Determination 326176

Delay in repairing home after insured burst pipe and claimed consequential losses

FirmFinancial Firm (Unknown - Insurer)
Decided2014-05-13
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$750
Amount claimed$14,027
SourceAFCA PDF

Summary

The applicants claimed about $14,027 in consequential losses after a burst pipe damaged their home and the FSP's repairs took roughly eight months. AFCA found the repairs were delayed and the claim could have been managed more closely, but rejected the consequential financial losses and awarded $750 for non-financial loss.

Consequential losses (mortgage, electricity, garden, rent) were not shown to be caused by the delay and were not covered by the policy, while delay in managing the repairs justified non-financial loss compensation under the Terms of Reference.

Issues

Subjects and remedies

home or building damagepay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 326176 Determination Page 1 of 16 Case number: 326176 General Insurance - Domestic Insurance - Home Building - Service - Delay in Claim Handling 11 April 2014 Summary Description:  This dispute concerns a claim by the Applicants under a home and contents insurance policy for damage to their home as a result of an insured event, the time taken to repair the home, the nature of the work done and claimed losses consequent to the repairs. Basis for Determination:  On the information provided it was not accepted that the time taken to do the repairs or the nature of the repairs was such that it was established this caused the consequential losses claimed. The policy or the Terms of Reference did not respond to this consequential financial loss either. Determination:  The FSP is not obliged to pay the consequential losses claimed or any further cover to the Applicants;  Should the Applicants accept this Determination, within 7 days of acceptance, the FSP is to pay the Applicants $750 compensation for non financial loss pursuant to the Terms of Reference. Background 1. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the background as set out in the Recommendation is accurate and is as follows. 2. The Applicants held a home and contents policy with the Financial Services Provider (FSP) from 21 December 2011 for their former home in Tasmania. The policy provided building cover for complete replacement and contents cover for up to $110,855. Determination Case No: 326176 Determination Page 2 of 16 3. On 27 June 2012, the Applicants lodged a claim for damage caused by a burst pipe in the ceiling which had flooded areas of the home and contents. They were in the process of relocating to Queensland, where they now live. 4. The FSP accepted the claim and arranged for experts to inspect and repair the damage. The Applicants became dissatisfied with the quality of work done, the extent of damage that was to be covered and the time taken to repair the home. They say they were unable to rent or sell the property during this period and sought compensation, which the FSP declined. 5. In December 2012 the Applicants arranged for a different repairer to attend to work at the home. They seek cover for this and compensation for the time taken by the FSP. 6. The Applicants did not agree with the FSP’s decisi on, hence the dispute which was the subject of a Recommendation. The Recommendation was in favour of the FSP and was not accepted by the Applicants. The FSP accepted the Recommendation. In the circumstances, the matter has been referred to me for Determination. Summary of Applicants’ p osition 7. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the Applicants’ position as set out in the Recommendation is accurate and is as follows. 8. The Applicants say that the FSP took too long to repair the home and left it in a state where they could neither rent nor sell the property. They say the house could not be lived in from 27 June 2012 until January 2013. 9. Further the Applicants had to pay to have the garde n maintained and the electricity supply had to be connected so the repairs could be done. 10. They claim losses of $14,027 which include:  7 months of mortgage repayments;  Electricity $742;  Builder $2,105; and  Garden maintenance $400. 11. They consider that the quality of the work conducted was not acceptable and so they required the retention of their own repairer to ensure that the work was completed promptly and to an acceptable standard. 