Denial of balcony damage claim under deterioration and faulty workmanship exclusions

FirmFinancial Firm (Unknown - Insurer)
Decided2014-02-27
ProductGeneral Insurance · Home building and contents
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed for balcony damage after the FSP's contractor repaired storm damage in 2010, and a later earthquake inspection with another insurer found pre-existing rot. AFCA found the deterioration and faulty workmanship exclusions applied and the FSP need not contribute to demolition and reconstruction.

Section 46 of the Insurance Contracts Act does not assist where the exclusion for gradual deterioration is not temporal in nature and applies generally.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 329019 Determination Page 1 of 10 Case number: 329019 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 26 February 2014 Summary Description  Claim under a Home Building and Contents Policy for damage to a balcony in or about March 2010. The FSP has declined the claim relying upon exclusions contained within the policy relating to faulty construction, gradual deterioration and rot. Basis of Determination  The Applicant first lodged a claim on 6 March 2010 for water damage to the balcony of the Applicant’s home sustained during major storms. Repairs were completed by the FSP.  In June 2012, the Applicant lodged a claim for earthquake damage on their current Insurer “C” . During that claim, there was damage identified to the balcony which was considered to be pre-existing.  The Applicant lodged a claim with the FSP with respect to the damage on the grounds that the FSP’s repairer had failed to adequately repair the storm related damage.  Engineering evidence establishes that the balcony has suffered from pre-existing damage which pre-dated the policy period and was most likely caused by gradual deterioration, faulty workmanship and/or rot.  As the exclusion does not apply by reference to the condition of the balcony at the time the contract was entered into, then Section 46 of the Insurance Contracts Act 1984 has no application. Determination  The FSP is entitled to rely upon the terms of the policy to deny liability for the claim. Determination Case No: 329019 Determination Page 2 of 10 Background 1. The Applicant held a home building and contents insurance policy (the policy) with the Financial Services Provider (FSP) with the relevant term of insurance being 31 October 2009 to 31 October 2010. 2. A claim was lodged on 6 March 2010 for storm damage sustained to the balcony. This claim was accepted and repairs completed. 3. On or about 21 June 2012, the Applicant lodged a further claim on his then current home insurance policy with Insurer “C” for possible earthquake damage including damage to a balcony. 4. Following investigation of the claim by Insurer C and including investigations by Independent Specialist Technical Consultants, it was determined that the damage was not related to earthquake. The consultants identified damage to the balcony and identified water had been flowing over and around the main beam. They suspected possible rot and suggested inspection and repair was urgent. 5. Arising from the investigations, it was noted that the damage to the balcony section of the home was possibly related to previous works undertaken by the FSP in 2010. The Applicant contacted the FSP and requested the previous claim be reopened and sought indemnity for this portion (the balcony) of the damage. 6. The FSP investigated the cause of the damage and proceeded to decline indemnity for the claim on the basis the cause for the damage was pre- existing damage (deterioration and rot) and therefore excluded from cover under the policy. 7. The Applicant remains dissatisfied with the FSP’s position and is seeking a review of the decision to decline the claim by the Financial Ombudsma n Service (FOS). Summary of Applicant’s position 8. The Applicant has sought the assistance of his broker “RR” to dispute the FSP’s decision to decline indemnity to him under the claim. In the interest of brevity reference to “the Applicant” will include both RR as well as the Applicant for the purpose of this Determination. 9. A claim was lodged under the policy held with the FSP on 6 March 2010 for damage to the balcony. The claim was accepted and significant repairs were authorised to the balcony by the FSP th rough its preferred builders “MI”. 10. During the investigations undertaken by Insurer C in 2012, it was noted that damage to the balcony was related to the previous repairs completed under the 2010 claim with the FSP. Case No: 329019 Determination Page 3 of 10 11. The Applicant maintains that the whole frame of the balcony was exposed as part of the repairs undertaken by MI in 2010. Therefore, MI should reasonably have identified the pre -existing damage referred to at this time and its failure to do so has now resulted in the current damage to the balcony. 12. The Applicant is concerned the FSP maintains that it was unreasonable for MI not to have adequately investigated the balcony framework in its entirety. The fact that MI acknowledges in 2010 some deterioration of the framework confirms that it should have investigated this aspect further. It should not just have assumed that the previous rectification works noted were satisfactory. 