Text of the determination
Case No: 324833 Determination Page 1 of 7
Case number: 324833
Credit - Business Finance - Business Loans - Financial Difficulty - Decline of
Financial Difficulty Request
Credit - Business Finance - Business Loans - FSP Decision - Maladministration
in lending
18 October 2013
Background
1. As advised to the parties, the Financial Ombudsman Service (FOS) has
considered it appropriate to expedite the dispute in accordance with the
Operational Guidelines to the FOS Terms of Reference. The dispute has not
been the subject of a Recommendation and has proceeded directly to
Determination.
2. The Applicants are a married couple. The dispute concerns financial difficulty
they have experienced in relation to a facility agreement (the facility) with the
with the financial services provider (FSP). The facility was initially approved
on 11 August 2008 for $4.1 million. The Applicants also have an overdraft
facility (the overdraft) with the FSP.
3. The outstanding balance of the facility as of 18 September 2013 was
$5,317,274.69, and $87,763.09 on the overdraft facility.
4. The original term of the facility was 18 months, and is secured by mortgage
given by the Applicants for their residential home (the security property) The
overdraft is unsecured.
5. The Applicants lodged an earlier dispute with FOS on 3 August 2011. This
dispute was closed on 27 March 2013 because the Applicants’ claim of
maladministration in lending exceeded our $500,000 jurisdiction limit under
Paragraph 5.1 (o). This claim will not be considered as part of the dispute.
6. The FSP commenced legal proceedings by filing an application to take
possession of the security property on 29 May 2013. The FSP has not yet
obtained judgment against the Applicant, and the legal proceedings are on
hold while FOS is considering the dispute.
7. The FSP appointed Receivers and Managers (the Receivers) on 10 April
2013. FOS cannot review or intervene in any action by the receiver
appointed over the security property, and the receiver is not obliged to
suspend its enforcement action, including sale of the security property.
8. This dispute is about:
Determination
Case No: 324833 Determination Page 2 of 7
whether the FSP has met its obligations to give genuine consideration to
the Applicants’ requests for financial difficulty assistance
whether the FSP breached any obligation to the Applicants’ in respect of
any enforcement action.
Reasons for Decision
Financial difficulty
9. I consider that under section 25.2 of the Code of Banking Practice an FSP
has an obligation to genuinely consider a customer’s request for assistance,
where the customer is in financial difficulty.
10. I also expect a customer to be willing to work with their financial services
provider, and to propose a realistic repayment plan that will result in the
repayment of the debt within a reasonable timeframe.
11. I have outlined below a brief chronology of events.
History of key events
12. The purpose of the facility was, predominately, to acquire a block of land and
either sell this to a developer or jointly develop the parcel of land (the
development property). This was to be achieved within 18 months from the
date of the first draw down, which was the duration of the loan. The
Applicants first drew down on the loan on 15 September 2008.
13. The facility was one that made provision for interest to be capitalised. It was
not intended that the Applicants make any payments toward the facility, but
rather, to have developed or sold the parcel of land within the 18 month
period.
14. On 12 July 2010, the Applicants advised the FSP that they were in
discussions with a joint venture partner, and that they would provide a copy
of paperwork confirming refinance the following week. The Applicants asked
for an extension of the loan term.
15. By letter of variation dated 2 August 2010, the FSP extended the facility until
1 November 2010. This was accepted by the Applicants on 30 August 2010.
16. The facility had not been repaid by the expiry date of 1 November 2010. The
FSP agreed to another extension of the facility term, by a period of three
months, until 15 February 2011.
17. The FSP wrote to the Applicants on 9 February 2011. It raised concerns
regarding the Applicants’ ability to repay the debt by the due date, and their
deteriorating equity position. The FSP advised that it was not prepared to
extend the term of the facility further, or to continue to capitalise interest and
fees. It asked the Applicants to outline their strategy to address its co ncerns
Case No: 324833 Determination Page 3 of 7
within 14 days. It said that because of the increased risk, it may increase the
risk margin rate on the facility by 3.45 per cent per annum.
18. The Applicants did not respond to this letter.
19. The FSP issued notices of demand on 6 April 2011, requiring repayment
$4,243,417.87 by 13 April 2011.
20. The Applicant’s informed the FSP by email dated 13 April 2011 that they
were discussions with a major financial institution along with a joint venture
partner. They said this would provide sufficient funds to clear the debt,
however, they required more than seven days.
21. On 3 June 2011, the FSP issued Power of Sale notices pursuant to the
relevant section of the State’s Property La w Act. This provided the
Applicants with 31 days to remedy the default by paying the amount of
$4,295,725.03; failure to comply would result in the FSP taking steps to
possess the security property with a view to selling it.
