Hail crop loss percentage reduced after assessor calculation error

FirmFinancial Firm (Unknown - Insurer)
Decided2014-05-21
ProductGeneral Insurance · Other general
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant disputed the FSP reducing the hail loss percentage on two paddocks from 58.69% to 21.43% after an assessor's mathematical error, notified some time later. AFCA rejected reinstating the original figure but required a further 10% settlement increase plus statutory interest.

The FSP was entitled to correct the calculation error, but its delay in notifying the insured prejudiced his opportunity to reassess the crop, so fairness required additional compensation.

Issues

Subjects and remedies

natural disasterpay compensationpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 327369 Determination Page 1 of 8 Case number: 327369 General Insurance - Small Business/Farm Insurance - Fire or Impact by hail damage - FSP Decision - Claim amount 16 April 2014 Summary Description  A claim under a Crop Protection Insurance Policy following loss arising from a hail event. Basis of Determination  A consideration of the evidence regarding the FSP’s assessment of the loss. Determination  I determine that the FSP is to amend its offer of settlement under the claim with respect to the paddocks MB and WP. The offer of settlement is to be increased by 10%.  The FSP is to pay interest, on the additional settlement amount, in accordance with the Insurance Contracts Act 1984, from the date the initial offer was made, until the date of settlement. Background 1. The Applicant held a Crop Protection Insurance Policy (the policy) , with the Financial Services Provider (FSP). 2. A claim was lodged upon the policy for damage to the Applicant’s crop , due to impact by hail. 3. The claim was accepted by the FSP and after undertaking an assessment of the loss, the FSP proceeded to offer settlement to the Applicant. 4. The Applicant remains dissatisfied with the amount of settlement offered with respect to particular paddocks/areas “MB” and “WP” , affected by the hail storm and has sought an independent review by the Service. Determination Case No: 327369 Determination Page 2 of 8 Summary of Applicant’s position 5. On 29 November 2012, the Applicant’s crops suffered hail storm damage to all paddocks containing Canola. The damage was assessed on or about 10 December 2012, by the FSP ’s appointed as sessor “AC” , a representative of “CI”. 6. AC presented the Applicant with the resu lts of his “Crop Summary Forms”, i.e. his assessment of the damage. The parties agreed upon the outcome of the assessment with respect to some paddocks and not others. Reassessment was arranged for the paddocks the Applicant was dissatisfied with and a combined claim of an additional $31,410 was approved. 7. The Applicant maintains, with respect to the two paddocks (MB & WP), the subject of this dispute before the Service, the agreed (between the parties) calculation percentage of damage to the crop noted within the forms , was 58.69%. However, this calculation was reduced to 21.43%, without the knowledge of the Applicant and some two months after the assessment. 8. The Applicant does not dispute the FSP is entitled to check the calculations by the assessor in the field, prior to settlement. Rather, his concern relates to the change in the percentage of the claim, in addition to the time that was taken to advise him of the change. 9. Arising from the delay the Applicant was prevented from having the paddocks reassessed, which he would have done had he been aware the claim percentage was to be downgraded. The Applicant and AC had agreed on a percentage and he was not aware of any errors made b y the assessor in his calculations at the time. 10. As is normal practice the Applicant had left test strips in all of the hail affected paddocks whilst they were harvested, so as to allow them to be assessed and/or reassessed in the instance he believed the original assessment was not reasonable. This the Applicant maintains proved to be the case with seven paddocks, which were originally assessed as “no claim” areas only to be reassessed by a different assessor and determined to be claimable. 11. The Applicant acknowledges that AC contacted him subsequent to the assessments to inform him mistakes had been made with respect to the calculations of two paddocks, with “SL” going from 30.33% to 20.72% and “BD” from 33.78% to 14.93%. No reference was made to MB and/or WP, which had been reduced from 58.69% to 21%. The Applicant maintains the visual assessment clearly showed the damage to these paddocks was more than 21% and therefore he would have arranged/requested for a reassessment, keeping in mind AC’s previous mista kes. 12. The Applicant does not accept (it is a reasonable position) the FSP’s view that its corrected percentage is in line with neighbouring paddocks. He maintains that the damage varies between 10% and 20%, which is a 100% increase. If this pattern is applied, then it would be reasonable to accept the Case No: 327369 Determination Page 3 of 8 damage to MB and WP could easily be around 40%, which would be more consistent with the visual inspection of the damage. 13. The Applicant is of the opinion the manner in which the calculations were reduced was unacceptable and unethical. Further, he maintains that had the original inspection been done correctly this matter would not now be in dispute. Also, that a settlement somewhere between the original 58% and reduced 21% damage, is not an unreasonable expectation. Summary of FSP’s position 14. The policy provides indemnity for loss or damage to crops at the insured property due to fire and hail. It carries a 5% excess which is deducted (per paddock), from any claimed loss. 15. As it is an after harvest policy, the premium is calculated subsequent to submission by the policyholder, of the yield declaration data. 16. The dispute pertains to the calculated percentage of loss assessed by CI with particular reference to two crop paddocks. Subsequent to the infield assessment being completed, the relevant documentation was sent to its headquarters for review. Arising from the review a mathematical error was found in the assessor’s calculations. Accordingly, the loss perc entage was adjusted down from 58.69% to 21.43%. 