Determination 330175
Delay in loan approval and settlement
Summary
The SMSF trustee's property settlement was delayed by the FSP's loan process, and the SMSF paid penalty and default interest as a result. AFCA found the FSP unreasonably delayed settlement for three days and ordered it to compensate the SMSF, rejecting the conveyancing costs as too remote.
Settlement could reasonably have occurred on 10 May 2013 once the discrepancy was resolved, and the extension charges were a foreseeable direct loss from that delay.
Subjects and remedies
smsfpay compensationpay interest
Text of the determination
Determination
Case No: 330175 Determination Page 1 of 7
Case number : 330175 9 Ju ly 2014
1 Overview
1.1 Dispute
The Applicant is the trustee of a self managed superannuation fund (SMSF). The
Applicant applied for and received approval for a loan from the Financial Services
Provider (FSP) which was used to purchase a property in the name of the SMSF.
The settlement of the property purchase was delayed due to a delay in approving
the loan by the FSP. The Applicant suffered loss as a result of the delayed
settlement which the Applicant attributes to the FSP. The Applicant is seeking
compensation from the FSP for that loss.
1.2 Issues and key findings
Did the FSP unreasonably delay settlement and cause the SMSF to suffer
loss? If so, did the SMSF take reasonable steps to mitigate its losses?
The information available in this dispute supports a conclusion that the FSP did
unreasonably delay settlement for a period of three days - resulting in the SMSF
suffering direct losses. The SMSF acted appropriately to limit those losses.
Is the FSP liable for the SMSF’s loss?
The SMSF is entitled to recover from the FSP compensation for the direct losses
it incurred, being –
the penalty interest the SMSF was required to pay for the three day
extension of the Notice of Completion, and
the default interest that the SMSF was required to pay under the contract
of sale for the three day delay, plus
interest on these amounts at a rate of 5% per annum.
The FSP is not liable to the SMSF for the conveyancing costs or any other costs
claimed by the Applicant in this dispute.
1.3 Determination
This Determination is in favour of the Applicant. If the Applicant accepts this
Determination within 30 days of its date of issue, the FSP must within a further 14
days of that acceptance - pay to the SMSF an amount of $7,850.74 - plus interest
on that amount calculated at the rate of 5 per cent per annum from 13 May 2013
until the date that the FSP makes the payment required by this Determination.
Case No: 330175 Determination Page 2 of 7
2 Reasons for Determination
2.1 Did the FSP unreasonably delay settlement?
The FSP unreasonably delayed settlement for a period of 3 days
The Applicant says that the FSP delayed settlement by:
delaying the review of the initial documents so that the loan approval was not
granted until 22 April 2013;
not reviewing the trust and custodian deeds until after the loan approval was
granted;
its solicitor’s delay in reviewing the trust and custodian deeds ; and
not responding to repeated requests by the Applicant and its broker leading up
to 9 May 2013.
A chronology of key events leading up to settlement is set out in section 3.3
below.
When FOS investigates claims of delayed settlement we will consider whether the
circumstances show that settlement was effected within a reasonable timeframe,
having regard to industry practice and the complexity of the particular transaction.
The FSP took 40 days to approve the loan sought by the SMSF from the date of
the SMSF’s initial applicat ion (on 3 April 2013) until settlement (on 13 May 2013).
In making this Determination I sought the advice of FOS’s Banking Adviser who
has extensive experience in the banking and financial services industry. He
regularly provides FOS with advice about ba nking and financial services practice
and procedure and what constitutes good (and common) industry practice. The
FOS Banking Adviser stated that in his view:
while the loan and purchase were standard and simple - and would usually be
approved and completed in 30 days, where a purchaser is a SMSF, a delay of
an extra week to allow for due diligence to be conducted upon the purchaser
would be both prudent and commonplace; and that
the due diligence process would ordinarily involve referring the relevant
constituent documents for the self managed superannuation fund to (an
internal) legal counsel for review.
Taking into account the Banking Adviser’s opinion, I accept that the FSP was
entitled to have the SMSF trust and custodian deeds reviewed by its legal
counsel. Given the cost incurred for doing so , it was reasonable for the FSP not
to instruct legal counsel until formal loan approval was granted. Consequently,
while I consider the need for legal advice and the minor amendments requested
by the FS P’s legal counsel added to the delays in settlement for the Applicant’s
loan, in the circumstances I do not consider those delays to be unreasonable.
