knew that the balcony tiles had been installed incorrectly, or that it was apparent that water was entering the building prior to November 2010. 33. However, the FSP has continued to deny the Applicants‟ claim for the remainder of the damage (including the structural damage), on the basis that this occurred after the claim was lodged in November 2010, by which time the Applicants had become aware of the defect in the construction of the balcony. The FSP says that this further damage occurred as a res ult of water continuing to enter the property during subsequent periods of rainfall due to the Applicants failing to take any remedial action. 34. As is apparent from the chronology set out above, the Applicants‟ claim was not assessed by the FSP until 1 November 2012, when the FSP‟s internal assessor and engineer attended the property to inspect the damage. This was almost two years after the Applicants had first lodged their claim, and it Case No: 332339 Determination Page 10 of 15 appears that the Applicants had not taken any action in the meantime to repair the existing damage or to prevent further damage. 35. The type of damage sustained to the Applicants‟ property (ie rotting due to water entry) by its nature occurs over a prolonged period of time, rather than as the result of a single event. Accordingly, it is very difficult to determine when the damage observed by the FSP‟s assessor in November 2012 occurred (ie before November 2010, during November 2010 or between November 2010 and November 2012). 36. The FSP‟s assessor noted the possibility that a significant portion of the damage observed in November 2012 may have occurred well before the Applicants‟ claim was lodged in November 2010 (particu larly in light of the Applicant‟s advice that they obtained a quote for $69,000 for repairing the damage in January 2011). I accept that this is entirely possible. It is not uncommon for structural damage of the type sustained to the Applicants‟ property to be well advanced before any external evidence of the damage becomes apparent. 37. However, given the nature of the damage and the fact that no steps were taken to address the underlying cause, I consider it likely that significant additional damage also occurred after the Applicants lodged their claim in November 2010. It is not disputed that water was continuing to enter the property through the balcony floor tiles, and the FSP‟s assessor observed evidence of recent water entry when he attended the property on 1 November 2012. 38. Both the difficulty of determining the extent to which the claimed damage occurred prior to 30 November 2010, and the fact that additional damage continued to occur since that date, are attributable to the period of approximately 23 months which elapsed before the FSP assessed the Applicants‟ claim. 39. The Applicant s claim that this has occurred solely due to the FSP‟s inadequate claim handling. However, the FSP says that the manner in which the claim was handled (and, in particular, the delay in undertaking an assessment) can be explained in part by the FSP‟s relian ce on certain information and undertakings provided by the Applicants. 40. Accordingly, it is appropriate for me to consider the obligations of each party in relation to the claim, and the extent to which each party should be held responsible for the delay i n the FSP assessing the damage to the Applicants‟ property. Obligations in relation to the claim 41. In accordance with law and good industry practice, both an insurer and an insured are expected to comply with certain obligations in order to ensure the effective resolution of a claim lodged under a policy of insurance. Case No: 332339 Determination Page 11 of 15 42. The product disclosure statement (PDS) in relation to the Applicants‟ policy sets out the obligations of the insured when an event giving rise to a claim occurs. Under the policy, such obligations include:  doing everything reasonably possible to prevent further damage;  contacting the FSP without delay to lodge the claim and providing accurate details of the damage;  allowing the FSP to inspect the damage and arrange for experts to assess the damage and quote on repairs;  providing a quote for repairs if requested to do so by the FSP (unless the insured elects to use the FSP‟s recommended repairers, if available); and  not authorising repairs without the FSP‟s consent unless emergency repairs are required and the FSP cannot be contacted. 43. An insurer is also required to act promptly and without due delay in assessing a claim, and arranging for the claim to be settled in an appropriate manner. In this regard, I note that the PDS for the Applicant‟s policy states that: “Usually allowing us, a repairer or an expert appointed by us, to look at what is damaged is all that is needed to prove your loss.” Compliance with obligations 44. In my view, the chronology of events (as set out above) indicates that both the FSP and the Applicants have failed to comply with their obligations in relation to the claim process. 45. As outlined above, where a claim is lodged under the policy, responsibility rests with the FSP to assess the damage. In the present case, the available information indicates that the FSP and the Applicants initially agreed that the Applicants would be responsible for obtaining two quotations for the repair of the damage and providing photographs in order to enable the FSP to make a desktop assessment (in part, because of the lack of availability of panel builders in the area and due to the number of claims which the FSP was dealing with as a result of the Queensland floods). The FSP says that, in adopting this approach, it relied on the initial description of the damage provided by the Applicants when the claim was lodged, which led it to believe that the claimed damage was relatively minor. 