Delays in storm damage repairs and lost rental income claim

FirmFinancial Firm (Unknown - Insurer)
Decided2014-01-31
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$3,000
Non-financial loss$3,000
Amount claimed$215,992
SourceAFCA PDF

Summary

After two storm claims, the Applicants said delays by the FSP and its contractor stopped them renting out the home and led to mortgage arrears, and they sought $214,287 in lost rent. AFCA found the home remained fit to live in, so the lost rent benefit did not apply, but ordered $3,000 non-financial loss and $3,000 consequential loss for the delays.

The out-of-pocket lost rent benefit requires the home to be unfit to live in, which was not met, while compensation under FOS Terms of Reference 9.3 was available for unusual delays attributable to the FSP.

Issues

Subjects and remedies

financial hardshiphome or building damagepay compensationpay non financial loss

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 321469 Determination Page 1 of 19 Case number: 321469 General Insurance - Domestic Insurance - Home Insurance - FSP Decision - Denial of Claim - Lost Rental Income - Compensation 4 November 2013 Background 1. The Applicants hold a home building insurance policy with the Financial Services Provider (FSP). The policy was incepted on 5 March 2007, renewed annually and was current at the time of the losses occurring. 2. On 17 March 2010 a claim was made that the property was damaged by rain and hail during a storm event on 6 March 2010. The Applicants lodged a claim with the FSP for the damage sustained. The property was again damaged by a storm on 4 February 2011, with a second claim lodged for damages on 10 February 2011. The FSP accepted both claims and arranged for repairs to be undertaken by „ J ‟ . 3. The Applicants say the FSP overly delayed the commencement of repairs and unnecessarily prolonged the claim leading the Applicants being unable to rent the property out as planned. The Applicants are seeking lost rental income of $214,287, which does not include interest. 4. They also seek $172.22 for door hardware and $1,533 for computer problems as a result of the work done by J. Summary of Applicants ’ position 5. The Applicants say at the time of the first claim occurring, they were in the process of arranging to rent their property. However, they were unable to do so due to the delays caused by the FSP in commencing and completing repairs. When this was finally resolved, the second claim occurred leading to further delays in tenanting the home as planned. 6. The Applicants say ultimately, it took over two years for the repairs to be completed to a standard where they were able to finally rent the property out, causing them severe financial hardship as a result. They say they are now being forced to sell the property due to the FSP‟s inaction. 7. The Applicants consider that as a minimum they are entitled to a settlement of $48,000, representing the period from November 2011 to April 2012, when they had vacated the premises and signed a rental agreement on a Determination Case No: 321469 Determination Page 2 of 19 property elsewhere, in anticipation of the completion of the repairs. However, they consider the true reflection of their loss is the figure of $214,287 as this reflects the rental income they would have been able to realise had the property been rented from March 2010 onwards. 8. The Applicants say had they been able to rent the property earlier, they would not have experienced financial hardship and would not be in arrears with their home loan. Their bank has started re-possession proceedings against them. They are seeking the lost rental income in order to alleviate their financial hardship. The Applicants believe their bank „ B ‟ and the FSP are affiliated. Summary of FSP’s position 9. The FSP says the Applicants are not entitled to be paid the loss of rental income benefit under the terms of the policy. The FSP says the property was not an investment or rental property but was the Applicants‟ residence. Therefore, the loss of rental benefit does not apply as the property was not tenanted nor was there any evidence supplied to suggest the Applicants had made arrangements for this to occur when the damage arose. 10. Further, the property remained fit to live in through both the period before repairs commenced and whilst repairs were undertaken, with one short exception of three weeks whilst the floors were repaired. The FSP has paid the Applicants for three weeks temporary accommodation in respect of this period and considers this is the extent of their liability under the policy. 11. The FSP denies it overly delayed either the commencement of repairs or the handling of the claim. The FSP says whilst there were delays experienced, these are attributable to the Applicants and non-claim related repairs outside of the scope of the claim. The FSP considers it handled the claim and repairs in a timely manner. 12. The policy is one that specifically lists the events for which cover is provided. Storm is covered by the policy and the FSP accepts the Applicants have established a prima facie claim. 13. The FSP contends the policy specifically outlines the circumstances when loss of rent will be paid. The FSP says the policy is clear and unambiguous and states that the policy cover is limited to loss of rent for homes rented out at the time of loss or if the insured can show they would have leased the home during the time taken to repair the damage and if they can show the damage to the home means that the property was not fit to live in. 14. The FSP notes the Applica nts‟ contentions but say that the material from H does not support their claim; that the Applicants have provided no documentation which supports their assertion that the home would have been leased during the period repairs were underway; and that on the completion of repairs the Applicants have been unable to lease the home until September 2012. Case No: 321469 Determination Page 3 of 19 15. The FSP contends the Applicants have not provided any evidence of a possible tenant interested in renting the property up until then. 16. The Applicants have not suffered a loss as they continued to live in the home while the repairs were undertaken. 