17. The FSP maintains the Claim Summary Form (CSF) provided to the Applicant after the infield assessment showing the assessors calculations and initialled by the Applicant detailing the net loss, includes the following statement: “ The above counts and yields are agreed to by the undersigned and its further agreed that, subject to checking for mathematical error, they will be the basis for payment of loss within the definitions of the Company’s Crop Policy held by the Insured.” 18. With respect to the Applicant’s assertion that he was not contacted with respect to the mathematical error identified, this is denied as the FSP maintains having made inquiries with CI, it is claimed that the assessor was adamant he contacted the Applicant in this regard. Therefore, this may always remain a matter in dispute between the parties. 19. Regardless, the Product Disclosure Statement (PDS) clearly informs of “How We Will Settle Your Claim” and which provides that the net loss percentage is the percentage of loss of potential yield determined by the assessor. In this instance, it is clear a mathematical error occurred in the original assessment which was later discovered and rectified. Therefore, the correct net loss percentage was calculated by the assessor(s). 20. Further, the FSP notes the amended net loss percentage is consistent with the other surrounding paddocks, all assessed at 21%. The FSP also maintains CI discovered there was a discrepancy with respect to the Case No: 327369 Determination Page 4 of 8 reported yields. It was noted that it appeared the Applicant had arranged the yields by crop type rather than reporting actual yield by paddock i.e. regardless of the paddock, the crop was all the same, which is unlikely to ever occur in nature (varies paddock to paddock). 21. The Applicant had done this with the Canola crop as well, but as some of the crops were damaged, the Applicant had tried to spread the total harvested tonnage by adjusting the declared yield, on each paddock, by the amount of damage. The higher the damage, the lower the declared yield, this is, however, not the intention of the policy. 22. The expectation is that the grower declares the actual harvested yield, either paddock by paddock or if the facilities to report on this are not available, as an average by crop type. 23. The FSP maintains its calculation of the Applicant’s claim and therefore of the actual entitlement under the policy are accurate and therefore it wishes to stand by its calculated offer of settlement under the claim. 24. The FSP relies on the following policy provisions: “ How We Will Settle Your Claim We will pay you the amount calculated by multiplying the net loss percentage by the sum insured. The net loss percentage is the percentage loss of potential yield determined by our assessors, less the excess listed on the policy schedule for the crop. …” Issue 25. Whether the Applicant is entitled to a higher settlement under the claim, for the damage to the crops in paddocks MB and WP. Reasons for decision 26. As advised to the parties, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This is due to the circumstances of the dispute. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. 27. Prior to coming to a Determination, I have read and considered all the evidence made available by the parties to this dispute. 28. The parties do not dispute the following:  The Applicant held an active after harvest crop policy with the FSP, at the time of the loss. Case No: 327369 Determination Page 5 of 8  The FSP provided and the Applicant received the relevant policy documentation prior to the loss.  The Applicant ’s crops were damaged due to a significant hail storm.  The FSP accepted the claim and the parties agree upon its settlement with respect to a majority of the paddocks damaged, except for the two paddocks the subject of this dispute.  The assessor after having completed his assessment noted within the CSF the loss percentage for MB and WP was 58.69% and the Applicant initialled the CSF, accepting AC’s assessment.  However, on review of the CSF at the headquarters of the assessor a mathematical error was noted within and which established the loss percentage was 21.43%.  The FSP proceeded to amend the calculations to represent the assessor’s findings and the loss percentage was also s ubject to a 5% excess reduction.  The surrounding paddocks also show a loss percentage in the 20% range and which has been accepted by the Applicant under the claim.  The FSP notified the Applicant of the said mathematical error and resultant reduction in the loss percentage for the paddocks in dispute, sometime after the original assessment. 29. I have considered the available evidence in particular the CSF in question and note that it does provide that the final calculations will be subject to checking for mathematical errors after which they will form the basis for payment of loss. Accordingly, I accept the FSP and/or CI were entitled to undertake a final review with respect to the calculations to determine the extent of its liability under the claim. 30. I have carefully reviewed the relevant calculations , the subject of this dispute for MB and WP. It is clear that AC made an error in the field representing the “ 2 nd Total ” for the “ Total Heads x Factor ”, noted this as being 9450. On calculating the relevant figures I accept the correct total amount should have been noted as 3450 (1385 + 2065). In noting the total figure as 9450 and using this in his calculation of the loss percentage, AC arrived at the original loss percentage of 58.69%. However, if the correct totals are used the loss percentage comes to 21.43%. 31. Therefore, having considered the evidence, I am satisfied that after completing his assessment and recording what he considered the amount of damage to the crop in MB and WP, AC’s intention was , on balance, to record the loss percentage as 21.43%. 