Determination 322608

Termite damage denial and cash settlement of building rectification

FirmFinancial Firm (Unknown - Insurer)
Decided2014-01-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss$3,000
Amount claimed—
SourceAFCA PDF

Summary

The insured disputed the insurer's cash settlement of home repairs after a burst pipe and its denial of termite damage. AFCA ordered cash settlement of slab replacement, temporary accommodation and 50% of termite repairs, plus $3,000 non-financial loss and expert report costs, less $26,125.19 already offered.

The lifetime workmanship guarantee required the insurer to arrange rectification, and the termite exclusion could not be relied on without convincing evidence, so termite liability was apportioned equally.

Issues

Subjects and remedies

financial hardshippay claimpay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 322608 Determination Page 1 of 19 Case number: 322608 General Insurance - Domestic Insurance - Home Building - FSP Decision - Claim amount 23 January 2014 Summary Description  This dispute concerns issues raised by the Applicant about the quality of repairs carried out by the FSP to address subsidence of the concrete slab under the extension area of his home resulting from a burst pipe. The FSP rejected the Applicant‟s claim for compensation for the continuing unevenness of the slab and denied liability for termite d amage to the Applicant‟s home.  The Applicant is also dissatisfied with the manner in which the FSP has handled his claim. Basis of Determination  In the Panel‟s view, the FSP‟s handling of the Applicant‟s claim during the past four years has been extremely poor.  The FSP has acknowledged that it is unable to repair the ongoing issues with the concrete slab, which were caused by the initial inadequate repairs. Given that the slab is not capable of being repaired, the FSP is liable for replacing the slab and rebuilding the extension in its entirety.  The available information is highly suggestive of a causal link between the burst pipe and the termite infestation and the FSP has failed to provide a com pelling alternative explanation. In light of both the FSP‟s actions over the course of the claim and the Applicant‟s failure to mitigate further damage, it is fair in all the circumstances that liability for the termite damage to the remainder of the Applicant‟s house be apportioned equally between the FSP and the Applicant. Determination  The FSP must cash settle the Applicant for: a. the costs of replacing the slab and rebuilding the extension; b. 50% of the costs of repairing the termite damage to the remainder of the house; and c. the costs of temporary accommodation for the Applicant and his family for the period while the above works are carried out. Determination Case No: 322608 Determination Page 2 of 19  The FSP must pay the Applicant the amount of $3,000 as compensation for non-financial loss suffered due to the handling of his claim and must reimburse him for the cost of obtaining his expert‟s report. Background 1. The Applicant held a home building and contents insurance policy with the FSP which was current at the time of the loss. The policy provided building cover (up to a sum insured of $168,800) and contents cover (up to a sum insured of $63,000). 2. On 26 March 2009, the Applicant lodged a claim under the policy in relation to a burst water pipe under the concrete slab of his house. The FSP recorded the claim for notification purposes only, as the Applicant had repaired the pipe and there was no apparent resulting damage. 3. On 23 September 2009, the Applicant notified the FSP of damage to his home resulting from movement of the slab, which he believed had been caused by the burst pipe earlier in the year. 4. The FSP appointed an engineer who reported that the damage was directly related to the burst pipe. In January 2010, the FSP accepted the Applicant‟s claim and arranged for repairs to be carried out to re-level the slab and repair resulting internal damage to the house. 5. For various reasons, these repairs were not completed until November 2010. The Applicant subsequently raised concerns about the quality of the repairs and after further investigations, in May 2011 the FSP authorised rectification works. Further delays occurred and the rectification works did not commence until October 2012. 6. When the rectification works began, the builders discovered termite damage to the home. The FSP advised the Applicant that it was not liable to repair the termite damage as this was excluded under the policy, and it was unable to complete the rectification works until the termite damage had been addressed. Accordingly, the FSP offered to cash settle the Applicant for the remainder of the rectification works. 7. The Applicant disputes the FSP‟s denial of indemnity for the termite damage to his home, as well as the FSP‟s decisi on to settle his claim by way of a cash settlement. He wants the FSP to arrange all necessary repairs to his home. S ummary of Applicant’s position 8. The Applicant says that:  the initial repairs carried out by the FSP caused further damage to his home. In ca rrying out the repairs, the FSP‟s contractors overfilled the Case No: 322608 Determination Page 3 of 19 slab which means that it is now uneven and the floor of the house slopes significantly;  the builder who was authorised by the FSP to carry out the rectification repairs in October 2012 emptied out the back two rooms and cut the power to that half of the house. However, when the termite damage was discovered, the builder stopped all work and left without returning the home to a liveable state;  since then, the Applicant and his family have been “camped out” in the lounge room and a smaller bedroom. In its current, unrepaired state, the house is dangerous to live in. There are limited cooking facilities which can only be used by running power cords to the kitchen. His wife has already broken her toes twice from tripping over the cords, they are all getting back problems from the lack of proper bedding and there have been a number of fires as a result of the temporary power arrangements; and  the contents from