Home / Financial Firm (Unknown - Credit) / Determination 330768

Determination 330768

Judgment listing linked to wrong person on credit report

FirmFinancial Firm (Unknown - Credit)
Decided2015-02-16
ProductCredit · Other credit
OutcomeFor the complainant
Amount awarded$1,839
Non-financial loss$1,000
Amount claimed$1,839
SourceAFCA PDF

Summary

A judgment listing belonging to a namesake was linked to the applicant's credit report, delaying his property settlement. AFCA ordered reimbursement of $1,839.13 in default interest and credit report cost plus $1,000 for non-financial loss.

The Credit Reporting Code requires reasonable steps to ensure listings are accurate, and the FSP's linking error caused the applicant's settlement delay and financial loss, though its removal was prompt.

Issues

Subjects and remedies

pay compensationpay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Consumer Credit - Non FSP Debt - Privacy & Confidentiality - Consumer credit reporting Determination Case No: 330768 Determination Page 1 of 6 Case number : 330768 12 February 201 5 1 Overview 1.1 Dispute The Applicant purchased a property and sought a home loan from a bank. The Applicant’s application for finance was initially declined due to a judgment listing on his personal credit information file (Credit Report) maintained by the Financial Services Provider (FSP), which is a credit reporting agency. Upon further investigation, it was apparent that the judgment listing should have been linked to the credit information file of another person with the same first name and last name. Subsequently, the FSP removed the judgment listing from the Applicant’s Credit Report . The Applicant claims that settlement on the purchase of his property was delayed due to the judgment listing causing him loss in default interest. The Applicant is seeking compensation in the sum of:  $1,769.18 in additional default interest paid under the Contract of Sale, and  $69.95 for the cost of obtaining his Credit Report. 1.2 Issues and key findings Did the FSP take reasonable steps in accurately recording the judgment listing? The FSP did not take reasonable steps to ensure the judgment listing was accurate. Did the FSP unreasonably delay amending the Applicant’s Credit Report? The FSP did not unreasonably delay amending the Applicant’s Credit Report. The FSP reviewed the Applicant’s concerns and took appropriate steps to check the accuracy with the relevant third party within a reasonable period of time, which resulted in removal of the judgment listing. Did the Applicant suffer a loss as a result of the Judgment Listing? The Applicant suffered a loss as a result of the judgment listing on his Credit File for which he should be compensated (should he accept this Determination) in accordance with section 2.3 of this Determination below. 1.3 Determination Case No: 330768 Determination Page 2 of 6 This Determination is substantially in favour of the Applicant. The FSP did not take appropriate steps to ensure the accuracy of the judgment listing on the Applicant ’s Credit Report in the first instance. The FSP made an error in linking the Applicant’s credit information file with a third party’s credit information file, which caused him to suffer a loss. However, the FSP did take reasonable steps in amending the Appli cant’s Cr edit Report in a timely manner, namely within 14 days after the dispute was raised. Should the Applicant accept this Determination within 30 days of its date (above), within a further 14 days of that acceptance, the FSP must pay to the Applicant a total of $2,839.13 in compensation for his financial and non-financial loss. That award is comprised of the following components:  $1,769.18 in reimbursement of default interest paid as a result of the Applicant’s property settlement having to be delayed (due to the delay in finance approval resulting from the judgment listing shown on the Applicant’s Credit Report maintained by the FSP).  $69.95 for the cost of obtaining his Credit Report.  $1,000 in non-financial loss for the stress and angst suffered by the Applicant as a consequence of discovering the incorrect information in his Credit Report. 2 Reasons for Determination 2.1 Did the FSP take reasonable steps to ensure the judgment listing was accurate? The FSP made an error in creating the judgment listing on the Applicant’s credit file The FSP did not take reasonable steps to ensure that the listing was accurate. The FSP failed to ensure the full name of the judgment debtor was checked on its system and link it to the correct person. The Court had provided the FSP with the full name of the judgment debtor, including middle name. Given that the Applicant’s full name, which includes a middle name is not that of the jud gment debtor identified by the Court to the FSP, the judgment listing on the Applic ant’s Credit Report could have been avoided in the first instance. The FSP relied on its automated system using set linking parameters and algorithms. Whilst the system operated as intended, the system does have a margin of error and can in some circumstances link the credit information files of unrelated parties in the instance where they have the same first and last name, and address. It does not appear that the full name and judgment debtor ’ s date of birth were used when the search was conducted, whic h in this instance may have also prevented the judgment listing being made against the Applicant. The FSP has Case No: 330768 Determination Page 3 of 6 confirmed it only used the first name and last name, and street address to identify the Applicant when the judgment listing was entered. Despite the judgment debtor and the Applicant having had the same listed street address, it is clear the discrepancy in their full names was enough to have caused the FSP to make further enquires before making the listing in the first instance. 