Home / Financial Firm (Unknown - Credit) / Determination 326923

Determination 326923

Hardship assistance and mortgage sale settlement proceeds disputed

FirmFinancial Firm (Unknown - Credit)
Decided2014-08-14
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The borrower in arrears on an investment home loan disputed the FSP's hardship handling and the payment of sale proceeds to a second mortgagee. AFCA found the FSP met its financial difficulty obligations and made no settlement error, so the FSP may enforce.

The Code of Banking Practice requires genuine consideration of hardship requests, and AFCA had no power to vary an investment loan entered into before 2010.

Issues

Subjects and remedies

financial hardshipno remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Case No: 326923 Determination Page 1 of 6 Case number: 326923 Credit - Consumer Credit - Home Loans - Financial Difficulty - Request to Suspend Enforcement Proceedings 15 July 2014 1 Overview 1.1 Dispute This dispute concerns the financial difficulty the Applicant has experienced in meeting repayments on her Investment Home Loan. The FSP approved two Investment Home Loans in 2008 to assist the Applicant construct two luxury town houses on a subdivided block. The Applicant planned to sell one and live in the other. This dispute relates to the Investment Home Loan approved to assist with the construction of the townhouse on Lot 2. This loan was approved for an amount of $3,440,000 and was secured by a mortgage over both Lots 1 and 2. 1.2 Issues and key findings Did the FSP make any error when settlement proceeds for Lot 1 were paid to the second mortgagee ? The FSP made no error in relation to the settlement for the sale of Lot 1. Lot 1 was sold by the Applicant and payment of funds to the second mortgagee was organised by her solicitor in accordance with their instructions. The FSP only received funds sufficient to discharge its mortgage over the property and was not in control of distributing funds to the second mortgagee. The Applicant is not entitled to compensation for this aspect of the dispute. Did the FSP meet its obligations to give genuine consideration to the Applicant’s requests for financial difficulty assistance? The FSP met its obligations to give genuine consideration to the Applicant’s requests for assistance following the issue of Defa ult Notices on 18 April 2012. It agreed to accept a payment arrangement for clearance of the arrears. The loan arrears were cleared in full by 12 June 2012. Determination Case No: 326923 Determination Page 2 of 6 The FSP also met its obligations to give consideration to the Applicant’s circumstances in September 2012. Whilst it initially declined assistance on 12 September 2012, the FSP reconsidered its position and on 26 September 2012 agreed to the Applicant’s request for a timeframe to clear arrears, and requested Personal Money Plan and additional informa tion to be provided in order to assess the Applicant’s circumstances. Would I vary the credit contract? I do not have the power to vary an investment contract entered into prior to 2010. In any event, even if I had the power to vary the credit contract I would not do so in this case as the Applicant has said that her financial situation remains unchanged and she is not in a position to offer any payments towards the loan. 1.3 Determination This Determination is in favour of the FSP. The FSP has met its financial difficulty obligations to the Applicant. The Applicant has failed to submit a realistic repayment proposal that would see the loan repaid in full. When FOS closes its file the FSP is entitled to commence enforcement action to recover the debt owed. 2 Reasons for Determination 2.1 Did the FSP make any error when it paid the second mortgagee at the settlement of the Applicant’s first property? The Applicant completed construction of the townhouse on Lot 1 and sold the property in 2010 for an amount of $3,600,000. Settlement occurred on 10 December 2010 and the mortgage over Lot 1 was discharged. At settlement, the FSP collected funds totalling $3,285,905.93 and funds totalling $132,301.13 were paid to a second mortgagee. The Applicant is disputing the payment of sale proceeds to the second mortgagee as she believes she should have received those funds to assist with completion of the townhouse on Lot 2. As the Applicant voluntarily sold Lot 1, the settlement was managed by her lawyers and funds were paid in accordance with their instructions. The FSP only received funds sufficient to discharge its mortgage over the property, and was not in control of distributing funds to the second mortgagee. Case No: 326923 Determination Page 3 of 6 In order to obtain a discharge of t he second mortgage, the Applicant’s lawyer organised for the purchaser to provide a cheque made payable to the second mortgagee or its solicitor. This payment was made directly to the second mortgagee and the FSP did not control the payment. Presumably if the Applicant’s lawyer had not made the arrangement to pay the second mortgagee, it would not have provided a discharge of its mortgage and the sale would not have proceeded. The FSP has not caused the losses claimed. An FSP should give ge nuine consideration to a customer’s request for assistance Under the Code of Banking an FSP has an obligation to genuinely consider a customer’s request for assistance, where the customer is in financial difficulty. I also expect a customer to be willing to work with their financial services provider, and to propose a realistic repayment plan that will result in the repayment of the debt within a reasonable timeframe. The FSP met its obligations to give genuine consideration to the Applicant’s requests for financial difficulty assistance The FSP met its obligations to give genuine consideration to the Applicant’s request for financial assistance. The following is a su mmary of key records relating to the Applicant’s requests for assistance. Record Key points Credit contract 2008 The Applicant took out an Investment Home Loan totalling $3,440,000 to assist with the construction of a townhouse, which was security for the loan. Payment arrangement June 2012 The FSP issued Default Notices on 18 April 2012 demanding payment of arrear s totalling $108,076.72 plus enforcement costs of $595.54. The Applicant cleared the arrears in full by 7 June 2012. The FSP informed the Applicant’s partner that the Applicant’s payment of $21,526.82 that was due on 1 June 2012 had been dishonoured, and as a result the loan was in arrears by $21,222.01. The FSP said that it was happy to consider additional time for the Applicant to clear these arrears. The Applicant made a payment of $24,921.11 on 12 June 2012 which cleared the arrears.  