Progress payments, refused funds and financial hardship handling on building loan

FirmFinancial Firm (Unknown - Credit)
Decided2014-12-29
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$350
Amount claimed—
SourceAFCA PDF

Summary

Borrowers building an investment property disputed progress payments, a refusal to advance further funds, hardship handling and misdirected statements. AFCA found the claims largely unestablished but ordered $350 non-financial loss compensation.

The FSP was not obliged to advance further funds on a defaulted loan, and the Applicants bore responsibility for monitoring the building work, but the FSP's initial refusal of hardship assistance and misdirected statements warranted modest non-financial loss awards.

Issues

Subjects and remedies

financial hardshippay non financial loss

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Case No: 328348 Recommendation Page 1 of 2 Case number : 328348 28 November 2014 1 Overview 1.1 Dispute The dispute is about the FSP’s conduct in:  managing the Applicants’ building loan for their construction of an investment property, in particular its release of progress payments to the builder  refusing to release further funds for the Applicants to complete the investment property  responding to the Applicants’ financial hardship with the building loan  sending the Applicants’ corresponde nce to an incorrect address The case manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was substantially in favour of the FSP. A copy of the Recommendation is attached to this Determination. 1.2 Issues and Key findings Were the findings of the Recommendation correct? The findings contained in the Recommendation were correct and are adopted in this Determination. Further submissions provided after the Recommendation have been considered. Was the award for loss appropriate? The award of, in total, $350 for non-financial loss was appropriate compensation for the Applicants stress and inconvenience as a result of the FSP’s conduct. Is the FSP obliged to provide financial hardship assistance? The FSP is not obliged to provide further credit and financial difficulty assistance to the Applicants. The Applicants must sell the investment property to repay the building loan debt. If there is a resulting shortfall debt, then the Applicants will also be liable to repay it. 1.3 Determination This Determination is substantially in favour of the FSP. I agree with the case manager’s reasons for the Recommendation and the recommended outcome. Case No: 328348 Determination Page 2 of 2 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? I am satisfied that the case manager’s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. 2.2 Was the award for loss appropriate? The award for non-financial loss was appropriate The Applicants disputed the amount of compensation for non-financial loss given the nature of the FSP’s conduct. However, w e will only award compensation for non-financial loss if there has been an unusual degree or extent of inconvenience. If we do award compensation, it is unlikely to be substantial. The award of $350 for loss was appropriate given that:  the FSP did eventually seek to assist the Applicants with their financial hardship over an extended period of time  its sending of correspondence to an incorrect address was a minor error. The statements were sent in an envelope. As such, it is not a breach of privacy to send a letter or statement in a sealed envelope to an incorrect address There is otherwise no information to suppo rt the Applicants’ position that the FSP placed mortgagee in possession notices at the investment property in November 2012. The FSP did take possession briefly in June 2011 after loan payments had not been made. The Applicant was aware from ongoing conversations with the FSP about the status of the building loan and the investment property leading up to them lodging their dispute at FOS in mid-2013. 2.3 Is the FSP obliged to provide financial hardship assistance? The Applicants do not have capacity to repay the debt The Applicants have requested further credit and financial hardship assistance to complete and sell the investment property. The Applicants have not made any repayments since 2012. The FSP is not obliged to support the Applicants with a building loan they cannot afford to repay nor approve further credit. Once FOS closes our file the FSP can recommence recovery action against the Applicants, noting their current request to send correspondence to them via their solicitor in South Australia. Recommendation Case No: 328348 Recommendation Page 1 of 10 Case number: 328348 30 July 2014 1 Overview 1.1 Dispute The FSP approved a loan of $2,600,000 to the Applicants in May 2009 to assist with building an investment property. During the period 22 May 2009 to 11 February 2010, the FSP made progress payments to the builder, at the Applicant’s request, totalling $1,7 24,700. Since March 2012 and no further payments have been made to the loan. The Applicants say that the FSP did not give them sufficient support. The FSP:  did not check the building work before it made the progress payments to the builder;  would not advance funds of approximately $52,000 in the first quarter of 2010 to enable the Applicants to complete the roof on the property to prevent internal damage;  did not provide financial difficulty assistance;  sent correspondence to an incorrect address in the Northern Territory. 