17. As for the quantum of the claim, the FSP requires a professional appraisal to be conducted to assess it. 18. Loss of rent is not payable after the completion of repairs as a ny loss due to “missing the market for high end properties” is consequential loss and excluded under the policy. 19. As for the claims for $172.22 for door hardware and $1,533 (the Applicants had claimed $533 originally) for IT and computer problems as a result of the work done by J, the FSP says it does not have a record of those invoices and asks the Applicants provide a copy for further consideration. 20. The FSP relies on the following policy provision, which the Applicants do not dispute receiving: “ Insured events You can only claim for loss or damage to your home, contents or both, if it is caused by one or more of the 11 insured events as described under “What w e cover” below .  What we do cover We will pay you for loss or damage to your home, contents or both caused by:  1. storm , rain or flood ... Related expenses – additional protection When you insure your home or contents , or both with us under this policy, we will also insure you for up to 15 types of related expenses – additional protection as set out below. Any amount we may pay you for related expenses is in addition to any amount we pay you as your sum insured . ...  4. Out-of-pocket expenses If you have insured your home and we agree to pay a claim under this policy, and the loss or damage to your house means that it is not fit to live in, we will pay these out-of-pocket expenses for you: ▼ Temporary accommodation If you own and live in your house at the time of the loss or damage , we will pay for the reasonable cost of temporary, similar accommodation while your house is being replaced, rebuilt or repaired. Please remember , that we will only pay for reasonable costs that you actually incur. ▼ Lost rent If you: Case No: 321469 Determination Page 4 of 19  lease out your home at the time of the loss or damage, or  can show that you would have leased your home out during the period reasonably necessary to replace, rebuild or repair it, then we will pay you: ▼ the actual rent you lose, or ▼ the rent you show us you would have lost, while your home is being replaced, rebuilt or repaired. We will pay these out of pocket expenses;  for up to 12 months from the time of the loss or damage , or  for all reasonable time taken to replace, rebuild or repair your home , whichever is shorter.” Issues 21. As a result of delays in repairs being finalised, are the Applicants entitled to the out of pocket expenses benefit under the terms of the policy? 22. Are the Applicants entitled to compensation for financial or non-financial loss under the Terms of Reference? Reasons for decision 23. Due to the nature of this dispute, FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. This dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. The parties have been previously advised that a Determination will be issued in this case. 24. I am satisfied a full exchange of information has taken place between the parties and each party has had the opportunity to address any issues raised. 25. Each FOS case is decided on its merits, taking into account the facts of the case. I have carefully reviewed all the material submitted by the parties in order to reach my decision. I will only refer to the relevant submissions and materials raised. 26. It is not disputed the Applicants suffered a loss from a risk insured against or that the FSP accepted the claims and undertook repairs. However, a dispute has arisen regarding the Applicants‟ entitlement to claim for lost rental income under the terms of the policy. 27. It is an accepted principle of general insurance law that an insured bears the onus to establish, on the balance or probabilities, that the insured has suffered a loss caused by an event to which the policy responds. This is known as a prima facie claim. Case No: 321469 Determination Page 5 of 19 28. Once so established, the onus shifts to the insurer to prove on the balance of probabilities that an exclusion applies, if it wishes to deny or limit its liability for the loss. 29. In this matter, the Applicant must prove that they have suffered a loss to which the policy responds. That is, that they have lost rent as provided for in the policy. The out of pocket expenses benefit. 30. For the policy to respond the Applicants must establish the following:  The related expense is the result of an insured event occurring during the period of insurance  The related expenses is not excluded in the relevant section or generally  The related expenses is connected to the home and the home is insured  The loss or damage to the house means it is not fit to live in  The home was leased out at the time of the loss or damage or  The Applicants can show that they would have leased the home out during the period reasonably necessary to replace, rebuild or repair it. 31. The policy sets out what the FSP will pay for these out of pocket expenses and also provides that the FSP will not pay for lost rent any more than an amount equal to 20% of the building sum insured. The building sum insured was $543,000 so the maximum payable under that policy limitation is $108,600. 32. The first three dot points above are not in dispute. Nor is it in dispute that the home was not leased out at the time of the losses. 33. Rather the property in question was the Applicants‟ family home. They lived there at the time of both losses occurring. The Applica nts mostly remained in residence throughout although the Applicants say the children lived mainly in another leased property after November 2011. 34. What is in dispute is whether the house was fit to live in and whether the Applicants can show they would have leased the home out during the period it was being repaired. 