Determination 324651
Delay in processing home loan application
Summary
The applicant said the lender unreasonably delayed her home loan approval, causing penalty interest under a property contract, and that she was forced into a fixed rate loan and unfairly charged break costs. AFCA found the lender partly responsible for a 28-day delay, awarded penalty interest compensation and a small break costs refund, plus interest, and rejected the forced fixed rate claim.
A lender is liable only for delay its own conduct caused, and break costs are payable only to the extent they exceed a reasonable estimate of the lender's loss.
Issues
- Delay primary · upheld
“the FSP was partially responsible for the delay in settlement under the contract of sale”
- Incorrect fees or charges secondary · upheld
“the break costs charged by the FSP exceed the amount which represents a reasonable estimate of the loss”
- Pressure selling secondary · not upheld
“the available information does not support the Applicant's claim that the FSP forced her to accept a fixed rate loan”
Subjects and remedies
pay compensationpay interestrefund fees or charges
Text of the determination
Case No: 324651 Determination Page 1 of 8
Case number: 324651
Credit - Consumer Credit - Home Loans - Instructions - Delay
8 April 2014
Summary
Description
This dispute involves a claim by the Applicant that the Financial Services
Provider (FSP) unreasonably delayed processing her application for a loan to
finance the purchase of a property. She says that as a result she incurred
penalty interest under the contract of sale for the property.
The Applicant also says that the FSP forced her to enter into a fixed rate loan
when she wanted to enter into a variable rate loan and therefore she should not
be liable for the break costs charged by the FSP when she repaid the loan
early.
Basis of Determination
While the FSP was not solely responsible for the delay in processing the
Applicant’s loan application, the FSP’s actions did contribute to the delay .
Accordingly, the FSP should compensate the Applicant for part of the penalty
interest costs payable under the contract of sale.
The FSP did not force the Applicant to accept a fixed rate loan. The FSP
offered the Applicant the alternative of a fixed rate loan in order to allow her to
borrow a higher amount while still complying with the FSP’s serviceability
requirements.
The break costs charged by the FSP are slightly higher than the amount which
constitutes a reasonable estimate of the FSP’s loss .
Determination
The FSP is to pay to the Applicant the amount of $2,176.06 plus interest,
comprising $2,109.52 as compensation for penalty interest payable under the
contract of sale and $66.54 as a partial refund of break costs.
Background
1. As advised to the parties, the Financial Ombudsman Service (FOS) has
considered it appropriate to expedite the dispute in accordance with the
Determination
Case No: 324651 Determination Page 2 of 8
Operational Guidelines to the FOS Terms of Reference. Accordingly, this
dispute has not been the subject of a Recommendation and has proceeded
directly to Determination.
2. In February 2011, the Applicant entered into a contract of sale to purchase a
vacant block of land. Under the contract of sale, $251,100 was payable at
settlement due on 23 September 2011 and the vendor was entitled to charge
penalty interest from that date.
3. The Applicant obtained approval from another financial services provider for
a loan to finance the purchase but this subsequently lapsed.
4. On 13 September 2011, the Applicant made an online application to the FSP
for a loan to finance the purchase. The FSP approved the loan application
but settlement of the loan (and the purchase of the property) did not occur
until 30 January 2012. At settlement, the Applicant was charged penalty
interest for 129 days.
5. The loan granted by the FSP provided for an initial three year fixed rate term.
In December 2012, the Applicant refinanced the loan with another lender
and was charged break costs of $4,448.09.
Reasons for decision
Did the FSP unreasonably delay settlement of the property?
6. Based on the information provided by the parties, the key events in relation
to the processing of the Applicant’s loan application are as set out below.
I note that in some cases there are minor differences between the versions
provided by the Applicant and the FSP. As far as possible, I have adopted
the version which is more consistent with the contemporaneous
documentary information.
Date Event
13 Sept 2011 Applicant submits online loan application .
8 Oct 2011 Applicant s ends supporting paperwork to FSP .
10 Oct 2011 FSP receives 102 pages of paperwork from Applicant and starts
application process .
11 Oct 2011 FSP receives 208 pages of paperwork from Applicant .
12 Oct 2011 FSP advises Applicant by email that it requires additional
documents to verify Applicant’s income .
