Determination 328360

Mismanagement of property development work schedule and payments under Deed of Forbearance

FirmFinancial Firm (Unknown - Credit)
Decided2015-04-07
ProductCredit · Business lending
OutcomeFor the complainant in part
Amount awarded$13,084
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

The Applicants disputed the FSP's management of their property development finance under a Deed of Forbearance, including timelines, consultant costs, payment delays and enforcement. AFCA found avoidable delays and excessive consultant costs and ordered the loan balance reduced by $25,899, but found the DOF was not unconscionable and the FSP may exercise its power of sale.

The FSP acted within the powers agreed in the finance documents, but it must compensate for unreasonable payment delays, a double debit and consultant fees it could not show were reasonably required.

Issues

Subjects and remedies

financial hardshipdebt waiver or reductionpay compensationpay interestpay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Business Finance - Business Loans - FSP Decision - Maladministration in loan manage ment Determination Case No: 328360 Determination Page 1 of 13 Case number : 328360 6 March 2015 1 Overview 1.1 Dispute The Financial Service Provider (FSP) and the Applicants had enjoyed a business banking relationship that pre-dates 2003. The FSP, since at least 2003, has provided the Applicants with working capital finance facilities that have enabled them to pursue their vocation as property developers. Under a Loan Agreement dated 8 November 2006, the FSP made available commercial finance of $2.8 million (the Finance Offer) to enable the Applicants to undertake a high end development of a property known as the B units (the B project). The completion date for the B project was originally 30 August 2007 with the Finance Offer to expire on 30 June 2008. The expiry date of the Finance Offer was extended by the FSP on a number of occasions after July 2008. On 2 November 2012, with the B project yet to be completed and the Applicants in default of the Finance Offer, the Applicants accepted a Deed of Forbearance (DOF) that set out the terms and conditions upon which the FSP would make available further loan funds to enable completion of the B project. This dispute is in respect to the FSP’s management of the B project under the DOF. 1.2 Issues and key findings Were the DOF time lines unrealistic? The time lines set out in the DOF for the Building Completion Date (BCD) and the Forbearance Period (FP) were 31 December 2012 and 31 March 2013 respectively and they were unrealistic. Was the DOF drafted to entrap the Applicants in technical default to gain vacant possession of the B property? It has not been established that the FSP drafted the DOF to entrap the Applicants. In late 2012, the FSP did not require the signed DOF to exercise its right of power of sale if it chose to do so. Case No: 328360 Determination Page 2 of 13 Were the clauses of the DOF that held the Applicants responsible for the cost and performance of the third party consultants unconscionable? The terms and conditions of the DOF were not unconscionable. Did the FSP mismanage the Building Work Schedule (the Work Schedule) giving rise to default of the BCD? The information provided by the Applicants, FSP and the Building Project Consultant (the Project Manager) does establish that there were avoidable delays in the overseeing of the project and in payment of invoices for work authorised under the Work Schedule. Did the FSP mismanagement payment of outstanding accounts under the DOF It has not been established that the FSP mismanaged the payment of utility and other outstanding accounts provided for unde r the DOF. Did the FSP withhold payment of invoices for rectification work authorised by the Project Manager and carried out by the Applicants? There are unpaid invoices totalling $14,250 submitted by the Applicants that remain unpaid by the FSP. Are the Applicants in default of the DOF and the subsequent variations to the DOF? The Applicants are in breach of the DOF in that:  the FP has expired  they have not vacated the remaining unsold B unit  no unconditional contract of sale is held for the unsold B unit  the outstanding debt secured by the B project remains unpaid. Is the FSP entitled enforce its power of sale and seek vacant possession of the remaining B unit? The FSP is entitled to exercise its rights as mortgagee of the B project which includes the power of sale. Case No: 328360 Determination Page 3 of 13 1.3 Determination This Determination is substantially in favour of the FSP.  The FSP pursuant to its rights and remedies available under the General Conditions of the Finance Offer and its mortgage security over the B project, was entitled to appoint the third party consultants to oversee management of the Work Schedule and the marketing of the B project units.  The terms and conditions of the DOF were not unconscionable.  