the emptied rooms are currently stored in a shipping container on the Applicant‟s driveway. The container blocks access to the home and makes it difficult to get around, particularly for his elderly father who is in a wheelchair and his wife who has been on crutches. Items from the emptied rooms are stacked around the house, making it dangerous for his young grandchildren who also live with him. 9. The Applicant says that the pest report obtained by the FSP confirms that the water damage from the burst pipe attracted the termites to his house and therefore the termite damage is a direct consequence of the initial inadequate repairs carried out by the FSP. The termites are still active in the home and the Applicant and his family can hear them chewing through the walls at night. Some of the walls have become „spongy‟ due to the termite damage. Every day the home remains unrepaired, the damage gets worse. The roof at the back of the house has recently collapsed and he has been advised by builders that the house will need to be demolished. 10. The Applicant says that the cash settlement offered by the FSP is insufficient to return his home to its pre-loss condition. The Applicant says that the termite infestation was caused either by the burst water pipe or by the initial repairs carried out by the FSP‟s contractors, and therefore the FSP should be liable for repairing the termite damage. 11. The Applicant wants the FSP to carry out the necessary repairs and provide a lifetime guarantee. If his home cannot be restored to its pre-existing condition, the Applicant wants the FSP to compensate him for the reduction in the value of his home, which is estimated to have fallen by up to 25% due to the damage to the concrete slab. 12. The Applicant is also dissatisfied with the F SP‟s handling of his claim and believes that the FSP has deliberately withheld information from him which supports his position. The Applicant seeks compensation for the stress which the FSP‟s handling of his claim has caused him and his family during the four years since the claim was lodged. Case No: 322608 Determination Page 4 of 19 Summary of FSP’s position 13. The FSP says the Applicant‟s policy is a defined events policy, which covers only the events specified in the policy, subject to any applicable exclusions. 14. The FSP says that it repaired the damage to the Applicant‟s property caused by the burst pipe, which is a defined event under the policy. When it identified that the initial repairs were inadequate, it authorised another builder to carry out rectification works, in accordance with the life time guarantee provided under the policy. 15. The FSP relies on its engineer‟s report in support of its position that the termite infestation has occurred because of the Applicant‟s failure to take sufficient measures to protect against termites when the extension to the home was built, and not because of water damage caused by the burst pipe. 16. As the policy expressly excludes liability for damage caused by termites, the FSP says that it is not liable for this portion of the damage to the Applicant‟s home. 17. The FSP says that the termite damage needs to be addressed before rectification of the claim related repairs can be completed. Accordingly, it has elected to cash settle the Applicant for the cost of the rectification repairs, as it is entitled to do under the terms of the policy. 18. The FSP says that, under the terms of the policy, it is not required to compensate the Applicant for any alleged reduction in the value of his home. 19. The FSP considers that it has handled the Applicant‟s claim in a timely manner and has promptly addressed any concerns that have arisen during the claim process. Issues 20. Whether the FSP is liable for the ongoing issues with the concrete slab and the termite damage to the Applicant‟s house. 21. Whether the FSP is entitled to cash settle the App licant‟s claim or is required to undertake rectification repairs. 22. Whether the Applicant is entitled to compensation for the manner in which the FSP has handled his claim. Reasons for decision 23. As advised to the parties, FOS has considered it appropriate to expedite this dispute in accordance with the Operational Guidelines to the FOS Terms of Reference, due to the nature of the dispute. Accordingly, this dispute has not Case No: 322608 Determination Page 5 of 19 been the subject of a FOS Recommendation and has proceeded directly to Determination. 24. This decision has been made by a Panel consisting of an Ombudsman and two Panel members with extensive experience in insurance industry matters and consumer claims. 25. The Panel is satisfied that there has been a full exchange of material between the parties and that each party has had the opportunity of addressing any issues raised therein. 26. There is no dispute between the parties that the Applicant‟s home was damaged from a risk insured against under the policy (the burst pipe). The primary issues in dispute are:  whether the FSP is required to compensate the Applicant for the ongoing issues with the concrete slab;  the extent of the FSP‟s liability for the termite damage to the Applicant‟s home and, in particular, whether this damage occurred as a result of the burst pipe; and  whether the FSP is entitled to cash settle the Applicant for further rectification repairs or is required to arrange those repairs itself. 