Standard and completeness of storm repairs following an earlier FOS determination
Text of the determination
Case No: 322249 Determination Page 1 of 31
Case number: 322249
General Insurance - Domestic Insurance - Home Building - Service - Delay in
claim handling
31 May 2013
Background
1. This matter involves a dispute arising from the standard of repairs to the
Applicant’s dwelling following a Determination issued by the Financial
Ombudsman Service in November 2011.
2. On 29 January 2011 the Applicant’s home and contents sustained substantial
damage during a severe storm in the area. The Financial Services Provider
(FSP) accepted liabil ity for a claim under the Applicant’s home cover
insurance policy and arranged for the damage to be assessed.
3. The Applicant disputed the extent of the scope of works in relation to the
building damage accepted by the FSP and referred the matter to the Financial
Ombudsman Service (FOS).
4. In November 2011 FOS issued a determination as follows:
“1 The FSP is entitled to assess the loss based on the policy vesting in the joint
names of the Applicant and his estranged wife.
2 The FSP is to replace the entire roof sheeting as agreed by it.
3 The FSP is not liable for the condition of the north wall.’
4 The FSP is entitled to replace the damaged ceilings with the same material
which existed prior to the storm being polystyrene.
5 The FSP is liable for rectifying cracks in the walls above the windows and
doors.
6 The FSP is liable for 50% of the cost of reinstating the shower base and unit.
7 The FSP is not liable for the wall lining sheet adjacent to the bathroom.
8 The FSP is liable for rectifying all the flooring apart from the area near the
end of the wall in the living room. This involves sanding only and not
replacement.
9 The FSP is to seek recovery of the water system pump from the sub
contract builder.
10 The FSP is not liable for the stove covers.
11 The Applicant has not established the fences were damaged by the storm.
12 The FSP is not liable for the condition of the veranda
Determination
Case No: 322249 Determination Page 2 of 31
13 The FSP is to re-inspect the roller doors and replace them if found to be
faulty.
14 The FSP is to commence repairing the insured damage. In the event that
this work requires removal and replacement of undamaged items, then the
FSP is to include the removal and replacement of these items within the
SOW. This does not include the bathroom which has been addressed
separately in the determination.
15 The FSP’s offer to settle the contents claim by replacement of the damaged
items through nominated suppliers is according to the terms of the policy
and good insurance practice.
16 The FSP is to indemnify the Applicant for the Toshiba laptop computer and
Cannon printer up to the value specified on the proposal form.
17 The FSP is not liable for the condition of the ride on mower.
18 The FSP is liable for the Applicant’s temporary accommodation expenses for
accommodation similar to the accommodation enjoyed in his home. The
FSP is to reimburse the Applicant for any sums incurred within 5 working
days of receiving the relevant documentation.
19 The FSP is not liable to pay compensation.
20 The FSP is to reimburse the Applicant with the contents premiums paid to it
on instruction from the Applicant that the cover is to be removed from the
policy. The refund is to be calculated on a pro rata basis from the time the
contents were no longer in the home and the FSP was not at risk”.
5. The building wor ks were completed by the FSP’s contractor in June 2012.
6. In January 2013, following a period of time overseas, the Applicant inspected
the property prior to its sale and considered all the works to the dwelling had
not been completed and other works had not complied with current building
standards.
7. The Applicant referred his complaint to FOS. Following an extensive number
of communications between the Applicant, the FSP and FOS, in February
2013 a site visit was arranged which included representatives from the FSP,
the contractor and the Applicant.
8. As a result of the site visit the issues of concern to the Applicant were
addressed by the FSP and where required, remedial works carried out.
9. The Applicant remained dissatisfied with the outcome following the site visit;
asserting the FSP had failed to comply with the FOS Determination and had
failed to complete other repairs satisfactorily.
10. On 18 March 2013 the property was sold at a mortgagee’s sale for the sum of
$225,000.
11. The Applicant is seeking payment of the full sum insured for the building and
contents and compensation for mental and physical injury suffered as a result
of the FSP’s management of the claim and for the cost of preparation of his
submissions to the parties involved.
Case No: 322249 Determination Page 3 of 31
Summary of Applicant’s position
12. By email dated 7 January 2013 the Applicant enquired about the delay in
selling the property, he having signed it over to the mortgagee. He further
advised having inspected the property on 5 January 2013 and considered the
FSP had not completed repairs to the house in accordance with the FOS
Determination. He listed the following items:
The entire roof which was to be replaced had not been completed.
Braces on the side of the house had not been done.
Carpet was not supplied and laid.
Plumbing to the bathroom shower had not been done.
Walls have separated and holes were present.
Curtains had not been supplied or fitted.
A water pump stolen by the contractor had not been returned.
The breather pipe to the septic had been cut and did not extend beyond
roof level.
13. The Applicant submitted a large number of photographs in support of his
claim.
14. By email dated 11 January 2013 to FOS the Applicant informed FOS of the
issues listed in his email to the mortgagee on 7 January 2013. He included the
following additional items:
A slow combustion heater and hearth are missing.
Screws and nails in the roof have been put through the roof and do not
hold anything together.
Reports all state the home lifted and the house may have moved
further while in the contract or’s control. It is therefore unsafe.
No work was inspected by the shire engineer to confirm the work was
carried out to any standard at all.
15. By email dated 11 January 2013 to FOS the Applicant submitted further
photographs showing:
Roof falling apart
Hole in shower floor with no plumbing fitted.
Space on floor where hearth has been removed which housed a slow
combustion heater and flue.
Walls that have not been repaired
16. By further email dated 11 January 2013 to FOS the Applicant stated:
Contrary to the FSP’s advice that he or a representative declined to
attend a meeting with the builder to sign off the works, at no time was
Case No: 322249 Determination Page 4 of 31
he asked to attend although he had a Justice of the Peace waiting to do
so.
The following list of items remained uncompleted:
i. Roof not replaced.
ii. Wall supports not placed on external walls under pine logs.
iii. Bathroom not completed – shower plumbing and pipe works not in
place.
iv. Floor covering in bathroom, laundry and kitchen not supplied.
v. Carpets not supplied.
vi. Curtains not supplied.
vii. Guttering on house fitted incorrectly and hanging from house.
viii. Breather pipe from septic cut off below the roof.
ix. Hearth and heater removed. Roof above flue is repaired and
closed.
x. Water pump stolen by contractor not returned.
xi. Floors in bedroom adjacent to bathroom have not been
adequately repaired and sanded.
xii. Cornice in 2 nd bedroom not suppled.
xiii. Vent to air conditioner in 2 nd bedroom hanging from ceiling.
xiv. Cracks to all walls not repaired.
xv. Walls damaged by builder not repaired.
17. By email dated 14 January 2013 the Applicant submitted a letter dated 14
January 2013 from the Shire Council. The council letter confirmed the FSP’s
contractors had been issued with a Building Licence for work to be undertaken
and that the council was not obliged to carry out inspections of the works
undertaken.