35. The Applicants say the home was not really fit to live in while works were being carried out from 5 January 2012 to 16 March 2012 but even if it was, it was not fit to rent. They say the works were mostly completed on 16 March 2012 and the house opened for inspection the next day. Final works were completed by 25 May 2012. They say they made arrangements to live elsewhere and signed a lease for another place to live on 9 November 2011. A copy of the first page of a lease is referred to in a letter to the FSP dated 8 Case No: 321469 Determination Page 6 of 19 May 2012. They say the children primarily lived there and lived between the two places. 36. Having considered all the evidence, I am satisfied the property remained fit to live in after the storm damage and during both the time before repairs commenced and for the duration of repairs, excepting one period where the floorboard repairs were undertaken. The FSP has paid temporary accommodation to the Applicants in respect of that period, which is currently not in dispute. 37. I note the final invoice from J was in the amount of $17,890 for the first claim and $10,335 for the second claim, suggesting the claim related repairs to the home were not overly significant in nature and adds weight to the F SP‟s contention the property remained fit to live in throughout the relevant periods. No compelling evidence from the Applicants suggesting otherwise has been presented. 38. I have also considered the work done that made up the invoices and the nature of the work done by J and I remain of the view the house was fit to live in at all relevant times. I agree that the damage done and works necessary to repair the damage would have resulted in making it difficult to rent the home out to tenants but that is not the test. The policy only provides this additional protection if the house is not fit to live in. In my view the policy is clear and unambiguous in this regard. 39. Accordingly, I am of the opinion then the Applicants‟ claim for the out of pocket expenses benefit fails at this first hurdle, but I will go on to consider what happened and the attempts to rent the home as this is relevant to my consideration as to whether compensation is otherwise payable to the Applicants by the FSP under the Terms of Reference. Compensation under the Terms of Reference 40. Whilst I accept the FSP has fulfilled its obligations to the Applicants pursuant to the terms of the policy, this does not preclude me from considering whether the Applicants are entitled to compensation pursuant to the FOS Terms of Reference 9.3. 41. I am able to compensate the Applicants for consequential financial loss up to a maximum amount of $3,000 per claim made in the Dispute. 42. I am also able to compensate the Applicants for non-financial loss up to a maximum amount of $3,000 per claim made in the Dispute. 43. The FOS Terms of Reference (the Terns) relevant to this dispute are: “ 9.3 Other compensation a) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for consequential financial loss or damage up to a maximum amount of $3,000 per claim made in the Dispute. Case No: 321469 Determination Page 7 of 19 b) Subject to paragraph 9.3 c) and paragraph 9.7, FOS may decide that the Financial Services Provider compensate the Applicant for non- financial loss but only where: (i) an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant‟s expectation of enjoyment or peace of mind has occurred; or ... The maximum amount of compensation for non-financial loss will be $3,000 per claim made in the Dispute. c) Notwithstanding paragraphs 9.3 a) and b), FOS will not provide compensation for: (i) consequential financial loss; or (ii) non-financial loss, In a Dispute arising as a result of a claim on a General Insurance Policy that expressly excludes such liability. ” 44. The FSP has provided various reports from J, numerous letters and emails and its claims messages enquiry screens. The Applicants have also provided a great deal of material. I am of the view that a chronology is helpful in this decision. I note from the material that:  December 2009 the Applicants claim they engaged „ H ‟ to sell or rent the home.  6.03.10 storm damage to the home but the Applicants say the work to be done by the FSP is delayed as floods in Queensland overwhelmed the FSP.  19.3.10 J appointed.  26.3.10 the FSP resent request to J as insured called, as she had not heard from J. J did not answer phone.  31.8.10 FSP resent request to J as insured called, as she had not heard from J. J said had not received documentation from FSP.  3.9.10 and 14.9.10 a site visit took place to inspect damage to the kitchen ceiling and external damage to the first floor. The assessor asked for a roofing contractor to confirm the cause of the water entry. A revised scope of works was provided regarding the lounge, kitchen, upstairs toilet and rear yard in the new total amount of $6,840.  4.10.10 a site visit took place to inspect water damage but J could not attribute the claimed damage to hailstones associated with the storm on 6.3.10.J concluded the hail damaged 3 window frames and that paving (about 20msq metres) had started to subside. Estimated cost of repairs was $2,890.  18.10.10 Applicants told J will be authorised to proceed with repairs. Discussion re cash settlement of painting. Case No: 321469 Determination Page 8 of 19  15.11.10 email indicates that a roof inspection was to take place by a third party contractor. A cash settlement for all painting works was agreed at $3,550.  24.11.10 email indicates J re attended 2.11.2010 to report and quote on damage to the kitchen.  24.11.10 email indicates cash settlement for the paving works would be $680 inc GST  13.12.10 email indicates cash settlement to remove and relay the pavers would be $1,300 inc GST  10.12.10 letter from CR the roofer indicated no storm damage to the roof but a failure at installation.  24.12.10 Applicants advised.  11.1.11 SOW submitted by J to the Applicants.  2.2.11 email from the Applicants indicated various issues with the scope of works (SOW).  