Text of the determination
Case No: 329050 Determination Page 1 of 8
Case number: 329050
General Insurance - Domestic Insurance - Home Building - Service - Delay in
claim handling
26 May 2014
Summary
Description
This dispute involves a claim by the Applicant under a home insurance
policy issued by the Financial Services Provider (FSP) for damage to her
home building and contents following a storm. The Applicant is dissatisfied
with the repairs carried out by the FSP’s contractors, as well as the delays
in settling her claim and the level of service provided by the FSP.
Basis of Determination
The cash settlement paid by the FSP is sufficient to enable the Applicant
to repair the damage to her property, including rectifying the inadequate
roof repairs previously undertaken by the FSP.
The inadequate r oof repairs have resulted in the Applicant’s property
sustaining further damage following a second storm. The FSP should be
required to compensate the Applicant for her resulting stress and
inconvenience.
Determination
The FSP has satisfied its obligations under the policy in relation to the
damage to the Applicant’s property.
The FSP is to pay the Applicant the amount of $500 as compensation for
non-financial loss. The FSP is not otherwise liable to compensate the
Applicant.
Background
1. On 4 February 2013, the Applicant lodged a claim under her policy for
damage to her home and contents which occurred on 26 January 2013
following severe storms in the local area.
2. The FSP accepted the Applicant’s claim and organised make safe repairs to
the roof. After appointing contractors to assess the damage and prepare a
Determination
Case No: 329050 Determination Page 2 of 8
scope of works for repairs to the building, the FSP engaged a builder (“AB”)
to carry out the repairs.
3. In or around May 2013, AB completed the repairs to the internal area and
the roof of the property, other than the repainting of the roof. After AB
advised the FSP that the Applicant had denied it access to complete the
repainting, the FSP cash settled the Applicant for $660 so that she could
arrange this herself.
4. However, the Applicant was dissatisfied with the quality of AB’s repairs to the
roof and was concerned that the FSP’s contactors had caused further
damage to her property. She also sought compensation for financial and
non-financial losses suffered as a result of the manner in which the FSP had
handled her claim.
5. On 27 March 2014, the FOS Case Manager issued a Recommendation in
which he recommended that the FSP be required to replace one additional
roof sheet. The Case Manager found that the FSP had otherwise complied
with its obligations under the policy and should not be required to
compensate the Applicant.
6. It subsequently became apparent that, shortly before the Recommendation
was issued, the Applicant’s property had suffered additional damage as a
result of a further storm and the Applicant had lodged a second claim.
7. During the course of assessing the damage from the second storm, the
FSP’s contractor identified an issue with the roof repairs carried out in 2013.
The FSP subsequently acknowledged that the earlier roof repairs were
inadequate and offered to cash settle the Applicant for the cost of rectifying
them and repairing the further internal damage to the property arising from
the storm in March 2014.
Issues
8. Whether the FSP has satisfied its obligations to the Applicant, having regard
to the terms of the policy.
9. Whether the Applicant is entitled to compensation for financial and non-
financial losses as a result of the manner in which the FSP has handled her
claim.
Reasons for decision
10. I am satisfied that there has been an exchange of ma terial information
between the parties and that each party has had an opportunity to respond
to issues raised by the other.
Case No: 329050 Determination Page 3 of 8
Has the FSP complied with its obligations to repair the storm related damage
to the Applicant’s property?
11. When the Applicant lodged her dispute with FOS, she said that the repairs to
the roof carried out by the FSP’s builder (AB) were inadequate as A B only
replaced two roof sheets not three, as required under the scope of works
approved by the FSP in March 2013. The Applicant provided a copy of a
report from her builder (“BB”) which confirmed that only two roof sheets had
been replaced.
12. The FSP has provided a copy of the builder’s assessment report and scope
of works for the repairs to the Applicant’s property prepared by AB in March
2013. While the assessment report identifies damage to two roof sheets, the
scope of works provides for the removal, replacement and repainting of three
roof sheets. The FSP has also provided an email from AB which suggests
that he replaced three existing roof sheets with two new roof sheets (in order
to achieve the correct overlap).
13. Following the second storm in March 2014, the FSP engaged another
builder (“W”) to attend the Applicant’s property and inspect the damage. In
his report dated 26 March 2013, W reported that:
the water damage to the bedroom ceiling had been caused by the fact
that when AB installed the replacement roof sheets, he had over-
tightened the screws used to attach them which had resulted in
damage to the washer seals under the screw heads, meaning that they
did not form a watertight seal; and
the water damage to the laundry ceiling had been caused by the
deterioration of the Dektite seal around the vent pipe and the absence
of washer seals under the screws attaching the TV antenna.
14. In conjunction with his report, W prepared a scope of works and a quote for
$6,837.55 (including GST) which included the following works:
the removal and replacement of the two roof sheets installed by AB;
the repair of internal damage to the bedroom and laundry ceiling and
walls; and
the removal and replacement of the water damaged light and fan in the
bedroom and the testing of lights and power points in other rooms.