1.2 Issues and key findings Should the FSP have made the progress payments? The FSP made all progress payments following receipt of signed invoices from the Applicants. There is no specific information to show why the payments should not have been made or what loss the Applicants suffered as a result. Was the FSP required to provide funds requested by the Applicants in the first quarter of 2010? There is no information to show that the Applicants requested the FSP to advance funds of approximately $52,000 in the first quarter of 2010 to complete the roof. The Applicants have asked for the funds to be paid since the claim was lodged with FOS, but given the loan is in default, the FSP not obliged to agree to this request. Did the FSP meet its obligations to provide financial difficulty assistance to the Applicants? The FSP initially refused financial assistance on the basis that the loan was a progressive drawing loan. However, it subsequently put a hold on recovery action Case No: 328348 Recommendation Page 2 of 10 for some time to allow the Applicants to attempt to resolve fraud allegations against the builder and possibly recover funds from the builder. Compensation for non- financial loss of $250 is payable for the initial refusal to provide assistance. Did the FSP breach the Applicant s’ privacy ? The FSP has acknowledged that mail was sent to the Northern Territory. It appears that this was an error. An award of $100 compensation for non- financial loss is appropriate. 1.3 Recommendation This Recommendation is substantially in favour of the FSP.  There is no information to show why the progress payments should not have been made or how this caused a loss to the Applicants.  The FSP was not obliged to advance further funds to the Applicants.  The FSP has provided financial hardship assistance to the FSP by not pursuing recovery action for a period of time. However, the FSP initially refused financial hardship assistance because the loan was a progressive drawing loan, without giving genuine consideration to the Applicants’ position. Compensation of $250 is payable.  The FSP breached the Applicants’ privacy and should pay compensation of $100.  The total of $350 compensation for non-financial loss should be paid to reduce the loan balance outstanding within 7 days of both parties accepting this Recommendation.  The Applicants remain liable to repay the loan in accordance with the loan agreement.  The loan is default so the FSP is entitled to recommence its recovery action once the dispute with FOS is closed. Case No: 328348 Recommendation Page 3 of 10 2 Reasons for Recommendation 2.1 Should the FSP have made the progress payments? Loan terms and conditions require signed invoice for progress payments The loan terms and conditions state that to draw a progress payment the customer must provide an invoice for payment from the builder signed by the builder and customer. A progress inspection by a licensed valuer is only required before a progress payment is made if the FSP tells the customer it is required. There is no information to show that the FSP told the Applicants inspection by a licensed valuer was required. The terms and conditions also state that the FSP will arrange inspection by a licensed valuer when the construction is complete. As the construction was not completed, this did not occur. FSP policy required progress inspections The FSP’s policy required progress inspections for each progress payments for loans where the value of the construction was over $2m. The information from the FSP shows that an inspection was conducted for the first progress payment of $290,000. The payment was not initially made because the work had not been completed and payment was not consistent with the payment schedule. The builder provided a revised payment schedule and payment was made after the FSP’s valuer confirmed the work had been completed and the bala nce of the loan was sufficient to complete the construction in accordance with the revised payment schedule. There is no information to show the FSP conducted further inspections before making the other progress payments. It is of some concern that the progress payments after the second progress payment are not consistent with the revised schedule of payments. However, for each progress payment the FSP’s notes show that it satisfied itself that the amount remaining to be drawn under the loan was sufficient to pay the outstanding balance of the building contract stated on the invoice. I also note that the FSP’s policy is an internal policy to protect the FSP’s interests, not the customer’s, although that may be an indirect effect. It still remained incumbent on the Applicants to monitor the progress of the building, particularly when they were signing the invoices to be paid. Progress payments were made following receipt of signed invoices The Applicants say they thought the FSP would have inspected the property for each progress payment to ensure the loan being sought was sufficient to complete the project. They do not say the FSP told them it would do this. Case No: 328348 Recommendation Page 4 of 10 There was an initial draw down on the loan of approximately $805,000. I have no further information about this payment other than to note that the revised schedule of payments included preliminary costs of $841,000 which the FSP’s notes indicate had been paid. The Applicants say they have no knowledge of this. Each of the progress payments (totalling $1,742,700) were made after invoices were submitted for payment. The invoices were signed by the Applicants. The Applicants say they signed the invoices for payment relying on the FSP and its valuer to inspect the works to ensure the work was done and to a standard fit for the type of development. The loan terms and conditions state that the responsibility for any inspection of the property or its value, and ensuring that the loan is spent on the relevant purpose, is the responsibility of the borrower. It is not reasonable to expect that