7.2.11 email from the Applicants confirms issues with the SOW, which the Applicants wanted to sign urgently so work could start. He also reported other various issues. He noted that there was a storm on 4.2.11 and excess water flowed off the south corner of the roof and that and heavy rain flowed into the courtyard and as the paving had not been fixed, water began entering the house. He notes a window broke in the storm too and water came in the window and damaged the work done by the painters. He says CR needs to re attend to inspect the entire roof.  Job request sent to J on 10.2.11 and re sent on 17.2.11.  10.2.11 email from J revised the quote slightly to include some paintwork.  10.2.11 J was authorised by the FSP to proceed with the works. He replied he would once he had the signed authority from the FSP.  15.3.11 J reported he had attended to report on the damage as a result of the second claim. He said both claims should be considered together. He reassessed the damage at $8,400 to the rear yard and he also suggested 10 square metres of paving had dropped and noted estimated cost of repairs to the rear yard paving to be $2,980. The total of the variation to the SOW was $11,380. However he also recommended cash settlement as he said that current drainage issues will cause for wood rot to reappear and further damage the paving. He said the insured is advised to install storm water drainage across the back of the property to ensure no ongoing damage to the claimed areas. He estimated this cost to be $2,000.  15.3.11 J wrote a separate report under the new claim number. He recommended denial of the claim as he noted long term water damage at or near the back door due to poor design and he was concerned the Case No: 321469 Determination Page 9 of 19 drainage to the rear paved area was inadequate. The SOW to the rear living room and kitchen was $5,370.  6.4.11 an email from J to the FSP notes the insured asked that internal repairs begin 2.5.11. As for the rear yard repairs, he said a cash settlement should be $5,960 but that the drainage should be upgraded first.  6.4 11 and 11.4.11 the drainage situation was explained to the female Applicant in phone calls.  14.4.11 an email from the FSP says: “I will follow up with (J) the SOW for drainage also as this rectification work needs to be completed prior to repairing resulting damage”.  11.5.11 J amended the SOW to include work to the upstairs toilet and adjusted the work to the kitchen at $6,400.  13.5.11 J amended the SOW again - noting works to be carried out in conjunction with repairs for the first claim.  16.5.11 the Applicants sent back the SOW with amendments. She concerned that damage to the walls might reoccur.  24.5.11 the Applicants made some changes to the SOW because of the interaction of the two claims. She also wanted to investigate the rising damp.  30.5.11 the FSP asked J to keep the scopes separate and authorised the investigation of the rising damp on the scope. J was asked to commence repairs as soon as possible once the SOW were finalised and signed.  14.6.11 revised scope of works received from Applicants and J emailed to proceed with works  29.6.11 J emailed to say the insured delayed the repairs until after the school holidays (27.7.11) and that a quote was provided for the drainage works.  5.8.11 J emailed to report he had attended the site to confirm J could implement the new storm drainage system with the insured. He noted the insured wanted the repairs to begin mid to late September due to multiple skiing commitments. It was agreed to carry out the external repairs first and then internal repairs and flooring last.  19.9.11 the FSP emailed J to see if the repairs had commenced.  September 2011 H says the Applicants now accepted they would not get the “hope” sale price and H agreed to rent the property.  18.10.11 marketing documentation signed with H.  Early to mid November 2011, H says there is intention to have the property leased by then.  November 2011 the Applicants received letters from their Bank advising their line of credit was over the limit. Case No: 321469 Determination Page 10 of 19  6.1.12 the FSP emailed J to see if the repairs had commenced and called the female Applicant.  7.1.12 email from J to advise repairs had started.  11.1.12 file note indicated delay is because of the insured‟s private works.  12.1.12 file note that works will be finished in 4 weeks but was delayed, as the insured has still not selected the metal drainage gate.  6.2.12 the real estate agent H emailed the Applicants to advise that the best time to rent the property is in the January to February time period and the high end tenants will have found property by March. He noted the property will rent out in this market for $1,500 per week.  9.2.12 file note says J advised the only outstanding works was the front pavers and the flooring.  9.2.12 file note - the insured is not happy with the repairs and the time taken.  13.2.12 email from J headed complaint. J summarised that J could not proceed with any further repairs until the insured had “their repairs responsibility completed.” The outstanding matters were the rear yard paving, painting the first floor windows and floor sanding. The insured had some additional matters too not on the SOW.  J and the Applicants were negotiating over the price of the drainage (it appears the Applicants offered $2,400) but on 27.2.11 J sent a tax invoice to the Applicants to install the drainage system in the rear paved courtyard at a cost of $2,500.  28.2.12 J reported the floor/painting/contents would be completed on 6.3. 12 and he said “this allows new tenants to move into the property at any stage from t his time onwards.”  2.3.12 file note shows dispute re quality of work and the insured has still not paid the deposit for the drainage work. J wants it cash settled.  7.3.12 an email from the Applicants to the FSP indicates a claim against J for alleged damage and for refusing to do the drainage works.  