18. By email dated 23 January 2013 the Applicant advised:
The email sent by the FSP in relation to the meeting with the builder to
sign off the scope of works was sent to the email address which he had
cancelled before leaving Australia. The FSP had been informed of the
correct email address.
He did not receive any emails from the FSP sent to his correct address
re attending the sign off with the builder.
The final inspection was carried out by the assessor and the contractor
who sent photos to the building consultant. The building consultant’s
appraisal of the work was based on the photographs. The photos only
show clean areas of the house.
The contractor has not returned the pump, and other items remain
missing. The FSP has failed to comply with the Insurance Contracts Act
Case No: 322249 Determination Page 5 of 31
1984 (the Act) to complete the work agreed on and has allowed
persons hired by the builder to do the work and take possession of
items on site and remove them illegally.
He requires the FSP pay the full amount of $300,000 for the total loss
of his property due to its inability to comply with the Act. He also
requires the FSP to pay the full amount of $125,000 for the contents of
his home which was not paid.
The FSP owes him the cost of his mortgage due to its failure to comply
with the Act.
He also seeks compensation for the two years the FSP has been
unable to repair his home. The FSP and the builder are responsible for
over $1,000,000 in total due to failure to comply with the FOS
Determination.
19. By emails dated 29 January 2013 the Applicant submitted further
photographic evidence supported by captions.
20. By email dated 31 January 2013 the Applicant made a further submission
setting out his complaints as follows:
The builder appointed by the FSP employed a contract maintenance
builder “KB” to repair the home. He was not a registered builder.
The water pump had been removed from the site by KB and has not
been returned.
He attended the site once a week but was informed by the FSP that it
was a work site and he was not allowed on the property.
Twelve months after the storm he was suffering anxiety stress and
other illnesses brought on by the standard of works and on 29 January
2012 he moved to Thailand.
He lodged a complaint with FOS which issued a work order. This work
order was not completed and in some areas was totally ignored.
On 6 June 2012 he was informed by the FSP all work had been
completed as ordered by FOS.
On 5 January 2013 he attended the site and found most work had been
ignored and some areas not completed at all. The Applicant noted the
following:
SOW 2 Roof
i. The builder’s report suggested the whole roof be replaced. The
condition of the roof does not comply with Australian Standards.
ii. No cladding had been removed to identify and construct anchor
points to form a tie down to secure the roof around the perimeter
of the existing timber external walls.
iii. Metal brackets placed on the roof do not meet Australian
Standards. This does not comply with the SOW ordered by FOS.
Case No: 322249 Determination Page 6 of 31
iv. Due to the home lifting, the roof will lift off, the house will most
likely also lift and be completely demolished in a similar storm.
This is why the engineer should have inspected the structure.
v. The eastern end of the roof has not been completed at all.
SOW 2 has therefore not been completed to Australian Standards
SOW 5 Internal
vi. No work has been started on most windows and no doors at all.
vii. The main bedroom door has holes in it, cracks to one side and is
not fastened to the door frame.
viii. Bedroom 2 door is split at the edges and hinges are falling apart.
ix. All door frames connected to the wall have parted at the joints on
the top corners and not repaired.
SOW 6 Shower
x. The main tap is missing.
xi. The plumbing connecting the shower drainage to the septic was
not in place.
xii. In relation to the bathroom, FOS was misled as not being storm
damaged. In fact the base of the shower was completely cracked
due to a heavy steamer on top of the single door cupboard.
During the storm the roof above this area was removed partially
allowing the wind to tip the cupboard allowing the steamer to fall
on the shower base.
xiii. The shower unit, vanity unit and all floor coverings and walls had
been replaced and were new at the time of the storm.
xiv. The FSP must take responsibility for the condition of the shower
which is unusable.
SOW 8 Floor, PC allowance for sanding and prep particle board
xv. The floor covering in a number of rooms has not been replaced.
xvi. The section which has had work attempted is part of the entire
floor which lifted during the storm.
xvii. The lounge room floor has a gap of about 1cm which has not
been repaired. This occurred when the house lifted and should
have been inspected by an engineer.
xviii. A stain on the lounge room wall is long term leakage not caused
by the storm.
xix. Old carpet fasteners have not been removed to allow sanding
next to the walls.
Case No: 322249 Determination Page 7 of 31
xx. The floor in bedroom 2 has not been touched. The FSP denied
this part of the claim stating the floor was damaged from long term
leakage from the shower which had been replaced.
xxi. If the house lost its roof and a huge amount of rain fell during the
storm a large amount of water would have landed in the area.
xxii. This room also received damage to the wall when a tree fell on
the roof. The tree was not visible when the damaged was
assessed as it had been removed by the authorities. The FSP
denied this damage.
xxiii. No works has been done in relation to all carpet, vinyl and
underlay.
SOW 9 Pump
xxiv. KB stole the pump. It has not been returned.
xxv. The 70 mega-joule gas heater has not been supplied. No cover
has been supplied for the pool.
TV Antenna
xxvi. The old antenna connections remain visible.
Solar Heater
xxvii. The operation has not been inspected.
Cleaning
xxviii. Clean up of the entire area had not been completed. It was being
done at the time of his visit on 5 January 2013.
Supervision
xxix. No supervisor has been on site during the works. As KB is not a
registered builder a supervisor was required.
xxx. Collection of the allowance for this portion of the contract may
constitute a criminal fraud as someone has benefitted by the
words on the order and payment made.
Roller doors
xxxi. No allowance has been made to carry out further repairs to roller
doors.
The Applicant states the only solution is to order the FSP to pay the full
amount of his claim being $300,000 for the building and $150,000 for
the contents cover.
The FSP should also be ordered to pay out the mortgage and if the
property is not sold at auction return the property to him.
The claims process has not been completed to regulations prescribed
by the Act.
Case No: 322249 Determination Page 8 of 31
The following items have been removed from the site, stolen or not
supplied; 1. 1HP water pump; 2.Main water supply pump; 3. Spa heater
(not supplied); 4. Pool cover (not supplied); 5. Air conditioner from
spare room on garage; 6. Internal combustion heater and flue; 7. All
floor coverings; 8 All window dressings.
21. By email dated 31 January 2013 the Applicant provided additional captioned
photographs.
22. By emails dated 19 February 2013, 20 February 2013 (2) to FOS, the
Applicant advised the following:
T he FSP’s report of 14 February 2013 states what work was not
completed. This is the reason for his claim as the FSP at an earlier date
in June 2012 advised him that the work had been fully completed
according to the FOS order.
On receiving the FOS work order the FSP appears to have left out the
rest of the claim and only focused on the items mentioned in the order.
The FSP appears to believe it has no responsibility for the rest of the
claim.
In failing to comply with the work order, the FSP should be made to pay
the full amount of his claim for both building and contents.
FOS is asked to consider the truth about his wife being a co-claimant
as the policy clearly states any member of the family not residing in the
insured property for more than 60 days is not covered in the event of a
claim.