The third party costs of one consultant were excessive and unreasonably incurred by the FSP in protecting its exposure to the Applicant under the Finance Offer.  Unreasonable delays and mismanagement of the Work Schedule under the DOF by the FSP and the Project Manager delayed the BCD resulting in additional interest accrual to the Applicants.  The FSP is required to reduce the outstanding loan balance by the sum of $25,899. The compensation payable comprises reimbursement of: o $13,084 representing 75% of external consultants unreasonable fee of $14,744.50. o $1,025 compounded interest accrual on the consultant ’ s fee o $10,500 approximately five weeks interest accrual due to the delay attributable to the FSP and Project Manager. o $290 for the compounded interest accrued on the FSP’s administration error; and o $1,000 for non-financial loss for the distress and inconvenience caused by the FSP mismanagement.  The Applicants are in default of the DOF  In the absence of an agreement entered into between the Applicants and the FSP for the marketing and sale of the remaining unit within 30 days from the date of the Applicants ’ accepting or rejecting this Determination, the FSP is entitled to enforce its rights and remedies under its mortgage security. Case No: 328360 Determination Page 4 of 13 2 Reasons for Determination 2.1 The original DOF time lines were unrealistic On 30 October 2012, the Applicants questioned the viability of the proposed BCD of 31 December 2012 due to the ability to acquire trades and material approaching the Christmas holiday period. The Applicants sought to vary the DOF by having some flexibility with the BCD. The variation request was declined by the FSP. On 2 November 2012, under commercial pressure to complete the B project, the Applicants, notwithstanding their reservations regarding the BCD and the FP, signed the DOF. On 13 December 2012, the Applicants contacted the FSP and raised concerns about the delay being experienced in payment of presented invoices, which was delaying delivery of materials required to complete work identified in accordance with the Work Schedule which would cause them to breach the BCD. On 20 December 2012, the FSP acknowledged the Applicants ’ concerns with the BCD and agreed to extend the BCD until 14 February 2013. All other terms of the DOF remained unchanged. The FSP’s variation letter of 20 December 2012, would not have been required, if the original BCD of 31 December 2012 was viable from the outset. The Applicants claim that they incurred legal costs of “$450.00” for challenging the BCD which proved to be unrealistic. However, the BCD was only one of four issues challenged by the Applicants. The cost incurred by the FSP, which I reconcile to be the $440.95 charged by the FSP on 8 November 2012, for its solicitor to respond to the Applicants’ legal representative was not unreasonable. 2.2 The DOF was not drafted to entrap the Applicants The B Project funding was first made available by the FSP to the Applicants in late 2006, with the project expected to be completed by end of August 2007. The Expiry date of the Finance Offer was the 30 June 2008. In 2006 it was the Applicants ’ plan that the B units would be retained for their superannuation and the Finance Offer would be varied/repaid in cons ultation with the FSP as and when other planned projects were completed. That did not occur due to a number of reasons including the FSP’s withdrawal of ongoing support for their development program. Variations to the Finance Offer were required and approved by the FSP with the expiry date extended on at least four occasions with the final variation extending the Expiry date of the Finance Offer to 30 July 2012. The Applicants did not repay monies due under the Finance Offer on or before the Expiry date and thus they were in default of the Finance Offer. Case No: 328360 Determination Page 5 of 13 On 24 October 2012, the FSP issued Notices of Demand for repayment of all monies owed and Notices of Exercise of Power of Sale. The Applicants had 30 days to remedy the default by paying the full amount outstanding. In the event that the Applicants failed to remedy the Notice of Demand, the FSP was legally entitled to then act under its mortgage and exercise its power of sale of the B units. The DOF was prepared and offered to document the FSP’s final Finance offer to enable the Applicants to complete the B project, obtain the required certificates and subdivide the property so it could be marketed and sold to repay the secured monies. It has not been established that the DOF was prepared to entrap the Applicants or in order to enforce its power of sale. The FSP did not require the DOF to enforce its rights if it had chosen to do so. Its purpose was to document the terms on which the FSP was prepared to extend funding. The Applicants could have declined to sign it. The alternative was perhaps unpalatable but that does not mean there was entrapment. 