12. The Applicants rejected the Recommendation. They essentially reiterated their position that:  The repairs took 8 months when they expected the work to be completed in one month as they were not living there;  Photos and invoices were sent to the FSP of what needed to be done; Case No: 326176 Determination Page 3 of 16  A report from their builder CT is provided and describes the work done by CT;  The scope of works was not large and yet it took too much time;  The back yard was full of debris from repair work. Damaged furniture had to be removed. Labour costs were incurred;  Some insulation work was never completed;  They are seeking compensation for their losses not lost rent or temporary accommodation;  The FSP acknowledged that the repairs took too long and the case manager didn’t manage the claim well;  The repairs were delayed. The repairers told neighbours that they were doing a quick repair as the Applicants were selling the house;  The Applicants are satisfied that the FSP’s initial response was prompt but the subsequent repairs were mismanaged;  The Applicants could not supervise the repairs as they were in Queensland but received feedback from neighbours who kept an eye out for them; and  The Applicants had a similar experience with the claim on their furniture and its removal which the Service also had to resolve as it was also mismanaged. Summary of FSP’ s position 13. I have reviewed all the material submitted by the parties and save where I make note specifically, I am satisfied the FSP’s position as set out in the Recommendation is accurate and is as follows. 14. The FSP says that the Applicants have not established any entitlement to further cover under the policy. It concedes that some of the repairs took longer than might be desired but it is of the view that the Applicants were not unduly prejudiced by this. The policy does not provide compensation for the inconvenience arising from the claims process. The Terms of Reference (TOR) do make provision for compensation but they are not invoked. 15. The FSP also says the Applicants have not provided any evidence to support that the FSP’s handling of the claim left the property un - tenantable for an unreasonably extended period of time and so it is not satisfied that the Applicants suffered a financial loss. 16. Whilst it concedes that some rectification work may have been required, the Applicants have not provided evidence to establish that there were claims related to workmanship issues, provided copies of the relevant invoice(s) to support the work done, allowed its repairer to address the concerns or the opportunity to review and rectify this damage as stipulated under the terms of the policy. Case No: 326176 Determination Page 4 of 16 17. The Applicants / their builder were asked but did not provide photographs of the alleged faulty workmanship. The FSP says it has been prejudiced in its ability to assess its liability for the repairs. If the claim was substantiated the FSP was willing to consider the claim under its guarantee. 18. Further the policy states an insured is not to authorise any rectification work without the FSP’s written authority. 19. The Applicants have sought cover for items such as loss of rent, temporary accommodation, garden maintenance, mortgage costs and electricity costs which are simply not covered under the terms of the policy. 20. Mortgage costs would still have to be paid if the property was being repaired. In any event it is a consequential loss for which there is no cover under the policy. 21. Electricity costs are also a consequential loss. Electricity supply would still have to be continued while repairs took place. 22. The garden was not damaged in the event or the repairs. The policy does not respond to this claim. 23. The FSP relies on the following policy provisions: Page 18 of the Product Disclosure Statement (PDS) “ The [FSP] Home Repair Guarantee The quality of workmanship and the materials used in any repair or rebuilding of your home and contents that we arrange and authorise will be guaranteed for the life of the property. If you are concerned about the quality of the repair or rebuilding of your home building, you must call us... We will arrange with you to inspect the repair or rebuilding and we will arrange any necessary rectification work. You must not authorise any rectification work without our written authority. ” Page 20 of the PDS “ We help with… The cost of temporary accommodation When an insured event has caused damage or loss to your building, we will help with the cost of temporary accommodation for you and, where necessary, for your domestic pets, provided: we are satisfied your building is no longer habitable, and you were living permanently in it at the time, and you have claimed on this policy and we are satisfied everything is in order. We will pay the reasonable cost incurred by you for comparable accommodation for up to 12 months while your building is being rebuilt or repaired. ” Page 23 of the PDS Case No: 326176 Determination Page 5 of 16 “ Damage to garden beds, trees, shrubs and other plants We will help pay for damage or loss to trees, shrubs, plants, hedges or garden beds on your site caused by fire or the impact of vehicles (not driven by you or by any person living at your home). The most we will pay is shown on the most recent of your policy schedule and renewal notice. ” Page 36 of the PDS “ Cover for landlords We provide a separate policy for landlords who rent their property for domestic residential purposes. Please ask us about the [FSP] Landlord Policy. ” 24. The FSP accepted the Recommendation and did not provide any further documentary information in support of its position or make substantive comment about the Applicants’ further submissions. Issues 25. Whether the Applicants are entitled to compensation due to the time taken by the FSP to process the claim. 