The FSP has ignored this position and insisted his wife was covered.
However every policy he held with the FSP was a separate policy and
his wife was only involved in a policy relating to a hearing aid covered
against loss or damage. The building policy, contents policy and car
policy were held by him and were only in his name as he paid all fees
and owned the house prior to their marriage. His wife does not appear
on any title deed for the land or on the mortgage held with the bank.
The FSP has breached the Privacy Act by talking to his employer in
relation to his claim.
He is seeking payment in full for his building policy in the sum of
$300,000 and contents in the sum of $150,000. He has received
$25,000 for contents which is well under the claimed amount and is
therefore entitled to have the difference made up.
He is also seeking payment for his time taken to investigate and report
on every aspect of the claim. He has worked about 200 hours and as
an investigator received $35/hour, this should be added to legal
expenses incurred by him.
23. Following a site visit by representatives of the FSP, the builder and the
Applicant, by email dated 13 March 2013 the Applicant stated:
Case No: 322249 Determination Page 9 of 31
The FSP has incorrectly allowed his wife to claim under the policy,
although she has no legal right to do so.
At no time after his marriage was he informed his wife was part of the
contract. However the FSP now includes her as a person able to make
a claim on his property.
Even though the policy states his wife is not covered as she has not
resided in the property for 60 days and photographs show no female
clothing in the wardrobes the assessor accepted her claim.
The FSP has allowed his wife to be part of the claim for his property
without applying the policy statement which shows she is not a legal
claimant.
At the time he rented premises he entered into a bond. The FSP paid
the bond money which was placed in the agent’s trust account. At no
time had he received the money. The FSP has deducted this bond from
a payment to him but it is in fact the FSP’s responsibility to recover the
bond.
A number of areas relating to the claim but not included in the SOW
issued by FOS have not been completed. The FSP has referred only to
the FOS order and ignored areas of the claim which they are required
to repair.
The FSP is required by the Act to complete all work relating to the
damage and have not done so because of the FOS order.
He does not agree with the FSP that as the property has been sold it
has no further involvement in the claim. This was established in the
email in June 2012 advising that all work is finalised.
For this reason the FSP should be found in breach of the work order
and be held liable to pay the full amount of the claim being $300,000 for
building and $150,000 for contents.
The SOW required fencing to be installed. In addition he was also told
he was not able to attend the property as the work order was not
completed. The FSP should therefore be held liable for any malicious
damage caused to the home.
The FSP by neglecting security at the site had shown a failure in its
duty of care and in doing so has contributed to the damage and should
therefore be held responsible for his loss in the sale of the property.
The property sold for less than half its market value estimated prior to
the storm.
The FSP refers to poor workmanship in the original building but fails to
mention all the work completed on the property complied with building
standards.
The Applicant referred to items 2, 5, 6, 8, 9 of the SOW and enlarged
on his comments noted in his email of 5 January 2013. The Applicant
also revisited his arguments in relation to the TV antenna, solar heater,
cleaning, supervision, and roller doors.
Case No: 322249 Determination Page 10 of 31
Photographs with descriptions of the condition of the items have been
submitted in the report.
The FSP has not carried out works as ordered by FOS. The FSP
should be found guilty of non compliance with FOS orders and as such
lose its licence.
The FSP failed to comply with the Act in relation to the claim. As such it
should be held liable for his claim in full being $300,000 for the building
and $150,000 for contents.
The FSP should also pay for his costs for preparing his report, emails,
letters, and photographs during the last 26 months.
He has worked over 500 hours during this time and, travelled back to
Australia from Thailand once. The costs for this and his
accommodation in Perth for 2 weeks should be paid by the FSP.
The FSP is also liable for medical expenses as a result of his stress
and depression rela ted to the FSP’s management of the claim.
The FSP has acted with malice to ensure the property could not be sold
for a fair price or for the pre storm value thus causing him a massive
loss assessed as follows:
The pre storm valuation $439,000
Contents lost $150,000
Expenses incurred $ 30,000
Health loss $500,000
24. The FSP should be required to pay this sum to him as he was the sole owner
of the property and the only person named in the building and contents
policies.
25. The FSP should recover the money paid to his wife as she is not a named
owner on the Title Deed, or the mortgage and as such has no financial rights
to any payment under the policy.
26. His wife did not reside on the property for over 60 days prior to the claim. The
policy states that any family member not residing at the property for over 60
days prior to the loss is not covered under the policy.
27. By email dated 13 March 2013 the Applicant submitted additional
photographs.
28. By email dated 4 April 2013 the Applicant advised:
The FSP confirmed in June 2012 the work required according the FOS
order was completed. At the time he was in Thailand and could not
inspect the work. It was not until January 2013 that he inspected the
work and found most items ordered had not started or been completed.
Case No: 322249 Determination Page 11 of 31
The FSP has failed to comply with the FOS order and as such it should
pay compensation for the loss and damage he suffered since January
2011.
The builder used a contractor who was not a registered builder in WA.
The BRBWA Code states any builder or site foreman undertaking
repairs at or above a certain cost must be a registered builder.
The FSP has ignored his complaint and as such the FSP should be
liable for the cost of his home.
The FSP has ignored the policy conditions and named his wife as co-
insured. This person has no rights to the property and allowing her to
receive benefits is a breach of the policy terms and Code of Conduct.
The Applicant refers to the policy condition limiting cover when the
property has been unoccupied for more than 60 days and argues his
wife should be ruled a non insured person as she had not lived in the
house for over 60 days.
When the property was sold it was not in good condition and was sold
for a sum under its value. The actions of the FSP should be taken into
account when directing compensation to him for monies lost on the
sale. The compensation should include the insured amounts for the
building and contents plus compensation for all damage and extra
costs incurred by him.
Due entirely to the FSP’s actions he has suffe red mental and physical
injury. He has also spent hundreds of hours working on submissions,
statements and photographs to substantiate his claim. He has also had
to travel as he had to return to Australia from Thailand to check the
work which was found by him to be uncompleted.
29. By email dated 30 April 2013 the Applicant advised:
The contractor employed by the builder was a local maintenance
contractor and not a registered builder as defined by the builder
registration board. As such he was not qualified to undertake the repair
work.
During the time the FSP had possession of the property the following
items disappeared:
i. Air conditioner servicing the garage as shown on a number of
photographs.
ii. Slow combustion heater and hearth in the main dwelling.
The site was not secured as required in the SOW. There was no forced
entry and works having been completed in July 2012 show the items
missing as having been removed with both areas appearing to have
been cleaned as required.
Therefore the FSP is liable for these items.
Shade cloth covering frame work on the western side has not been
touched.
Case No: 322249 Determination Page 12 of 31
The Applicant discussed a number of items which did not form part of
the SOW agreed according to the FOS order. The Applicant contends
these should also form part of his dispute with FOS. These include:
i. Security and signage.
ii. External work.
iii. Window treatments and floor coverings.
iv. General demolition.
v. Internal works.
vi. External wall modifications.
vii. Roof, roof plumbing.
viii. Ceilings.
ix. Slow combustion stove.