13. The Applicant is seeking for the FSP to take responsibility for the failure of its appointed consultants and therefore provide completed indemnity to him for repair of the balcony structure and floor. Summary of FSP’s position 14. A claim was lodged under the policy in March 2010 for water damage to the soffit of the balcony. The Applicant believed the water had leaked through the balcony to the soffit during major storms. 15. The FSP appointed engineers “AB” to the claim and it was determined that the balcony was leaking as a consequence of the failure of the waterproofing system. AB recommended that the balcony flooring and waterproofing be replaced. 16. AB also recommended that the balcony structure be checked during the rectification works to confirm if there was any deterioration/rot damage and if so, to remove any damaged/deteriorated building elements/members accordingly. 17. The FSP commissioned MI to undertake the scope of works recommended by AB. MI inspected the veranda substrate in line with AB’s recommendations and found rot and deterioration of the existing structure. However, MI also sighted previous rectification works and reasonably assumed that these works were sufficient to address the deterioration. 18. AB is of the view that the damage subject to this dispute was caused by pre- existing timber deterioration and rot, which are specifically excluded under the policy. 19. Even if MI had identified the damage at the time it undertook the works, the early detection would not have made a difference to the repair costs. It would not have altered the fundamental proposition that the damage was caused by pre-existing timber deterioration and rot. 20. The FSP maintains gradual deterioration and pre-existing damage were, at the very least, a cause of the need to rectify the damage. At its highest, the Applicant’s case is “ the weight of the ne w balcony could contribute to the Case No: 329019 Determination Page 4 of 10 bowing .” The Applicant’s builder concedes that “ compromised joints ” was a cause of the need to rectify the balcony. 21. The FSP notes faulty construction, gradual deterioration and rot had occurred before policy inception. This raises the question as to whether the FSP is precluded from relying upon the exclusion relating to faulty design, gradual deterioration and rot by virtue of Section 46 of the Insurance Contracts Act 1984 (the Act). 22. Section 46 of the Act does not come to the assistance of the policyholder as it does not apply if the time of entry into a contract of insurance is not relevant to the application of an exclusion. 23. The FSP relies on the following policy provisions: “ Specific Exclusions The following exclusions apply to this Section of Your Policy: … VI. Existing Damage We do not cover any loss or damage which occurred prior to the Policy Period. VII. Faulty, Inadequate or Defective Planning We do not cover any loss or damage caused by faulty, inadequate or defective: a. planning, development, surveying, siting; b. design, specifications, workmanship, repair, construction, renovation, remodelling, grading, compaction; c. materials used in repair, construction, renovation or remodelling; or d. maintenance; of part or all of any property whether on or off the Residence. However, this exclusion does not apply to ensuing covered loss unless any other exclusion applies. … IX. Gradual Deterioration, Breakdown, Wear and Tear We do not cover any loss or damage caused by: a. wear and tear, gradual deterioration; b. inherent vice, latent defect, mechanical or electrical breakdown that You: i were aware of at the time this Policy was entered into; or ii could have been reasonably expected to be aware of when this Policy was entered into; or c. warping or shrinkage, rust or other corrosion, wet or dry rot. However, this exclusion does not apply to ensuing covered loss unless any other exclusion applies or where the gradual deterioration, breakdown or wear Case No: 329019 Determination Page 5 of 10 and tear causes water to escape from a household appliance, swimming pool or plumbing, heating or air conditioning system. Exclusion (IX b.) does not apply to damage to household electrical motors if there is actual burning out of the motor which is not caused by improper maintenance. ” Issues 24. Whether the FSP is entitled to decline indemnity to the Applicant in line with the relevant policy exclusions. 25. Whether there is an application of Section 46 of the Insurance Contracts Act 1984 . Reasons for decision 26. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is due to the circumstances of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 27. Prior to coming to a Determination, I have read and considered all the evidence made available by the parties to this dispute. 28. The parties do not dispute the following:  The Applicant held a current home insurance policy with the FSP at the time of the loss subject to this dispute.  The FSP provided and the Applicant had received the relevant policy documentation including the Product Disclosure Statement (PDS) prior to the loss.  The Applicant lodged and the FSP accepted a claim for damage to the balcony flooring and waterproofing in 2010.  Repairs were authorised to be completed based on recommendations by the appointed engineers AB.  MI proceeded to undertake the repairs. However, concerns have been raised by AB with respect to the repairs (to be discussed in detail below).  The Applicant (subsequent to the 2010 claim) changed insurers and a claim was lodged in 2012 with Insurer C for earthquake damage to the property including the balcony, however, it was determined there was no earthquake damage.  