7.3.12 a further email details the claims against J and notes “please note we have wanted to rent out our home since December 2011 but have been waiting for the works to be completed. We are losing rent of $1,6 50 per week...”  7.3.12 J advised the FSP that as the deposit was not received that J was withdrawing the quotation “as this has been ongoing for well over 6 months.” J recommended a cash settlement of $2,980 for the paving and acknowledged the claims by the Applicants but wanted official invoices from them.  15.3.12 the FSP advised the Applicants that part of the claim would be cash settled and asked for more information about the “outstanding items.” Case No: 321469 Determination Page 11 of 19  19.3.12 the Applicants wrote to the FSP noting issues with the paving and the drainage, the front paving and damaged rendering and other sundry complaints. The Applicants said they left the house on 21.2.12 while the floorboards were done but the front paving was not completed until 16 March 2012.  17 March 2012 first open for inspection.  21.3.12 email from the Applicants indicated an “open for inspection this Saturday.”  21.3.12 file note notes that the insured has not secured a contractor to do the drainage works. J was dealing with complaints of the insured about rectifying works.  22.3.12 the FSP advised the Applicants by letter the circumstances regarding the paving and drainage issue and confirmed it was entitled to make this cash settlement. It also noted temporary accommodation was paid until 6 March 2012 in the amount of $3000 for 3 weeks. It is noted J has advised the property was habitable on 6 March 2012. As for the other issues concerning alleged damage done by J, J was to contact the Applicants.  27.3.12 the Applicants asked about quotes for the paving as they were arranging quotes for paving and drainage.  16.4.12 the Applicants advised the FSP that J had not contacted her and work was still incomplete. The last work was the front paving completed on 19.3.12. The Applicants also made the claim for lost rent noting they wanted to rent out the property since November 2011 and they had signed a lease on another property in about October 2011. She indicated the rent would have been $1,500 in the peak period but was now $1,350. She claims 5 months lost rent.  24.4.12 the FSP confirmed its decision that it can cash settle the cost of paving.  1 May 2012 the Applicants made claim for lost rent claiming $43,264 but said they would accept $25,000. I note from that claim: i. 1 July 2011 signed SOW with J ii. Works would start 1.9.11 and take 8 weeks iii. The property should have been rented by 1 December 2011 at $1,500 per week iv. The works began January 2012 and were mos tly completed by 16 March 2012 v. There are still some issues with the works impacting on the amount for rental vi. They decided to rent the house in October 2011 due to financial crisis with someone to move in by 1 December 2011 at the latest vii. 9.11.11 signed a lease for another apartment viii. H told them they could get $1,500 per week in the peak periods Case No: 321469 Determination Page 12 of 19 ix. They missed the peak period and now cannot rent the home even though the rent is lowered to $1,295 per week.  3.5.12 an offer was made to cash settle the quote from LL to do rear paving, as J was not prepared to do it.  3.5.12 the FSP denied the claim for lost rent, as the property was fit to live in.  4.5.12 the Applicants advised they would accept $7,987.21 inclusive of GST for work to be done by LL for paving and drainage. Work was likely to start in September 2012 because of the weather and LL‟s backlog. A cheque was sent to the Applicants on 7.5.12.  8.5 12 the Applicants asked for the decision of the FSP re lost rent to be reviewed. They said the house was not fit to live in for tenants and otherwise essentially re iterated their position.  5.6.12 the FSP denied the claim for lost rent as on 4 February 2011 as the Applicants did not intend to rent out the property.  8.6.12 conversation with J is noted as all work from SOW now completed and all rectifications done.  12.6.12 the Applicants asserted the majority of the storm damage occurred in the first claim yet the repairs did not begin until January 2012. They relied on H to establish an intention to rent or sell the property in December 2009.  27.8.12 J invoiced the FSP $10,335 and $17,890 for labour and materials as per SOW‟s.  August 2012 a tenant was secured for about $3,800 per month.  15 August 2013 the Applicants letter regarding the dispute with the Bank shows the following: i. The work were completed end May 2012 ii. 7 September 2012 tenancy for one year begins at $3,800 per month.  23.5.13, the Dispute Form to FOS encloses letters and asks for $48,000 for rent loss and $172.22 for door hardware and $1,533 for the computer problems. I note the disputes re the paving and drainage, the front paving and damaged rendering and painting were resolved on or about 25 May 2012.  23.05.13 letter to FOS calculates the rent loss from June 2010 to August 2013 at $214,287 not including interest. Calculations are included.  18.07.13 the Applicants say they would not have been in default to the Bank if the FSP had paid the rent loss or had fixed the damage to the home promptly.  14 August 2013 a letter from H is provided setting out the Applicants‟ dealings with H. Case No: 321469 Determination Page 13 of 19  4 and 8 October 2013 letters to FOS. I note many reiterations but I also note the following new assertions: i. The works were to be completed before July 2011 but the contractors were too busy and the works were delayed because of that and waiting for spring. ii. The property couldn‟t be liv ed in before 17 March 2012 as items couldn‟t be brought into the house as the front paving was not yet fixed iii. The main storm damage in March 2010 led to mould and other concerns.  12.10.13 auction of the property. 