Shower was damaged by the storm and bathroom repair should form
part of the claim.
Summary of FSP’s position
30. By email dated 17 January 2013 the FSP confirmed:
a report had been received from the technical consultant “MCS” dated
26 May 2012 confirming an inspection of the agreed works had been
carried out. The report detailed the state of the works including those
that had been completed and others which required further attention.
the vinyl and carpets had not been installed at that time as the
Applicant was overseas and not available for selection of colours.
31. By letter dated 14 February 2013 to the Applicant, the FSP advised that a site
meeting held on 6 February 2013 was attended by the FSP, the builder, the
technical consultant MCS, the assessor and the Applicant’s representative.
The letter responded to the building complaints set out by the Applicant in his
email dated 31 January 2013 to FOS summarised as follows:
Scope of Works (SOW)
i. Item 2 roof. Completed as per FOS determination.
ii. Item 5 Internal. All gaps above doors and windows sealed as
viewed on site – FSP agreed to include 4 th cornice on an ex gratia
basis as it was not present prior to the storm – The event was
secured.
iii. Item 6 Shower. Not completed as FSP contribution was 50% only.
iv. Item 8. Floor A cash settlement was agreed for flooring $5,440
and curtains $1,500. The payment had not been made at that
time. The payment was to be split between the Applicant and his
wife with the sum of $3,470 to be paid to each party.
Case No: 322249 Determination Page 13 of 31
v. Item 9. Pump, gas heater. The gas heater was not listed on the
FOS Determination and had not been supplied. Electrical
certificate of completion issued. Offers had been made to return
the pump none of which had been agreed to or pursued by the
Applicant. The 70 meg-joule gas heater was not supplied as there
was no gas connection at the pool. In addition the Applicant had
advised this was stolen by his wife. Property taken by a
policyholder is not classed as stolen. The pool cover was not
replaced as it is excluded under the policy.
vi. Cleaning. This item has been completed.
vii. Roller doors. The roller doors are functioning correctly.
Additional matters not included in the FOS Determination.
i. The Applicant’s photos were taken of parts of the property not
included in the SOW. The issues relating to these photos are
maintenance issues and not the FSP’s responsibility.
ii. The 5hp water pump, main supply water pump. Spa heater. Pool
cover. Air conditioner. Internal combustion heater and flue. Floor
coverings and curtains.
iii. Apart from the heater and flue, all items have been addressed.
The heater and flue may have been removed by the cleaners
instructed by the bank. The air conditioner was on site throughout
the repairs. If the Applicant considers the heater and flue and air
conditioner have been stolen he will need to lodge a report with
police and report the loss to his current insurer.
iv. Return of $1,200 bond. The Applicant has not returned the bond
paid by the FSP in relation to his temporary accommodation.
v. Advice has been received that since the repairs were completed
the property was subject to numerous incidents of malicious
damage and vandalism including windows and lights smashed.
The Applicant cancelled his policy on 19 December 2012 and
therefore all new damage is not the FSP’s re sponsibility.
vi. The property was unconditionally sold therefore ceasing all the
Applicant’s future involvement with the property.
32. The FSP relies on a report dated 12 February 2013 issued by the technical
consultant following inspection of the outstanding works at the site meeting on
8 February 2013. The report details the findings as set out in the FSP’s letter
of 14 February 2013 to the Applicant.
33. The FSP notes the mortgagee lawyers advised the property had been sold for
$225,000 on 18 March 2013 and the sale was finalised.
Case No: 322249 Determination Page 14 of 31
Issue
34. Whether the building repairs determined by FOS in November 2011 have
been carried out and completed in accordance with the FOS Determination
(247514) in a professional and workmanlike manner.
Reasons for decision
35. A dispute arose in relation to the extent of repairs following damage to the
Applicant’s property as a result of a severe storm on 29 January 2011. The
dispute was referred to FOS with a Determination being issued by the Panel.
The Determination required the FSP to rectify certain damage as set out in
paragraph 4 of this Determination.
36. This matter involves the standard and extent of repairs affected following the
Panel Determination and other matters raised by the Applicant. The Applicant
was not satisfied the standard or scope of repairs was completed satisfactorily
and referred his complaint in this regard to FOS. Due to the complex nature of
this dispute, FOS has considered it appropriate to expedite the dispute in
accordance with the Operational Guidelines to the FOS Terms of Reference.
The dispute has not been the subject of a FOS Recommendation and has
proceeded directly to Determination.
37. This dispute has been referred to a Panel consisting of an Ombudsman and
two Panel members with extensive experience in insurance claims and
consumer disputes.
38. There has been an exchange of material between the parties. Each party
therefore is aware of the issues and has had the opportunity to respond.
39. Prior to arriving at a determination the Panel has read and considered all the
material submitted by the parties in addition to the previous Determination.
40. The Applicant submitted a large number of photographs depicting areas of
concern to him. While the Panel has examined each of these photos it is not
intended to comment on each photo in this determination, however it
particularly notes the following:
(email 29/1/13)
a. No curtains installed.
b. No vent supplied, no vinyl in laundry/toilet.
c. Bathroom drain not repaired.
d. Bedroom 2 vent just hanging – no cornice fitted – crack above window
not repaired – window out of line.
e. Fan not operational.
Case No: 322249 Determination Page 15 of 31
f. Pool cover and spa heater not supplied.
g. Water pipes to storage tanks have been removed - main water pump
removed by KB – inside shed water pump from collection tank removed.
h. Guttering falling apart.
i. Roof on south side not replaced. Workmanship below Australian
Standards.
j. Beams poorly fixed with bent nails.
k. Roof screws missing beam.
Email 13 March 2013
l. Damaged roof end.
m. Depicting roof did in fact collapse.
n. Air conditioner in place confirming it was damaged after the works
ordered by FOS commenced.
o. Electrical wire hanging in area of cornice in place at wall/roof joint.
41. There have been a considerable number of emails exchanged between the
parties and FOS including copies of emails to other parties not directly
involved in the dispute in order to have the matter resolved. As the Applicant’s
complaints were not resolved during this process, in order to clearly identify
the issues of concern to him, the Applicant was asked to provide a report
setting out his complaints.
42. The Applicant subsequently provided a final submission by email dated 13
March 2013. This report was exchanged with the FSP to allow a formal
response to the outstanding issues of concern to the Applicant.
43. The Applicant then submitted further reports by emails dated 4 April 12013
and 30 April 2013.
44. In determining the issues, the Panel will for the most part refer to the 13
March 2103 report and the photographs provided by the Applicant and the
FSP’s response to it as these appear to encapsulate those issues which the
Panel considers most relevant.
