Text of the determination
Case No: 322608 Determination Page 1 of 19
Case number: 322608
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
23 January 2014
Summary
Description
This dispute concerns issues raised by the Applicant about the quality of
repairs carried out by the FSP to address subsidence of the concrete slab
under the extension area of his home resulting from a burst pipe. The FSP
rejected the Applicant‟s claim for compensation for the continuing unevenness
of the slab and denied liability for termite d amage to the Applicant‟s home.
The Applicant is also dissatisfied with the manner in which the FSP has
handled his claim.
Basis of Determination
In the Panel‟s view, the FSP‟s handling of the Applicant‟s claim during the past
four years has been extremely poor.
The FSP has acknowledged that it is unable to repair the ongoing issues with
the concrete slab, which were caused by the initial inadequate repairs. Given
that the slab is not capable of being repaired, the FSP is liable for replacing the
slab and rebuilding the extension in its entirety.
The available information is highly suggestive of a causal link between the
burst pipe and the termite infestation and the FSP has failed to provide a
com pelling alternative explanation. In light of both the FSP‟s actions over the
course of the claim and the Applicant‟s failure to mitigate further damage, it is
fair in all the circumstances that liability for the termite damage to the
remainder of the Applicant‟s house be apportioned equally between the FSP
and the Applicant.
Determination
The FSP must cash settle the Applicant for:
a. the costs of replacing the slab and rebuilding the extension;
b. 50% of the costs of repairing the termite damage to the remainder of
the house; and
c. the costs of temporary accommodation for the Applicant and his family
for the period while the above works are carried out.
Determination
Case No: 322608 Determination Page 2 of 19
The FSP must pay the Applicant the amount of $3,000 as compensation for
non-financial loss suffered due to the handling of his claim and must reimburse
him for the cost of obtaining his expert‟s report.
Background
1. The Applicant held a home building and contents insurance policy with the
FSP which was current at the time of the loss. The policy provided building
cover (up to a sum insured of $168,800) and contents cover (up to a sum
insured of $63,000).
2. On 26 March 2009, the Applicant lodged a claim under the policy in relation
to a burst water pipe under the concrete slab of his house. The FSP
recorded the claim for notification purposes only, as the Applicant had
repaired the pipe and there was no apparent resulting damage.
3. On 23 September 2009, the Applicant notified the FSP of damage to his
home resulting from movement of the slab, which he believed had been
caused by the burst pipe earlier in the year.
4. The FSP appointed an engineer who reported that the damage was directly
related to the burst pipe. In January 2010, the FSP accepted the Applicant‟s
claim and arranged for repairs to be carried out to re-level the slab and
repair resulting internal damage to the house.
5. For various reasons, these repairs were not completed until November 2010.
The Applicant subsequently raised concerns about the quality of the repairs
and after further investigations, in May 2011 the FSP authorised rectification
works. Further delays occurred and the rectification works did not commence
until October 2012.
6. When the rectification works began, the builders discovered termite damage
to the home. The FSP advised the Applicant that it was not liable to repair
the termite damage as this was excluded under the policy, and it was unable
to complete the rectification works until the termite damage had been
addressed. Accordingly, the FSP offered to cash settle the Applicant for the
remainder of the rectification works.
7. The Applicant disputes the FSP‟s denial of indemnity for the termite damage
to his home, as well as the FSP‟s decisi on to settle his claim by way of a
cash settlement. He wants the FSP to arrange all necessary repairs to his
home.
S ummary of Applicant’s position
8. The Applicant says that:
the initial repairs carried out by the FSP caused further damage to his
home. In ca rrying out the repairs, the FSP‟s contractors overfilled the
Case No: 322608 Determination Page 3 of 19
slab which means that it is now uneven and the floor of the house
slopes significantly;
the builder who was authorised by the FSP to carry out the rectification
repairs in October 2012 emptied out the back two rooms and cut the
power to that half of the house. However, when the termite damage
was discovered, the builder stopped all work and left without returning
the home to a liveable state;
since then, the Applicant and his family have been “camped out” in the
lounge room and a smaller bedroom. In its current, unrepaired state,
the house is dangerous to live in. There are limited cooking facilities
which can only be used by running power cords to the kitchen. His wife
has already broken her toes twice from tripping over the cords, they are
all getting back problems from the lack of proper bedding and there
have been a number of fires as a result of the temporary power
arrangements; and
the contents from the emptied rooms are currently stored in a shipping
container on the Applicant‟s driveway. The container blocks access to
the home and makes it difficult to get around, particularly for his elderly
father who is in a wheelchair and his wife who has been on crutches.
Items from the emptied rooms are stacked around the house, making it
dangerous for his young grandchildren who also live with him.
9. The Applicant says that the pest report obtained by the FSP confirms that
the water damage from the burst pipe attracted the termites to his house and
therefore the termite damage is a direct consequence of the initial
inadequate repairs carried out by the FSP. The termites are still active in the
home and the Applicant and his family can hear them chewing through the
walls at night. Some of the walls have become „spongy‟ due to the termite
damage. Every day the home remains unrepaired, the damage gets worse.