45. In support of their position, the Applicants have provided an email dated 6 February 2012 and a letter dated 14 August 2013 from the local real estate agent H who was assisting them in their endeavours to sell or tenant the property. H has provided the following statement in support of the Applican ts‟ case: “Please find below a summary of our correspondence/interactions over the years. 1) Dec 2009 – I visited your home in December 2009 as you wanted advise to either rent or sell your property in the New Year, due to the financial crises. I didn‟t think you could get your sales price so we discussed renting. In the end we agreed you would wait to see what the New Year would bring. (sic). 2) February 2010 – you called me back to see the property due to a significant tree which was going to be removed in a development behind your property as you wanted to know the impact it would have on the valuation of your property, we also spoke about the sale or rental of your property. 3) March 2010 – Storm damages your place – all your plans are put on hold for renting or selling the property. 4) May 2010 – I write a Statement of Evidence for your VCAT hearing with regard to the tree (attached). I then don‟t hear from you until September 2011. 5) September 2011 – You have accepted that you will not get the „hope‟ sale price and we agree to rent out your property. 6) October 2011 – On 19 th October 2011 marketing documentation was signed with us, with the intention of having the property leased by early to mid-November 2011 (attached). 7) There are delays in repairing your property so we didn‟t start. 8) February 2012 – I send you a letter warning you that the market was dropping (attached). 9) June 2012 – You decided to replace me as your rental agent as I couldn‟t get the rent you were seeking primarily because you unfortunately missed the peak period of the market, and [A] promised you a rental that they eventually could not achieve. Case No: 321469 Determination Page 14 of 19 10) October 2012 – You had an issue with how [A] managed your property (and the promises they made which they were unable to achieve) and we again took over your rent al management in about October 2012.” Non-financial loss 46. The Applicants are seeking compensation for emotional and financial stress they state has been caused by the FSP‟s handling of the claim. I am to consider whether the FSP‟s conduct unduly delayed t he repairs and caused the Applicants stress or inconvenience as a result of the handling of the claim. 47. The FSP was asked to comment on this aspect of the dispute and said in a n email dated 29 October 2012: “ I do not agree compensation for non financial or financial loss is warranted in this circumstance, and maintain the majority of the delays were experienced due to the Applicant.” 48. The Service continually pressed for additional file notes, which were provided on 30 October 2013, and I note the FSP admits that J “did not receive the job request prior to September 2010” and that “(the FSP) would have to concede that (the FSP) is responsible for the initial delay following the initial claim being lodged.” 49. I accept that to some degree, all insurance claims are stressful and inconvenient. In order to invoke an order of compensation under 9.3b, I must be satisfied that some action or inaction of the FSP caused the Applicants an unusual degree of inconvenience or time taken to resolve the situation. I do not consider the simple passage of time to be a sufficient trigger for an award of compensation. 50. The Applicants say the FSP „forgot‟ about the first claim due to the Queensland flood event and thus failed to ensure their claim was managed in an appropriate and timely manner. The Applicants say it took until October 2010 for anyone to attend the premises to view the damage, despite repeated requests by them to have the matter followed up. The Applicants say they have many emails to J „begging‟ them to start works but are unable to supply those emails due to computer issues. 51. They say it then took until February 2011 for the scope of works (SOW) to be finalised, at which time the second claim occurred, resulting them being put back to „square one‟. Although the second c laim was fairly minor, the FSP insisted on preparing a new SOW, which was not agreed on until May 2011. The FSP‟s contractor J then refused to start works until spring, as J could not undertake the work in winter. J did not actually start the works until January 2012. 52. The Applicants had arranged to rent another property in November 2011, in anticipation of the repairs being completed by then and the property able to be placed on the rental market. Most of the works were completed by March 2012, with some rectification required which was completed by May 2012. Case No: 321469 Determination Page 15 of 19 The Applicants say they were not able to secure a tenant until September 2012 as they had missed the peak of the m arket due to the FSP‟s delays. 53. The Applicants say as the actual repairs only took approximately three months to complete, had the FSP been more proactive in ensuring the repairs were commenced earlier, they would have been in a position to rent the home much sooner and therefore potentially not be facing the forced sale of the home. 54. The FSP d enies it has unduly delayed the Applicants‟ claim. It says the delays experienced are attributable to a combination of the Applicants‟ actions, disagreements over the SOW and requests by the Applicants to delay the start dates as well as works required to the property which were not claim related. Those works were required to be completed by the Applicants before the claimed works could commence. 55. The FSP has not responded to the Applicants‟ allegation that it „forgot‟ about the first claim due to the Queensland flood event, however I note the floods occurred in late 2010/early 2011 and therefore could not have impacted the Applicants‟ first claim. 56. I have considered the information available to me. The FSP has supplied five copies of the „vendor forms‟ it us ed to instruct J to inspect the property. 57. Four forms are dated 28 April 2010 and one is dated 24 December 2010. Only one bears the second claim number. 