45. The FSP is required to comply with the previous Panel Determination. Any
works carried out as a consequence of the Determination should be carried
out in a workmanlike and professional manner. The FSP therefore has a
responsibility to ensure the works are completed according to the SOW and in
a professional manner.
46. The FSP involved a building contractor specialising in insurance and
commercial building maintenance and a specialist technical consultant in the
Case No: 322249 Determination Page 16 of 31
repair process. The Panel is satisfied that these parties were appropriately
qualified to carry out and supervise the work. The Applicant alleges the
contractor who performed the work was not a licensed builder and as such a
supervisor was required on the site.
47. According to the principal building company, the contractor involved was a
contracted carpenter and it was the builder as per the license registered for
the repairs. The Panel notes the local council has confirmed the issue of a
licence to the principal building company.
48. The Panel is therefore satisfied the repairs were carried out under the
authority of a licensed builder.
49. The SOW agreed with the builder is as follows:
“2 - Roof remove remaining damage section of Colourbond roof
sheeting area approx 96m2.
RC Allowance included modifying and installing roof structure
tie downs to comply with BCA standards.
This will involve removing & re-fitting of external cladding to
determine, indentify & construct anchor points to form a tie
down method to secure roof structure around perimeter of
existing timber consecution external walls.
Note. This does not include the veranda areas of the roof.
5- Internal PC allowance included to rectify cracks around internal
windows and doors where gaps are visible at wall sheets.
6 – Shower PC allowance included for 50% of costs relating to re-
installation of shower base & unit.
8- Floors PC Allowance to sand & prep particle floor boards panels to
best possible outcome.
Supply & install vinyl to bathroom, laundry & toilet.
Supply & lay Cerad lane carpet & underlay to lounge, main bed
1, bed 2.
9-Pump Recovery of water supply pump.
Allowance to supply & install swimming pool 1.5hp pump,
C100 cartridge filter, salt chlorinator, 150SL 70 mega-joule gas
heater & spa blower, cover & cleaner, insulation and operation
testing.
TV antenna supply & install new TV antenna
Solar heater Supply & install new solar hot water system on to roof & pump
as required.
Cleaning PC Allowance to include clean up external area of site only in
relation to repair works & internal final clean.
Remove & disposal of builder’s debris.
Supervisor PC Allowance to include a supervisor of works in progress &
final handover.
Case No: 322249 Determination Page 17 of 31
Note No allowance included to carry out further repair work to roller
doors as these have already been reinstated to original work
condition, notes have been made on the original installation
which does not conform to regulation installation methods.”
50. On reviewing the SOW and the November 2011 Panel Determination, the
Panel is satisfied the SOW reflects the items determined by the Panel which
were to be rectified.
51. It is therefore appropriate to consider the Applicant’s complaints in relation to
the standard of repairs and the evidence in relation to those repairs for these
items.
Scope of Work
2 Roof:
The Applicant
52. The Applicant states the home was constructed 26 years ago and complied
with Australian Standards at that time. Thus any partial work to the roof
requires the whole roof to comply with those standards.
No cladding was removed to construct anchor points for a tie down.
Instead metal brackets have been placed on the roof external beams
securing them to the roof. The brackets do not meet Australian
Standards and have been secured with tech screws and bent brackets.
This will secure the roof, only to the roof and not to the roof structure of
the building structure.
The FSP (letter dated 14/2/13)
53. The FSP’s response follows a site visit on 7 February 2013 by the FSP’s
representative and those from the builder, the specialist technical consultant
and the Applicant’s representative.
54. The builder’s (report dated 12 February 2103) advised:
hoop iron strapping was installed and was completed on 6/2/13.
roof capping ends were sealed on 9/2/13
55. Specialist technical consultant report dated 12 February 2013
The roof sheeting has been replaced as per the SOW and revised
SOW. It does not include the verandas.
The works have been carried out to a satisfactory level to the perimeter
of the building.
The capping to the ridge gable has been cut short. The capping has not
been sealed. This was to be addressed by the builder within 2 days.
56. The FSP submits this work is completed as per the FOS Determination.
Case No: 322249 Determination Page 18 of 31
Item 5
Internal: PC allowance includes to rectify cracks around internal windows
and doors where gaps are visible at wall sheets.
The Applicant
57. The Applicant states:
Some works has been done but most windows and doors have not
been repaired.
The door to the main bedroom is holed, cracks are on one side and it is
not fastened correctly to the door frame.
Bedroom 2 door is split at the edges and hinges are falling to pieces.
All door frames connected to wall sheets have parted at the joints on
the top corners.
The FSP
58. The FSP relies on the builder and the specialist technical consultant’s reports.
The builder:
The cracks have been rectified.
Bedroom 2 – cracks to wall filled.
Bedroom 2 cornices in situ.
Bedroom 2 conditioner vent secured.
The technical consultant:
There were no cracks found above doors and window frames. All open
joints above windows and doors that appeared to have light penetrating
through were sealed prior to and on the day of the inspection.
This item has been carried out. All gaps above doors and windows
were sealed as viewed on site.
The FSP
Only 3 cornices were present in bedroom 3 at the time of the storm.
However it agreed to place the 4th cornice into bedroom 2 as an ex
gratia addition.
The vent which was hanging slightly in bedroom 2 was also secured
while on site.
Case No: 322249 Determination Page 19 of 31
Item 6: Shower PC allowance for 50% of costs relating to installation of shower
base and unit.
The Applicant
59. The Applicant states the tap was missing and plumbing under the house
connecting to the septic system was not in place.
60. FOS was misled as the bathroom was damaged by the storm.
The FSP
61. The FSP states that the Applicant and his estranged wife were requested to
contribute the $960 share to the bathroom costs. Both policyholders declined
to do so. The FSP paid $960 according to the Determination to the mortgagee
account.
Item 8: Floor
The Applicant
62. The Applicant states the floor coverings supposed to have been replaced
have not been. The floor in the lounge area has a gap of about 1cm which has
not been repaired.
63. The stain to the western end of lounge has been sanded but has resurfaced
over the sanding. This shows it is not a leak.
64. The old carpet fasteners have not been removed to allow sanding next to the
walls. The floor in bedroom 2 has not been touched.
65. Although the FSP stated the floor was damaged from long term leakage from
the shower, the shower had been replaced along with the walls and floor. As
the house lost its roof during the storm, a large amount of water would have
fallen on that area as it was the only area not covered by furniture.
66. No work has been done for all vinyl, carpet and underlay.
The FSP
67. The FSP states the carpets were to be addressed at finalisation of the building
works under the contents claim.
68. The property was measured for replacement vinyl and carpet. The supplier
was advised on site at the time the Applicant attended that he was obtaining a
cash settlement for these items.
69. The costing for these items was
Flooring $5,440
Curtains $1,500
Case No: 322249 Determination Page 20 of 31
70. This has not been paid. The payment will be made and divided between the
policyholders as instructed by FOS. Each party will receive $3,470.
The builder:
Floors sanded at joints.
