Home / Financial Firm (Unknown - Insurer) / Determination 323915

Determination 323915

Denial of claim for cyclone tile damage

FirmFinancial Firm (Unknown - Insurer)
Decided2014-06-16
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants claimed for cracked floor tiles after Cyclone Yasi and the insurer denied it, citing no expansion joints. AFCA found the insured event established and ordered the FSP to meet the claimed loss, with interest on any cash lump sum.

The builder's evidence of expansion joints was preferred because the FSP failed to obtain its engineer's promised reconsideration.

Issues

Subjects and remedies

home or building damagenatural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 323915 Determination Page 1 of 5 Case number: 323915 General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of claim 20 May 2014 Summary Description:  A claim under a Home Building and Contents Insurance Policy following damage to the Applicants’ home caused by cyclone Yasi. Basis for Determination:  A consideration of evidence regarding the cause of the Applicants’ loss. Determination:  The FSP is not entitled to deny the Applicants’ claim. Background 1. The Applicants held a Home Building and Contents Insurance Policy (the policy) with the Financial Services Provider (FSP). 2. A claim was lodged against the policy on 23 September 2011 for damage to the insured building and contents caused by Cyclone Yasi (the cyclone) on 3 February 2011. 3. The FSP accepted the claim, however, limited its liability to the damage it deemed to be the result of the cyclone and excluded certain aspects of the damage claimed. 4. The dispute was considered by a Case Manager of the Service who issued a Recommendation. In that Recommendation, the Case Manager determined the dispute in favour of the FSP on the grounds that he was not satisfied that the Applicants had established the loss arose from an event covered by the terms of the policy. 5. The Recommendation was not accepted by the Applicants. Pursuant to clause 8.5(c) of the Terms of Reference of the Service, the Applicants requested that the dispute proceed to Determination. Determination Case No: 323915 Determination Page 2 of 5 Summary of Applicants’ p osition 6. The Applicants say that the tiles were in perfect condition before the cyclone and have cracked and deteriorated only since the cyclone. 7. Further, the Applicants say the tiles were laid to building specifications at the time when they were put down and the correct glue was used and the correct expansion joints were put in place. 8. Further, the Applicants say that during the cyclone and the torrential rain, water also entered the areas where the tiles had been affected and since that day, the tiles are getting worse. In addition, the Applicants say that if the water from the rain did not enter and the velocity of the wind the house experience had not occurred, the Applicants believe the tiles would not have been affected by the water having got into the timber flooring and making it expand and contract and increasing the chances of the tiles moving and cracking. 9. Finally, the Applicants say that the reason there is no cracks on the walls is that the gyprock is not glued or screwed directly into the walls but to a 30mm batten on the cement wall, first making a cavity between them and also the tiles had a sufficient gap around the perimeter of the area, for expansion, as they needed a 19mm skirting board around it. Summary of FSP’ s position 10. The FSP maintain that the Applicants have not established that their loss arises from an event covered by the terms of the policy. 11. In particular, I note that the FSP says that their expert confirms in writing that he did not observe any expansion joints in the tiles and the Applicants have failed to provide the evidence from builders regarding the presence of expansion joints. 12. The FSP relies on the following policy provisions: “ The [FSP] Home Building Insurance Product Disclosure Statement states on pages 12-13: YES Storm and rainwater including stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. Storm means violent wind (including a cyclone or tornado), thunderstorm or a heavy fall of rain, snow or hail. NO Damage or loss caused by flood. Flood means the inundation or covering of normally dry land by water which: Case No: 323915 Determination Page 3 of 5 escapes or overflows from, or cannot enter, because it is full or has overflowed, or is prevented from entering, because other water has already escaped or been released from it, the normal confines of any watercourse or lake, including any that may have been modified by human intervention, or reservoir, canal, dam or stormwater channel. Flood does not mean stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. The cost of cleaning or clearing debris from any pool or spa. Damage or loss caused by water seeping into or otherwise entering your building due to: a defect or fault in the design, structure or construction of your building where you could reasonably be expected to be aware of the defect or fault, building alterations, renovations or additions. Damage or loss caused by dust where your building has not been otherwise damaged by storm. ” … The [FSP] Home Building Insurance Product Disclosure Statement states on pages 14-15 “ General exclusions You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: mould, wet or dry rot, rising damp or dampness, ” Issue 13. Whether the FSP is entitled to deny the Applicants’ claim. Reasons for Decision 14. I have reviewed all of the material provided by the parties and included within their respective submissions. 