The roof at the back of the house has recently collapsed and he has been
advised by builders that the house will need to be demolished.
10. The Applicant says that the cash settlement offered by the FSP is insufficient
to return his home to its pre-loss condition. The Applicant says that the
termite infestation was caused either by the burst water pipe or by the initial
repairs carried out by the FSP‟s contractors, and therefore the FSP should
be liable for repairing the termite damage.
11. The Applicant wants the FSP to carry out the necessary repairs and provide
a lifetime guarantee. If his home cannot be restored to its pre-existing
condition, the Applicant wants the FSP to compensate him for the reduction
in the value of his home, which is estimated to have fallen by up to 25% due
to the damage to the concrete slab.
12. The Applicant is also dissatisfied with the F SP‟s handling of his claim and
believes that the FSP has deliberately withheld information from him which
supports his position. The Applicant seeks compensation for the stress
which the FSP‟s handling of his claim has caused him and his family during
the four years since the claim was lodged.
Case No: 322608 Determination Page 4 of 19
Summary of FSP’s position
13. The FSP says the Applicant‟s policy is a defined events policy, which covers
only the events specified in the policy, subject to any applicable exclusions.
14. The FSP says that it repaired the damage to the Applicant‟s property caused
by the burst pipe, which is a defined event under the policy. When it
identified that the initial repairs were inadequate, it authorised another
builder to carry out rectification works, in accordance with the life time
guarantee provided under the policy.
15. The FSP relies on its engineer‟s report in support of its position that the
termite infestation has occurred because of the Applicant‟s failure to take
sufficient measures to protect against termites when the extension to the
home was built, and not because of water damage caused by the burst pipe.
16. As the policy expressly excludes liability for damage caused by termites, the
FSP says that it is not liable for this portion of the damage to the Applicant‟s
home.
17. The FSP says that the termite damage needs to be addressed before
rectification of the claim related repairs can be completed. Accordingly, it has
elected to cash settle the Applicant for the cost of the rectification repairs, as
it is entitled to do under the terms of the policy.
18. The FSP says that, under the terms of the policy, it is not required to
compensate the Applicant for any alleged reduction in the value of his home.
19. The FSP considers that it has handled the Applicant‟s claim in a timely
manner and has promptly addressed any concerns that have arisen during
the claim process.
Issues
20. Whether the FSP is liable for the ongoing issues with the concrete slab and
the termite damage to the Applicant‟s house.
21. Whether the FSP is entitled to cash settle the App licant‟s claim or is required
to undertake rectification repairs.
22. Whether the Applicant is entitled to compensation for the manner in which
the FSP has handled his claim.
Reasons for decision
23. As advised to the parties, FOS has considered it appropriate to expedite this
dispute in accordance with the Operational Guidelines to the FOS Terms of
Reference, due to the nature of the dispute. Accordingly, this dispute has not
Case No: 322608 Determination Page 5 of 19
been the subject of a FOS Recommendation and has proceeded directly to
Determination.
24. This decision has been made by a Panel consisting of an Ombudsman and
two Panel members with extensive experience in insurance industry matters
and consumer claims.
25. The Panel is satisfied that there has been a full exchange of material
between the parties and that each party has had the opportunity of
addressing any issues raised therein.
26. There is no dispute between the parties that the Applicant‟s home was
damaged from a risk insured against under the policy (the burst pipe). The
primary issues in dispute are:
whether the FSP is required to compensate the Applicant for the
ongoing issues with the concrete slab;
the extent of the FSP‟s liability for the termite damage to the Applicant‟s
home and, in particular, whether this damage occurred as a result of
the burst pipe; and
whether the FSP is entitled to cash settle the Applicant for further
rectification repairs or is required to arrange those repairs itself.
27. In his initial submissions to FOS, the Applicant disputed the FSP‟s denial of
liability for damage to the floor of his house due to water from the burst pipe
continuing to seep upwards through the slab. The FSP initially denied liability
for this damage on the basis that it was caused by groundwater seepage,
and not by the burst pipe. However, after the Applicant lodged his dispute
with FOS, the FSP agreed to accept liability for the cost of waterproofing the
slab and repairing any resultant damage. Accordingly, this issue is no longer
in dispute, although the extent of the FSP‟s liability for this damag e has not
yet been quantified.