2.3 The terms of the DOF were not unconscionable The Applicants were responsible for the costs of the consultants The DOF expressly stated that the Applicants were responsible for the performance and cost of the third party consultants nominated by the FSP to oversee the Work Schedule and the marketing and selling of the B project. The appointment of the third party consultants as agents of the Applicants was a not negotiable condition for the FSP agreeing to extend further finance to the Applicants to enable completion of the B project. The Finance Offer accepted by the Applicants was subject to the FSP’s Commercial Rate Loan Facility General Conditions (the General Conditions), and the Memorandum and Common Provisions (MCP) that applied to the mortgage security provided in favour of the FSP over the B project property. The Applicants appointed the FSP as their Power of Attorney In accepting the General Conditions (clause 46) and the MCP (clause 7.1), the Applicants appointed the FSP and its authorised officers (and solicitors) as their attorneys. After an event of default, the FSP under the Power of Attorney was authorised to: “ do anything which you can lawfully authorise an attorney to do in connection with this facility agreement , the security property or any arrangement with us or which the attorney believes is expedient to give effect to any of our rights …” The FSP was entitled to appoint the third party consultants on behalf of the Applicants acting under the Power of Attorney provided by the Applicants when they agreed to be bound by the General Conditions and the MCP. Case No: 328360 Determination Page 6 of 13 As the Finance Offer was provided fo r construction purposes, the Construction Provisions under the General Conditions (clauses 27) and MCP (clause12) in the event of default by the borrower specifically empowered the FSP to: “ employ any consultants or builders we consider appropriate and if construction is not complete, engage all necessary builders and consultants to complete the construction and add the cost of completing the construction to the Secured Moneys. ” In nominating the third party consultants and holding the Applicants responsib le for their cost and conduct, the FSP did not act unconscionably. It acted within the terms and conditions agreed by the Applicants when they accepted the Finance Offer. These conditions were reasonably necessary to protect the legitimate interests of the FSP in seeing the completion of the project. The costs incurred by the marketing consultant were excessive and unreasonably incurred for the protection of the FSP’s interest The FSP’s appointment of a consult ant to oversee the marketing and selling of the B project was not unlawful. However, in exercising the discretion to appoint a third party consultant, the FSP was obliged to ensure that the cost of same would be reasonably incurred and added value in the protection of its asset. On 27 November 2012, the FSP received terms of engagement from the consultant that estimated that its costs would be in the vicinity of $5,000 to $7,500 plus out of pocket expenses. The cost estimate was based on time billing at hourly rates that varied subject to the experience of the consultant engaged. The hourly rate range was from $130 to $575. The invoices received by the FSP were for $18,720.92 of which the FSP recovered $17,444.50 from the Applicants by debiting their loan account. On 3 December 2012, the Applicants provided the consultant with a draft marketing campaign which the consultant did not act upon because it had not been formally engaged by the FSP. However, its billings commenced on 12 November 2012 which predated its 27 November 2012 Terms of Engagement letter and the FSP’s formal notice of engagement that was provided on or about 31 January 2013. I consider the billings prior to the appointment are not recoverable from the Applicants. On 7 March 2013, the Applicants provided the consultant with two marketing campaigns, one from the firm that provided the December 2012 strategy and a fresh marketing submission from another party. On or about 20 June 2013, the consultant provided its marketing approval to the FSP. The marketing approval in essence recommended the December 2012 strategy with only nominal variation. The author of the December 2012 marketing strategy was engaged on 30 May 2013 to market and sell the B units. Based on my review and analysis of the interactions between the FSP/consultant and Applicants, the engagement of the consultants added a significant level of administration onto the management of the B project with little, if any, Case No: 328360 Determination Page 7 of 13 enhancement to a marketing strategy that was received before the consultant was formally engaged by the FSP. The FSP has not provided any information that establishes that the appointment of the marketing consultant added any significant value to the marketing campaign strategy recommended by the Real Estate Agent and/or that the engagement of the consultant was reasonably required for the protection of its asset. Accordingly, I consider