Case No: 330175 Determination Page 3 of 7
There were additional delays that flowed from the FSP’s lack of responsiveness
to the broker’s requests. Having regard to the fact that the transaction involved
an SMSF purchaser (requiring the FSP to conduct a level of due diligence on its
customer) and mindful of the Banking Adviser’s advice , I do not consider that the
FSP’s delays leading up to 9 May 201 3 were unreasonable.
However, the delays from 9 May onward warrant separate consideration.
On 9 May 2013, the FSP advised the Applicant’s broker by email that its legal
counsel had approved the SMSF trust and custodian deeds. However an hour
later the FSP identified a discrepancy with the vendor’s name o n the Transfer of
Land. The FSP says it was that discrepancy that delayed settlement from
possibly occurring on 10 May until 13 May (the intervening days being a
weekend).
The discrepancy identified by the FSP was explained by the special conditions set
out in clause 32 of the contract of sale.
The FSP received the contract of sale with the Applicant’s loan application on 3
April 2013. The Transfer of Land was received by the FSP on 6 May 2013.
The above timing is significant for the following reasons:
the FSP was aware that the Notice of Completion expired on 9 May 2013, with
the possibility of the sale being rescinded;
given the immediacy of this situation, it is not unreasonable to expect the FSP
to have reviewed the Transfer of Land prior to 9 May 2013;
in any event, the discrepancy with the vendor’s name was able to be quickly
resolved by a review of the contract of sale that was already in the FSP’s
possession; and
at 8.48am on 10 May 2013 the FSP booked settlement for 13 May 2013,
which suggests that the FSP had resolved its concern with the Transfer of
Land the day before.
In light of the above factors, it is not clear why settlement did not occur on 10 May
2013 . The Applicant’s broker had provided all necessary documentation, the
FSP’s legal counsel had approved the relevant deeds and the last minute
“discrepancy” with the Transfer of Land had been resolved.
Having regard to the above circumstances and in particular the expiry of the
Notice of Completion on 9 May, I consider it was unreasonable for the FSP to
delay settlement beyond 10 May 2013.
2.2 Is the FSP liable for the SMSF’s loss ?
Based upon the above findings, the issue of loss relates solely to the losses
suffered by the SMSF as a result of settlement being delayed beyond 10 May
2013.
Case No: 330175 Determination Page 4 of 7
Compensation for loss does not automatically follow a determination that the FSP
has delayed settlement. In the current dispute for the Applicant to succeed it
must be shown that the SMSF’s claimed losses are :
not too remote, and
could not have been avoided if the SMSF had taken reasonable steps to
mitigate its losses.
The FSP is liable for Applicant’s interest for 3 days
The Applicant is claiming the $2,500 per day payable by the SMSF to the vendor
in consideration of the vendor not exercising its rights under the Notice of
Completion (a failure to settle on 9 May 2013 could have resulted in the SMSF
forfeiting its deposit of $28,363 had the vendor exercised its rights under the
Notice of Completion).
The FSP says that the Applicant agreed to pay the $2,500 per day to retain the
property. As the FSP was not a party to that agreement the FSP suggests that it
should not be responsible for what was agreed.
Whether the A pplicant’s claim for loss is too remote is assessed by looking at
whether:
the loss fairly and reasonably arose di rectly from the FSP’s delay, and
it was reasonable for such losses to be contemplated by the FSP as a
possible consequence of the FSP’s delay.
I consider it clear from the circumstances here - that the Applicant incurred the
$2,500 per day loss as a direct result of the failure to settle on 9 May 2013, which
in turn was caused by the FSP’s delay in approving the loan.
The FSP was informed of the extension arrangement reached between the
Applicant and the vendor on 8 May 2013. Accordingly, the loss of $2,500 per day
of delay was (or should have reasonably been) in the FSP’s con templation at the
relevant time (being 9 May 2013, when settlement did not occur).
Likewise, the FSP would have been reasonably aware that default interest would
accrue under the contract of sale for the delayed settlement (it being standard
practice for such interest to be charged).