27. In his initial submissions to FOS, the Applicant disputed the FSP‟s denial of liability for damage to the floor of his house due to water from the burst pipe continuing to seep upwards through the slab. The FSP initially denied liability for this damage on the basis that it was caused by groundwater seepage, and not by the burst pipe. However, after the Applicant lodged his dispute with FOS, the FSP agreed to accept liability for the cost of waterproofing the slab and repairing any resultant damage. Accordingly, this issue is no longer in dispute, although the extent of the FSP‟s liability for this damag e has not yet been quantified. Chronology 28. This dispute has an extensive and convoluted history which has played out over a four year period and involved a number of different assessors, contractors and experts. Without recounting this history in its entirety, the key events are as follows:  after the Applicant notified the FSP in September 2009 of subsidence damage to the slab, the FSP obtained an engineer‟s report which confirmed that the damage was caused by the burst pipe under the slab in March 2009;  on or around 20 January 2010, the FSP accepted the Applicant‟s claim and agreed to undertake the work required to re-level the slab and repair the resulting internal damage to the home;  on 18 April 2010, the FSP authorised its builder (“TBS”) to undertake repairs; Case No: 322608 Determination Page 6 of 19  on 4 August 2010, due to delays in TBS finalising the scope of works and commencing repairs, the FSP authorised another builder (“PI”) to undertake the repairs, including further repairs which were necessary to address additional damage which had occurred since January 2010;  on 27 September 2010, the Applicant raised concerns with the FSP about the progress of his claim, as the repairs had still not commenced;  during the course of the repairs in October and November 2010, additional damage was identified and accepted by the FSP on two further occasions;  during December 2010, the Applicant advised the FSP that he was unhappy with the quality of the repairs and the FSP arranged for its builder (PI) to re-attend the property on 21 December 2010;  on 1 April 2011, the Applicant advised the FSP that he was still waiting on a response from PI in relation to the issues raised in December 2010;  on 23 May 2011, the FSP received an engineer‟s report confirming that PI had raised sections of the slab too much while carrying out the initial repairs, which had caused further damage. The FSP authorised PI to carry out resultant rectification works;  on 8 July 2011, the FSP discussed the rectification works with the Applicant, who advised that he was not happy for PI to carry out the proposed works and was concerned that not all of the remaining damage had been identified;  between July and October 2011, the FSP sought further clarification from its engineer and appointed an assessor to inspect the damage, after PI queried the findings in the first engineer‟s report. Ultimately, the FSP concluded that PI was responsible for the rectification works and instructed PI to attend to them;  on 30 January 2012, the FSP was advised by PI that the rectification works had not yet been carried out. The FSP instructed PI to attend to the works urgently;  on 14 February 2012, the FSP contacted the Applicant to discuss the progress of the rectification works. The Applicant told the FSP that PI had advised that some of the repairs co uld not be completed. After a site meeting, the FSP instructed PI to proceed with the repairs;  on 26 May 2012, the Applicant advised the FSP that PI had carried out some of the rectification works but had once again advised that the slab was unable to be repaired due to safety reasons;  in August 2012, after receiving a report from PI, the FSP advised the Applicant that no further repairs to the walls and slab would be undertaken, as it did not consider that the issues with these areas had been caused by the initial repairs;  following a further review and after obtaining a report from a second engineer, the FSP accepted that further rectification works were Case No: 322608 Determination Page 7 of 19 required and appointed another builder (“CC”) to attend the property and prepare a scope of works for the remaining rectification works, with a view to recovering the costs from PI;  on 5 October 2012, the FSP authorised CC to undertake the remaining rectification works. On 17 October 2012, in preparation for the works to commence, the Applicant‟s contents were placed in a storage container, and the two back rooms of the property were stripped and the electricity supply to those rooms cut;  on commencing repairs, CC found termites in the walls and the slab was found to have an excessively high moisture reading. The FSP took the view that it was not liable for the termite and moisture damage. As a result, the FSP suspended further works by CC and offered to cash settle the Applicant for the cost of the outstanding rectification works; and  over a year later the Applicant‟s home remains in the partially stripped state in which it was left by CC, and the Applicant and his family are living in sub-standard conditions in the remainder of the house. 29. In the Panel‟s view, the chronology of key events set out above esta blishes that the FSP‟s handling of this claim over the past four years has been extremely poor. In particular, the Panel notes that:  there was an initial delay of over three months after the Applicant notified the FSP that the slab had subsided before the FSP accepted his claim and authorised repairs;  the initial repairs did not commence until approximately one year after the Applicant notified the FSP of the subsidence damage, during which time the Applicant‟s property sustained further damage as a result of the delay;  there was a delay of six months after the Applicant advised the FSP that he was unhappy with the quality of the initial repairs before the FSP acknowledged his concerns;  even after the FSP obtained an engineer‟s report confirming that the initial repairs were inadequate, it took a further six months before rectification repairs commenced. It appears that the FSP was more focussed on addressing its builder‟s concerns that the e ngineer‟s report was inaccurate, than rectifying the problems with the Applicant‟s property. By this point, almost two years had passed since the FSP had accepted liability for the Applicant‟s claim;  despite acknowledging that it is unable to repair the continuing problem with the slab, the FSP did not offer the Applicant any compensation for this issue and appears to have dismissed his repeated requests for it to be addressed; and  the available information establishes that most (if not all) of the delays in the handling of the Applicant‟s claim were caused by the actions (or lack of action) of the FSP and its contractors. The FSP‟s claim records indicate that the Applicant followed up the FSP at regular intervals for Case No: 322608 Determination Page 8 of 19 an update on the progress of his claim, and appears to have been remarkably patient given the errors and delays which occurred. 