26. Whether the FSP is liable for any other compensation, costs incurred or claimed by the Applicants. Reasons for decision 27. There has been an exchange of material between each party, and I am satisfied each party has had an opportunity to reply to the issues raised. 28. Each FOS case is decided on its merits, taking into account the facts of the case. I have reviewed all the material submitted by the parties both before and after the Recommendation was issued, in order to reach my decision. I will only refer to the relevant submissions and materials raised. 29. In reaching a decision, it is appropriate to consider the Terms of Reference under which FOS operate. The Terms of Reference require that I consider what is fair in all the circumstance having regard to the relevant legal principles, the terms of the relevant policy and good industry practice. Regard should also be had to prior Determinations, although such Determinations are not binding or precedents. Materials from the parties 30. The Applicants have provided some emails and invoices which are referred to in the chronology set out below. Case No: 326176 Determination Page 6 of 16 31. After the Recommendation the Applicants provided a description of the work done by their builders as follows: “ Category Item Trade/Service Description Instructions Bedroom/Study Ceiling Builder Plaster Ceiling Replace and Paint to match existing Bedroom/study Wall Builder Plaster walls Replace and paint/finish to match existing Bedroom/Study Other Builder Ceiling insulation Replace to match existing Bedroom/Study Ceiling Builder Bedroom light Replace to match existing Living areas Ceiling Builder Plaster ceiling to sitting area Repair and paint/finish to match existing Living areas Wall Builder Plaster Walls Repair and paint/finish to match existing .” 32. The FSP appointed an assessor and his report dated 3 July 2012 says: “ Extra assmt will be required at later date to inspect property following drying. Emergency works have not been completed to satisfactory standard with property remaining very wet. Assr has included carpet & structure drying in building sow as no contents exposure was added. Carpet replacement will be added following contents assmt. ” (sic) 33. The Resultant Damage is described by the assessor: “ Damage to bedroom 2 ceiling (collapsed), bedroom wall, electrical circuit. Sitting area ceiling. carpets to bedrooms, sitting room, lounge & dining. various contents- more to follow ” .(sic) 34. The assessor prepared a scope of works (SOW) to dry carpets, fix ceiling, replace and paint plaster ceiling, walls and insulation in bedroom/study, replace bedroom light, replace and paint plaster walls and ceiling in living areas, dry interior and re-lay carpet and clean following building repairs. The estimate of the repairs was $6,200. 35. The assessor took photographs of the damage at this and subsequent assessments. 36. Extra damage was noted in an inspection on 16 July 2012 Also noted during assmt was extra building damage not present during initial assmt. c/m please add these 2 items to building sow. - Repair wall oven cupbd end edge strip & re - lacquare. Bedroom 1 ceiling repair & paint to match existing.(sic) 37. The assessment report 19 October 2012 notes remaining repairs required as: Case No: 326176 Determination Page 7 of 16  “ bedroom 2 robe melamine shelf to be replaced ( AB)  Stub wall paint next to wall oven unit to be touched up. (AB)  Bedroom 1 ceiling to be painted (AB )  Dining room ceiling crack at plaster joint to be repaired (AB)  General cleaning (vacuum floors, several dirty marks on walls & general post repairs clean ) The following items were discussed & confirmed as non claim related.  Shelf under cook top stained - Not covered, these marks appear to be oily stains from cook top above.  Dirty marks inside robe of bedroom 3 - Not covered, Non claim related.  No mould was found on any melamine robe shelves.  Curtains throughout were found to be undamaged.  Wall oven myrtle veneered side - Not covered- this damage appears to be old, long term damage due to the colour of the damaged area & inconsistent pattern not related to this water damage. ” (sic) 38. On 22 October 2012 a new SOW was prepared to include these new minor repair items. Chronology 39. The FSP has provided its file notes and supporting material which are very lengthy. I have reviewed them carefully together with material from the Applicants. 40. The dispute the subject of this Determination has a lot of detail and is intertwined w ith issues with the Applicants’ contents. A chronology is useful to set out what was done and when as far as this part of the dispute is concerned. The use of “Applicants” refers to the male or female Applicant. AB is the builder appointed by the FSP. CT i s the Applicants’ builder. 