Arising from investigations it was determined that there was evidence of pre-existing damage to the balcony structure due to gradual Case No: 329019 Determination Page 6 of 10 deterioration and rotting of the timber within the substructure of the balcony.  Further, loss and/or damage arising from gradual deterioration and/or rot is specifically excluded from cover under the policy.  The recommendation of the experts provided that rectification of the damage will consist of the need to demolish, re-design and reconstruct the balcony. 29. On 1 4 July 2012, “MSC” provided an engineering report to Insurer C. They concluded that whilst it was not possible to see the actual beams of the balcony, the main beam appeared to be a steel beam and the other beams connected to it with timber. The beams appear to have moved downwards at the end connections. There was evidence of water flowing over and around the main beam and MSC suspected the timber beams may have rotted at the connection points. MSC recommended the beams and connections be directly inspected by a certified engineer. 30. It was after receiving this report and Insurer C ’s rejection of the claim that the Applicant referred the claim to the FSP arguing the damage arose from the repairs undertaken by MI in 2010. 31. Relevant comments and/or opinions of the various consultants relevant to the repairs and assessments completed in 2010 are summarised below: “G” Plumbers Report dated 16 March 2010  Found balcony ceiling facing the swimming pool area had sustained extensive water damage. Water had been collecting in the ceiling causing the plaster to bulge slightly, then, flooding out the down lights.  After dye test, it appeared railing and glass panelling may have been stressed by excessive winds, pulling the fixings of the railing uprights compromising the integrity of the waterproofing.  As a temporary measure, G replaced the fixings and applied some grout to the suspect areas which appeared to prevent further water ingress. AB’s (Engineers) Comments via an email to the FSP dated 26 June 2010  Noted widespread water staining to the soffit linings that line the underside of the external north facing balcony.  It was apparent that the waterproofing system of the existing balcony was defective / damaged.  As part of the rectifications, AB recommended that the FSP check the condition of the substrate/sub-structure to determine whether or not there was any evidence of damage and/or deterioration.  The FSP was to remove any damaged/deteriorated members/elements as necessary. Case No: 329019 Determination Page 7 of 10 AB (Engineers) Report dated 5 August 2013  AB reviewed its previous official reports as well as more recent correspondence regarding the claim in dispute before FOS.  On the basis of its 2010 review, AB provided the following relevant opinions/recommendations:  After the inspection in 2010, AB recommended that the balcony flooring and waterproofing system be replaced.  Also, importantly, AB recommended checking the condition of the balcony substrate during the course of the rectification works for any evidence of damage deterioration and to remove any damage / deteriorated building elements / members accordingly.  In August 2012, AB was again commissioned to reassess the conditions of the balcony with respect to new damage claimed. AB determined:  There was evidence of failure of the waterproofing system undertaken by MI.  The failure of the waterproofing was considered to have occurred due to excessive sag that had developed with respect to existing balcony floor structure over a prolonged period of time.  It was assumed the sag was due to deterioration and/or rotting of the original timber members (joists) over a prolonged period of time (5-10 years), which pre-dates remedial works completed by MI.  It was apparent remedial attempts had been made by others approximately 5-10 years prior to rectifying the deteriorated framing members by way of laminating timber blocks to the deteriorating joists. However, the adopted rectification works were considered inadequate.  There was evidence that the compressed sheet flooring installation methods adopted by MI were not in accordance with manufacturers specifications.  Although the installation methods can be considered a contributing factor to the failure of the waterproofing, it is considered somewhat irrelevant with respect to the primary cause of the failure (ie) existing timber deterioration.  AB notes MI removed and replaced the balcony floor tiling and substrate (compressed sheets) flooring only. It did not undertake any works to the balcony substrate as recommended by AB in its initial report.  MI advised it did not replace the balcony sub-structure in accordance with the recommendation because MI believed that the rotted joists had been rectified by others, by placing new joists alongside the rotted joints. Case No: 329019 Determination Page 8 of 10  In AB’s opinion when MI noticed some timber rot to the balcony substrate, even if it appeared rectified, it should have reported the condition and recommended the balcony be re-assessed by a suitably qualified building professional (engineer) before continuing repairs.  The installation of 18mm compressed sheet flooring is considered appropriate material for external balcony substrate flooring.  AB recommends the existing flooring structure must be demolished, re-designed and reconstructed. 