30. The Applicant says that he and his family have suffered considerable stress, inconvenience and interference with their peace of mind as a result of the FSP‟s handling of the claim. 31. The Panel notes that the Applicant‟s policy excludes consequential losses following an insured incident. However, the Panel consider that this does not prevent the award of compensation for non-financial loss, where the relevant loss is cau sed by the FSP‟s claim handling, rather than the insured event itself. 32. Having considered the information provided by the Applicant, the Panel is satisfied that the stress and inconvenience suffered by the Applicant and his family as a result of the errors by the FSP and its contractors (and the failure of the FSP to act promptly to resolve such issues) is sufficient to justify an award of the maximum amount of compensation available under FOS‟s Terms of Reference, being $3,000. 33. In the Panel‟s view, the FSP‟ s arbitrary abrogation of its commitment to complete the repairs (both the original repairs and the subsequent rectification for which it was liable) when faced with the difficulties outlined above was tantamount to an abandonment of its responsibilities. The Panel considers that it is appropriate to have regard to this abrogation of responsibilities when considering an appropriate remedy in relation to other aspec ts of the Applicant‟s claim. Damage to concrete slab 34. As outlined in the chronology of key events above, the Applicant complained to the FSP on a number of occasions about the quality of the initial repairs. One of the specific matters which the Applicant raised was the fact that the concrete slab under the extension appeared to be uneven. 35. In respon se to the Applicant‟s complaints, the FSP engaged an engineer (“C”) who attended the property on 4 May 2011 and reported that:  the concrete slab under the extension had risen by 8 millimetres per one metre, giving rise to a difference of 28.8 millimetres o ver the 3.6 metre width of the room. This had also caused the northern wall to move out of plumb by 24 millimetres over its 2.4 metre height;  it was quite common for contractors who injected polyurethane to lift a slab to inject slightly more than required and therefore lift part of the slab higher than intended;  while the original contractor had suggested that the wall may have been out of plumb prior to the repairs being undertaken, it was unlikely that this fully explained the extent of misalignment observed, given that other walls within the house were found to be plumb; Case No: 322608 Determination Page 9 of 19  the deviation of the wall exceeded the tolerances set out in standards issued by the Office of Fair Trading, which provided that deviation in a plane in excess of 4 millimetres over 2 metres was regarded as a defect;  although the deviation did not give rise to any dangerous or structural issues, he agreed with the Applicant that the out of plumb wall may reduce the sale price which could be achieved for the home in the future; and  he recommended rectification works including realignment of the wall frame and repair of other damage resulting from the excessive lifting of the slab. 36. After the original contractor queried C‟s findings, the FSP subsequently engaged a second engineer (“S”) who i nspected the property on 19 October 2011. S confirmed that the polyurethane injection process had raised a section of the slab beyond its original level and distorted a section of the northern wall frame resulting in misalignment. 37. While both C and S recommended rectification works to address the misalignment of the northern wall of the extension, neither engineer proposed any works to address the incline in the slab itself. 38. The FSP has subsequently confirmed to the Applicant (and to FOS) that there is no safe and effective way to fix the excessive elevation at the northern end of the slab. The FSP has advised that the proposed rectification works to realign the wall frame may be effective to make the incline in the slab less noticeable. However, the extent to which this will be successful cannot be determined until after completion of the works. 39. The Applicant says that the incline in the slab has reduced the value of his home. He has provided views from two estate agents indicating that the extent of the value reduction is between 10% and 25%. The Panel notes that these views have been provided in a relatively informal fashion only, and it is not clear whether they also take into account the termite damage to the Applicant‟s home. 40. Under the Applicant‟s policy , where the FSP elects to repair damage to the insured property, it must repair the damaged property “new for old”, and to the same standard and specification as when new. The policy also provides for a lifetime guarantee of repair work in the following te rms: “ We guarantee the material used and standard of the workmanship to be free of defects. If a defect arises in the lifetime of your home as a result of poor quality workmanship or use of incorrect materials, then we will rectify the problem.” 41. Accordingly, when the FSP accepted the Applicant‟s claim for subsidence of the slab due to the burst pipe, it was required to repair the slab to its original condition. If the initial repairs were inadequate to do so, it was obliged to rectify the problem. Case No: 322608 Determination Page 10 of 19 42. The Panel is satisfied that a rise of 28mms over a 3.6 metre wide room represents a noticeable incline, and one which could reasonably be considered to reduce the value of the property. Further, the Panel notes that the ongoing issues with the slab were not caused by the insured event itself, but resulted solely from the manner in which the initial repairs were carried out. 43. In light of this, the Panel considers that the FSP should be liable for replacing the slab and rebuilding the extension in its entirety, in order to restore this part of the Applicant‟s house to the condition it was in prior to the insured event. 