Home / Financial Firm (Unknown - Insurer) / Determination 330118

Determination 330118

Cash settlement amount for fire-damaged home rebuild

FirmFinancial Firm (Unknown - Insurer)
Decided2014-05-21
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant disputed the cash settlement of his fire-damaged home, seeking the difference to his builder's higher quote, interest, temporary accommodation costs and legal costs. AFCA found the FSP entitled to settle at the lower quote and ordered no further payment.

Under the policy the insurer may settle by compensating the cost of repair or replacement, and the lower quotation reflected the cost the FSP would incur.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 330118 Determination Page 1 of 7 Case number: 330118 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 14 May 2014 Summary Description  A claim under a home building and contents insurance policy following damage to the home by fire. Basis of Determination  A consideration of the evidence regarding the cost to repair/rebuild the damaged home and the coverage provided by the policy. Determination  The FSP was entitled to settle the Applicant’s claim for his home building by a cash payment of $288,615.94, being the equivalent to the final quotation by B.  The FSP has no further liability with respect to the Applicant’s temporary accommodation costs.  The FSP is not required to pay interest on any of the claim amounts paid.  The FSP is not required to contribute to the Applicant’s legal or other costs with respect to the dispute. Background 1. The Applicant held an insurance policy with the Financial Services Provider (FSP), covering his home building and home contents for sums insured of $350,000 and $277,000 respectively. 2. In May 2012, a fire severely damaged his home building and contents. A claim was lodged with the FSP. Determination Case No: 330118 Determination Page 2 of 7 3. The FSP accepted liability for the damage and the contents claim was cash settled. The FSP arranged for a building consultant (“S”) to draw up a Scope of Works (SOW) for the replacement of the home building, which needed to be demolished because of the extent of the damage. The FSP provided two quotations from two builders, based on the SOW. 4. The Applicant does not accept that the SOW and quotations obtained by the FSP are adequate for the purpose of reinstating his home and the Applicant has obtained an alternative quotation which is substantially higher than the FSP’s quotations. 5. The FSP cash settled the claim based on the lower of the two of its quotations. However, the Applicant is not happy with the settlement amount and seeks a review of the matter by the Service. Summary of Applicant’s position 6. The Applicant is represented and for convenience and simplicity, both the Applicant and his representative will be referred to as “the Applicant” in the remainder of this Determination. 7. The Applicant says that a number of issues existed with the SOW produced by S, some of which have still not been addressed by the FSP. 8. The quotation for the rebuild of his home produced by “B”, upon which the FSP has based its settlement offer, was purportedly changed to account for corrections to the SOW, but the amount of the quotation remained unchanged. 9. The Applicant is not satisfied with the competence of B or the FSP and does not accept that the quotation by B is sufficient for the rebuild of his home. He wants the FSP to pay him the difference between the quotation by B and the quotation provided by his own builder, “D”, as well as interest on this amount. 10. The Applicant also says that the FSP has not adequately compensated him for the cost of temporary accommodation. 11. The Applicant seeks payment of legal costs. 12. Finally, the Applicant’s legal representatives provided a submission dated 14 May 2014. I have considered the content of that submission as part of this Determination. Summary of FSP’s position 13. The FSP says that the SOW by S has undergone several revisions, in direct response to the Applicant ’ s concerns and queries. It says, however, that Case No: 330118 Determination Page 3 of 7 most of these changes have been a clarification of terms, rather than being a deviation from the original SOW. 14. It obta ined two quotations for the reinstatement of the Applicant’s home, both based on the SOW and the settlement it paid to the Applicant was based on the quotation by B, which was the lower of the two quotations. 15. Although the Applicant would prefer to be settled based on the quotation from D, the FSP says that its settlement is in accordance with the policy which provides that any settlement is based on the costs the FSP would incur. 16. Further, it says that the quotation from B is an actionable quotation and the FSP would be prepared to authorise B to undertake the rebuild of the Applicant’s home building, if the Applicant were to repay the settlement amount. 17. The FSP relies on the following policy provisions: “ Home insurance cover This cover is optional. If you have chosen to include this cover, it will be shown on your certificate. If your home suffers loss or damage caused by an event listed below, we will choose to do one of the following:  repair the damaged portion of your home,  replace your home,  compensate you for the amount we would have paid for repair or replacement. ... Paying your claim How we pay a claim for your home Where we pay a claim for your home, we will choose to do one of the following:  repair your home,  replace the damaged portion of your home,  compensate you the amount it would have cost us for repair or replacement. If you decide not to repair or replace your home, or do not commence repair or replacement within six months of the date the loss or damage occurred, we will only compensate you for what it would have cost to repair or replace your home at the date of the loss or damage. ” Issues 18. Whether the FSP is required to base its settlement on the quotation from the Applicant’s builder. Case No: 330118 Determination Page 4 of 7 19. Whether the FSP is required to pay interest on any amounts paid or payable. 20. Whether the FSP is required to pay any additional amount for temporary accommodation or to pay any amount for costs. Reasons for decision 21. Due to the nature of the dispute, the FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. Thus, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. The parties have been previously advised that a Determination will be issued in this case. 22. There has been an exchange of information between the parties and I am satisfied that each party has had the opportunity to address any issues raised by the other. 