32. In an email to the FSP dated 8 March 2013, AB advised that the work carried out by MI did not cause failure of the balcony structure nor by extension, any damage resulting from the failure of the balcony and save for the negligible increase in labour and material costs, there would be no difference in the balcony rectification costs. This arises from the fact that the balcony should have been totally demolished and replaced initially due to the underlying issues discovered and in its current condition, the same scope of works apply. 33. I have carefully considered the available evidence including the FSP’s commissioned engineers’ findings, initial assessment and recommendations as well as its subsequent observations and recommendations. I am satisfied that amongst the various consultants appointed to the claim, AB is the more qualified. It was involved with the claim prior to repairs being authorised (ie) for the most part since the concerns of the Applicant were brought to the FSP in 2010. 34. I am also satisfied that it was on the basis of AB’s assessment and recommendations that the scope of works provided to MI were authorised and were to be followed. Essentially, in order to consider whether the scope of works were completed appropriately, it is necessary to consider the recommendation put forward by AB, MI’s completion (or not) o f the recommendations and AB’s subsequent assessment of the repairs completed by MI under the claim. I note the following:  It is not in dispute that AB was clearly concerned about the possible existence of damage/deterioration of the balcony’s substrate/st ructure and therefore clearly recommended that the FSP arrange for this to be checked as part of the rectification works.  Upon re-inspection of damage to the balcony in 2012 (after repairs were completed by MI) it was apparent to AB that the rectification works completed by the previous owner were inadequate.  AB noted the repairs undertaken by MI were not to manufacturers’ specifications.  AB was of the opinion that when MI noticed the existence of timber rot to the balcony substrate it should have reported this, as opposed to Case No: 329019 Determination Page 9 of 10 continuing with repairs, so that a suitably qualified building professional could investigate/assess. 35. I am concerned that MI failed to report the extent of the damage to the balcony to the FSP and in particular, the existence of the deterioration and rot. 36. Whilst I acknowledge that the northern end of the balcony sub-structure was not accessible at the time MI undertook the repairs, I am not satisfied that it is a reasonable position for a professional organisation to take, to not notify the FSP and in turn the Applicant, of what are potentially very serious issues. 37. In my view, MI should have made all efforts to inspect the substrate given the fact that it identified the deterioration and rot. If this had been done, then the true extent of the pre-existing deterioration and rot would have been discovered resulting in a more accurate and informed decision with respect to the parties ’ liability under the claim in 2010. 38. Despite MI’s failings and my concern as to this, I am satisfied the evidence establishes on balance that the balcony substrate had been subject to gradual deterioration and timber rot for quite some time and most likely this rot had occurred prior to the Applicant arranging the policy with the FSP. This is further supported by the fact that there existed evidence of previous temporary repairs completed to the balcony area. AB has identified these repairs as being inadequate in any instance. 39. Whilst it is arguable that the Applicant was not aware of the pre-existing defect or imperfection in the balcony and therefore Section 46 of the Act may apply to prevent the FSP relying upon the relevant exclusion, Section 46 does not come to the assistance of the Applicant if the time of entry into the contract of insurance is not relevant to the application of the exclusion. 40. The case of Nelson v The Hollard Insurance Company Pty Ltd [2010] NSWSC 199 states that Section 46 of the Act does not apply to an e xclusion of an event which makes no reference to when the event occurs. Therefore only exclusions which refer to a condition existing before entry into the contract of insurance are affected by Section 46. 41. In this dispute, the exclusion from cover loss or damage arising from gradual deterioration (proximate cause) relied upon by the FSP applies generally and is not temporal in nature. Accordingly, I am not satisfied that Section 46 assists the Applicant in this dispute. Contribution to loss 42. Whilst I accept that the balcony requires demolition and reconstruction, I note from the opinion of AB that he accepts there would be a negligible increase in labour and material costs. 43. As the balcony would have required demolition and reconstruction regardless of the actions of MI and as there is no evidence of the Applicant Case No: 329019 Determination Page 10 of 10 suffering any unusual degree of inconvenience as a result of the actions of MI, I am satisfied in the circumstances that the FSP should not be required to contribute to the costs of demolition and reconstruction. Determination 44. On the basis of the available information I determine the FSP is entitled to decline indemnity to the Applicant with respect to the damage to the balcony which now requires total demolition, redesign and reconstruction.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.