the FSP should bear 75% of the cost of the marketing consultant and is required to reimburse costs of $13,083.37 plus compensate the Applicants for the interest that has accrued on that amount since it was debited to their loan account on 21 January 2014. I estimate the amount required to be reimbursed as at 31 January 2015 is $13,965 rounded up. 2.4 The appointment of the Project Manager did give rise to delays in completing the Work Schedule The FSP insisted on the Project Manager as a not negotiable condition of extending further loan monies to oversee the completion of the Work Schedule and the obtaining of all relevant certificates to enable the B Units to be marketed. The appointment of the Project Manager was expressly stated in the DOF which was accepted by the Applicants. The Applicants state that they entered into the DOF and engaged with the Project Manager in good faith to avoid breaching the BCD, but many avoidable delays arose from:  the inability to access the Project Manager due to leave of absence and/or him not being available because he was also managing other work commitments  the Project Manager not establishing a payment system to monitor invoices and payments authorized until approximately one month after the date of the DOF  delays in forwarding invoices to the FSP for payment The FSP’s insistence on the Project Manager vetting al l invoices/quotes for approval before release of loan funds did cause delay in the release of loan funds that were required before requirements of the Work Scheduled could be commenced/completed. The Applicants were required to have the supplier forward the quotes to the Project Manager who was then required to vet, collate and then forward same to the FSP for payment. The process was time consuming and added administrative overseeing that was not the usual practice in the past conduct of the FSP where it made available loans to the Applicants that were disbursed at the discretion of the Applicants. The FSP also made mistakes in managing the B Project It is also observed that the FSP’s payment of approved quotes and invoices was irregular with evidence of delayed payments made direct to suppliers delaying delivery of product to the building site. The FSP further erred in payment of accounts which in one instant resulted in the Applicants’ loan account being debited twice for one invoice totalling $7,306. Inconvenience was caused by this Case No: 328360 Determination Page 8 of 13 error and whilst the error was reversed seven months later there is no evidence that the interest that accrued on the error was reversed. I estimate that the compounded interest on the cost of $7,306 for seven months amounts to approximately $290 (rounded up). In addition to the compounded interest, the FSP initially rejected the Applicants’ reporting of the double payment which clearly caused distress to the Applicants. The Applicants provided voluminous emails evidencing requests for release of money to suppliers to enable delivery of materials which appear to have gone unanswered or not actioned in a timely manner. I accept that avoidable delays were experienced but I am not satisfied that those delays alone gave rise to a breach of the BCD. The FSP was tolerant of the delays being experienced to the Work Schedule which was evident by its agreement to vary the BCD from 31 December 2012 to 14 February and then 23 June 2013. On 19 June 2013, a Certificate of Classification (C of C) was issued for the B Project that was required before the Applicants could have the plans submitted and sealed for subdivision. Due to the delay in receipt of the C of C, the Applicants were not able to meet their obligation under clause 3.2(f) to: “ have all documents and do all things necessary to subdivide the Security property into Two units and create a community titles scheme…no later than the BCD ” Practical completion of the Work Schedule and the rectification work required to be undertaken did extend beyond the BCD. Delays were experienced that required the BCD to be varied and I am satisfied that the FSP and the Project Manager contributed to the delay in practical completion. The materials made available, in my view, establish that unreasonable delay did occur in delivery of goods to the building site. On 19 November 2012, the Applicants provided quotes to the Project Manager for goods that the suppliers would not deliver until they had received payment. The Project Manager did not forward those quotes to the FSP until 28 November and the FSP did not pay the suppliers until 20 December 2012. Thirty one days to approve and pay an invoice when all parties were aware that time was of the essence, in my view, was unreasonable. Further evidence of unreasonable delay arises in March 2013 with the payment of the supplier of CCTV and Security goods that were being held pending payment. The outstanding payment was the subject of emails dated 7, 8, 14, 19, 20 and 27 Marc h 2013 from the Applicants to the Project Manager before payment occurred on 28 March 2013. I estimate the time delay directly attributable to the FSP and the Project Manager to be in the vicinity of five weeks. . To compensate the Applicants for the delay in payment of supplier accounts and the distress caused by its mismanagement of the accounting, the FSP is required to reduce the outstanding loan balance by $11,790. This amount reflects compensation for additional interest accrual of approximately $10,500 (five weeks interest accrual) as a result of delayed payments, $1,000 non-financial loss for the Case No: 328360 Determination Page 9 of 13 distress and inconvenience caused by its accounting error and $290 for the direct loss of compounded interest in rectifying its error. 