13 Oct 2011 FSP receives some but not all of the additional documents
req u ested .
18 – 21 Oct 2011 FSP ’s mortgage services team liaises with loan officer about
outstanding documents .
2 5 Oct 2011 Applicant calls FSP and is told the loan officer is on lea ve.
A pplicant s tresses the matter is urgent. Applicant’s solicitor calls
Case No: 324651 Determination Page 3 of 8
FSP to clarify what additional documents are required .
26 Oct 2011 Applicant calls FSP and is advised that additional documents are
required and therefore the loan has not yet been approved,
meaning that settlement cannot occur on 28 October 2011 .
30 Oct 2011 FSP emails Applicant confirming the documents which remain
outstanding .
1 Nov 2011 PUBLIC HOLIDAY
4 Nov 2011 FSP emails Applicant confirming receipt of further documents,
requesti ng confirmation of lodgement of 20 11 company tax return ,
confirmation that personal tax returns were not required to be
lodged and bank statements . FSP receives page 1 of 2011 tax
return .
10 Nov 2011 Applicant calls FSP saying she has sent the outstanding
documents and seeking confirmation of receipt .
11 Nov 2011 Applicant’s solicitor calls FSP for an update .
15 Nov 2011 Applicant calls FSP for an update .
25 Nov 2011 Applicant’s solicitor call s FSP for an update .
18 Nov 2011 Applicant contacts FSP for an update .
25 Nov 2011 Applicant’s solicitor calls FSP for an update .
26 Nov 2011 Applicant’s solicitor calls to speak with the home loan officer .
30 Nov 2011 Applicant complains to FSP about lack of responsiveness . FSP
forwar ds the application to its credit team for in principle approval.
5 Dec 2011 FSP ’s credit team provides in principle approval and a valuation is
ordered .
12 Dec 2011 FSP calls valuer for update and is advised by valuer that contract
of sale is missing .
13 Dec 2011 FSP resends contract of sale to valuer and valuer provides
v aluation .
14 Dec 2011 FSP ’s cre dit team provides formal approval of the l oan .
15 Dec 2011 Applicant advises FSP she will be away for next 4 days .
16 Dec 2011 FSP sends l etter of offer to Applicant by express post .
21 Dec 2011 Applicant tells FSP she has not received letter of offer .
23 Dec 2011 FSP reissues letter of offer and sends to Applicant by express
post .
26 Dec 2011 PUBLIC HOLIDAY
27 Dec 2011 PUBLIC HOLIDAY
2 Jan 2012 PUBLIC HOLIDAY
6 Jan 201 2 Applicant receives letter of offer .
11 Jan 201 2 FSP receives signed documents from Applicant but discovers that
some documents have not been si g n ed and returned .
12 Jan 2012 FSP advises Applicant’s solicitor of missing documents .
18 Jan 2012 FSP calls Applic ant seeking missing documents. Applicant
Case No: 324651 Determination Page 4 of 8
resends d ocuments to FSP.
23 Jan 2012 FSP receives documents from Applicant’s solicitor .
25 Jan 2012 FSP receives transfer of land from Applicant’s solicitor. Settlement
is booked for 30 Jan 2012 .
26 Jan 2012 PUBLIC HOLIDAY
30 Jan 2012 Settlement occurs.
7. The FSP initially quoted the Applicant a timeframe of 7 to 10 working days
for approval of her loan application. This is consistent with the views of the
FOS Banking Industry Adviser who has advised that a period of around 10
working days is reasonable for a lender to review a loan application and
submit it for credit approval, with the credit approval process to be completed
within a further three working days. However, this timeframe assumes that
prior to the start of the approval process the lender has access to all of the
information which is reasonably necessary to allow it to undertake a
serviceability assessment.
8. In the circumstances of the current dispute, at the time the Applicant applied
for the loan:
she had not previously taken out a loan with the FSP and had only held a
savings account with it;
she was self employed and had changed from carrying on her business as
a sole trader to using a company structure. As a result, she was unable to
provide two years of financial records for the company; and
she was unable to provide copies of her personal income tax returns for
previous years.