15. W’s quote also included a contingency provision of $1,200 in the event that
electrical tests revealed damage to other lights or power points and these
needed to be replaced. However, this contingency provision was not
included in the cash settlement amount of $6,837.55.
16. The FSP has provided a copy of a letter emailed to the Applicant on 9 April
2014 advising her of the proposed settlement amount of $6,837.55 and
attaching a copy of the scope of works. The FSP has confirmed that it issued
a cheque to the Applicant for this amount, which has subsequently been
Case No: 329050 Determination Page 4 of 8
presented. The FSP separately cash settled the Applicant for the
replacement of a mattress which had sustained water damage in the storm.
17. In the FSP’s letter of 9 April 2014, it advised the Applicant that she could
send it copies of any quotes she obtained for the necessary repairs which
differed from the settlement amount. The Applicant subsequently sent the
FSP a quote from her builder for $4,450 (including GST). This quote covered
the repair of the internal damage and the replacement of three roof sheets,
but excluded any electrical works (as these were to be separately quoted for
by an electrician). The Applicant has subsequently advised FOS that she
has paid the builder to undertake the quoted works.
18. In light of the above, I am satisfied that the cash settlement amount paid by
the FSP is sufficient to enable the Applicant to undertake the necessary
repair works to the roof and internal areas of her property. I note that the
amount paid by the FSP is $23,877.55 higher than the amount quoted by the
Applicant’s builder to undertake the repairs and therefore should be sufficient
to also cover the electrical works (even if the contingency amount provided
for in the FSP’s scope of works is required).
19. The Applicant has not identified any damage to her property caused by
either the first storm in January 2013 or the second storm in March 2013
which is not provided for in the FSP’s scope of works. Accordingly, I consider
that payment of the cash settlement amount of $6,837.55 satisfies the FSP’s
obligations under the policy in relation to the storm-related damage.
20. I have considered whether it was appropriate for the FSP to elect to cash
settle the Applicant for the cost of the repairs (rather than rectifying the
repairs itself), in circumstances where it has been established that the earlier
repairs were defective.
21. The FSP says that it made the decision to cash settle the Applicant’s claim in
light of her behaviour towards its contractors over the course of the claim
process, which included removing a ladder while the contractors were on the
roof. The FSP says that, as a result, it was concerned about safety issues
associated with sending its contractors to the Applicant’s property.
22. The FSP’s claim notes reflect t hat there were a number of incidents involving
the FSP’s contractors during the claims process, which resulted in multiple
contractors refusing to re- attend the Applicant’s property. In the
circumstances, and given that the amount of the cash settlement offered was
sufficient to fund the necessary repairs, I consider that the approach adopted
by the FSP was reasonable.
Did the FSP’s contractors cause further damage to the Applicant’s roof?
23. The Applicant says that the FSP’s contractors caused addit ional damage to
the paint on her roof when they walked on the roof at various stages during
the course of the repair process. She says that at least fifteen people walked
on the roof leaving scuff marks and causing other damage.
Case No: 329050 Determination Page 5 of 8
24. Accordingly, the Applicant says that the FSP should be required to pay for
the repainting of the entire roof, not just the painting of the replacement roof
sheets as specified in the original scope of works.
25. The report provided by the Applicant’s builder (BB) states that when he
inspected the roof in June 2013, there were signs of minor scratches and
footprints on the paint in previously undamaged areas of the roof.
26. Following receipt of BB’s report, the FSP sought further comment from its
builder (AB), who confirmed that when he attended the property to carry out
the repairs in May 2013, there were no visible scuff marks or footprints on
the roof.
27. The FSP’s claim notes reflect that, after the Applicant raised concerns about
the damage to the roof, the FSP sent a building supervisor to inspect the
roof. However, it appears from the claim notes that the Applicant denied the
supervisor access to inspect the roof.
28. Based on the available information, I am not satisfied that the minor
scratches and foot prints which BB identified on th e Applicant’s roof were
caused by the FSP’s contractors, given the statement provided by AB and
the passage of time between the completion of repairs and BB’s inspection
of the roof. It is unfortunate that the FSP’s building supervisor did not have
an opportunity to inspect the roof, as his report may have provided further
support for the Applicant’s position.
29. For the reasons outlined above, I am satisfied that the cash settlement of
$660 paid to the Applicant for the repainting of the replacement roof sheets
(based on AB’s quote) satisfies the FSP’s obligations in relation to the
repainting of the roof.
Did the FSP’s contractors cause damage to the Applicant’s porcelain figurine?
30. The Applicant is seeking compensation for damage to a porcelain figurine
which she says is valued at $1,000. She says that the figurine was moved by
the FSP’s contractors in the course of undertaking repairs and was replaced
with a foot missing.
31. Based on the available information, it appears that the Applicant did not raise
concerns about any damage to the figurine until some weeks after the
repairs had been completed.
32. Based on the available information, I do not consider that the Applicant has
established that the damage to the figurine was caused by the FSP’s
contractors.