Based upon the above, I am satisfied that the FSP was aware that the Applicant
would have incurred a $2,500 per day loss plus default interest for the 3 day delay
in settlement (which was attributable to the FSP).
Had the Applicant not negotiated the extension arrangement of $2,500 per da y,
the FSP’s unreasonable delay may have resulted in the rescission of the contract
of sale by the vendor and the loss to the SMSF of its deposit of $28,363.
Case No: 330175 Determination Page 5 of 7
The Applicant therefore acted to mitigate his loss by agreeing to the extension
arrangement. In doing so, I find that the Applicant took reasonable steps to avoid
an even greater loss to the SMSF, and possibly the FSP.
FSP not liable for SMSF’s legal costs
The Applicant has claimed $660 for the conveyancing costs relating to the delay
in settlement.
It is not clear to me that these conveyancing costs directly relate to the FSP’s
delay to the settlement from 10 May to 13 May 2013. Based upon the information
provided to FOS, there was little additional activity by the Applicant’s
convenyancer after 10 May 2013 when it was reasonable for settlement to have
occurred.
Accordingly I consider the Applicant’s claim for conveyancing costs too remote to
warrant recovery as those costs did not directly arise in relation to the FSP’s
delay.
FSP to compensate the SMSF $7,860.74 plus interest
It follows from my findings above that settlement could have reasonably occurred
on 10 May 2013. Consequently the FSP is liable to compensate the SMSF in
relation to the direct losses suffered as a result in the three day delay in
settlement (being 11 – 13 May 2013 inclusive). That loss amounts to a sum of
$7,860.74 (plus interest at a rate of 5% per annum) calculated as follows:
Penalty interest for the extension of the Notice of Completion
- $2,500 @ 3 days
$7,500.00
Default interest under the contract of sale – 10% per annum
calculated on a balance of $438,897 @ 3 days
$360.74
Total loss $7,860.74
Plus interest on that amount at a rate of 5% per annum from 10 May 2013 until
payment in full is made by the FSP.
Case No: 330175 Determination Page 6 of 7
3 Supporting information
3.1 FOS Approach
Expedited Determination
This dispute has not been the subject of a FOS Recommendation. Due to its
nature, it was appropriate to proceed directly to a Determination in line with the
Operational Guidelines to the FOS Terms of References.
There has been a full exchange of material between the parties, and each party
has had the chance to address any issues raised by the other.
Assessment of disputes
FOS is not a court of law. This means that FOS is not able to take evidence on
oath. When presented with differing accounts of what occurred in a scenario,
FOS will decide what was most likely to have occurred on the balance of
probabilities, taking into account available contemporaneous documentation.
3.2 Documents relevant to this decision
In considering this dispute, I have taken into account all relevant information
provided by the FSP and the Applicant, including the:
F SP’s client file notes
contract for sale, and
Notice to Complete.
Case No: 330175 Determination Page 7 of 7
3.3 Chronology
The relevant events for this dispute are as follows:
Date Event
3 April 2013 The Applicant lodged a loan application for the SMSF with
settlement due date of 21 April 2013 .
11 April 2013 The Applicant provides FSP requested documentation –
some additional details are required.
18 April 2013 All requested documentation is received by the FSP .
22 April 2013 Formal loan approval provided by the FSP and trust deed
for SMSF forwarded by FSP to its solicitors for review.
30 April 2013 A Notice to Complete was issued by the purchaser
requiring settlement by 9 May 2013. Applicant’s broker
advised the FSP.
1 May 2013 The Applicant’s broker returns s igned documents to the
FSP and copy of the Notice to Complete.
6 May 2013 Insurance documents and T ransfer of L and are received
by the FSP.
7 May 2013 The FSP advises broker of change required to the
custodian deed.
8 May 2013 Amended custodian deed is received by the FSP.
The Applicant negotiates an extension of the Notice of
Completion with penalty interest accruing at $2,500 per
day. The Applicant’s broker advises the FSP of the
arrangement by email.
9 May 2013 FSP’s solicitor signs off on the tru st and custodian deeds.
FSP advises FSP transfer of land is incorrect and
settlement cannot occur as a result.
Notice of Completion expires.
10 May 2013 FSP certifies the title.
13 May 2013 Settlement occurs.