Chronology
28. This dispute has an extensive and convoluted history which has played out
over a four year period and involved a number of different assessors,
contractors and experts. Without recounting this history in its entirety, the
key events are as follows:
after the Applicant notified the FSP in September 2009 of subsidence
damage to the slab, the FSP obtained an engineer‟s report which
confirmed that the damage was caused by the burst pipe under the
slab in March 2009;
on or around 20 January 2010, the FSP accepted the Applicant‟s claim
and agreed to undertake the work required to re-level the slab and
repair the resulting internal damage to the home;
on 18 April 2010, the FSP authorised its builder (“TBS”) to undertake
repairs;
Case No: 322608 Determination Page 6 of 19
on 4 August 2010, due to delays in TBS finalising the scope of works
and commencing repairs, the FSP authorised another builder (“PI”) to
undertake the repairs, including further repairs which were necessary to
address additional damage which had occurred since January 2010;
on 27 September 2010, the Applicant raised concerns with the FSP
about the progress of his claim, as the repairs had still not commenced;
during the course of the repairs in October and November 2010,
additional damage was identified and accepted by the FSP on two
further occasions;
during December 2010, the Applicant advised the FSP that he was
unhappy with the quality of the repairs and the FSP arranged for its
builder (PI) to re-attend the property on 21 December 2010;
on 1 April 2011, the Applicant advised the FSP that he was still waiting
on a response from PI in relation to the issues raised in December
2010;
on 23 May 2011, the FSP received an engineer‟s report confirming that
PI had raised sections of the slab too much while carrying out the initial
repairs, which had caused further damage. The FSP authorised PI to
carry out resultant rectification works;
on 8 July 2011, the FSP discussed the rectification works with the
Applicant, who advised that he was not happy for PI to carry out the
proposed works and was concerned that not all of the remaining
damage had been identified;
between July and October 2011, the FSP sought further clarification
from its engineer and appointed an assessor to inspect the damage,
after PI queried the findings in the first engineer‟s report. Ultimately, the
FSP concluded that PI was responsible for the rectification works and
instructed PI to attend to them;
on 30 January 2012, the FSP was advised by PI that the rectification
works had not yet been carried out. The FSP instructed PI to attend to
the works urgently;
on 14 February 2012, the FSP contacted the Applicant to discuss the
progress of the rectification works. The Applicant told the FSP that PI
had advised that some of the repairs co uld not be completed. After a
site meeting, the FSP instructed PI to proceed with the repairs;
on 26 May 2012, the Applicant advised the FSP that PI had carried out
some of the rectification works but had once again advised that the slab
was unable to be repaired due to safety reasons;
in August 2012, after receiving a report from PI, the FSP advised the
Applicant that no further repairs to the walls and slab would be
undertaken, as it did not consider that the issues with these areas had
been caused by the initial repairs;
following a further review and after obtaining a report from a second
engineer, the FSP accepted that further rectification works were
Case No: 322608 Determination Page 7 of 19
required and appointed another builder (“CC”) to attend the property
and prepare a scope of works for the remaining rectification works, with
a view to recovering the costs from PI;
on 5 October 2012, the FSP authorised CC to undertake the remaining
rectification works. On 17 October 2012, in preparation for the works to
commence, the Applicant‟s contents were placed in a storage
container, and the two back rooms of the property were stripped and
the electricity supply to those rooms cut;
on commencing repairs, CC found termites in the walls and the slab
was found to have an excessively high moisture reading. The FSP took
the view that it was not liable for the termite and moisture damage. As a
result, the FSP suspended further works by CC and offered to cash
settle the Applicant for the cost of the outstanding rectification works;
and
over a year later the Applicant‟s home remains in the partially stripped
state in which it was left by CC, and the Applicant and his family are
living in sub-standard conditions in the remainder of the house.
29. In the Panel‟s view, the chronology of key events set out above esta blishes
that the FSP‟s handling of this claim over the past four years has been
extremely poor. In particular, the Panel notes that:
there was an initial delay of over three months after the Applicant
notified the FSP that the slab had subsided before the FSP accepted
his claim and authorised repairs;
the initial repairs did not commence until approximately one year after
the Applicant notified the FSP of the subsidence damage, during which
time the Applicant‟s property sustained further damage as a result of
the delay;
there was a delay of six months after the Applicant advised the FSP
that he was unhappy with the quality of the initial repairs before the
FSP acknowledged his concerns;
even after the FSP obtained an engineer‟s report confirming that the
initial repairs were inadequate, it took a further six months before
rectification repairs commenced. It appears that the FSP was more
focussed on addressing its builder‟s concerns that the e ngineer‟s report
was inaccurate, than rectifying the problems with the Applicant‟s
property. By this point, almost two years had passed since the FSP had
accepted liability for the Applicant‟s claim;
despite acknowledging that it is unable to repair the continuing problem
with the slab, the FSP did not offer the Applicant any compensation for
this issue and appears to have dismissed his repeated requests for it to
be addressed; and
the available information establishes that most (if not all) of the delays
in the handling of the Applicant‟s claim were caused by the actions (or
lack of action) of the FSP and its contractors. The FSP‟s claim records
indicate that the Applicant followed up the FSP at regular intervals for
Case No: 322608 Determination Page 8 of 19
an update on the progress of his claim, and appears to have been
remarkably patient given the errors and delays which occurred.