Case No: 326923 Determination Page 4 of 6 The Applicant failed to maintain the monthly loan repayments following clearance of the arrears on 12 June 2012 and as a result the loan fell into arrears again. On 9 August 2012 the total amount owing on the loan was $3,486,126.92. Request for Hardship Ass istance 12 September 2012 The FSP’s lawyers emailed the Applicant’s partner on 12 September 2012 in response to his email to the FSP on 6 September 2012. The lawyers stated that the FSP would consider withholding further legal action on the condition that the Applicant made a paym ent of $56,087.13 to the loan account by 19 September 2012, made the scheduled monthly repayments to the loan when they fell due, and that she accepted service of a Writ and Statement of Claim. The Applicant did not accept the FSP’s offer. The Applicant’ s partner emailed the FSP’s lawyers on later on 12 September 2012 in response, and requested financial hardship assistance due to the Applicant having lost her job. He requested the FSP agree to allow until 28 September 2012 to pay $56,087 to bring the lo an up to date, and for the October and November loan repayments to be made in December 2012. The Applicant wanted to complete construction of the home and to meet the loan repayments but required a temporary restructured payment plan. The FSP’s lawyers r esponded on 26 September 2012 and confirmed that the FSP was prepared to accept payment of $56,087.13 to the loan by 28 September 2012 but it would not accept the repayments for October 2012 and November 2012 being made in December 2012. It required the mo nthly repayments to be made when they fell due. The FSP’s lawyers requested the Applicant complete a Personal Money Plan and provide supporting income documentation in order to assess her eligibility for assistance. No information has been received to con firm that the Applicant provided the requested information. The Applicant submitted three proposals to the FSP requesting it accept offers for the sale of security property. The offers submitted were for $1.670M (gross and inclusive of GST) on 5 December 2012, $1.8M on 12 February 2013, and $1.95M on 12 April 2013. The FSP rejected the first two offers as they were gross figures and inclusive of GST. The FSP, however, was prepared to consider the third offer but it required net funds of $1.95M to be paid to it at settlement, and an executed unconditional contract of sale to be provided, with settlement to occur within 60 days. The Applicant failed to provide an unconditional contract of sale confirming these details. Case No: 326923 Determination Page 5 of 6 At the telephone conciliation conference held 3 October 2013 the Applicant’s partner proposed three options to resolve the dispute, two of which involved the FSP agreeing to accept a sale to a third party for an amount of $1.95M, and the third was for the FSP to reduce its debt to $2.8M and allow the Applicant to complete construction of the home. The FSP rejected these proposals and requested the Applicant provide it with vacant possession of the security property so that it could be sold as mortgagee in possession. The Applicant’s partner put the following proposals to the FSP, each of which were rejected :  On 22 November 2013, the Applicant’s partner informed the FSP that a prospective purchaser had offered $2M for the security property, with vacant possession to be given to the FSP on acceptance.  On 20 December 2013, he requested the FSP to assign its mortgage to another lender for $1.8M, with settlement to occur within 21 days. The FSP gave consideration to each of the offers received, however, I note that none of the offers received were for amounts sufficient to repay the outstanding debt in full. The FSP’s decision to accept or reject the offers for sale of the property or assignment of its mortgage, was a commercial decision for the FSP. I do not have the power to compel the FSP to accept any of these offers. Nor do I have the power to compel the FSP to waive debt. The Applicant is not entitled to compensation It is my v iew that the FSP gave genuine consideration to the Applicant’s requests for financial assistance and the Applicant is therefore, not entitled to receive compensation for this aspect of the dispute. 2.2 Would I vary the credit contract? There is no information to show a contract variation would assist the Applicant to overcome her financial difficulty. I am able to vary a credit contract that is regulated under the National Credit Code (NCC), which came into effect in July 2010. I may do this in circumstances where an Applicant has asked for a variation that is reasonable and will assist in overcoming their financial difficulties, but the FSP has refused the request. As the Applicant’s Investment Home Loan was approved in 2008 it is not regulated under the NCC and I do not have the power to vary the credit contract. In any event, even if I had the power to vary the credit contract, I would not exercise this power in this case as the Applicant has failed to demonstrate an ability to service Case No: 326923 Determination Page 6 of 6 the loan repayments and has provided no information to indicate that her circumstances are likely to improve. In the circumstances, I would not exercise my power to vary the loan contract.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.