58. The content of these forms confirms J was asked to attend the premises to inspect the roof and provide a breakdown of the interior painting; to attend to inspect the damage to the kitchen, the roof and the paving; to proceed to repair the ceiling in the kitchen and replace the range hood (noting the insured will take care of the repairs to damage the roof); and to proceed with external damage repairs. There are also discussions about the rear pavers, which required rectification outside of the scope of the claim. 59. On the only form which bears the second claim number and which is also dated 28 April 2010 (which is clearly incorrect), J was asked “for a report and quote for the storm damage to the rear room on 4/2/2011.” (I note the FSP says that after the storm damage claim on 10 February 2011 the first claim was closed and both claims were managed under the second claim number). 60. Although I was unable to determine when these visits occurred from the information provided at first by the FSP, the FSP has now been able to find other file notes at the insistence of the Service. It now concedes that it is responsible for the initial delay. 61. J‟s report of 28 October 2010 shows J initially attended on 3 September 2010 and re-attended on 15 September 2010, with the initial SOW being prepared and submitted to the FSP on 4 October 2010. A variation was submitted later in October 2010. There is then delay as there are discussions between the parties over the pavers, the cause of the damage to Case No: 321469 Determination Page 16 of 19 the roof and the painting works and there is therefore difficulty in reaching a SOW that was acceptable to the Applicants before they were willing to sign an agreement for the works to begin. Discussions still ensue about the SOW in January and February 2011. 62. Unfortunately, once agreement on the first claim was about to be reached and repairs poised to commence, the home was damaged again in a second event thus necessitating J to prepare an additional SOW. 63. I note that there were also issues in agreeing to the second SOW and further issues identified with the drainage and pavers in the rear yard which meant that the Applicants were required to undertake non-claim related work to ensure the property was safeguarded from future water ingress. These works were required before the claim related repairs could commence. 64. It is also apparent there was disagreement over the start date for the works. The Applicants say this is because J refused to undertake the works over winter. J says this was delayed at the Applicants‟ request as they had other commitments in school holidays and wanted a start date of mid-late September. 65. Having carefully considered the material I am of the view it shows the works could have commenced by June 2011 but there were delays because of school holidays (at the Applicants‟ requ est) and the non-claim related drainage works. 66. Repairs ultimately did not commence until January 2012 but in my view the objective evidence is that the works could have been commenced sooner and finished sooner. 67. The FSP file notes show the SOW was agreed and J to begin on or about 14 June 2011. J did not begin because of school holidays. J‟s file notes show J contacted the Applicants on 5 August 2011 to discuss works , but the Applicants wanted to delay repairs until late September due to skiing commitments. The Applicants were still in the process of selecting drainage gates and pavers. It is clear there are discussions between the Applicants and J‟s contractors until January 2012 regarding the works to the drainage and pavers and the Applicants‟ actions in choosing those materials, before repairs commenced on 11 January 2012. 68. In my view, the Applicants were aware they were required to select the drainage gates and pavers before the claim related works could commence, and therefore should have made arrangements for this to be completed before the requested and anticipated June or September start date. Thereafter there is further delay, as the Applicants had not paid the deposit to J for the drainage works and had not completed their repair responsibilities. Therefore, on balance, I prefer the submissions of the FSP as to reason why there was the delay in commencing repairs. 69. I am unsure as to why the Applicants say the repairs would be completed by late November/early December 2011 when discussions were still taking Case No: 321469 Determination Page 17 of 19 place around then about the non-claim related work to be completed, let alone the claim related repairs beginning. The Applicants‟ decision to lease other premises in early November 2011 appears to be unrelated to the storm damage done and the repairs but is in my view evidence of an intention to live elsewhere and rent out this property. However, I am of the view that this and the letter from H establish that the Applicants were not ready to commence to rent out their home until mid November at the earliest. 70. Although I am of the view the delay was caused by the Applicants, I am not satisfied about the conduct of the FSP in handling both claims due to the delay in ensuring J had received instructions and attended to quote after the first claim. Nor am I satisfied that after the second claim, the FSP diligently chased J to commence the works in the latter part of 2011. 71. Therefore, after considering the available information before me, it is my view both parties have contributed to the delays in bringing both claims to a conclusion and that the delays were to an unusual degree, the delays would have caused physical interference and would have interfered with the Applicants‟ peace of mind. 72. In all the circumstances I propose to award the amount of $3,000 for compensation for non-financial loss arising from both claims in this dispute. Consequential Financial Loss 73. Consequential financial loss is not payable for the lost rent benefit as the property was not a rental or investment property earning the Applicants rental income, nor was it unfit to live in as a result of either the damage done by the storms or the repairs undertaken. That is, the Applicants were not in receipt of rental income in respect of the property at the time of either the losses occurring or when the repairs were being undertaken which was then foregone as a result of the claimed damage and the repairs. 