44. The Panel considers that, as the existing issues with the slab have arisen as a result of the inadequate repairs carried out by the FSP (and were not caused by the original insured event) the FSP‟s obligations in this respect should not be limited by the sum insured under the policy. Termite damage 45. The FSP says that it is not liable for the termite damage to the Applicant‟s home, as the Applicant‟s policy contains a general exclusion for loss or damage caused by insects or vermin, including termites. 46. The Applicant accepts that the relevant damage was caused by termites, but says that the FSP should be liable because the termite problem arose as a consequence of the burst pipe in March 2009. 47. The contractor engaged by the FSP to carry out the initial repair of the subsidence damage drilled holes in the slab through which it injected polyurethane, in order to raise the slab. The Applicant says that the termites were attracted by the moisture around the drill holes and entered the house through these holes. He also says that the plastic membrane laid under the concrete slab was punctured by the drilling, resulting in moisture bleeding upwards through the concrete slab. 48. The FSP disputes this, and says that the termite problem arose because of the construction of an inadequate termite barrier at the site of the extension when the home was extended approximately 20 years ago, and not because of the water damage caused by the burst pipe or the repairs carried out by its contractor. 49. After the termite damage was discovered in October 2012, the Applicant advised the FSP that he had engaged a pest contractor to install termite baits in December 2011. The pest contractor had agreed to inspect the baits regularly but had failed to do so after May 2012. Accordingly, the FSP says that it is most likely that the termite damage arose after this date. Case No: 322608 Determination Page 11 of 19 Available information as to cause of damage 50. After the termite damage was discovered in October 2012, the FSP appointed a termite expert (“TT”) who attended the property on 6 Novem ber 2012 and reported that:  there were live termites in various areas of the house which had caused visible damage to the timber frame, wall sheeting and timber plate;  internally, there were termites in the western wall of the lounge over the sliding door, in the wall of bedroom 3 beside the sliding door, in the top plate of the bathroom and in the main bedroom cold joint at the rebate to the walk in robe;  externally, there were termites in the western wall on the right hand side of the sliding door, on either side of the sliding door in bedroom 3, in the weatherboard on the right hand side of the sliding door to bedroom 3, as well as in the timber stumps;  the termite entry points were at the cold joint at the slab rebate in the main bedroom, the slab edge on the front wall right hand side of the sliding door to bedroom 3 and the slab edge on the southern wall either side of the sliding door to bedroom 3; and  drill holes and bait stations were found, indicating prior termite treatment. However, no termite management notice was found in the meter, which would be expected if a termite treatment had been carried out. 51. In his report, TT noted that the presence of significant amounts of water is one of the factors conducive to termite infestation. Specifically, TT commented that water leaks, poor drainage and inadequate ventilation in the sub-floor area increase the likelihood of termite infestation. TT did not identify any visible leaks during his inspection of the Applicant‟s property and appears to have considered the ventilation to be adequate. He was not able to assess the drainage. 52. TT also noted that high moisture readings increase the likelihood of termite infestation. Such readings can be caused by factors including poor ventilation, ineffective drainage, leaking pipes, leaking roofs, defective flashing and concealed termite activity. TT identified high moisture readings in the front wall of the lounge room and beside the sliding door of bedroom 3 in the Applicant‟s property. 53. In light of TT‟s findings, the FSP engaged a plumber who confirmed that there were no leaks at the property and stated that, in his opinion, the high moisture readings at the front left of the house were most likely caused by seepage due to the slope of the property. 54. On 29 November 2012, the FSP determined that it would not cover the termite damage or the moisture damage to the slab, on the basis that the high moisture levels were due to stormwater runoff, which had in turn caused Case No: 322608 Determination Page 12 of 19 the termite damage, together with the Applicant‟s failure to monitor the termite baits. 55. The Applicant disputed the FSP‟s decision and provided a report from his own expert (“SD”) who has expertise in the areas of hydraulic services design and plumbing and draining. SD reported that:  the concrete floor in the extension showed evidence of moisture wicking through it, which appeared to be associated with the edge of the building perimeter;  in his opinion, this was caused by damage to the vapour barrier on the underside of the concrete slab as a result of drilling by t he FSP‟s contractor or by the heat of the chemicals used by the contractor melting the vapour barrier;  there were termite trails in the underlay leading to the drilling holes, which indicated termites chasing water or using the holes as a point of entry to the building;  given the vertical separation between the top of the concrete slab and the natural ground level, it was very unlikely that the moisture in the slab was caused by water flowing overland; and  further investigation was required to determine the cause of the water entering the concrete slab. 56. In January 2013, the FSP‟s Internal Dispute Resolution (“IDR”) department reviewed the partial denial of the Applicant‟s claim. The IDR department accepted that the termite infestation was caused by high levels of moisture but considered that there was conflicting information about the proximate cause of the moisture and recommended that further investigations be carried out to categorically determine the cause. 