41. I note the following relevant events: o 19.4.12 – 15.1.13 electricity charges to house total $742.03 o 14.5.13 $2,056 deducted to pay mortgage this day and monthly thereafter o 11.6.12 Property last occupied (file note of FSP 28.6.12) o 25.6.12 House up for sale/ rental as evidenced from email from property manager o 27.6.12 pipe burst in the ceiling o 27.6.12 claim lodged Case No: 326176 Determination Page 8 of 16 o 28.6.12 H authorised to arrange a make safe to the property o 28.6.12 Assessor appointed o 28.6.12 property assessed – couldn ’t restore c arpets as ceiling had collapsed o 3.7.12 assessment report and SOW prepared o 4.7.12 furniture due for removal as Applicants relocated to Queensland o 4.7.12 drying equipment installed o 4.7.12 FSP advised Applicants that claim is accepted and the builder AB organised to do repairs o 16.7.12 assessor reports on damaged contents and noted other minor building damage o 19.7.12 Applicant raised issues including skirtings and cupboards that are standing in water and wet and swelling o 27.7.12 complaint noted about the scope of work. Assessor to call Applicants o 27.7.12 AB noted additional damage to 7 internal doors and rectification work required o 1.8.12 Applicants’ email request to halt repairs because of dissatisfaction with work done o FSP sent assessor to re attend re quality of workmanship and mould damage o 9.8.12 FSP conversation with the Applicants re concerns o 10.8.12 SOW provided by FSP to Applicants o 14.8.12 mould inspection report and carpet at back of house was beyond salvage, window sill in back bedroom has mould and will need to be replaced and concrete floors have mould growth o 15.8.12 Applicants advise they have arranged for another to attend the house and report on the works (no report provided) o 29.8.12 FSP notes assessor to attend with insured o 3.9.12 AB updated FSP on limited remaining work to be done – he noted ceiling plaster damage not near burst pipe o 5.9.12 Applicants email FSP with concerns re investigation of water damage o 7.9.12 lengthy conversation: FSP updating Applicants o 7.9.12 FSP asked AB to comment on Applicants’ concerns o 13.9.12 message left with Applicants to update o 13.9.12 email from FSP and AB answering concerns and noting all carpet to be replaced save for carpet in lounge room and main bedroom and all wet insulation to be replaced on completion o 14.9.12 lengthy telephone discussion re various issues Case No: 326176 Determination Page 9 of 16 o 19.9.12 Applicant wants confirmation that wet ceiling insulation removed o 23.9.12 email: Applicants say repairs can re-commence o 23.9.12 Applicants asks for work to be completed as the house is to be put back up for sale after the repairs. o 28.9.12 email from FSP: builder to proceed with repairs and confirming guarantee on repairs o 28.9.12 replacement of 7 sets of curtains put in train o 11.10.12 Applicants advised property manager had forwarded photos showing faulty workmanship and a mess left by the builders. (photos not provided). FSP said AB must be allowed to address the issues o 11.10.12 FSP note: repairs are not yet completed but will be in 3 to 4 days but insured said repairs were completed and builder handed back keys. FSP to contact AB o 12.10.12 FSP contacted Applicants to discuss repairs and complaints and said an assessor was to attend o 12.10.12 Replacement curtains arranged o 15.10.12 assessor appointed o 19.10.12 Assessor Report – The assessor met with the builder and reported repairs were of a reasonable standard and two additional repairs were required and scope of work (SOW) to be forwarded. Noted non claim related issues and debris to be removed o 21.10.12 the Applicants’ builder CT inspected t he house and made a list of what still needs to be fixed by FSP o 24.10.12 SOW sent to Applicants. Some items not claim related. Arranged removal and disposal of unsalvageable items o 29.10.12 AB aware of new items and rectification works and need to clean up o 12.11.12 FSP notes show it approved AB’s account o 14.11.12 FSP spoke to AB - all repairs completed including extra work and all necessary insulation installed o 14.11.12 the FSP agreed to cover the cost of transport of contents o 16.11.12 email from FSP: AB confirms with FSP that all repairs have been completed including replacement of all necessary insulation o 22.11.12 Applicants said repairs not completed, clean up and removal of debris required. All insulation has still not been replaced. Wall has been patched up but now blotchy. Carpet is dirty. Own builder appointed. Insured asked to send in photo of poor repairs. (Photos not sent) o 5.12.12 FSP left message to discuss Case No: 326176 Determination Page 10 of 16 o 5.12.12 FSP confirmed it had arranged for the restorer to attend to the carpet clean and dispose of carpet debris o 7.12.12 FSP follow up re cleaning and disposal o 7.12.12 FSP to follow up builder re complaint about insulation o 7.12.12 Applicants said their repairer had completed the repairs and clean up so people can be shown through the home and some of the insulation had not been replaced o 12.12.12 FSP confirmed the carpets had been cleaned and debris removed and curtains hung o 11.12.12 invoice from CT in the amount of $3,520 for gardening work, painting, new shower screens and labour o 12.12.12 email from FSP advising Applicants that the FSP had completed all repairs o 20/12/12, 10/1/13 and 29/1/13 gardening work done by CT - $205. o End January 2013 - this is when the Applicants say the house was liveable o 4.2.13 