The technical consultant:
Sanding of the floor had been completed across all joints to provide a
smooth transition. This item is complete as per the request.
Fixing of the flooring sheets has not been carried out as per the
builder’s report 65960.
Item 9: Pump.
The Applicant
71. The Applicant states the pump was in the possession of the contract
carpenter. It has not been returned to him or paid for, despite numerous
requests.
72. The pool pump and filter cartridge have been installed but it is unclear
whether it is operating.
73. The 70 mega-joule gas heater has not been supplied. The spa blower is part
of the pool operating system and he is unaware if it is operating.
74. No cover has been provided for the pool.
The FSP
75. The FSP states the Applicant had been offered ways for the pump to be
returned to him. However, the Applicant did not agree to these or pursue the
matter.
76. The pump has been taken to the site and witnessed by all parties attending.
The pump was placed in the bottom pot draw under the stove as instructed by
the mortgagee.
77. The electrical Safety Certificate was witnessed by all members on site.
78. The 70 mega-joule gas heater was not supplied as there is no gas connection
at the pool.
79. This was not purchased or included in the settlement as the Applicant
previously advised in a list of items that this was stolen by his wife. Items
taken by a policyholder are not classed as stolen.
80. Pool covers are excluded under the policy and the Applicant was advised of
this when the claim was lodged. The relevant policy wording states:
Section 1.12 page 30 of the PDS
Case No: 322249 Determination Page 21 of 31
“We will not pay for damage caused by storm, rain or flash flood to:
Spa or swimming pool covers, solar covers or plastic liners
Cleaning
The Applicant
81. The Applicant says the entire area has not been cleaned. It was being done at
the time of his visit on 5 January 2103 by an unknown person. This was 6
months after he was advised the work had been completed.
The FSP
82. The builder advised that all debris had been removed from the site at
completion. The site was free of debris at the time of the site visit on 7
February 2013.
The technical consultant
The cleaning was completed.
FSP’s response to other ma tters submitted by the Applicant
83. The FSP made the following comments in relation to other matters raised by
the Applicant which did not form part of the SOW.
Photograph depicting adjoining timber beams with bent nails protruding.
This was pre-existing damage with the veranda and was not within the
section of roof repairs carried out by the builder.
Photograph depicting roofing sheets with nails through the roof sheeting
missing the batten.
This was pre-existing original work with the veranda and not within the
section of roof repairs carried out by the builder.
Timber beam fixed on upright.
This was pre-existing original work with the veranda and not within the
section of roof repairs carried out by the builder.
Heater and flue, air conditioner.
The air conditioner was on site through the repairs.
The heater and flue was on site when the builder left the premises. It
was possible that it may have been removed in the clean up.
If these items were believed to have been stolen then the Applicant
should lodge a report with police and report it to the current insurer.
It is not responsible for these items.
Return of bond
A bond was paid by it for the Applicant’s temporary accommodation. The
agent had advised in writing the bond had been refunded to the
Case No: 322249 Determination Page 22 of 31
Applicant. The Applicant had been informed of this and advised he
would refund the payment to the FSP.
The bond repayment has not been received from the Applicant.
Malicious damage
Since the repairs were completed the property has been subject to
numerous incidents of malicious damage and vandalism including
windows and lights being smashed.
Sale of property
It has been advised the property has been unconditionally sold and as
such ceasing all the Applicant’s future involvement with the property.
Consideration of the evidence
84. The Applicant’s initial complaints followed his inspection of the property in
January 2013. The photographs submitted by him following that inspection
clearly show what appear to be areas of unsatisfactory construction.
85. The Applicant’s complaints were submitted to the FSP for its attention. As a
result the site inspection was carried out on 7 February 2103 attended by
representatives from the FSP, the builder, the specialist technical consultant,
the assessor and the Applicant. The site meeting was arranged to address the
Applicant’s concerns in relation to the agreed SOW to discharge the FSP’s
obligations pursuant to the FOS Determination issued in November 2011. The
substance of those works are listed in paragraph 4 of this Determination.
86. The Panel’s comments follow in relation to each item.
Item 2 Roof
87. According to the builder and specialist technical consultant, roof sheeting was
replaced according to the SOW. At the time of the inspection, the capping to
the ridge gable was cut short. However, this was to be rectified by the builder
within 2 days. According to the builder, this work was carried out and the roof
capping ends were sealed on 9 February 2013.
88. The roof over the veranda was not included in the SOW.
89. According to the FSP, photographs depicting beams which appear to be
poorly fitted, roof screws not screwed into battens/beams and beam poorly
fitted to upright form part of the veranda. This area was not included in the
works carried out by the builder and was pre-existing.
90. According to the 2011 Panel Determination the FSP had agreed to replace the
roof. As such, the Panel determined as the FSP had agreed to replace the
entire roof sheeting of the main dwelling, this part of the original dispute had
been resolved. (para 135)
Case No: 322249 Determination Page 23 of 31
91. The Panel has some difficulty understanding why the roof over the veranda
which forms part of the main dwelling was not included in the replacement of
the entire roof sheeting.
92. In the absence of any explanation to the contrary the Panel is of the opinion
that the veranda roof formed part of the November 2011 Determination and as
such the Applicant was entitled to have this area of the roof sheeting replaced.
The November 2011 Determination provided that in the event that this work
required removal and replacement of undamaged items, then the SOW is to
include the removal and replacement of these items. This did not include the
bathroom.
Item 5 Internal
93. The November 2011 determination required the FSP to rectify cracks in the
walls above the windows and doors. The SOW is consistent with the
determination.
94. According to the evidence the cracks observed were repaired. In addition the
missing cornice in bedroom 2 was fitted and the hanging vent secured.
95. The November 2011 Determination did not require the FSP to rectify damage
to doors.
96. Accordingly the Panel accepts the FSP has complied with the Determination
in relation to these items.
Item 6 Shower
97. The November 2011 Determination found that the FSP was liable for 50% of
the cost to reinstate the shower base and unit.
98. The FSP advised the Applicant and his wife were asked to contribute 50% of
the cost to repair this damage while the builder was on site, being the sum of
$960. Neither party contributed to the cost. Accordingly the FSP paid the sum
of $960 to the mortgagee account.
99. The Panel is satisfied that the FSP has discharged its obligations pursuant to
the November 2011 Determination and is not responsible for the cost of
rectifying the shower base or unit.
Item 8 Floor
100. The FSP acknowledged the carpets and curtains had not been replaced. The
FSP has since assessed the replacement cost for both the carpet and curtains
in the sum of $6,940. The payment will be divided equally between the named
insureds (the Applicant and his estranged wife) so that each will receive
$3,470.
101. The Panel is satisfied payment for these items discharges the FSP’s
responsibility to replace the carpets and curtains. As the policy vests in joint
Case No: 322249 Determination Page 24 of 31
names, 50% payment to each party discharges the FSP’s obligations in
relation to these items.
102. The November 2011 Determination required the FSP to rectify all the flooring
apart from that area near the end of the wall in the living room. This involved
sanding only and not replacement.