15. The Recommendation of the Case Manager has not been accepted by the Applicants and as such, this matter will proceed to Determination in accordance with the Terms of Reference of the Service. “8.5 Dispute is resolved on the basis of the Recommendation. c) If, within 30 days of receiving the Recommendation, either: (i) The Financial Services Provider does not accept the Recommendation in relation to the Dispute; or (ii) Either party requests FOS to proceed from a Recommendation to a Determination FOS will proceed to a Determination by either an Ombudsman or by a FOS Panel (as the Chief Ombudsman or his or her delegate decides is appropriate). Before the Determination is made, the parties will be given a reasonable opportunity to make submissions, Case No: 323915 Determination Page 4 of 5 and provide any further information, in response to the Recommendation.” 16. Subsequent to the Case Manager’s Recommendation, the Applicants have provided a further submission by way of an email of 3 April 2014. Attached to the further submission, the Applicants have provided a builder’s report dated 20 March 2014. 17. The FSP has provided a further submission dated 14 May 2014. 18. I have considered all of the material as part of this Determination. 19. As part of the Applic ants’ submission, they maintain that three separate builders have advised that there were expansion joints present. 20. The FSP’s commissioned e ngineer has confirmed that they did not observe any expansion joints in the tiles. 21. I note that the FSP’s commissione d engineer has specifically said that if the Applicants were able to provide evidence of the existence of joints, it would be prepared to reconsider its position. 22. The additional report provided by the Applicants within their further submissions says “ the floor tiles have expansion joints 3000mm from front wall and 3300mm from back wall and 3600mm from side walls all in accordance with the manufacturer’s specifications.” 23. Upon receipt of the Applicants further submissions, the FSP said “ I have requested comme nt from (FSP’s) engineers in regards to the report provided by the Applicant’s (sic) and am awaiting this information .” 24. Subsequently, the FSP has provided an additional response dated 14 May 2014, which is not an additional comment from the FSP’s engineer , but rather a further submission from the FSP in respect to this matter. 25. The FSP has not provided any explanation as to why it has not provided comment from its engineer. 26. This is particularly concerning given that, as stated, the engineer has specifically said that if the Applicants were able to provide evidence of the existence of expansion joints, then the engineer would be prepared to reconsider its position. 27. This is specifically detailed within the Case Manager’s Recommendation and the email from the FSP confirming that they have requested comment from the engineer. This would suggest that the FSP was specifically seeking to deal with this issue. 28. As such, it is unclear and uncertain as to why the FSP has not provided further comment from its engineer, and whether the further commentary from the engineer assisted the FSP’s position, or not. Case No: 323915 Determination Page 5 of 5 29. The FSP’s further submission is limited to challenging the qualifications of the Applicants’ builder and stating that the FSP has not been provided with any photographic evidence of the relevant expansion joints. 30. The FSP submits that the report provided by its engineer is to be preferred due to the expertise and qualifications of its writers. 31. However, in my view, the opinion of the FSP’s engineer is predicated on there not being any expansion joints. 32. Indeed and as previously stated, the FSP’s engineer was prepared to reconsider its position if the Applicants were able to provide evidence of the existence of joints. 33. The report from the Applicants’ builder provid es details of the specific location of the expansion joints. The FSP in response to that report from the builder, said that it had requested comment from its engineer, but the FSP has not provided comment from the engineer. 34. In my view, the failure of the FSP to provide the promised further comment from the engineer, in light of the engineer’s earlier remark that it would be prepared to reconsider its position, significantly challenges the conclusions of the FSP’s engineer. 35. Considering all these matters, I prefer the opinion expressed by the Applicants’ builder and the description provided by the Applicants as to the cause of the Applicants’ loss. 36. Further, given what was undoubtedly a significant weather event during the course of Cyclone Yasi, I am satisfied that the Applicants have established an insured event under the terms of the policy and are entitled to have their loss claimed, covered by the terms of the policy. Determination 37. I determine that the FSP is to meet the claimed loss within the terms of the policy. 38. I further determine that should any part of this claim be settled by way of cash lump sum, then the FSP is to pay interest on that cash lump sum in accordance with the Insurance Contracts Act 1984, from the date of denial of the claim to the date of payment.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.