46. I accept that it was reasonable for the FSP to adopt this process to manage the claim in circumstances where the Applicants had expressly agreed to this. However, in choosing to rely on the brief description of the damage and awaiting the provision of additional information by the Applicants, the FSP exposed itself to the risk that the damage might turn out to be more extensive than initially reported and/or its approach to managing the claim might limit its ability to accurately assess the claim. Case No: 332339 Determination Page 12 of 15 47. As time passed and the Applicants failed to provide the necessary information to enable the FSP to assess the claim, the ri sks of the FSP‟s chosen approach increased. At any time during the claims process, it was open to the FSP to take positive action to appoint its own contractors to assess the claim and arrange an appropriate settlement, thereby mitigating its potential risk exposure. Further, I consider that, as a well-resourced, professional organisation with the primary responsibility for assessing the Applicants‟ claim, it would have been appropriate for the FSP to do so. In particular, I note that:  the FSP could have taken action to appoint its own assessor and/or builder in April 2011, by which time it was clear that the Applicants were having difficulty obtaining the necessary quotations; and  when the Applicant provided the initial repair quotations in April 2012, it should have been apparent to the FSP that the damage was considerably more extensive than was apparent from the Applicants‟ initial report. Notwithstanding this, the FSP did not carry out its own assessment of the damage until more than six months later. 48. Additionally, it appears that the FSP ceased following up the claim in June 2011, when the claim was closed due to the Applicants‟ failure to respond. However, the available information indicates that the FSP‟s letter advising that the claim would be closed was not sent to the correct address. Accordingly, the FSP must bear some responsibility for the period of inactivity which occurred between June 2011 and March 2012, when the Applicants contacted the FSP again to follow up on the progress of the claim. 49. However, it is apparent that the Applicants have also failed to comply with their obligations under the policy to provide the information requested by the FSP to assess their claim, in accordance with the approach agreed between the parties. 50. I note that the Applicants have stated that they sent information to the FSP by mail, fax and/or email, but the FSP appears to have no record of this. The FSP‟s claim records indicate that it attempted to assist the Applicants to send through the necessary documentation by providing them with alternative contact details on a number of occasions. However, the Applicants have not been able to provide any independent evidence (such as copies of correspondence or contemporaneous notes of telephone conversations) to support their position. Accordingly, it is not entirely clear which party bears responsibility for this failure in communication. 51. However, I note that:  it appears that at no time have the Applicants provided photographs of the initial damage, despite advising the FSP on 30 November 2011 that such photographs were available. Given that they were taken at the time the initial damage occurred, such photographs may have been of considerable assistance in allowing the FSP to assess the damage and determine its liability; Case No: 332339 Determination Page 13 of 15  based on the information in the FSP‟s claim records, the Applicants appear to have provided inconsistent information to the FSP in relation to their progress in obtaining quotations for the necessary repairs. The claim records indicate that in January 2011, the Applicants advised the FSP that two builders had attended the property and would provide quotations. However, in April 2011, the Applicants advised that they had not yet been able to obtain any quotations;  the reports of the FSP‟s assessor and en gineer indicate that the Applicants did not make any attempt to prevent further damage to the property as a result of the rain entering through the tiled balcony floor after 30 November 2010. The Applicants say that they did not undertake any repairs as a result of advice from their broker that this may prejudice their claim. However, they have not provided any correspondence from the broker to this effect. I have also reviewed a letter dated 14 July 2013 from the male Applicant to the broker, which suggests that, prior to this date, the Applicants had not approached the broker for assistance in relation to their claim;  while I accept that the policy imposed restrictions on the Applicants authorising repairs without the consent of the FSP (subject to an exception for emergency repairs), I consider that it was not reasonable for the Applicants to take no remedial action at all over the course of almost two years, in circumstances where it would have been apparent that there was a significant further damage to the property; and  while the Applicants say that they advised the FSP that further structural damage was occurring and their property had become unsafe, the FSP‟s contemporaneous records do not reflect this and the Applicants have not provided any further information to support this. Liability for property damage 52. For the reasons outlined above, I consider that both the FSP and the Applicants have contributed to the ongoing delays in resolving the claim. This has made determining the FSP‟s liability under the original claim more difficult (given the amount of time which passed before the damage was assessed) and has also resulted in further damage to the property occurring over the course of a two year period. 