2.2 Did the FSP unreasonably delay amending the Applicant’s Credit Report? The FSP amended the Applicant’s Credit Report in a timely manner The FSP took reasonable steps to investigate and remove the disputed judgment listing. The FSP’s usual procedure in removal of Court jud gments is a 30 calendar day timeframe. In this instance, it received the corresponden ce from the Applicant’s lawye r on 17 July 2013 in relation to the disputed judgment listing, it then investigated the matter and removed the disputed entry and responded to the Court and the Applicant’s law yer within 14 days, on 31 July 2013. The following is a chronology of events: Date Action Saturday, 29 Jun e 2013  The Applicant executed contract of sale for property Wednesday, 3 July 2013  The Applicant obtained approval in princip l e from the bank for t he property purchase Monday, 15 July 2013  The Applicant ’ s banking institution sought Applicant’s individual credit report f r o m the FSP Wednesday, 17 July 2013  The Applicant ’ s banking institution declined to progress his home loan application due to the listing  The Applicant was notified by his mortgage broker of the judgment listing on his Credit Report  The Applicant sought the Court Judgment records  The Applicant ’s lawyer emailed the FSP ’s corrections de partment regarding its error noting Applicant’s full details (including full name, date of birth, driver’s licence, current and previous addresses) Thursday, 18 July 2013  The Applicant’s lawyer emailed the FSP ’s customer support department informing them of the error Friday, 19 July 2013  The Applicant’ s lawyer wro te a Letter of Demand to the FSP putting it on notice regarding the purchase of property and settlement date of 29 July 2013, noting finance could not be approved due to judgmen t listing Monday, 22 July 2013  The Applicant’s lawye r wrote to the FSP requesting Case No: 330768 Determination Page 4 of 6 the removal of the judgment as it was delaying the property settlement causing financial loss Tuesday, 23 July 2013  The FSP received correspondence from the Magistrates’ C ourt regarding the error in judgment listing the Applicant and requesting credit file to be amended accordingly Wednesday, 24 July 2013  The Applicant’s lawyer delayed the settlement of the purchased property which was scheduled on Monday 29 July 2013 t o 12 August 2013, and confirmed default interest will be paid for the 14 day period at 2% in the sum of $1,769.18 Thursday, 25 July 2013  The FSP received correspondence from the Applicant’s lawyer forwarding the Magistrates’ Court email of 23 July 2013  Th e FSP emailed the Magistrates’ Court seeking further information Monday, 29 July 2013  The Applicant’s lawye r wrote to the FSP requesting timeframe within which the Credit Report would be amended, noting that the Applicant was now paying default interest under the Contract of Sale as the property could not be settled today Wednesday, 31 July 2013  The FSP remov ed the judgment listing dated 30 January 2012 , from the Applicant’s Credit Report  The FSP notified the Applicant’s lawye r and the court in relation to same via email Monday, 12 August 2013  The Applicant s ettled on the purchased property 2.3 Did the Applicant suffer a loss as a result of the Judgment Listing? The Applicant did suffer a loss as result of the FSP’s actions Based on the available information, the Ap plicant’s claim that the erroneous listing of the judgement on his Credit Report caused a delay in his property settlement has been established. The Applicant had an in principle approval of the finance from his bank in May 2013, and in principle approval for the purchase of the property on 3 July 2013. The Applicant was subsequently advised on 17 July 2013 of the judgment listing on his Credit Report. Despite the FSP removing the listing in a timely manner, the available information shows that the Applicant’s property settlement would most likely have proceeded on time, on the 29 July 2013, as intended, had it not been for the FSP’s error. Accordingly, the FSP should compensate the Applicant for costs incurred due to the erroneous listing being made. Case No: 330768 Determination Page 5 of 6 In addition, during the 18 month period that the judgment listing was on the Applicant’s Credit Report (31 January 2012 to 3 July 2013), his Credit Report was viewed by a number of separate entities on a periodic basis. On this basis, I award $1,000 in non-financial loss on the basis that a number of entities viewed the incorrect information and the delay in settlement would have caused him undue stress. The Applicant’s lawyer has claimed that the Applicant should be reimbursed $69.95 for the cost of obtaining his Credit Report. While I acknowledge that the Applicant could have obtained a free copy of his credit report, requiring him to wait 30 days for a free copy – in my view – given the time critical nature of his circumstances would be unreasonable. I note that the FSP’s $69.95 fee is for a bundled credit report and alert service – which the FSP’s website d oes not indicate can be unbundled. Consequently I am satisfied that it is appropriate to reimburse the Applicant for the cost of obtaining his Credit Report from the FSP. The total compensation to be awarded to the Applicant is $2,839.13, to be paid to the Applicant within 14 days of his acceptance of this Determination. 3 Supporting information 3.1 Other key considerations The FSP has legal obligations in the use of the Applicant’s information Part IIIA of the Privacy Act and the Credit Reporting Code of Conduct impose obligations on the FSP about how it maintains and processes information. In particular, the FSP must:  be open, fair and accountable in its use of information  ensure that personal information contained in credit information files is accur ate, up - to - date, complete and not misleading  remove any errors in a credit file and report those amendments to the relevant parties. 3.2 FOS Approach Expedited Determination This dispute has not been the subject of a FOS Recommendation. Due to its nature, it was appropriate to proceed directly to a Determination in line with the Operational Guidelines to the FOS Terms of Reference. There has been a full exchange of material between the parties, and each party has had the chance to address any issues raised by the other. In considering this dispute, I have taken into account all relevant information from the FSP and the Applicant. Case No: 330768 Determination Page 6 of 6 Assessment of disputes FOS is not a court of law. This means that FOS is not able to take evidence on oath. When presented with differing accounts of what occurred in a scenario, FOS will decide what was most likely to have occurred on the balance of probabilities, taking into account available contemporaneous documentation. If we find that the available information is not conclusive, we may find that a claim cannot be established.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.