Applicants complain about claims service and time taken to finish works and say lost rent of $350 per week o 7.2.13 FSP spoke to Applicants about the claim. Applicants agreed shower screen not part of claim. Applicants asked for further information to resolve the dispute but o nly wanted now to deal with IDR o 21.2.13 invoice shows gardening work done by CT - charge $65. o 27.2.13 IDR letter from FSP – FSP agrees that the claim could have been processed in a timelier manner through closer management but otherwise not liable without further proof o 15.3.12 further IDR letter o 22.3.13 email from FSP asking for evidence that there were workmanship or material issues with the completed work and any costs to correct this so the claim can be considered o 13.6.13 FSP asks for proof of poor workmanship o 5.7.13 Applicants reply to say invoices previously given and matter now in the hands of FOS. Analysis 42. The Applicants had a claim for loss and damage to their home and contents to which the policy responded. Having accepted the claim, the FSP agreed to repair the property. The essence of this dispute is that the repairs were not done well and took too long as a result of which the Applicants have suffered further loss as they could not rent or sell the home. In order to do so they say they had to engage their own builder. Case No: 326176 Determination Page 11 of 16 The time taken to do the repairs 43. A careful review of the FSP’s claim file shows there were many issues of concern to the Applicants and much of the file notes are taken up with issues concerning the Applicants’ contents which is not the subject of this Determination. 44. As for this dispute from the information to hand I accept that:  The Applicants were no longer living in the house when it flooded but their contents were still there;  They had moved to Queensland and made arrangements to rent or sell the house;  The damage was assessed promptly on 3 July and repairs began in a timely fashion;  The water damage was throughout the house and the initial estimate of repairs was $6,200;  The damage was assessed twice more and some extra but minor items noted for repair as the SOW prepared in October was just $6,300;  There was a delay in the works as the Applicants halted the works on 1 August 2012 and did not allow resumption of the works until 23 September 2012;  Once the works were resumed, they were completed on or about 14 November 2012 save for carpet cleaning and disposal of some debris. The FSP confirmed this was done on or about 12 December 2012;  The Applicants have had the property inspected by their neighbours, the property manager and another builder and indicate photographs were taken of the poor workmanship yet despite requests these photographs have not been produced;  The FSP acknowledges in its IDR letter there were issues with timeliness but the FSP was not satisfied the Applicants had sustained a financial loss as a result of the claims handling;  No reports or statements in support have been provided by the Applicants save for the description of work done by their builder and provided after the Recommendation; and  At all times the FSP was willing to investigate and rectify the complaints made by the Applicants but the Applicants did not allow this and had the work done by their own builder. 45. Having carefully considered the available information I am satisfied that the work took about 10 weeks to complete in total as I accept the bulk of the work was done by mid November 2012. The works were delayed for about 7 weeks from 1 August 2012 when the Applicants called a halt to the works. The work that remained after mid November 2012 was only some cleaning of the carpet and removal of debris. I have carefully considered the photographs taken by the assessor in October 2012 and I am not satisfied Case No: 326176 Determination Page 12 of 16 that the state of the house was such that it could not have been rented or sold at that time. And from the limited information provided by the Applicants, I am not satisfied that this remaining work would have prevented the rental or sale of the property and caused the other consequential losses claimed. 46. The Applicants says that as the house was empty the repairs should have taken a month to finish but do not adduce any evidence to support this contention from their builder or any other source. 47. I do accept that the work was in many rooms in the house and was extensive and probably hampered initially by the fact that the house had to be dried out. However taking into account the photographs from the assessor, the descriptions by the assessor and the Applicants’ builder of the work to be done and the cost of the work to be done , I am not satisfied that the time taken to do the work was acceptable. Taking all matters into account, I am of the view that the work should have been completed at least by the end of October. After the final assessment, which took place on 19 October 2012 only some minor work remained to be done. The workmanship and claimed loss 48. However, the question then becomes did the failure to complete the work or this remaining work more quickly cause the Applicants ’ loss. Did it prevent the Applicants from renting the property or arranging for it to be sold? 49. The assessor’s photographs and the assessor’s report show that the work to be done was very minor – a replacement shelf, a touch up of paint next to the wall oven, the bedroom ceiling to be painted, a crack to be repaired in the dining room ceiling and some general cleaning. I am not satisfied on the material to hand that this remaining work was such that the Applicants have sustained the loss they claim. For example there are no photographs from them of the state of the property although it is indicated from the file notes some were taken. Further, there is no statement from the property manager saying that the state of the property was such that it could not be rented or sold at or about this time. 50. In that last assessment report the assessor says the work done was of a reasonable standard. The Applicants disagreed as evidenced by the email dated 22 November 2012. And some time before 11 December 2012 the Applicants engaged their own builder to rectify the work. 51. I note that if rectification work is requir ed, the FSP’s policy provides a lifetime guarantee on repairs. This ensures that any unsatisfactory work is completed by the original repairer. I also note the policy says that an insured must not authorise any rectification work withou t the FSP’s written authority. However, I also acknowledge the countervailing argument of the Applicants that they could wait no longer and so engaged their own builder. 52. The invoice from CT dated 11 December 2012 shows there was 18 hours of painting done and 11 hours of labour to clean up and organise works. Paint and a new water pipe were purchased. The invoice does not particularise Case No: 326176 Determination Page 13 of 16 where the work was done. CT’s email dated 22 October 2012 lists work he says had to be done but it is minor compared to the description of work provided after the Recommendation. 53. After the Recommendation, the Applicants attach a document which is called CT’s report but it is not dated or on letterhead. It indicates that work was done to the same areas worked on by AB – to the bedroom/study and living room. The work replicates work done by AB too – to replace and paint plaster ceilings, plaster walls, ceiling insulation and a bedroom light. 54. I do not find the material provided by the Applicants to be sufficiently compelling in view of the photographs and the last report from the assessor who says the work done was reasonable. There are no photographs from the Applicants of the faulty work despite many requests. Nor is there a statement from CT saying exactly what the state of the work was and what he had to do to rectify it. Moreover the list of work set out in the email 22 October 2012 lists work he says had to be done. It is not dissimilar to the work the assessor wanted AB to do to complete the work yet AB is not given that opportunity as the policy provides. 55. I note also that part of the invoice dated 11 December 2012 is for new shower screens. There is no compelling evidence that this relates to the damage from the insured event. I note also the file note made by the FSP that the Applicants concede this is not claims related. 56. The policy provides that an insured must not do rectification work without the FSP’s written authority yet work was done by CT without the FSP’s authority. Further the FSP had indentified the remaining work to do be done and had set in train for that work to be done. I am not satisfied on the material to hand that the work done by CT was justifiable in all the circumstances of the dispute and I do not accept that the FSP is liable to compensate the Applicants for the cost of CT ’s work. 57. The event caused damage that required repairs. During this time the Applicant still had to maintain the property, maintain the garden, keep on electricity and pay the mortgage. On the information provided and for the reasons stated, I do not accept that the event, the ensuing repairs or the policy terms respond to the claimed losses. I will deal with the specifics of each part of the rest of the claims in turn. The garden 58. The Applicants claim they had to maintain the garden for longer than was necessary because of the repairs. 59. Aside from the broad general finding that on the information provided I am not satisfied that the repairs and the time taken to do the repairs led to the claimed losses, the Applicants were still obliged to maintain the ho use and garden while the repairs were taken place. Case No: 326176 Determination Page 14 of 16 60. In addition the policy does not respond to any claim for damage to the gardens by this event. 61. Finally, much of the sum of the amount claimed is for work done after the repairs were finished. Mortgage and electricity 62. The Applicants claim they had to pay the mortgage and keep the electricity connected for longer than was necessary. 63. Aside from the broad general finding that on the information provided I am not satisfied that the repairs and the time taken to do the repairs led to the claimed losses, the Applicants were still obliged to pay the mortgage and keep on electricity while the repairs were taken place. 