9. These factors led the FSP to make more detailed inquiries and seek
additional information to support the Applicant’s loan application. In my view,
this was consistent with generally accepted industry practice and was an
appropriate step for a prudent lender to take for the purposes of assessing
the Appl icant’s ability to service th e loan.
10. Having regard to the above, I make the following comments about the time
taken to process the loan application:
it was unreasonable to expect that the entire loan approval process would
be completed within 10 working days, given the more detailed i nquiries
wh ich were required to verify the Applicant’s income, in light of her
business arrangements;
until 4 November 2011, the FSP was progressing the loan application
internally but was hampered by having not received all of the necessary
documents. It appears that this may have been due to a
misunderstanding between the Applicant and the FSP about the exact
documents required , given the Applicant’s business arrangements ,
together with the fact that the 2011 company tax return does not appear to
have been lodged until late October 2011;
Case No: 324651 Determination Page 5 of 8
between 4 November 2011 and 30 November 2011, it appears that the
progress of the loan application stalled, and the FSP failed to respond to a
number of calls from the Applicant and her solicitor. The Applicant says
that she provided all the necessary documents on 4 November 2011,
however the FSP’s systems notes indicate that it was not until
25 November 2011 that the FSP received confirmation (in the form
requested) that the 2011 tax return for the Applicant’s company had been
lodged;
the FSP has acknowledged that the delay in obtaining the valuation
between 5 December 2011 and 13 December 2011 occurred as a result of
the FSP failing to follow up the valuer to confirm that the contract of sale
had been received;
there is insufficient information to establish that the delay in the Applicant
receiving the offer documents was caused by the FSP’s actions . In my
view this is more likely to be attributable to the first set of documents
having been mislaid by the postal services, delays over the Christmas
period and/or the fact that the Applicant was away from home for four days
around this time;
the delay in processing the Applicant’s acceptance of the loan b etween 6
January 2012 and 30 January 2012 was due to the fact that not all of the
required documents were signed and returned by the Applicant. The
Applicant says that the FSP failed to send her all the necessary
documents, while the FSP says that the Applicant returned the original of
one of the documents unsigned. In the circumstances, I consider that there
is insufficient information available to establish that the FSP is responsible
for the delay during this period; and
once the FSP received the outstanding documentation on 25 January
2012, it acted promptly to arrange settlement on 30 January 2012.
11. Based on the above, I consider that, while the FSP was not solely
responsible for the delay in processing the Applicant’s loan application, the
FSP’s actions did contribute to the delay. Specifically, I consider that :
the FSP is responsible for some of the delay which occurred between 4
November 2011 and 30 November 2011. Even if it is accepted that the
Applicant had not provided all the necessary documents by 4 November
2011, it appears that the FSP failed to appropriately respond to the
Applicant’s follow up calls between 10 November and 30 November ( a
period of 20 days). Had it done so, it is likely that the loan application could
have been progressed more rapidly; and
the FSP is responsible for the delay of 8 days which occurred between
5 December 2011 to 13 December 2011 as a result of the FSP failing to
follow up with the valuer to confirm the contract of sale had been received.
12. The FSP was aware from the loan application and subsequent discussions
with the Applicant that the application was urgent, as the Applicant had
entered into a contract for the sale of land and was required to pay the
balance of the purchase price on settlement. It was therefore reasonably
Case No: 324651 Determination Page 6 of 8
foreseeable to the FSP that any delays in the loan approval process may
result in the Applicant incurring a financial penalty under the contract of sale.
13. In these circumstances, I consider that the FSP should compensate the
Applicant for the penalty interest costs payable under the contract of sale for
a total period of 28 days.
14. The contract of sale provides that penalty interest is payable at the rate of
2% plus the rate provided for under section 2 of the Penalty Interest Rates
Act 1983 (Vic). During the relevant period, this rate was 10.5%. Accordingly,
penalty interest was payable at a total rate of 12.5%. While the Applicant has
provided a settlement statement which indicates that she incurred penalty
interest at a rate of 14.5%, it is not clear on what basis this was calculated
given the terms of the contract of sale.