2.5 The FSP did not breach an obligation owed in payment of utility accounts pursuant to the DOF Clause 3.7 of the DOF provided: “ [f]unding for approved accounts up to the sum of $14,000 or such other amount as agreed to in the absolute discretion of the [FSP] relating to debts of the Borrowers for electricity, rates, water and phone charges or other expenses approved by the [FSP] in its absolute discretion.” The Applicants state that the FSP was fully aware that they had no resources or income to pay the utility and other costs associated with holding the property while the B project was completed. The provision up to $14,000 only covered the outstanding and projected accounts under the time lines imposed under the original DOF. The provision for ongoing holding expenses oug ht to have been met by the FSP, in a timely manner and without contest, due to the agreed variations to the DOF. As at May 2014, the FSP had paid utility and other holding expenses of $18,166.95. Although the Applicants have raised concerns with the timeliness of the payment of the outstanding accounts by the FSP and the frustration caused by the delay, they have not established that the FSP breached its obligation owed under the DOF in exercising its absolute discretion in payment of the accounts. 2.6 The FSP withheld payment of the Applicants’ invoices Billed labour costs The Applicants state that they were engaged by the Project Manager based on their hourly charge out rate to complete authorised work to:  line the cellar to enhance the end product ($1,500)  repair garage epoxy floor finish ($900)  remove and relay defective tiles ($7,300)  complete sound system wiring throughout the B units ($1,680)  repair water damage ($2,900) The billed invoices of $14,280 remain unpaid. The information available establishes that the Applicants:  commenced work lining the cellar without approval from the Project Manager. However, the Project Manager did acknowledge that this work was overlooked when he completed the Work Schedule.  The Project Manager did authorize the Applicants to remove and relay the tiles and to complete the water damage rectification. Case No: 328360 Determination Page 10 of 13  The Project Manager was satisfied with the quality of work completed by the Applicants. I am satisfied that the work completed by the Applicants was required to be completed to finish the B project to a level where the property could be actively marketed and presented to the market. Accordingly, if the Project Manager had authorized outside contractors to complete this work , it was a cost that would have been met by the FSP and passed on to the Applicants by debiting the invoiced amounts to the Applicants’ loan account. Therefore, notwithstanding that the FSP withheld payment, as the Applicants were ultimately responsible for the cost of the work, and if paid, the cost would have been added to the loan amount, the non-payment of same has not caused the Applicants to suffer direct financial loss because the Applicants would have to repay that amount to the FSP, with interest when the loan was repaid. However, I acknowledge that the Applicants were reliant on receipt of the billed invoices to assist them manage their pressing creditors and withholding payment did cause the Applicants to suffer distress because they did not have access to funds that may have been otherwise used to meet living costs and/or other pressing creditors. 2.7 The Applicants’ defaulted under the DOF The 31 May 2013 variation to the DOF required the Applicants to complete various obligations by the BCD (23 June 2013) and the FP (31 July 2013). Significantly, those obligations included but were not limited to: Clause 3.2(f) “ The Borrowers will register all documents and do all things necessary to subdivide the Security property into Two units and create a community titles scheme…no later than the B uilding Completion D ate.” Clause 3.3(a)(iii) “ The Borrowers must vacate the Security Property and remove all personal property from the Security Property by 26 June 2013. ” Clause 3.4(d) “ The Security Property must be sold and under unconditional contracts for sale approved by the Bank …by the end of the F orbearance P eriod” . The Applicants did not meet their obligations under clauses 3.2, 3.3 and 3.4 and thus