53. Accordingly, I consider that it is fair in all the circumstances to require both the FSP and the Applicants to contribute to the costs of repairing the damage to the property. Specifically, I consider that:  in addition to indemnifying the Applicants for the cost of repairing the initial damage to the ceiling, the FSP should be required to indemnify the Applicants for 65% of the costs of repairing the damage to the structural beam and any resulting damage (including to the upstairs bedroom windows). In determining the FSP‟s liability, I have had regard to the possibility that some of the damage to the structural beam occurred prior to 30 November 2010 (and may not have been covered by the insured event of storm , given the FSP‟s engineer‟s report ), as Case No: 332339 Determination Page 14 of 15 well as the extent to which the FSP was responsible for the delays in resolving the Applicants‟ claim, in light of its obligations as a well - resourced, professional insurer. The Applicants are to contribute the remaining 35% towards the cost of repairs arising from their part in the extended delay in finalising the claim and their failure to take reasonable steps to mitigate their loss;  the FSP is not liable for the water damage to the carpets, tiles, lounge or any other contents in the living room. The Applicants did not report any such damage when they lodged their initial claim and accordingly, it seems likely that any such damage occurred after 30 November 2010. I consider that this damage is attributable to the Applicants‟ failure to take action to mitigate the loss (which in respect of these items, could have been done relatively easily); and  the FSP is not liable for the costs of repairing the damage to the upstairs balcony, given that, based on the FSP‟s engineer‟s report, this was a structural or design fault which existed prior to the insured incident. The quotations from the tiler and the builder (RH) obtained by the Applicants in January 2011 indicate that, at that time, the complete replacement of the tiles and balcony flooring was required, and therefore I consider that no part of this damage is attributable to the delay in finalising the Applicants‟ claim. 54. I note that the quotation obtained by the FSP from its builder (P) relates to the repair of the initial damage to the living room ceiling only (on the basis that this was the only item for which the FSP had accepted liability). Accordingly, for the purposes of determining the amount of the cash settlement payable by the FSP in accordance with the above, the FSP is to appoint appropriately qualified contractors to prepare a scope of works and quotation for the repair of the damage to the structural beam and any resulting damage. Other claim handling issues 55. I have taken into account many of the issues raised by the Applicants in relation to the FSP‟s handling of their claim in the context of assess ing the FSP‟s liability for the claimed damage to the Applicants‟ property. In this regard, I consider that the requirement for the FSP to indemnify the Applicants for part of the costs of the structural damage to their property adequately compensates them for the effect of the delays they experienced in the handling of their claim. 56. However, the Applicants have also raised concerns that the FSP‟s assessor and engineer was biased, took into account untrue and irrelevant matters and made negative comments about the Applicants. 57. I have reviewed the reports prepared by the FSP‟s assessor (CV) and engineer (WG). It is clear from their reports that both CV and WG conducted an extensive inspection of the Applicants‟ property and noted a number of maintenance items, which were unrelated to the damage claimed by the Applicants. In an email dated 21 November 2012, the assessor advised the Case No: 332339 Determination Page 15 of 15 Applicants that these items were not relevant to the claim but should be rectified so as not to prejudice their insurance cover. The engineer‟s report noted that some of these items also gave rise to the risk of personal injury. 58. In his report, the FSP‟s assessor noted that the general poor condition of the property was consistent with the Applicants‟ apparent failure to take action to mitigate ongoing damage to the property after the claim was lodged on 30 November 2010. 59. Having considered the totality of the FSP‟s claim records, I am satisfied that the FSP‟s assessor and engineer acted appropriately in identifying various maintenance issues at the property, and bringing these to the attention of the Applicants. 60. I do not consider that the FSP relied on any irrelevant matters for the purpose of assessing the Applicants‟ claim. In particular, I note that the primary basis on which the FSP considered that the Applicants had failed to mitigate their loss was the state of the living room as observed by the assessor and engineer when they inspected the property on 1 November 2012 (rather than the general condition of the property). Determination 61. On the basis of the available information I determine that:  within 30 days of the Applicants accepting this Determination, the FSP is to appoint appropriately qualified contractors to prepare a scope of works and quotation for the repair of the damage to the structural beam and any resulting damage (including damage to the upstairs bedroom windows);  the FSP is to cash settle the Applicants for an amount equal to: i. 65% of the amount of the quotation for the repair of the damage to the structural beam and resulting damage (as determined in accordance with the above); and ii. $5,224.45 (being the estimated cost of repairing the initial ceiling damage), plus interest on this amount only, in accordance with section 57 of the Insurance Contracts Act 1984 from 30 May 2011 (being six months after claim lodgement) to the date of payment;  the Applicants are not entitled to indemnity for any of the remaining damage to the property; and  the Applicants are not entitled to compensation for non-financial loss as a result of the FSP‟s handling of their claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.