57. Accordingly, the FSP engaged a structural engineer (“J”) to further investigate the cause of the water entering the concrete slab. In his report dated 30 January 2013, J observed that:  there were patches of moisture throughout the concrete slab of the house extension. The moisture patches were present around the perimeter slab edges and around the drill holes;  there were areas of high moisture and efflorescence (the formation of mineral deposits) under the carpet, which had caused mould staining of the carpet; and  there was termite damage to the timber bottom plates, top plates and wall studs of the timber wall framing affecting the walls in the extension. The timber framing to the rooms in the extension also appeared to be extremely weathered. 58. In his report, J made the following findings regarding the cause of the moisture and the termite infestation: Case No: 322608 Determination Page 13 of 19  when a large amount of water leaked from the burst water pipe in March 2009, the water filled the small air voids in the compacted sand underneath the slab, which caused the small particles of sand to settle and fill the voids, resulting in the slab subsiding;  the fact that the slab edges and moisture patches were close to the perimeter of the building suggested that the compacted sand under the slab contained a high level of moisture. The moisture was evident in areas of the slab located near the edge of the plastic moisture barrier (which is placed over sand before concrete is poured), which typically ends in the slab edge thickening zone;  the continuing moisture in the slab was due to the large amount of moisture from the burst water pipe which was absorbed into the bedding sand in 2009. Although the sand was progressively drying out over a long period of time, in the meantime it was being absorbed into the concrete slab;  the moisture had not entered the slab through the drill holes used to inject the polyurethane (as suggested by the Applicant). The polyurethane used was non absorbent and the drill holes had been filled with a low shrinkage grout after the injection process was completed. Also, the presence of moisture was not consistent throughout the entire slab;  the concrete slab should have been treated with a waterproofing membrane or sealant after the pipe had been repaired and before the carpet was re-installed, to prevent moisture coming up through the slab being absorbed into the back of the underlay material and the carpet;  the house had originally been built using a visual termite barrier system, which involves an exposed slab edge which is inspected annually to identify any termite entry;  when the house was extended, a new concrete slab was placed beside the existing slab. This formed a “cold joint” which resulted in a distinct join between the two slabs when the wet concrete dried and shrank. This joint was covered by the timber walls and the floor coverings, which meant that the visual termite barrier was obscured; and  where a slab is extended, the cold joint needs to be protected against termite infestation. This involves mechanically covering the cold joint so termites cannot gain access. The cold joint between the new and the old slab in the Applicant‟s house had no termite protection and the evidence strongly suggested that this was the point of entry for the termites. Accordingly, the poorly protected cold joint was the cause of the termite infestation. 59. In August 2013, the FSP accepted liability for the cost of sealing the slab and repairing any resultant moisture damage, as it acknowledged that the slab should have been sealed as part of the initial repairs. However, the FSP has continued to rely on J‟s report to deny liability for the termite damage. Case No: 322608 Determination Page 14 of 19 60. The Applicant disputes J‟s findings that the cold joint was not properly protected when the extension was built. He has provided a copy of a “pre - construction termite treatmen t certificate” dated 21 December 1991 which indicates that the full area of the extension (approximately 30 square metres) was treated with a chemical called Aldrex. The Applicant says that he was advised at the time that this treatment (which has since been banned) would be effective for approximately 30 to 50 years. 61. The FSP‟s records indicate that the Applicant has advised that he had previously had problems with a termite infestation around 2009 to 2010. This was on the other side of the house from the extension and was treated with baits. The Applicant says that he had not previously had any problems with termites in the extension before they were discovered by the FSP‟s builders in October 2012. 62. The Applicant has confirmed that he has taken minimal remedial action to address the termite infestation since it was discovered in October 2012. The Applicant says that the termite infestation has since spread to other parts of his house, although he has put down baits to try and arrest the spread. Further, as a result of the extensive termite damage, the roof of the back part of the house has now collapsed and the house may need to be demolished. 63. The Applicant‟s lack of action to address the termite infestation appears to be due to his view that the FSP‟s contra ctors were responsible for the termites, and therefore he has focussed on pursuing the FSP to remedy this, at first directly and then through FOS. The Applicant has advised that he and his wife are both on disability pensions, and he also appears to be supporting various other family members. Accordingly, it appears likely that the Applicant‟s financial circumstances have limited his ability to take remedial action. Analysis 64. The Panel has carefully reviewed the available information for the purpose of considering the cause of the termite infestation. 65. The Panel notes that several alternative theories have been put forward in relation to the cause of the termite infestation, and the FSP itself has changed the basis for its denial after carrying out further i nvestigations. 