23. It is not in dispute that the Applicant’s home was damage d by fire in May 2012 and that the FSP is liable for the damage. I understand that the Applicant also claimed for loss of the contents of his home and that this claim has been settled and does not form part of this dispute. Basis for settlement of claim for home building 24. S produced a SOW dated 31 May 2012, for the reinstatement of the Applicant’s home. The FSP provided this SOW t o the Applicant, for his review and to two builders (B and J), so that quotations could be produced for the work. 25. After reviewing the SOW, the Applicant produced a series of questions and a list of items which needed to be corrected or added. 26. In response, S provided answers to the Applicant’s questions and the SOW was updated. Both builders, who had by that stage already provided quotations for the work, were asked to update their quotations to take into account the changes to the SOW. 27. The updated quotations, inclusive of GST, were as follows:  Quotation from J, dated 1 October 2012, for $289,918.27.  Quotation from B, dated 3 October 2012, for $262,573.44 (B later corrected this figure to $288,615.94). 28. On the basis of the updated quotations, the FSP authorised B to perform the rebuild of the Applicant’s home. 29. In the meantime, the Applicant had obtained an alternative quotation from builder D, in the amount of $326,370.00. Case No: 330118 Determination Page 5 of 7 30. The Applicant disputed the adequacy of the quotation by B, for the rebuild of his home. 31. I note that with a few minor exceptions, the Applicant’s issues with the initial SOW have been addressed through a combination of amendments to the SOW and “Special Notes” added to the quotation by B. 32. Although the Applicant would prefer to ha ve D rebuild his home, in my view the quotation by B provides a more detailed breakdown of the work to be performed than that of the quotation by D. 33. After considering the material submitted by the parties, I am not convinced that there is any evidence to support the Applicant’s contention that the SOW by S and the quotation by B, are inadequate for the reinstatement of his building. 34. This is particularly so in light of the FSP statement that it would be prepared to have B perform the rebuild of the Applican t’s home, providing the settlement funds it has provided, are reimbursed. This indicates to me that B is confident that it is able to rebuild the Applicant’s home for the amount quoted. 35. If the Applicant elected to have his home rebuilt by B, any deficienc ies in B’s quotation which emerged during the process would be covered by B or by FSP, not by the Applicant. 36. The policy provides that the FSP can settle a claim by compensating the Applicant the amount it would have cost it for the repair or replacement. 37. Accordingly, I am satisfied that the FSP was entitled to settle the Applicant’s claim for his home building by a cash payment of $288,615.94, being the equivalent to the quotation by B. For the removal of doubt, I do not accept that there is a requirement for the FSP to pay the Applicant the difference between the quotations by D and by B. Driveway 38. The driveway of the Applicant’s home was damaged during the demolition of the building, which was carried out by the FSP. 39. The Applicant says that his driveway is more than 12m in length and as such, the driveway replacement proposed in the SOW is inadequate. 40. However, in all the versions of the SOW presented to the Service, the driveway has been specified as “... a new 14.0m long by 4.0m wide concrete driveway t o the carport area...”. 41. As such, I do not accept that the SOW is inadequate in this respect. Case No: 330118 Determination Page 6 of 7 Temporary accommodation 42. The Applicant had included temporary accommodation costs as one of the issues in dispute. 43. However, the FSP has confirmed that it has paid a total of $39,200 or the equivalent of 98 weeks rent at $400 per week ; $19,200 direct to the real estate agent managing the Applicant’s rental accommodation and $20,000 direct to the Applicant in two payments on 8 May 2013 and 21 August 2013. 44. Based on a date of loss of 15 May 2012, the total of 98 weeks would cover the Applicant’s temporary accommodation needs until 1 April 2014. 45. As the FSP paid the Applicant the final payment of the building claim settlement in August 2013, I am satisfied that the FSP has no further liabilities with respect to the Applicant’s temporary accommodation costs. Interest 46. The Applicant has asked for consideration of interest on $26,042.50 (being the difference between the original and the adjusted quotation amounts provided by B). He also seeks interest on the temporary accommodation costs. 47. The FSP notes that section 57 of the Insurance Contracts Act 1984 provides that when payment is unreasonably withheld by an insurer, the insurer is liable to pay interest in addition to the prerequisite amount. It argues that there is no evidence to indicate that it unreasonably withheld payment to which the Applicant was entitled. 48. I agree with the FSP on this matter. Payment of an amount equivalent to B’s initial quotation was made on or around 8 May 2013, after instructions were obtained from the mortgagee of the Applicant’s property. 49. Although the updated quotation by B was submitted with an incorrect amount (effectively unchanged from its original quotation amount), I am satisfied that this was an inadvertent error on the part of B. I am also satisfied that once the FSP was provided with the updated amount, it made payment of the difference to the Applicant within a reasonable timeframe. 50. In addition, there is no evidence presented which indicates that the FSP unreasonably withheld or delayed payment of the Applicant’s temporary accommodation costs. 51. I am therefore satisfied that the FSP is not required to pay interest on any of the claim amounts paid to the Applicant. Costs 52. The Applicant has stated that he seeks payment of legal expenses. Case No: 330118 Determination Page 7 of 7 53. Paragraph 9.4 of its Terms of Reference provides that the Service may decide that an FSP contribute to the legal or other professional costs or travel costs incurred by an Applicant in the course of the dispute . 54. However, I am not satisfied that this dispute was sufficiently complex such that it required the Applicant to engage the services of a lawyer, although I acknowledge he was entitled to do so. 55. Accordingly, I find that the FSP is not required to con tribute to the Applicant’s legal (or other) costs in this matter. Determination 56. On the basis of the available information I determine that the FSP:  was entitled to settle the Applicant’s claim for his home building by a cash payment of $288,615.94, being the equivalent to the final quotation by B;  has no further liability with respect to the Applicant’s temporary accommodation costs;  is not required to pay interest on any of the claim amounts paid; and  is not required to contribute to the Applicant’s legal or other costs with respect to the dispute.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.