30. The Applicant says that he and his family have suffered considerable stress,
inconvenience and interference with their peace of mind as a result of the
FSP‟s handling of the claim.
31. The Panel notes that the Applicant‟s policy excludes consequential losses
following an insured incident. However, the Panel consider that this does not
prevent the award of compensation for non-financial loss, where the relevant
loss is cau sed by the FSP‟s claim handling, rather than the insured event
itself.
32. Having considered the information provided by the Applicant, the Panel is
satisfied that the stress and inconvenience suffered by the Applicant and his
family as a result of the errors by the FSP and its contractors (and the failure
of the FSP to act promptly to resolve such issues) is sufficient to justify an
award of the maximum amount of compensation available under FOS‟s
Terms of Reference, being $3,000.
33. In the Panel‟s view, the FSP‟ s arbitrary abrogation of its commitment to
complete the repairs (both the original repairs and the subsequent
rectification for which it was liable) when faced with the difficulties outlined
above was tantamount to an abandonment of its responsibilities. The Panel
considers that it is appropriate to have regard to this abrogation of
responsibilities when considering an appropriate remedy in relation to other
aspec ts of the Applicant‟s claim.
Damage to concrete slab
34. As outlined in the chronology of key events above, the Applicant complained
to the FSP on a number of occasions about the quality of the initial repairs.
One of the specific matters which the Applicant raised was the fact that the
concrete slab under the extension appeared to be uneven.
35. In respon se to the Applicant‟s complaints, the FSP engaged an engineer
(“C”) who attended the property on 4 May 2011 and reported that:
the concrete slab under the extension had risen by 8 millimetres per
one metre, giving rise to a difference of 28.8 millimetres o ver the 3.6
metre width of the room. This had also caused the northern wall to
move out of plumb by 24 millimetres over its 2.4 metre height;
it was quite common for contractors who injected polyurethane to lift a
slab to inject slightly more than required and therefore lift part of the
slab higher than intended;
while the original contractor had suggested that the wall may have
been out of plumb prior to the repairs being undertaken, it was unlikely
that this fully explained the extent of misalignment observed, given that
other walls within the house were found to be plumb;
Case No: 322608 Determination Page 9 of 19
the deviation of the wall exceeded the tolerances set out in standards
issued by the Office of Fair Trading, which provided that deviation in a
plane in excess of 4 millimetres over 2 metres was regarded as a
defect;
although the deviation did not give rise to any dangerous or structural
issues, he agreed with the Applicant that the out of plumb wall may
reduce the sale price which could be achieved for the home in the
future; and
he recommended rectification works including realignment of the wall
frame and repair of other damage resulting from the excessive lifting of
the slab.
36. After the original contractor queried C‟s findings, the FSP subsequently
engaged a second engineer (“S”) who i nspected the property on 19 October
2011. S confirmed that the polyurethane injection process had raised a
section of the slab beyond its original level and distorted a section of the
northern wall frame resulting in misalignment.
37. While both C and S recommended rectification works to address the
misalignment of the northern wall of the extension, neither engineer
proposed any works to address the incline in the slab itself.
38. The FSP has subsequently confirmed to the Applicant (and to FOS) that
there is no safe and effective way to fix the excessive elevation at the
northern end of the slab. The FSP has advised that the proposed
rectification works to realign the wall frame may be effective to make the
incline in the slab less noticeable. However, the extent to which this will be
successful cannot be determined until after completion of the works.
39. The Applicant says that the incline in the slab has reduced the value of his
home. He has provided views from two estate agents indicating that the
extent of the value reduction is between 10% and 25%. The Panel notes that
these views have been provided in a relatively informal fashion only, and it is
not clear whether they also take into account the termite damage to the
Applicant‟s home.
40. Under the Applicant‟s policy , where the FSP elects to repair damage to the
insured property, it must repair the damaged property “new for old”, and to
the same standard and specification as when new. The policy also provides
for a lifetime guarantee of repair work in the following te rms:
“ We guarantee the material used and standard of the workmanship to be free
of defects. If a defect arises in the lifetime of your home as a result of poor
quality workmanship or use of incorrect materials, then we will rectify the
problem.”
41. Accordingly, when the FSP accepted the Applicant‟s claim for subsidence of
the slab due to the burst pipe, it was required to repair the slab to its original
condition. If the initial repairs were inadequate to do so, it was obliged to
rectify the problem.
Case No: 322608 Determination Page 10 of 19
42. The Panel is satisfied that a rise of 28mms over a 3.6 metre wide room
represents a noticeable incline, and one which could reasonably be
considered to reduce the value of the property. Further, the Panel notes that
the ongoing issues with the slab were not caused by the insured event itself,
but resulted solely from the manner in which the initial repairs were carried
out.
43. In light of this, the Panel considers that the FSP should be liable for
replacing the slab and rebuilding the extension in its entirety, in order to
restore this part of the Applicant‟s house to the condition it was in prior to the
insured event.