15. Having regard to the above, I consider that the FSP should be required to
compensate the Applicant for 28 days of penalty interest at the rate of
12.5%, calculated on the loan amount of $220,000. This amounts to a total
sum of $2,109.52.
Was the Applicant forced into the fixed rate loan?
16. The Applicant says that she applied for a variable rate loan but was told at
“the very last minute” that the loan would have to be fixed or it would not be
approved. The Applicant says that by this stage it was late December 2011
and she had already incurred significant penalty interest under the contract
of sale. The Applicant says that she did not want a fixed rate as she was
intending to refinance the loan when she began building on the land.
However, as she believed she would have to recommence the approval
process if she wanted a variable rate, she felt she had no choice but to
accept the FSP’s position.
17. The FSP ’s systems notes reflect that the Applicant originally applied for a
variable rate loan of $223,200. The FSP says that its serviceability
requirements would only allow a loan amount of $210,000 and therefore it
offered the Applicant the option of taking out a fixed rate loan which would
allow her to borrow a higher amount ($220,000) while satisfying th e FSP’s
serviceability requirements.
18. The FSP’s systems notes show that on 30 November 2011 an officer of the
FSP discussed a fixed rate loan with the Applicant and explained to her “ the
workings and conditions ” of the fixed rate loan . In the absence of information
to the contrary, I accept that the FSP’s systems notes represent a
contemporaneous record of the relevant discussions.
19. The FSP’s systems notes are not consistent with t he Applicant’s claim that
the fixed rate option was forced upon her in late December. Given that the
loan documentation clearly set out the fixed rate nature of the loan and was
not signed by the Applicant until January 2012, I consider that she had
sufficient opportunity to consider whether the loan was appropriate to her
Case No: 324651 Determination Page 7 of 8
needs. I note that there was a clear advantage associated with the fixed rate
loan (namely, the ability to borrow a higher amount).
20. While the Applicant may have felt that she had little choice at the time the
loan was offered given the situation in which she found herself, this was to a
significant extent the result of her own actions in entering into an
unconditional contract of sale prior to obtaining finance approval.
21. For the reasons outlined above, I am satisfied that the available information
does not support the Applicant’s claim that the FSP forced her to accept a
fixed rate loan.
Should the Applicant be responsible for the break costs?
22. Given the above, the Applicant is bound by the terms of the loan contract,
which provide that break costs are payable where the loan is repaid early.
23. However, where a dispute involves break costs, FOS will consider whether
the amount charged by a financial services provider represents a reasonable
estimate of the loss it incurred as a result of the relevant loan being repaid
early.
24. In the present case, the FOS Banking Industry Adviser has reviewed the
information provided by the FSP in relation to the break costs of $4,448.09
charged by the FSP in December 2012. The Banking Industry Adviser has
advised that the break costs charged exceed a reasonable estimate of the
FSP’s loss (after allowing for the 3% tolerance adopted by FOS) . In reaching
this conclusion, the Banking Industry Adviser has independently calculated
the break costs which would apply to the Applicant’s loan u sing wholesale
fixed interest rates as published in the Australian Financial Review.
25. Accordingly, the FSP should pay to the Applicant the amount of $66.54
being the amount by which the break costs charged by the FSP exceed a
reasonable estimate of the loss incurred by the FSP (after allowing for a 3%
tolerance).
Ombudsman’s Determination
26. I have decided this case on its merits, having regard to the relevant law,
good industry practice, codes of practice and previous FOS decisions. I have
taken into account all the material submitted by the parties. I am satisfied
that the documentation I have relied on has been provided to both parties.
27. On the basis of the available information I determine in favour of the
Applicant that:
the FSP was partially responsible for the delay in settlement under the
contract of sale and accordingly, the FSP should pay to the Applicant the
amount of $2,109.52 plus interest at 5% calculated from the date of
settlement (30 January 2012) to the date of payment by the FSP; and
Case No: 324651 Determination Page 8 of 8
the break costs charged by the FSP in December 2012 exceed the
amount which represents a reasonable estimate of the loss incurred by the
FSP and accordingly, the FSP should pay to the Applicant the amount of
$66.54 plus interest at 5% calculated from the date the loan was repaid
(14 December 2012) to the date of payment by the FSP.