64. In addition the policy does not respond to any claim for these losses. 65. As for the amounts claimed, the mortgage payments and electricity charges claimed include periods before the repairs began and after the repairs were completed. Loss of rent 66. The Applicants also claim that they could not rent the property out as planned because of the poor repairs and the length of time to do the repairs. They say they would have got rental of $350 per week. They claim compensation for this loss. 67. Aside from the broad general finding that on the information provided I am not satisfied that the repairs and the time taken to do the repairs led to the claimed losses, the Applicants were still obliged to mitigate any loss. 68. I accept that they had approached an agent to sell or rent the property just before the insured event. However, there is insufficient information to satisfy me that the property could not be sold or rented out once the repairs or the bulk of the repairs were completed. The Applicants have provided no photographs of the property to show it was not fit to sell or rent at the relevant time. There is no statement from their builder or the property manager about how the property appeared and how it was not fit for sale or lease, when it became fit and when attempts were made to sell or lease it. 69. In addition the policy does not respond to any claim for these losses. Compensation 70. The Terms of Reference provide: 9.3 Other compensation a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for consequential financial loss or damage up to a maximum amount of $3,000 per claim made in the Dispute. Case No: 326176 Determination Page 15 of 16 b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non- financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind has occurred; or (ii) in the case of a Dispute pertaining to an individual’s privacy rights – injury has occurred to the Applicant’ s feelings or humiliation has been suffered by the Applicant. The maximum amount of compensation for non-financial loss will be 3,000 per claim made in the Dispute. 71. I have made a finding that the FSP does not have to compensate the Applicants for consequential financial loss on the information provided and for the reasons stated. 72. But there remains the question of non financial loss. The Applicants claim compensation for the time taken by the FSP to manage the claim. They say the amount of times they had to call due to issues with the house was unacceptable. 73. The FSP cites the relevant part of the Terms of Reference in its Notice of Response but does not address this issue specifically there. However , it does point out in its submissions that some part of the delay was caused by the Applicants’ halt in work for almost 2 months from 1 August 2012. 74. However, in its IDR letter dated 27 February 2013 it apologises that the Applicants “have not received the level of service (they) would expect throughout this claims process ”. And the letter also says: “(the FSP is) of the view that the claim could have been processed in a timelier manner through closer management.” 75. An insurance claim of this kind where there is significant damage to the house and contents will cause anxiety and inconvenience to an insured. From one perspective the Applicants were fortunate to no longer be living in the house, but I accept their situation was also made worse by the fact that they were not close by and able to deal with day to day issues. And I also accept that some of the angst had to do with the claim to their contents which claim has been settled and is not the subject of this dispute. 76. My careful review of the file notes show there were many items that were damaged and so the parties were in constant discussion about the resolution of the various aspects of the claim for the damage to the house and to the contents. Such claims which have so much detail take time to assess, repair and settle. 77. The file notes show the FSP was responsive t o the Applicants’ many contacts but nonetheless I am not satisfied that the FSP managed the builder and the repairs works as closely as is optimum even taking into Case No: 326176 Determination Page 16 of 16 account the location of the works and the detail of the claims both for the house and contents. 78. I accept that the FSP acknowledges the claim could have been managed more closely and faster. I also accept that the time taken to resolve the situation would have interfered with the Applicants’ expectation of enjoyment and peace of mind. 79. Taking into account all matters I am of the view that it is fair in all the circumstances to award the Applicants $750 for compensation for non financial loss. Determination 80. On the basis of the available information and for the reasons stated, I determine:  The FSP is not obliged to pay the consequential losses claimed or any further cover to the Applicants;  Should the Applicants accept this Determination, within 7 days of acceptance, the FSP is to pay the Applicants $750 compensation for non financial loss pursuant to the Terms of Reference.