66. The Panel considers that the report of the FSP‟s engineer (J) effectively refutes the Applicant‟s theory that the termites entered through the drill holes made in the process of stabilising the slab. The Panel also notes that, while the FSP has acknowledged that the initial repairs were inadequate in that they failed to seal the slab, this cannot be considered to be the cause of the termite infestation. This is because the sealing process would merely have stopped moisture entering the house through the top of the slab, but would not have addressed the issue of the moisture itself. 67. The FSP appears to have initially accepted that the termite infestation was caused by the presence of significant amounts of moisture under the slab. Case No: 322608 Determination Page 15 of 19 However, after J‟s report found that the moisture was the result of the burst pipe (rather than groundwater seepage) the FSP altered its position. 68. The FSP now says that, while it acknowledges that the presence of moisture increases the likelihood of a termite infestation, it does not in itself cause the infestation to occur. The FSP also relies on J‟s finding that the cold joint between the new and old slabs was not properly protected and provided a point of entry for the termites. Finally, the FSP says that the failure of the Applicant‟s contractor to check the termite baits meant that the termites were not readily detected. 69. The Panel notes that the concept of causation can be difficult to apply in the context of animate objects such as termites, which are capable of independent action. In these circumstances, the Panel considers that it is appropriate to consider underlying factors which trigger and/or enable such action to occur. 70. The Panel is concerned that the FSP does not appear to have specifically addressed the relevance of the termite treatment certificate provided by the Applicant, which was first provided to the FSP in March 2013. Further, the FSP does not appear to have provided a copy of the certificate to J so that he could consider whether it impacted his position. Instead, the FSP has continued to rely on J‟s report to deny liability for the termite damage. Nevertheless, J‟s view was that a physical barrier should have been installed at the cold joint, whereas the Applicant relies on a termite spray having been done at the time of the construction of the extension as being adequate for 30-50 years. 71. The Panel considers that there is insufficient information available to determine exactly when the termite infestation first occurred. There is information to suggest that termites were found around 2009 or 2010, but the infestation was successfully treated at the time. The fact that the Applicant engaged a pest controller in November 2011 suggests that he had reason to be concerned about termites at that time. However, there is no information to suggest that termites were found either when the baits were installed in November 2011 or when they were last checked in May 2012. 72. The FSP has suggested that the Applicant‟s failure to monitor the baits caused or contributed to the termite infestation. However, while the Panel accepts that baits assist in controlling an existing termite infestation, it is not satisfied that the failure to monitor baits can be considered to be the cause of the infestation itself. 73. The Panel considers that the available information establishes that:  the burst pipe caused a significant amount of water to be absorbed in the sand under the slab;  the presence of a significant amount of water materially increases the likelihood of termite infestation; and Case No: 322608 Determination Page 16 of 19  several of the areas in which TT observed termites were located in the area of the extension, where the pipe had burst and where high moisture readings were recorded. 74. In the Panel‟s view, the circumstances are highly suggestive of a causal link between the high levels of moisture resulting from the burst pipe and the termite infestation within the extension. Further, the Panel notes that:  the FSP initially accepted that the termite infestation occurred as a result of high levels of moisture; and  the FSP has failed to identify a compelling alternative explanation for the termite attack. 75. Further, the Panel considers that the difficulties associated with the termite infestation discovered in October 2012 have in part arisen because of the FSP‟s poor handling of the Applicant‟s claim from September 2009 onwards. Had the FSP appropriately managed the claim at that time, it is likely that the repairs would have been completed long before the current infestation commenced. In the event that there was any pre-existing termite damage at that time, it is likely that such damage would have been significantly less extensive and more localised, which may have assisted in now determining the cause of the damage. 76. In a case such as the present where the FSP‟s handling of the Applicant‟s claim has been clearly deficient on a number of levels over an extended period of time, the Panel is also concerned about the FSP‟s willingness to apply a policy exclusion in the absence of convincing evidence. The Panel notes that, not only did the FSP order its contractor to cease all work when the termite damage was disco vered it left the back rooms of the Applicant‟s home in an unliveable condition, and failed to implement any make safe arrangements. 77. Given the matters outlined above, the Panel considers that the FSP should not be entitled to rely on the exclusion under the policy to deny any liability for the termite damage to the Applicant‟s house. 78. However, the Panel recognises that it is likely that further damage has occurred since the termites were discovered in October 2012, as a result of the Applicant‟s failure to take appropriate action to address the infestation. 