FSP would be responsible for ensuring the required work had been completed to the appropriate standard. That is the Applicants’ responsibility. There is no information to establish that the FSP told the Applicants it would check the work and ensure it was completed to an appropriate standard. No information to establish why the progress payments should not have been made Although the FSP did not follow its policies and has paid progress payments outside the payment schedule for the building contract, the Applicants signed the progress payment requests and were responsible for ensuring they were satisfied with the building work before requesting the payments. The Applicants have not provided any information about why they say the payments should not have been made. They have not provided information about what work had not been completed. The Applicants lodged a dispute with Q Insurance against the builder and were awarded compensation of $200,000 for rectification of defects. The insurance report indicated there was still work of approximately $1.2m to be completed, whereas the Applicants in December 2013 said they needed another $300,000 to complete the building. There is also information on the file that suggests the builder stole work materials but no specific details. However, this information does not establish that if the FSP had conducted inspections it would not have made some or all of the progress payments. No information to establish what loss was caused by the FSP paying the progress payments Even if the FSP should not have made the progress payments, which I am not satisfied is the case, the Applicants have not clearly identified, or quantified, their loss. The available information does not establish why the payments s hould not have been made, what work is still to be done or what work materials are missing. Case No: 328348 Recommendation Page 5 of 10 2.2 Was the FSP required to provide funds requested by the Applicants in the first quarter of 2010? There is no information to show the Applicants requested further funds The Applicants say that in the first quarter of 2010, they asked the FSP on a number of occasions to use part of an amount of $52,428.72 that remained available on the loan to arrange for a different builder to complete the roof on the building to protect the inside from damage. The FSP refused. The Applicants do not have any records to show that this request was made, and there is no information in the FSP’s records about such a request. The last progress payment was made in February 2010 when there was still an amount of $51,300 owing under the building contract. The FSP’s notes show a further amount of $13,697.64 was paid in July 2010 to the Applicants’ account. It appears the amount transferred was a reversal of part of an amount paid to the loan account in error. The FSP notes indicate that Mr Applicant advised that the builder was dismissed in October 2010. It is therefore not likely that the Applicants requested funds to be released for a second builder prior to October 2010. The FSP notes do not show any requests for additional funds to complete the roof after the builder was dismissed. FSP not obliged to make funds available The Applicants have made requests for the release of the remaining loan funds since lodging the dispute with FOS. The Applicants' have an obligation to pay interest on the loan account whilst the loan was being drawn down commencing one month after the first loan drawing . The Applicants have consistently failed to meet their repayment obligations since March 2012. As no payments have been made on the loan since March 2012, it is in default, and the FSP is not obliged to advance the funds. It is also not clear why the Applicants did not use the insurance funds to complete the roof. 2.3 Did the FSP meet its obligations to provide financial difficulty assistance to the Applicants? FSP required to give genuine consideration to a request for financial hardship assistance Financial services providers have obligations to properly consider any hardship request in accordance with good industry practice and the Code of Banking Practice. Case No: 328348 Recommendation Page 6 of 10 FSP put recovery action on hold The loan went into arrears in March 2012. Since that time there were numerous discussions between the FSP and Mrs Applicant in particular. The FSP’s notes show that Mrs Applicant initially indicated they could fix the arrears and make the repayments. However on 11 July 2012 she told the FSP that she had not been employed for 18 months. At that time the FSP advised Mrs Applicant that it could not assist with progressive drawing loans. In responses to FOS the FSP says that hardship assistance is not dependant on the particular loan or product. Although the FSP told the Applicant it could not assist with progressive drawing loans, and issued default and demand notices, it did not take immediate action to repossess and sell the property. After 19 July 2012, the FSP put further recovery action on hold until at least November 2012 while issues about fraud by the builder were referred to the police so the Applicants could possibly recover funds from the builder and for the FSP and Applicants to try to resolve the issue. There is some dispute as to whether the FSP put up mortgagee in possession notices in November 2012. The FSP says it did not and Mrs Applicant has provided photos of what she says are the notices. However those photographs do not identify where the notice was placed, the property the notice applies to or the date of the notice. In any event, even if the notices were put on the property, it was some months after the FSP agreed to hold recovery action and requested copies of police reports