103. According to the evidence the floors have been sanded at the joints to make a
smooth transition.
104. The FSP was not required to rectify the condition of the flooring other than by
sanding. As such, the condition of the flooring observed by the Applicant did
not form part of the works ordered by FOS.
105. Accordingly the Panel is satisfied the FSP has complied with the November
2011 Determination in relation to the flooring.
Pump – pool cover
106. The November 2011 Determination required the FSP to arrange for the return
of the missing pump which was reportedly in the possession of the contractor.
107. The FSP advised the pump has since been returned to the site and placed in
the bottom pot draw under the stove. This was on instruction from the
mortgagee.
108. The Panel accepts that this item has now been resolved.
109. The FSP states the 70 mega-joule gas heater was not supplied as there was
no gas fitting at the pool.
110. Nevertheless, the Applicant was entitled to have the item replaced
notwithstanding it may not have been made operational.
111. The Panel therefore considers the FSP is liable for the cost of this item.
112. The policy does not cover storm damage to pool covers. The Panel is
therefore satisfied the FSP is not liable for this item.
Cleaning
113. According to the contractor and the technical consultant the site has been
cleared of all bu ilder’s debris.
114. Accordingly the Panel is satisfied this matter has been resolved.
Other matters (including Applicant’s email 30.4.13)
115. The Applicant raised other issues which were not part of the November 2011
Determination. The Applicant refers to the SOW “issued firstly” which the
Panel concludes is the SOW prepared prior to the initial dispute arising and
subsequent referral to FOS.
Case No: 322249 Determination Page 25 of 31
116. As a dispute arose in relation to the claim, the Panel is conscious of the fact
that the FSP at that time had not necessarily accepted all the damage claimed
was covered by the policy. As such, the initial SOW may not be an accurate
reflection of the items for which the FSP accepted responsibility.
117. The Panel does not have copy of this document. However, in the interest of
fairness and in order to bring this matter to a close, the Panel will consider
these items according to the evidence available to it, subject to them not
having been considered in the November 2011 Determination.
Heater/flue – Air conditioner
118. The Applicant says the hearth and heater had been removed and the roof
over the flue was repaired and closed.
119. The FSP asserts the heater, flue and air conditioner were on site during the
time the builders were onsite.
120. It is common ground between the parties that the property was left
unoccupied from June 2012 until it was sold in February 2013.
121. The policy does not cover loss arising from theft when the property is
unoccupied for 60 days or more. Further the Applicant cancelled the policy
effective 19 December 2012. As the date of the loss is unknown and theft
from an unoccupied property is not covered in the event these items were
stolen the policy will not respond.
122. Based on the available material the Panel concludes the FSP is not liable for
the cost of these items.
Security
123. The Applicant states that according to the SOW the builder was to protect the
site during construction by using temporary fencing or hoardings.
124. The Applicant says this was not carried out and therefore the FSP is
responsible for the cost of these missing items.
125. Nevertheless, it has been established the property was unoccupied from
about June 2012 when the Applicant was advised repairs had been completed
until it was sold in February 2013. From the time the Applicant was informed
the repairs had been completed, the care and control of the property became
his responsibility. Hence security from that time was to his account.
126. As the property was unoccupied for more than 60 days no cover is provided
under the policy for missing items.
127. In the absence of any substantive evidence to show when the items became
missing, the Panel is satisfied the FSP has no liability for these missing items.
Case No: 322249 Determination Page 26 of 31
External work
128. The Applicant referred to the initial SOW issued to repair the damage to
argue his case in the following matters.
Shade cloth
129. The Applicant says shade cloth over the frame work at the western end of the
house has not been touched.
130. Items 6 of the initial SOW provided for replacement of all previously removed
shade cloth to the shade house.
131. The November 2011 Determination at paragraph 192 notes the FSP is
responsible for rectifying the greenhouse, which included shade cloth.
132. The Panel has not been provided with any evidence to the contrary and
accordingly is of the opinion that this item remains outstanding.
General demolition
133. The Applicant states the SOW provides for removal and dumping of the
remainder of carpet in the master bedroom/study.
134. The Applicant says carpet remains in the main bedroom and office. He further
says he asked the carpet provider to not proceed at the time as the floor had
not been touched.
135. The Panel has not been provided with any evidence to the contrary.
136. In this case the Panel accepts that this element of the initial SOW has not
been carried out.
Internal works
137. The Applicant refers to eight items in the initial SOW under this heading. As
there has been an exchange of material the detail will not be recited in this
Determination. However, the items to a large extent refer to fixing flooring,
supply of a new door to the master bedroom, re-fixing of all panelling, supply
new architraves, supply of small edged cover batten to all vertical joints in
panelling above window and door openings.
138. The Applicant asserts that not one of these items has been completed in
particular the flooring has not been prepared for installing of floor coverings.
139. However, according to the reports following the site inspection on 7 February
2013, the flooring was sanded to allow for smooth joints. Additionally all
cracks observed in the wall had been sealed and a 4th architrave had been
fixed in the bedroom.
140. The November 2011 Determination did not require the FSP to repair/replace
doors.
Case No: 322249 Determination Page 27 of 31
141. It is therefore unclear to the Panel which of the eight SOW items remain
uncompleted and it is unable to find for the Applicant on this aspect.
External wall modifications
142. The Applicant refers to five items on the initial SOW. Again these will not be
recited in the Determination. However, item 1 states that due to the sub-
standard construction method chosen when building the veranda to the
perimeter of the dwelling a major modification is required.
143. According to the reports following the February 2013 site inspection no work
was carried out to the veranda.
144. The November 2011 Determination considered the Applicant’s com plaint in
relation to the veranda flooring and determined the FSP was not responsible
for rectifying this.
145. Based on the available material the Panel concludes the FSP was not
responsible for rectifying the condition of the veranda apart from replacing the
roof.
146. The Applicant says the new gutter put in place along one section had fallen
off. Photographs submitted by him appear to show guttering having partially
detached from the wall.
147. The Panel therefore concludes that the guttering work was not carried out
satisfactorily.
Ceilings
148. The Applicant refers to 5 items in the initial SOW under this heading.
149. The Applicant says the ceiling replaced does not conform to BCA standards.
Old ceilings remain in the main bedroom, en suite, walk in robe and ceiling in
the office area.
150. However, examination of the 5 items reveal no item in the SOW states,
replacement of ceilings is required other than those that have previously been
removed.
151. The Panel is therefore not persuaded the rectification works for these items do
not comply with the initial SOW.
Slow combustion stove
152. The Applicant refers to three items on the initial SOW which involve retiling to
the hearth around the fireplace.
153. The Applicant says the hearth and brickwork have been removed leaving the
area clean to make it look like nothing had been there before.
Case No: 322249 Determination Page 28 of 31
154. He says the slow combustion stove was removed from the property by the
builder.