44. The Panel considers that, as the existing issues with the slab have arisen as
a result of the inadequate repairs carried out by the FSP (and were not
caused by the original insured event) the FSP‟s obligations in this respect
should not be limited by the sum insured under the policy.
Termite damage
45. The FSP says that it is not liable for the termite damage to the Applicant‟s
home, as the Applicant‟s policy contains a general exclusion for loss or
damage caused by insects or vermin, including termites.
46. The Applicant accepts that the relevant damage was caused by termites, but
says that the FSP should be liable because the termite problem arose as a
consequence of the burst pipe in March 2009.
47. The contractor engaged by the FSP to carry out the initial repair of the
subsidence damage drilled holes in the slab through which it injected
polyurethane, in order to raise the slab. The Applicant says that the termites
were attracted by the moisture around the drill holes and entered the house
through these holes. He also says that the plastic membrane laid under the
concrete slab was punctured by the drilling, resulting in moisture bleeding
upwards through the concrete slab.
48. The FSP disputes this, and says that the termite problem arose because of
the construction of an inadequate termite barrier at the site of the extension
when the home was extended approximately 20 years ago, and not because
of the water damage caused by the burst pipe or the repairs carried out by
its contractor.
49. After the termite damage was discovered in October 2012, the Applicant
advised the FSP that he had engaged a pest contractor to install termite
baits in December 2011. The pest contractor had agreed to inspect the baits
regularly but had failed to do so after May 2012. Accordingly, the FSP says
that it is most likely that the termite damage arose after this date.
Case No: 322608 Determination Page 11 of 19
Available information as to cause of damage
50. After the termite damage was discovered in October 2012, the FSP
appointed a termite expert (“TT”) who attended the property on 6 Novem ber
2012 and reported that:
there were live termites in various areas of the house which had
caused visible damage to the timber frame, wall sheeting and timber
plate;
internally, there were termites in the western wall of the lounge over the
sliding door, in the wall of bedroom 3 beside the sliding door, in the top
plate of the bathroom and in the main bedroom cold joint at the rebate
to the walk in robe;
externally, there were termites in the western wall on the right hand
side of the sliding door, on either side of the sliding door in bedroom 3,
in the weatherboard on the right hand side of the sliding door to
bedroom 3, as well as in the timber stumps;
the termite entry points were at the cold joint at the slab rebate in the
main bedroom, the slab edge on the front wall right hand side of the
sliding door to bedroom 3 and the slab edge on the southern wall either
side of the sliding door to bedroom 3; and
drill holes and bait stations were found, indicating prior termite
treatment. However, no termite management notice was found in the
meter, which would be expected if a termite treatment had been carried
out.
51. In his report, TT noted that the presence of significant amounts of water is
one of the factors conducive to termite infestation. Specifically, TT
commented that water leaks, poor drainage and inadequate ventilation in the
sub-floor area increase the likelihood of termite infestation. TT did not
identify any visible leaks during his inspection of the Applicant‟s property and
appears to have considered the ventilation to be adequate. He was not able
to assess the drainage.
52. TT also noted that high moisture readings increase the likelihood of termite
infestation. Such readings can be caused by factors including poor
ventilation, ineffective drainage, leaking pipes, leaking roofs, defective
flashing and concealed termite activity. TT identified high moisture readings
in the front wall of the lounge room and beside the sliding door of bedroom 3
in the Applicant‟s property.
53. In light of TT‟s findings, the FSP engaged a plumber who confirmed that
there were no leaks at the property and stated that, in his opinion, the high
moisture readings at the front left of the house were most likely caused by
seepage due to the slope of the property.
54. On 29 November 2012, the FSP determined that it would not cover the
termite damage or the moisture damage to the slab, on the basis that the
high moisture levels were due to stormwater runoff, which had in turn caused
Case No: 322608 Determination Page 12 of 19
the termite damage, together with the Applicant‟s failure to monitor the
termite baits.
55. The Applicant disputed the FSP‟s decision and provided a report from his
own expert (“SD”) who has expertise in the areas of hydraulic services
design and plumbing and draining. SD reported that:
the concrete floor in the extension showed evidence of moisture
wicking through it, which appeared to be associated with the edge of
the building perimeter;
in his opinion, this was caused by damage to the vapour barrier on the
underside of the concrete slab as a result of drilling by t he FSP‟s
contractor or by the heat of the chemicals used by the contractor
melting the vapour barrier;
there were termite trails in the underlay leading to the drilling holes,
which indicated termites chasing water or using the holes as a point of
entry to the building;
given the vertical separation between the top of the concrete slab and
the natural ground level, it was very unlikely that the moisture in the
slab was caused by water flowing overland; and
further investigation was required to determine the cause of the water
entering the concrete slab.
56. In January 2013, the FSP‟s Internal Dispute Resolution (“IDR”) department
reviewed the partial denial of the Applicant‟s claim. The IDR department
accepted that the termite infestation was caused by high levels of moisture
but considered that there was conflicting information about the proximate
cause of the moisture and recommended that further investigations be
carried out to categorically determine the cause.