relating the Applicants’ attempts to follow up fraud issues in relation to the builder. There is no information to show what impact these notices had, if any. In all the circumstances, where the FSP did not progress its recovery action for some time, I am satisfied the FSP fid meet its obligations to a customer in financial difficulty. An FSP is not required to put recovery action on hold indefinitely where no repayments are being made and Mrs Applicant had advised the FSP she had no income and there was no information about if and when she may have income. However, I consider that the FSP did not initially meet its obligations when it told the Applicant it would not provide assistance for progressive drawdown loans, without any consideration of the circumstances at the time. That would have caused some concern and anxiety for the Applicants and an award of $250 for non-financial loss is appropriate. 2.4 Did the FSP breach the Applicant s’ privacy? Account statements/correspondence sent to Northern Territory The FSP acknowledges that it sent account statements to an address in the Northern Territory in error. As a result it waived the annual package fee for the loan. Case No: 328348 Recommendation Page 7 of 10 Mrs Applicant says she was concerned the statements, may have been received by her ex-husband. The Applicants were concerned that their personal information had been sent to an incorrect address and in the circumstances an award of $100 for non-financial loss is appropriate. Case No: 328348 Recommendation Page 8 of 10 3 Supporting and other information 3.1 Loan terms and conditions “ 4 (b) Progress Payment Requests Before you can draw a progress payment, you also need to provide us with the following:  An invoice for payment from the builder or home improvements firm signed by you all; and  A progress inspection by a licensed valuer (only required if we tell you so).” …… 4 (c) Final inspection When the construction or renovation is complete, we will arrange a final inspection by a licensed valuer.” “ 12. Security Property title and value We are not responsible for: ...  Any assessment or inspection of the property or its value (including any valuation); or  ensuring that the loan is spent on the relevant purpose. It is up to you, or your solicitor/conveya nce, to ensure that you are satisfied with the above.” 3.2 Financial Difficulty Assistance FSP notes of interactions with the Applicants Date Record 19 April 2012 Mrs Applicant told the FSP the direct debit payment was returned because the builder overspent in the last month so insufficient funds in the account. Discussion about a possible upcoming contract and sale of Mrs Applicant’s car. 27 April 2012 Mrs Applicant advised the FSP they would be in a position to clear the arrears by 14 May 2012 and would al so be able to cover the next due payment 7 May 2012 Call to Mrs Applicant so FSP can record arrangement for payment. Mrs Applicant Case No: 328348 Recommendation Page 9 of 10 said she would make the payment at the end of the month. 24 May 2012 payment dishonoured [check account statement] 28 May 2012 Default notice served 13 June 2012 Mrs Applicant advised the property was on the market for $3m. Unable to make payments in the meantime. 24 June 2012 Mrs Applicant advised she was going to a branch the next day to discuss her options. 3 July 2012 Demand issued 11 July 2012 Mrs Applicant advised the builder had done shoddy work and disappeared with two containers of goods; work had been rectified and reimbursed by insurance for missing tiles; she had not worked for 18 months due to stress and reque sted no payments for three months so they could put the property on the market. She was advised the FSP was “unable to assist for progress draws loan”. The FSP referred her to HRM or branch manager 16 July 2012 FSP advised Mrs Applicant that due to lack o f serviceability and no repayments since February FSP would be proceeding with enforcement action. From 19 July 2012 Further action was put on hold on the account while issues about the allegations of fraud by the builder were referred to the police. 22 August 2012 “please advise that no further action will proceed against [Applicants] for at least another 5 weeks until we can come up with an acceptable solution. ” 10 September 2012 Still waiting for a copy of the police report to stop any collection acti vity. 25 September 2012 Still waiting for a copy of the police report, does not appear to be a solution to the situation. 9 October 2012 Police report still not provided. Possession of security property approved. 21 November 2012 Property described as abandoned building site with unfinished building on it. For sale sign. Valuation range - $1.2m to $1.3m. Neighbour said mortgagee in possession Case No: 328348 Recommendation Page 10 of 10 signs had been put up. FSP said had not taken possession or put up signs. 16 May 2013 Request to vacate letter sent to Applicants. 31 May 2013 Applicant advised FSP property not completed, no plumbing etc. On the market since previous year and wants to sell as is. Applicant has no income to contribute to the loan. Builder is bankrupt and unable to claim funds from him. Waiting for police investigation. Applicant requested a further few months to resolve issues and will look at having property valued and sell for that amount. Also possibly get some work completed to increase sale price. Applicant advised debt increa sing each month. 3 July 2013 Dispute lodged with FOS 3.3 Special Disadvantage No information to establish that the Applicants were at a special disadvantage The Applicants have also said that they were at a special disadvantage but have not provided information or supporting documents to establish this.