79. On this basis, the Panel considers that, it is fair in all the circumstances that liability for the termite damage to the Applicant‟s house (other than the extension) be apportioned equally between the FSP and the Applicant. Cash settlement in lieu of rectification repairs 80. After the FSP ordered its contractor (CC) to cease rectification works in October 2012, it asked CC to provide a breakdown of the rectification works showing which had not yet been completed. CC provided a breakdown which showed that the cost of the outstanding works was $26,125.19, and the FSP cash settled the Applicant for this amount. Case No: 322608 Determination Page 17 of 19 81. The Applicant was dissatisfied with both the amount of the cheque and the fact that the FSP was requiring him to accept a cash settlement, as he wanted the FSP to arrange for the rectification repairs. The Applicant has confirmed to FOS that he has not cashed the cheque provided by the FSP. 82. The FSP cash settled the Applicant on the basis that it was not liable for the termite damage or the moisture damage to the slab and floor coverings, which needed to be addressed before rectification repairs could be undertaken. 83. The FSP has since acknowledged that it is liable for the moisture damage and, for the reasons outlined above, the Panel has found that the FSP is required to rectify the issues with the slab, by replacing it and rebuilding the extension and is also liable for 50% of the termite damage to the remainder of the house. 84. The Panel considers that the lifetime guarantee provided under the policy (as set out above) requires the FSP to arrange rectification repairs, and does not entitle it to choose to cash settle the Applicant for the rectification repairs. 85. The Applicant has throughout this dispute e xpressed a strong preference that the FSP be required to take responsibility for arranging the rectification repairs. However, in circumstances where the Panel has found that the Applicant is partly liable for the repair of the termite damage, for logistical reasons it is not practical to require the FSP to carry out the portion of the repairs for which it has liability. 86. Accordingly, the Panel considers that an appropriate remedy in these circumstances is for the FSP to cash settle the Applicant for an amount equal to:  the costs of replacing the slab and rebuilding the extension in its entirety; and  50% of the costs of repairing the termite damage to the remainder of the house. 87. In order to determine the amount of the cash settlement, the FSP is to, at its own cost:  appoint a suitably qualified and experienced engineer to prepare separate scopes of work in respect of the extension and the remainder of the house; and  engage an appropriately qualified builder to provide a costing for each scope of works, such costing to be prepared on an arms‟ length basis and without taking into account any insurer discounts or rebates. 88. The Panel considers that it is not appropriate to req uire the FSP to pay interest on the cash settlement amount, given that this amount will be determined based on costings prepared using current market rates. Case No: 322608 Determination Page 18 of 19 Other issues 89. Given the nature and extent of the works required, the Panel considers that the FSP should be required to fund the costs of temporary accommodation for the Applicant and his family during the period the works are being carried out. 90. Given the Panel‟s view that a cash settlement is appropriate, the FSP should be required to ensure that:  the builder appointed to cost the scopes of work provides an estimate of the time which will be required to complete the works; and  the cash settlement to be paid to the Applicant is increased by an amount representing the reasonable costs of temporary accommodation for the Applicant and his family for this period of time. 91. The Panel considers that the report prepared by the Applicant‟s expert (SD) accurately identified that the groundwater seepage was not the source of the continuing moisture problems, and convinced the FSP to undertake further investigations. Accordingly, the Panel considers that the Applicant should be compensated for the costs incurred in obtaining SD‟s report. Determination 92. On the basis of the available information, the Panel determines that:  within 28 days of the date the Applicant accepts this Determination, the FSP is to, at its cost, arrange for: i. a suitably qualified and experienced engineer to prepare separate scopes of work in respect of: i. the replacement of the slab and the rebuilding of the extension; and ii. the repair of the termite damage to the remainder of the house; ii. an appropriately qualified builder to provide a costing for each of the above scopes of work, such costing to be prepared on an arms‟ length basis without taking into account any insurer discounts or rebates, and to include an estimate of the number of days required to complete the works;  within 7 days after receiving the scope of works and costings referred to above, the FSP is to cash settle the Applicant for an amount equal to the: i. the costs of replacing the slab and rebuilding the extension (determined as set out above); ii. plus 50% of the costs of repairing the termite damage to the remainder of the house (determined as set out above); Case No: 322608 Determination Page 19 of 19 iii. plus the reasonable costs of temporary accommodation for the Applicant and his family for the estimated time period required to complete the works; iv. plus $3,000 as compensation for non-financial loss suffered by the Applicant as a result of the manner in which the FSP handled his claim; v. plus an amount equal to the costs incurred by the Applicant in obtaining SD‟s report, subject to the Applicant providing reasonable evidence of such costs; vi. less the amount of $26,125.19 previously paid the Applicant in settlement of his claim;  on acceptance of this Determination by the Applicant, he is entitled to cash the FSP‟s cheque for $26,125.19 already in his possess ion, as part of this settlement; and  if the Applicant disputes the amount of the cash settlement determined by the FSP in accordance with the process set out above, the parties may refer the dispute back to the Panel and the Panel will, after allowing for further submissions, determine the cash settlement amount.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.