were in default of the DOF. In the absence of any subsequent agreement to vary the DOF after 31 July 2013, the Applicants remain in default of the DOF. Case No: 328360 Determination Page 11 of 13 2.8 The FSP is entitled to exercise its power of sale The FSP met its obligations under the Code of Banking Practice (the Code) The FSP is a signatory to Code. Accordingly, it has contractual obligations owed under the Code to work with the Applicants to try and assist them overcome any financial difficulties they may be experiencing. However, if the FSP is not satisfied that a loan variation, that provides either long or short term assistance, is not viable, the FSP is under no obligation to approve financial hardship assistance. In considering the FSP’s position in late 2012, I am satisfied that by offering the DOF, as last measure of assistance, as opposed to proceeding with legal action at that time, the FSP met its obligation owed to the Applicants pursuant to the Code. The FSP is entitled to vacant possession of the unsold B Unit As the Applicants are in breach of the DOF, the FSP is entitled to vacant possession of the remaining unit to exercise its power of sale. The Applicants argue that it is not in the FSP ’s best interest for them to vacate the Unit that they are currently residing in as they are performing the functions of a property manager in maintaining security and maintenance of surrounds and swimming pool. Whether or not the FSP elects to allow the Applicants to remain in the remaining Unit while it is further advertised and sold is a matter of the FSP applying its policy or practice and exercising its commercial judgment. In the absence of a breach by the FSP in exercising that judgment, I have no power to review a decision. Case No: 328360 Determination Page 12 of 13 3 Supporting information 3.1 Variations to DOF The FSP’s letter dated 20 December 2012 sets out the firs t DOF variation that extends the BCD to 14 February 2013. 3.2 The Finance Offer and subsequent variations The Applicants accepted the following documents from the FSP and in doing so agreed to be bound by the terms and conditions contained therein:  The Finance Offer  18 January 2007 Variation to Finance Offer  16 May 2008 Facility letter extending the Finance Offer for a further two years  6 October 2009 Variation to Finance Offer  9 September 2010 Variation to Finance Offer  9 March 2012 Variation to Finance Offer The March 2012 variation to the Finance Offer is not ambiguous and expressly states: “The maximum term of the facility expires on 30/07/2012. The total amount owing is repayable on demand. The FSP made demand for payment on 24 October 2012. 3.3 The FSP was empowered to appoint third party consultants in the event of default The Applicants’ contention that the third party consultants could not be their agent in circumstances where they were not involved in the appointment and did not provide engagement instructions fails at law. The responsibility for the appointment and performance of the third party consultants was explicit in the DOF and the Applicants were legally represented when considering and eventually accepting the DOF. The FSP’s right and power to appoint the consultants is set out in the:  Commercial Rate Loan Facility General Conditions March 2005  Memorandum and Common Provisions (Document S.154) In respect to the consultant’s unreasonable costs the documents relied upon included:  27 November 2012 letter – Engagement terms  Consultant Invoice numbers: 7338189 $$7,031.20 (12 November 2012 to 26 April 2013) and 7338188 $11,689.72 (1 May to 31 October 2013) Case No: 328360 Determination Page 13 of 13 3.4 The recommended marketing strategy On 3 December 2012, the Applicants proposed to market the B Project over the Christmas holiday period to take advantage of the influx of tourists to the area. The marketing strategy was contained in a letter dated 29 November 2012 from the Real Estate Agent that was subsequently appointed at the end of May 2013 to market and sell the properties. The initial strategy recommended: An overall budget of $12,864 Professional photography, floorplan, 6x4 Sales banner, Prestige mailouts, Premier Property Listing - Realestate.com.au e-brochure 45 days and a five week advertising campaign in local and state newspaper publications (1 x full page colour, 1 x 4/5ths page full colour lift out, 6 x half page colour and 2 x 2/5ths page colour) On 21 June 2006, the FSP deposited $14,105 direct to the appointed Real Estate Agent’s Trust account to cover the approved marketing costs (photography costs had been paid previously). The marketing strategy approved included: Premier Property Listing Realestate.com.au 45 days Professional Full colour sign 6x4 and four week advertising campaign in local and state publications (5 x full page colour and three half page colour) The only significant difference in the marketing approved is in the page size of the paper advertisements.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.