74. However, the policy provides not only for lost rent where the home was leased at the time of the damage occurring but also where the insured can demonstrate they would have leased their home out during the period reasonably necessary to repair it. 75. The Applicants say they intended to rent the property to alleviate financial pressure they were facing and had the repairs not taken so long to complete, they would have been able to do so much earlier. The Applicants say the policy wording provides if they can show they would have leased the home out during the period it was being repaired, then the loss of rental benefit is payable. The Applicants consider they have sufficiently demonstrated an entitlement to claim this benefit. 76. The Applicants say they first considered renting out the property in December 2009 due to „ the global financial crisis ‟ and therefore they consider they have met the policy requirement to demonstrate they would have leased the home out whilst the repairs were being undertaken. On this Case No: 321469 Determination Page 18 of 19 basis, the Applicants consider they are entitled to the foregone rental income. 77. The Applicants claim $1,650 lost rent per week and la ter say “they should have rented (the home) by 1 December 2011 for $1,500” but due to delays by the contactor they did not rent the home until August 2012 when the tenant was secured for about $3,800 per month. The tenants moved in on 9 September 2012. 78. They say the home was not really fit to live in while works were being carried out from 5 January 2012 to 16 March 2012 but even if it was, it was not fit to rent. They say the works were mostly completed on 16 March 2012 and the house opened for inspection the next day. Final works were completed by 25 May 2012. They say they made arrangements to live elsewhere and signed a lease for another place to live on 9 November 2011. A copy of the first page of a lease is referred to in a letter to the FSP dated 8 May 2012. They say the children primarily lived there and lived between the two places. 79. I have considered the material from H carefully. In my view, this material in conjunction with others supplied by the Applicants, serves to confirm the Applicants were already in financial difficulty at the end of 2009, as they were investigating the possibility of either selling or renting the home due to „the global financial crises‟. Accordingly, I consider I can place limited weight on the Applicants‟ contention that the actions of the FSP were the sole cause of their financial distress. 80. Further, I consider the document from H demonstrates that although he was engaged to sell or rent the home, it suggests that at first a sale was preferable if they could get the “hope” sale price and that the decision to rent the home was not made until September 2011 and if all went well the property would be rented by early to mid November 2011. 81. Accordingly in my view if there was a consequential financial loss suffered for lost rent, the loss runs from early to mid November 2011 at the earliest until August 2012 at the latest when the property was rented. 82. Although there were delays in the first claim, I am not satisfied that a final decision had been made to rent the home until September 2011 when the Applicants had given up selling the property for the “hope” price. In my view therefore the actions of the FSP in the first claim are not relevant to an award of consequential financial loss compensation. 83. As for the second claim, the maximum amount I can award is $3,000. I note the Applicants have made various submissions about the amount of weekly rent. I also note the property was ultimately rented out for $3,800 per month. 84. I am of the view that although the Applicants have been responsible for the delay, that some of the delay was also caused by the FSP and by its repairer J. I am particularly concerned with the inaction of the FSP after it emailed J to see if repairs had commenced on 19 September 2011 and the eventual commencement of repairs in January 2012. Case No: 321469 Determination Page 19 of 19 85. Therefore I consider that there was at least one month‟s delay for which the FSP is responsible. As the property was eventually let for $3,800 per month I propose to award the maximum amount of $3,000 for consequential financial loss. 86. The FSP had submitted that consequential loss is excluded under the policy. I have considered all of the policy terms in the PDS provided by the FSP. There is no such exclusion (although I note such an exclusion in the PDS subsequent to this one). Other 87. As for the claims for $172.22 for door hardware and $1,533 (the Applicants claimed $533 originally) for IT and computer problems as a result of the work done by J, the FSP says it does not have a record of those invoices and asks the Applicants provide a copy for further consideration. 88. In the circumstances, I will make no finding on this issue, as it appears to be still under consideration by the FSP. Determination 89. On the basis of the available information and for the reasons stated, I determine:  The Applicants are not entitled to the out of pocket expenses benefit;  The Applicants are entitled to $3,000 non-financial compensation for the manner in which the FSP managed the claims;  The Applicants are entitled to $3,000 financial compensation for the manner in which the FSP managed the second claim;  As for the claims for $172.22 for door hardware and $1,533 for IT and computer problems as a result of the work done by J, the Applicants are to provide proof of loss and/or invoices to the FSP for its further consideration.