57. Accordingly, the FSP engaged a structural engineer (“J”) to further
investigate the cause of the water entering the concrete slab. In his report
dated 30 January 2013, J observed that:
there were patches of moisture throughout the concrete slab of the
house extension. The moisture patches were present around the
perimeter slab edges and around the drill holes;
there were areas of high moisture and efflorescence (the formation of
mineral deposits) under the carpet, which had caused mould staining of
the carpet; and
there was termite damage to the timber bottom plates, top plates and
wall studs of the timber wall framing affecting the walls in the extension.
The timber framing to the rooms in the extension also appeared to be
extremely weathered.
58. In his report, J made the following findings regarding the cause of the
moisture and the termite infestation:
Case No: 322608 Determination Page 13 of 19
when a large amount of water leaked from the burst water pipe in
March 2009, the water filled the small air voids in the compacted sand
underneath the slab, which caused the small particles of sand to settle
and fill the voids, resulting in the slab subsiding;
the fact that the slab edges and moisture patches were close to the
perimeter of the building suggested that the compacted sand under the
slab contained a high level of moisture. The moisture was evident in
areas of the slab located near the edge of the plastic moisture barrier
(which is placed over sand before concrete is poured), which typically
ends in the slab edge thickening zone;
the continuing moisture in the slab was due to the large amount of
moisture from the burst water pipe which was absorbed into the
bedding sand in 2009. Although the sand was progressively drying out
over a long period of time, in the meantime it was being absorbed into
the concrete slab;
the moisture had not entered the slab through the drill holes used to
inject the polyurethane (as suggested by the Applicant). The
polyurethane used was non absorbent and the drill holes had been
filled with a low shrinkage grout after the injection process was
completed. Also, the presence of moisture was not consistent
throughout the entire slab;
the concrete slab should have been treated with a waterproofing
membrane or sealant after the pipe had been repaired and before the
carpet was re-installed, to prevent moisture coming up through the slab
being absorbed into the back of the underlay material and the carpet;
the house had originally been built using a visual termite barrier
system, which involves an exposed slab edge which is inspected
annually to identify any termite entry;
when the house was extended, a new concrete slab was placed beside
the existing slab. This formed a “cold joint” which resulted in a distinct
join between the two slabs when the wet concrete dried and shrank.
This joint was covered by the timber walls and the floor coverings,
which meant that the visual termite barrier was obscured; and
where a slab is extended, the cold joint needs to be protected against
termite infestation. This involves mechanically covering the cold joint so
termites cannot gain access. The cold joint between the new and the
old slab in the Applicant‟s house had no termite protection and the
evidence strongly suggested that this was the point of entry for the
termites. Accordingly, the poorly protected cold joint was the cause of
the termite infestation.
59. In August 2013, the FSP accepted liability for the cost of sealing the slab and
repairing any resultant moisture damage, as it acknowledged that the slab
should have been sealed as part of the initial repairs. However, the FSP has
continued to rely on J‟s report to deny liability for the termite damage.
Case No: 322608 Determination Page 14 of 19
60. The Applicant disputes J‟s findings that the cold joint was not properly
protected when the extension was built. He has provided a copy of a “pre -
construction termite treatmen t certificate” dated 21 December 1991 which
indicates that the full area of the extension (approximately 30 square metres)
was treated with a chemical called Aldrex. The Applicant says that he was
advised at the time that this treatment (which has since been banned) would
be effective for approximately 30 to 50 years.
61. The FSP‟s records indicate that the Applicant has advised that he had
previously had problems with a termite infestation around 2009 to 2010. This
was on the other side of the house from the extension and was treated with
baits. The Applicant says that he had not previously had any problems with
termites in the extension before they were discovered by the FSP‟s builders
in October 2012.
62. The Applicant has confirmed that he has taken minimal remedial action to
address the termite infestation since it was discovered in October 2012. The
Applicant says that the termite infestation has since spread to other parts of
his house, although he has put down baits to try and arrest the spread.
Further, as a result of the extensive termite damage, the roof of the back part
of the house has now collapsed and the house may need to be demolished.
63. The Applicant‟s lack of action to address the termite infestation appears to
be due to his view that the FSP‟s contra ctors were responsible for the
termites, and therefore he has focussed on pursuing the FSP to remedy this,
at first directly and then through FOS. The Applicant has advised that he and
his wife are both on disability pensions, and he also appears to be
supporting various other family members. Accordingly, it appears likely that
the Applicant‟s financial circumstances have limited his ability to take
remedial action.
Analysis
64. The Panel has carefully reviewed the available information for the purpose of
considering the cause of the termite infestation.
65. The Panel notes that several alternative theories have been put forward in
relation to the cause of the termite infestation, and the FSP itself has
changed the basis for its denial after carrying out further i nvestigations.