22. In June and July 2011, t he Applicant’s contacted the FSP to say they were in
negotiations with a joint venture partner and that this would see the debt
cleared.
23. The FSP wrote to the Applicants on 12 July 2011. It reiterated that it had
issued Power of Sale notices which had since expired, but that in view of
their advice regarding refinance, it would forbear on enforcement action. The
FSP informed that Applicants that they were required to provide a copy of
the offer of refinance by no later than 5 August 2011.
24. The Applicants lodged a complaint with FOS on 3 August 2011.
25. The Applicants wrote to the FSP on 5 August 2011, informing it that they had
received offers of two joint venture and refinance. However, the Applicants
did not provide copies of these offers.
26. In a letter dated 5 August 2011, the FSP asked the Applicants to confirm the
timeframe they required to achieve refinance. The FSP again asked the
Applicants to specify how much time they required in emails dated 12 and 19
August 2011.
27. The male Applicant spoke with the FSP on 16 August 2011, and provided an
update on his situation. The FSP said that if the Applicant wanted it to
consider extending the facility it would need a proposal from him, including a
principle reduction in addition to clearance of interest arrears.
28. The Applicants emailed the FSP on 23 August 2011, asking for three months
to finalise joint venture negotiations.
29. The FSP wrote to the Applicants on 26 August 2011. In its letter, the FSP
said that it was prepared to forbear from further recovery action until 31
December 2011 on condition that they confirm their FOS dispute was
Case No: 324833 Determination Page 4 of 7
resolved and execute a settlement agreement. The FSP enclosed a Deed of
Forbearance.
30. The FSP wrote to the Applicants again on 12 September 2011. It reminded
the Applicants that there was no arrangement in place until the Deed of
Forbearance was executed by all parties.
31. The FSP spoke with the male Applicant on 7 October 2011. The male
Applicant advised in this conversation that he would be able to provide a
clear timeline of refinance and debt repayment on 10 October 2011.
32. An FSP file note indicates that it spoke with the male Applicant again on 25
October 2011, confirming that it had resent the Deed of Forbearance on 12
September 2011, requiring execution by 21 September 2011. The male
Applicant said he had not yet reviewed these documents, and did not realise
he was required to return them by that time. He said he would return these to
the FSP within the next two business days.
33. The Deed was not returned and the FSP attempted to follow up with the
Applicants in early November 2011. The Applicants emailed the FSP on 11
November 2011 outlining the details of their negotiations, including their
refinance attempts.
34. The FSP wrote to the Applicants on 12 December 2011, offering to forbear
for a further period, until 15 March 2012, subject to the Applicants finalising
their FOS dispute and executing a Deed, enclosed with its letter.
35. The male Applicant spoke with the FSP on 13 March 2012, saying that
refinance was expected within the refinance to be completed within the next
two or three weeks. He said that he would send a copy of the unconditional
refinance approval once this came through.
36. A telephone conciliation conference was conducted on 12 June 2012.
Following this, the FSP sent a new Deed of forbearance to the Applicants on
13 July 2012, providing them until 31 December 2012 to repay all debt owing
to the FSP, or to provide vacant possession of the security property within 14
calendar days of the end of a written notice from the FSP.
37. The Applicants declined the FSP’s offer. The Applicants claimed that the
FSP had breached its responsible lending obligations under the National
Consumer Credit Protection Act 2009 (NCCP). The amount claimed by the
Applicants exceeded our jurisdictional limit and so the dispute was closed on
27 March 2013.
38. The FSP issued a demand notice on 5 April 2013, and appointed Receivers
and Managers on 10 April 2013.
39. On 2 May 2013, the FSP issued notices requiring vacant possession, and a
notice of exercise of power of sale.
40. The Applicants lodged a new dispute with FOS on 29 May 2013 at which
time the FSP was informed.
Case No: 324833 Determination Page 5 of 7
41. The FSP’s solicitor filed an originating application with the Supreme Court on
29 May 2013. This was adjourned on the same day.
Analysis
42. I am satisfied that the FSP has genuinely considered the Applicants ’
requests for assistance, and has met its obligations to try to assist the
Applicant to overcome their financial difficulty. The reasons for this are as
follows:
The FSP extended the facility term twice in response to the Applicants’
requests, with the final period ending February 2011.
It sought supporting information from the Applicants on numerous
occasions, including copies of refinance offers, and provided informal
extensions of time in February 2011 and July 2011.
The FSP has offered a Deed of Forbearance to the Applicants in
August 2011, which proposed an additional period of four month for the
Applicants to repay the debts owed to the FSP.