Is the Applicant entitled to compensation as a result of the manner in which
the FSP has handled her claim?
33. The Applicant says that , as a result of the delays in the FSP’s handling of
her claim, she has suffered financial losses because she has been unable to
Case No: 329050 Determination Page 6 of 8
access her art studio to undertake her work as a painter while the FSP
completed the repairs.
34. The Applicant also says that she has suffered stress and inconvenience as a
result of the claim process. In particular, she says that the FSP ’s internal
dispute resolution (IDR) officer was hostile to her and deliberately sent her a
computer virus.
35. FOS is able to award an applicant compensation (capped at $3,000) for
consequential financial loss suffered in connection with a dispute. FOS is
also able to award an applicant compensation (also capped at $3,000) for
non-financial loss where the applicant has experienced an unusual degree or
extent of physical inconvenience, time taken to resolve the dispute or
interference with his or her expectation of enjoyment or peace of mind.
However, FOS expects an applicant to be moderately robust and bear the
usual degree of inconvenience experienced in the course of an insurance
claim.
36. Under FOS’s Terms of Reference, compensation for consequential financial
loss (such as loss of income) or non-financial loss may not be awarded in a
dispute which arises as a result of a claim on a home building insurance
policy that expressly excludes such liability.
37. The Applicant’s policy expressly excludes liability for consequential losses of
any kind. Accordingly, the Applicant is not entitled to compensation for any
losses which occurred as a result of the incidents which gave rise to her
claims under the policy.
38. However, in my view, this does not prevent the award of compensation for
losses which have arisen as a result of the actions taken by the FSP in the
course of handling the claim (rather than as a result of the underlying
incidents themselves).
Financial loss
39. The Applicant says that she couldn’t use her art studio because it was being
used as a storage area while her spare bedroom was being repaired. She
has provided varying estimates of the income she says she has lost as a
result, but has not provided any independent information to support these
estimates.
40. Further, in circumstances where the Applicant’s art studio was unavailable
for some time while repairs were carried out, I consider that it would have
been reasonable for her to make other arrangements to continue her work
as a painter – for example, by using other, undamaged rooms of the house.
41. Accordingly, I do not consider that the FSP should be required to
compensate the Applicant for loss of income during the claim process.
Case No: 329050 Determination Page 7 of 8
Non-financial loss
42. There is no dispute that the initial roof repairs were defective and this has
been acknowledged by the FSP. Having said that, the problems with the
initial roof repairs (as confirmed by W) were unrelated to the issues raised by
the Applicant.
43. I am satisfied that, once the defective roof repairs were identified following
the second storm in March 2014, the FSP acted promptly to cash settle the
Applicant for the amount necessary to rectify the roof repairs and address
the resulting damage.
44. I have carefully reviewed t he information available in relation to the FSP’s
conduct of the Applicant’s initial claim. I am satisfied that (other than in
relation to the adequacy of the roof repairs), the FSP’s conduct of the claim
was reasonable in the circumstances. In this regard, I note that the storm
which damaged the Applicant’s property caused widespread damage to the
surrounding area and resulted in a significant number of insurance claims.
Further, not all of the delays experienced during the claim process were
attributable to the FSP’s actions but were in part due to other factors,
including the difficult relationship between the Applicant and various of the
FSP’s contractors and the fact that additional damage was identified at
various stages throughout during the claim process.
45. Further, I am not satisfied that the available information establishes that the
FSP’s IDR officer was hostile to the Applicant or deliberately sent a virus to
her computer.
46. However, the FSP has acknowledged that some (although not all) of the
further damage to the Applicant’s property which occurred in March 2014
was caused by the problems with the earlier roof repairs. In these
circumstances, I am satisfied that the FSP’s conduct of the claim has caused
the Applicant stress and inconvenience, in that the FSP’s failure to carry out
the initial repairs correctly has r esulted in the Applicant’s property suffering
further damage in the subsequent storm.
47. The FSP says that, in recognition of this, it has not charged the Applicant the
excess of $500 which would otherwise have applied to her second claim.
48. I accept the FSP’s position that an excess would otherwise apply, given that
the report of the FSP’s building consultant (W) identified that some of the
damage from the second storm was caused by the failure of seals around
the roof vent and TV antenna, rather than by problems with the roof repairs
previously carried out by the FSP.
49. Taking into account the FSP’s waiver of the excess and having regard to
what is fair in all the circumstances, I consider that the Applicant should be
entitled to payment of an additional amount of $500, as compensation for
non-financial loss suffered as a result of the FSP ’s handling of her claim.
Case No: 329050 Determination Page 8 of 8
Determination
50. On the basis of the available information I determine that:
the FSP has satisfied its obligations to the Applicant in respect of the
damage to the roof and the interior of her property caused by the
storms in January 2013 and March 2014;
the FSP is to pay the Applicant the amount of $500 as compensation
for non-financial loss; and
the FSP is not otherwise liable to compensate the Applicant.