155. The November 2011 determination refers to stove covers. As such the Panel
accepts that a slow combustion stove was present in the house at the time of
the storm.
156. The reports following the February 2013 site visit are silent in relation to the
stove.
157. In these circumstances the Panel concludes the stove has not been returned
to the home and the Applicant is entitled to recover the cost of the stove.
Inclusion of the Applicant’s estranged wife on the policy.
158. The Applicant argues that the policy should vest in his name only. He has
submitted substantial arguments in support of his case in this regard.
159. However, this issue was considered in the previous dispute brought by the
Applicant to FOS. In the November 2011 Determination, the Panel found the
FSP was entitled to assess the loss based on the policy vesting in the joint
names of the Applicant and his estranged wife.
160. The Panel’s rea sons for this finding are found in paragraphs 101 to 118 of the
November 2011 Determination.
161. The Panel has carefully considered the arguments put forward by the
Applicant on this occasion. However, the Panel is not persuaded that any new
information has been presented to alter the 2011 finding.
162. The Applicant refers to the clause which excludes cover for a loss under
Section 1 of the policy when the property is unoccupied for 60 consecutive
days or more. This policy condition is a condition which excludes cover from
benefits which are otherwise payable under the policy. It has no relevance to
the named insureds.
163. Accordingly based on the available material the Panel considers any
settlement of the claim should include the Applicant’s estranged wife.
Applican t’s request for settlement of the claim
164. The Applicant states the FSP acted with malice to ensure the property could
not be sold for a fair price or for the pre storm value thus causing him
significant loss.
165. The Applicant calculated his loss as follows:
Pre storm valuation $430,000
Contents lost $150,000
Expenses incurred $30,000
Health loss $500,000
Case No: 322249 Determination Page 29 of 31
Payment of sums insured
166. The Applicant argues that due to the FSP’s management of the claim, he is
entitled to payment for the full sum insured of the building, namely $300,000
and the contents at $150,000.
167. The Panel does not accept this argument. The damage to the home caused
by the storm was assessed as repairable and within the sums insured.
Although a dispute arose in relation to the extent and standard of repairs, the
cost of rectifying those repairs did not render the home a total loss.
168. The Panel is therefore satisfied the Applicant is not entitled to payment of the
sums insured as asserted by him.
Payment for loss of value following sale of the property
169. The Applicant also considers any loss arising from the sale of his home,
compared with its alleged pre storm valuation, should be paid to him.
170. It has been established the damage was repairable and in the main, the
disputed items were rectified prior to the sale.
171. Moreover, prices achieved for the sale of a property would have reflected the
market conditions at that time. These fluctuate from time to time, depending
on many factors.
172. For these reasons the Panel does not accept that Applicant has established
an entitlement to compensation payments, in respect of any alleged
diminution in value, following the sale of his property.
Compensation for his time in submitting his claim
173. The Applicant seeks compensation for the two years the FSP has been
unable to repair the home. He estimates the time taken by him in preparing
submissions, statements and photographs is about 200 hours. As an
investigator, he received $35/hour (email 19/12 February 2013). By email
dated 13 March 12013 the Applicant increased the estimated number of hours
worked by him to 500. The Applicant further claimed he is entitled to travel
costs from Thailand to Perth and two weeks accommodation while in Perth.
174. The Panel is governed by the FOS Terms of Reference Operational
Guidelines. The Terms of Reference do not provide that FOS may
compensate a policyholder for the time taken in submitting a claim.
175. In these circumstances the Panel is not empowered to award such
compensation to the Applicant for his preparation costs incurred by him in
prosecuting his dispute.
Compensation for stress and depression
176. The Applicant also claims he suffered stress and depression arising from the
FSP’s management of the claim and is seeking compensation for this. The
Case No: 322249 Determination Page 30 of 31
Applicant says he is under the care of a doctor for these conditions and has
provided the doctor’s details. The Applicant says he is receiving treatment
with anti-depression medication.
177. However, there is insufficient evidence to show that the Applicant’s stress and
depression resulted from the management of this claim.
178. Further, from the evidence submitted, the Applicant has moved overseas to
take up residence and was absent from Australia for 12 months during the
period of the claim.
179. The Panel considers the FOS Terms of Reference relevant to this dispute are:
“9.3 Other compensation
a) ...
b) Subject to paragraphs 9.3 c) and 9.7, FOS may decide that the Financial
Services provider compensate the Applicant for non-financial loss but only
where:
(i) an unusual degree or extent of physical inconvenience, time taken to
resolve the situation or interference with the Applicant’s expectation of
enjoyment or peace of mind has occurred, or
(ii)...
The maximum amount of compensation for non-financial loss will be $3,000
per claim made in the Dispute.”
180. Having regard to all the circumstances involved in this matter since the loss
occurred in January 2011, there is no compelling evidence that the Applicant
has been unduly inconvenienced by the FSP’s management, rather, the
Applicant appears to have settled elsewhere at his own volition. The Panel is
not persuaded that the circumstances in this matter are such that the
Applicant is entitled to compensation under this head.
Summary
181. It has been established to the Panel’s sati sfaction that a number of items have
not been rectified or reinstated in accordance with the terms of the policy.
These include the veranda roof, the shade cloth, carpet in the main bedroom,
guttering, slow combustion stove and the 70 mega-joule gas heater.
182. The property has been sold so that it is now not possible to have these items
repaired or replaced. In this case the Panel considers having regard to the
period of time since the loss occurred in January 2011 and in order to bring
finality to the claim that a cash payment be made in satisfaction of the
outstanding items.
183. There is insufficient evidence available to determine the value of the
outstanding items and therefore in establishing an appropriate value the Panel
is inclined to rely on its remit to do what is fair in all the circumstances. Having
noted the outstanding items above, the Panel considers that a payment in the
sum of $10,000 is fair in all the circumstances.
Case No: 322249 Determination Page 31 of 31
184. As the property was mortgaged and sold by the mortgagee in possession, any
payment to the Applicant may need to be approved by the mortgagee.
Further, the Panel notes all net monies payable to the Applicant are to be
shared equally with his estranged wife as a joint insured.
185. The evidence in relation to repayment of the bond is contradictory. The FSP
says it was informed by the Applicant that the bond had been returned to him
by the agent. On the other hand the Applicant says the FSP had deducted the
bond from a payment made to him.
186. In the circumstances, and in the absence of any clear evidence, the Panel
determines that the FSP is not entitled to recover that money.
Determination
187. On the basis of the available information the Panel determines:
a. the Applicant’s estranged wife is a named insured under the policy and
the FSP is entitled to settle the claim accordingly.
b. the FSP is to pay the Applicant the sum of $10,000 in full and final
settlement of the claim.
c. the FSP is not entitled to deduct any amount for the bond money.
d. on acceptance of this Determination by the Applicant within 30 days,
the FSP is to pay the sum of $10,000 within 5 working days.
e. Payment of this amount is sufficient to discharge the FSP’s obligations
for this claim.