The FSP offered a second Deed of Forbearance to the Applicants in
December 2011, offering a period of three months.
The FSP offered a third Deed of Forbearance in July 2012, providing
the Applicants a period of more than five months.
43. It is now more than five years since the Applicants took out the loan and
more than two and a half years since the facility (as twice varied) expired on
15 February 2011. The Applicants have made no payments towards the
loan, apart from $50 in January 2009.
44. The Applicants have to date failed to provide a realistic repayment proposal
that would see the debt, including arrears, repaid within a reasonable
timeframe. In these circumstances, I do not consider that the FSP has acted
incorrectly when it declined the Applic ants’ request for assistance in
response to their most recent FOS dispute.
45. It is my view that no compensation is payable to the Applicant in relation to
this aspect of the dispute.
Enforcement action
46. The below table shows the date of the solicitors’ invoice, and the amount
billed including GST. The greyed items are those which were billed at a time
that there was an active FOS dispute. The FSP has agreed to reverse these
fees on a commercial basis.
Case No: 324833 Determination Page 6 of 7
Table 1
Invoice d ate Amount
20 - Apr - 11 $1,138.67
30 - Jun - 11 $435.60
31 - Aug - 11 $1,018.60
30 - Sep - 11 $508.75
15 - Feb - 12 $226.60
27 - Jun - 12 $840.40
30 - Jul - 12 $542.58
20 - Dec - 12 $566.50
28 - Feb - 13 $2,296.97
26 - Apr - 13 $1,969.06
30 - May - 13 $10,206.55
27 - Jun - 13 $2,211.50
29 - Jul - 13 $1,765.61
29 - Aug - 13 $2,249.50
47. The FSP says that the work undertaken while the FOS dispute was open
related to work undertaken by its solicitor included:
a. drafting three deeds of forbearance and assisting with “offers of
hardship assistance”
b. preparing responses to be issued by the FSP to FOS, and
c. correspondence to the Applicants’ representative.
48. In my view, it is appropriate for the FSP to reverse these fees.
49. The Applicants’ account statements reflect that the FSP has passed on the
reduced tax input credit where it applied fees to their facility account.
50. I am satisfied that the FSP was entitled to pass on the costs of enforcement
action taken prior to the FOS dispute was lodged in August 2011, which
appears to relate to demand notices issued in April 2011.
Appointment of Receivers and Managers
51. The FSP appointed Receivers and Managers on 10 April 2013. I am satisfied
that the FSP was entitled to do so.
52. However, I note that at the same time, the FSP initiated its own enforcement
proceedings.
53. In my view, having appointed Receivers, it was unnecessary for the FSP to
issue proceedings for possession of the property. The FSP says the
Receivers act as an agent of the mortgagors. If that is the case it is for the
Receivers to obtain vacant possession, not the FSP.
Case No: 324833 Determination Page 7 of 7
54. The FSP should therefore discontinue its Supre me Court proceedings and
refund the cost of any legal work associated with such proceedings (or not
pass on those costs if they have not been charged).
55. The FSP says that it is unwilling to provide a copy of its solicitors’ invoices to
the Applicants, because this is protected by legal professional privilege.
56. In view of its refusal to provide the Applicants with justification for the costs, I
do not consider the FSP is entitled to pass these costs onto the Applicants.
As such, the FSP should also reverse all costs associated with the invoices
dated 26 April 2013 and 30 May 2013.
Application to the Supreme Court on 29 May 2013
57. The Applicants say the FSP continued enforcement action after it became
aware, or ought reasonably have been aware, of the FOS dispute.
58. The FSP says it was unaware of the FOS dispute at the time it filed its
application with the Supreme Court.
59. I have concluded above that the FSP was not entitled to commence its own
enforcement action, and therefore must set aside these proceedings and
reverse all costs. As such, I will not consider this particular issue further.
Determination
60. I have decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions. I have
taken into account all the material submitted by the parties. I am satisfied
that the documentation I have relied on has been provided to both parties.
61. On the basis of the available information I determine that the FSP has met
its obligation to genuinely conside r the Applicant’s requests for financial
difficulty assistance.
62. For initiating its own enforcement proceedings, the FSP should set aside its
own proceedings within 14 days of the Applicants accepting this
Determination.
63. The FSP should reverse or refrain from applying all enforcement costs, other
than for the costs associated with the invoices dated 20 April 2011 and 30
June 2011, and recalculate the facility balance as if these costs were not
charged.
64. The FSP is entitled to exercise its contractual right to recover the debt owing
to it.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.