32. In saying that, I also acknowledge the concerns raised by the Applicant with respect to the outcome of a number of other assessments completed by AC which when challenged and reassessed did yield a different result i.e. a higher loss percentage. Further, that had the Applicant been made aware of the mathematical error in the CSF for MB and WP, he would have arranged for a similar reassessment to determine the loss percentage on the basis Case No: 327369 Determination Page 6 of 8 visually the damage to these particular paddocks did seem to be much more than 21%. 33. The Applicant stresses the fact that arising from the delay in identifying the mathematical error, as well as further delay of bringing this to his attention, he was deprived of the opportunity to arrange a reassessment of the damage to the crop in MB and WP. He maintains arising from the delay the paddocks had been grazed by sheep as well as had been subject to more weather events. Therefore, based on his visual inspection he agreed with what AC had originally calculated the loss percentage to be and therefore initialled the CSF, he is not prepared to accept the significant reduction in this percentage now offered by the FSP. 34. I am satisfied having regard to the above discussed matters, including undisputed evidence with respect to inaccuracies with other assessments completed by AC and the fact the current dispute arises from a mathematical error by AC, that this does give credibility to the Applicant’s concerns with respect to the assessment of the paddocks and possibility that the loss percentage may have been reassessed to be higher. I also note CI acknowledges that when the assessors are infield completing these assessments, the conditions are tough and it is not unusual for the head office to identify errors in the assessment information. 35. As a result, I am concerned that the FSP has not provided a statement from the assessor AC. 36. The Applicant and AC are at odds as to whether AC advised the Applicant of the discovery of the mathematical error and the altered calculation. 37. I also note from the provided documentation that in response to the Applicant’s statement that he discussed the 58% assessment for MB and WP with AC, the FSP reports that AC says he has no clear recollec tion of any conversation he had with the Applicant and the Applicant did not go with AC when AC carried out the assessment of MB and WP. 38. In my view, the FSP should have obtained a statement from AC to assist in the resolution of this dispute. 39. Given the absence of a statement from AC, I am inclined to accept the Applicant’s statement that he was not advised by AC of the altered calculation. 40. As such I am satisfied that the Applicant has established on balance that, arising from the delay in the FSP identifying the mathematical error and/or in bringing this to his attention , the Applicant’s entitlement and/or opportunity to have the paddocks reassessed, was prejudiced. Further, that arising from the prejudice suffered by the Applicant, it is now impossible to actually arrange a reassessment and therefore determine the accuracy and/or inaccuracy of AC’s assessment of the loss percentage for MB and WP. 41. I consider the FOS Terms of Reference (ToR) relevant to this dispute are: Case No: 327369 Determination Page 7 of 8 “ 8.2 Dispute resolution criteria Subject to paragraph 8.1, when deciding a Dispute and whether a remedy should be provided in accordance with paragraph 9, FOS will do what in its opinion is fair in all the circumstances, having regard to each of the following: a) legal principles; b) applicable industry codes or guidance as to practice; c) good industry practice; and d) previous relevant decisions of FOS or a Predecessor Scheme (although FOS will not be bound by these). ” 42. In line with the above provision of the ToR, when considering disputes brought before it, the Service will take into consideration what in its opinion is fair in all the circumstances. I have therefore, had regard to the matters discussed above, such as, but not limited to:  The cause for this dispute arises from a mathematical error by the FSP’s representative AC.  It is not in dispute that several other assessments when challenged and reassessed, resulted in different (higher) loss percentages.  The FSP’s delay in informing the Applicant of the error in calculations and therefore reduced loss percentage, prejudiced his ability to have the paddocks MB and WF reassessed.  The loss percentages of surrounding paddocks as well as the outcome of some of the reassessments and effects on the final loss percentage figures.  The fact that AC did not appear to find the incorrect loss percentage of 58.69% noted upon the CSF as grossly incorrect and/or inconsistent with what he observed which supports the Applica nt’s opinion that visually the damage to the crops in MB and WF seemed more than 21%.  The original data entered within the CSF by AC cannot be completely ignored and in my view does provide guidance on his opinion with respect to the damage to the paddocks. 43. Although, I am not prepared to accept the Applicant’s position that the prejudice suffered now requires the FSP to honour the inaccurate loss percentage calculated by AC i.e. 58.69%, I am satisfied that it would be fair in the circumstances to require the FSP to increase its settlement under the claim for the two paddocks in dispute, by a further 10%, in addition to the current settlement offer. Determination 44. I determine that the FSP is to amend its offer of settlement under the claim with respect to the paddocks MB and WP. The offer of settlement is to be increased by 10%, in line with paragraph 43 above. Case No: 327369 Determination Page 8 of 8 45. The FSP is to pay interest, on the additional settlement amount, in accordance with the Insurance Contracts Act 1984, from the date the initial offer was made, until the date of settlement.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.