66. The Panel considers that the report of the FSP‟s engineer (J) effectively
refutes the Applicant‟s theory that the termites entered through the drill holes
made in the process of stabilising the slab. The Panel also notes that, while
the FSP has acknowledged that the initial repairs were inadequate in that
they failed to seal the slab, this cannot be considered to be the cause of the
termite infestation. This is because the sealing process would merely have
stopped moisture entering the house through the top of the slab, but would
not have addressed the issue of the moisture itself.
67. The FSP appears to have initially accepted that the termite infestation was
caused by the presence of significant amounts of moisture under the slab.
Case No: 322608 Determination Page 15 of 19
However, after J‟s report found that the moisture was the result of the burst
pipe (rather than groundwater seepage) the FSP altered its position.
68. The FSP now says that, while it acknowledges that the presence of moisture
increases the likelihood of a termite infestation, it does not in itself cause the
infestation to occur. The FSP also relies on J‟s finding that the cold joint
between the new and old slabs was not properly protected and provided a
point of entry for the termites. Finally, the FSP says that the failure of the
Applicant‟s contractor to check the termite baits meant that the termites were
not readily detected.
69. The Panel notes that the concept of causation can be difficult to apply in the
context of animate objects such as termites, which are capable of
independent action. In these circumstances, the Panel considers that it is
appropriate to consider underlying factors which trigger and/or enable such
action to occur.
70. The Panel is concerned that the FSP does not appear to have specifically
addressed the relevance of the termite treatment certificate provided by the
Applicant, which was first provided to the FSP in March 2013. Further, the
FSP does not appear to have provided a copy of the certificate to J so that
he could consider whether it impacted his position. Instead, the FSP has
continued to rely on J‟s report to deny liability for the termite damage.
Nevertheless, J‟s view was that a physical barrier should have been installed
at the cold joint, whereas the Applicant relies on a termite spray having been
done at the time of the construction of the extension as being adequate for
30-50 years.
71. The Panel considers that there is insufficient information available to
determine exactly when the termite infestation first occurred. There is
information to suggest that termites were found around 2009 or 2010, but the
infestation was successfully treated at the time. The fact that the Applicant
engaged a pest controller in November 2011 suggests that he had reason to
be concerned about termites at that time. However, there is no information to
suggest that termites were found either when the baits were installed in
November 2011 or when they were last checked in May 2012.
72. The FSP has suggested that the Applicant‟s failure to monitor the baits
caused or contributed to the termite infestation. However, while the Panel
accepts that baits assist in controlling an existing termite infestation, it is not
satisfied that the failure to monitor baits can be considered to be the cause
of the infestation itself.
73. The Panel considers that the available information establishes that:
the burst pipe caused a significant amount of water to be absorbed in
the sand under the slab;
the presence of a significant amount of water materially increases the
likelihood of termite infestation; and
Case No: 322608 Determination Page 16 of 19
several of the areas in which TT observed termites were located in the
area of the extension, where the pipe had burst and where high
moisture readings were recorded.
74. In the Panel‟s view, the circumstances are highly suggestive of a causal link
between the high levels of moisture resulting from the burst pipe and the
termite infestation within the extension. Further, the Panel notes that:
the FSP initially accepted that the termite infestation occurred as a
result of high levels of moisture; and
the FSP has failed to identify a compelling alternative explanation for
the termite attack.
75. Further, the Panel considers that the difficulties associated with the termite
infestation discovered in October 2012 have in part arisen because of the
FSP‟s poor handling of the Applicant‟s claim from September 2009 onwards.
Had the FSP appropriately managed the claim at that time, it is likely that the
repairs would have been completed long before the current infestation
commenced. In the event that there was any pre-existing termite damage at
that time, it is likely that such damage would have been significantly less
extensive and more localised, which may have assisted in now determining
the cause of the damage.
76. In a case such as the present where the FSP‟s handling of the Applicant‟s
claim has been clearly deficient on a number of levels over an extended
period of time, the Panel is also concerned about the FSP‟s willingness to
apply a policy exclusion in the absence of convincing evidence. The Panel
notes that, not only did the FSP order its contractor to cease all work when
the termite damage was disco vered it left the back rooms of the Applicant‟s
home in an unliveable condition, and failed to implement any make safe
arrangements.
77. Given the matters outlined above, the Panel considers that the FSP should
not be entitled to rely on the exclusion under the policy to deny any liability
for the termite damage to the Applicant‟s house.
78. However, the Panel recognises that it is likely that further damage has
occurred since the termites were discovered in October 2012, as a result of
the Applicant‟s failure to take appropriate action to address the infestation.
79. On this basis, the Panel considers that, it is fair in all the circumstances that
liability for the termite damage to the Applicant‟s house (other than the
extension) be apportioned equally between the FSP and the Applicant.
Cash settlement in lieu of rectification repairs
80. After the FSP ordered its contractor (CC) to cease rectification works in
October 2012, it asked CC to provide a breakdown of the rectification works
showing which had not yet been completed. CC provided a breakdown
which showed that the cost of the outstanding works was $26,125.19, and
the FSP cash settled the Applicant for this amount.
Case No: 322608 Determination Page 17 of 19
81. The Applicant was dissatisfied with both the amount of the cheque and the
fact that the FSP was requiring him to accept a cash settlement, as he
wanted the FSP to arrange for the rectification repairs. The Applicant has
confirmed to FOS that he has not cashed the cheque provided by the FSP.
82. The FSP cash settled the Applicant on the basis that it was not liable for the
termite damage or the moisture damage to the slab and floor coverings,
which needed to be addressed before rectification repairs could be
undertaken.
83. The FSP has since acknowledged that it is liable for the moisture damage
and, for the reasons outlined above, the Panel has found that the FSP is
required to rectify the issues with the slab, by replacing it and rebuilding the
extension and is also liable for 50% of the termite damage to the remainder
of the house.
84. The Panel considers that the lifetime guarantee provided under the policy
(as set out above) requires the FSP to arrange rectification repairs, and does
not entitle it to choose to cash settle the Applicant for the rectification repairs.
85. The Applicant has throughout this dispute e xpressed a strong preference
that the FSP be required to take responsibility for arranging the rectification
repairs. However, in circumstances where the Panel has found that the
Applicant is partly liable for the repair of the termite damage, for logistical
reasons it is not practical to require the FSP to carry out the portion of the
repairs for which it has liability.
86. Accordingly, the Panel considers that an appropriate remedy in these
circumstances is for the FSP to cash settle the Applicant for an amount
equal to:
the costs of replacing the slab and rebuilding the extension in its
entirety; and
50% of the costs of repairing the termite damage to the remainder of
the house.
87. In order to determine the amount of the cash settlement, the FSP is to, at its
own cost:
appoint a suitably qualified and experienced engineer to prepare
separate scopes of work in respect of the extension and the remainder
of the house; and
engage an appropriately qualified builder to provide a costing for each
scope of works, such costing to be prepared on an arms‟ length basis
and without taking into account any insurer discounts or rebates.
88. The Panel considers that it is not appropriate to req uire the FSP to pay
interest on the cash settlement amount, given that this amount will be
determined based on costings prepared using current market rates.
Case No: 322608 Determination Page 18 of 19
Other issues
89. Given the nature and extent of the works required, the Panel considers that
the FSP should be required to fund the costs of temporary accommodation
for the Applicant and his family during the period the works are being carried
out.
90. Given the Panel‟s view that a cash settlement is appropriate, the FSP should
be required to ensure that:
the builder appointed to cost the scopes of work provides an estimate
of the time which will be required to complete the works; and
the cash settlement to be paid to the Applicant is increased by an
amount representing the reasonable costs of temporary
accommodation for the Applicant and his family for this period of time.
91. The Panel considers that the report prepared by the Applicant‟s expert (SD)
accurately identified that the groundwater seepage was not the source of the
continuing moisture problems, and convinced the FSP to undertake further
investigations. Accordingly, the Panel considers that the Applicant should be
compensated for the costs incurred in obtaining SD‟s report.
Determination
92. On the basis of the available information, the Panel determines that:
within 28 days of the date the Applicant accepts this Determination, the
FSP is to, at its cost, arrange for:
i. a suitably qualified and experienced engineer to prepare separate
scopes of work in respect of:
i. the replacement of the slab and the rebuilding of the
extension; and
ii. the repair of the termite damage to the remainder of the
house;
ii. an appropriately qualified builder to provide a costing for each of
the above scopes of work, such costing to be prepared on an
arms‟ length basis without taking into account any insurer
discounts or rebates, and to include an estimate of the number of
days required to complete the works;
within 7 days after receiving the scope of works and costings referred
to above, the FSP is to cash settle the Applicant for an amount equal to
the:
i. the costs of replacing the slab and rebuilding the extension
(determined as set out above);
ii. plus 50% of the costs of repairing the termite damage to the
remainder of the house (determined as set out above);
Case No: 322608 Determination Page 19 of 19
iii. plus the reasonable costs of temporary accommodation for the
Applicant and his family for the estimated time period required to
complete the works;
iv. plus $3,000 as compensation for non-financial loss suffered by
the Applicant as a result of the manner in which the FSP handled
his claim;
v. plus an amount equal to the costs incurred by the Applicant in
obtaining SD‟s report, subject to the Applicant providing
reasonable evidence of such costs;
vi. less the amount of $26,125.19 previously paid the Applicant in
settlement of his claim;
on acceptance of this Determination by the Applicant, he is entitled to
cash the FSP‟s cheque for $26,125.19 already in his possess ion, as
part of this settlement; and
if the Applicant disputes the amount of the cash settlement determined
by the FSP in accordance with the process set out above, the parties
may refer the dispute back to the Panel and the Panel will, after
allowing for further submissions, determine the cash settlement
amount.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.