Home / Financial Firm (Unknown - Insurer) / Determination 321113
Determination 321113
Hail-damaged roof repaired with nearest-match tiles rather than full roof replacement
Summary
A homeowner claimed for hail damage to his roof and sought full replacement of the tiles for $49,780, but the FSP offered to repair the damaged tiles with nearest-match tiles. AFCA found the FSP's repair proposal consistent with the policy and ordered only replacement of hail-damaged porch and garden tiles, with no compensation for delay.
The policy requires repair to the same condition using the nearest equivalent materials where originals cannot be matched, and does not pay for undamaged property.
Issues
- Claim denial primary · not upheld
“The FSP's proposal for repairing the damage to the Applicant's roof is in accordance with the terms of the policy and the FSP is not required to replace all the tiles”
- Delay secondary · not upheld
“Having reviewed the timeline for the processing of the claim, I am satisfied the FSP's handling of the claim was reasonable”
Subjects and remedies
home or building damagenatural disasterrepair or rectify
Text of the determination
Case No: 321113 Determination Page 1 of 6
Case number: 321113
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim Amount
28 October 2013
Background
1. The Applicant held a home building insurance policy with the Financial
Services Provider (FSP). The policy provided cover for accidental damage
and had a sum insured of $360,000 with a standard excess of $300.
2. The Applicant’s home was damaged as a result of a hail storm on 25
December 2011. He lodged a claim with the FSP through his broker.
3. The FSP asses sed the damage to the Applicant’s roof and found that four
tiles had been damaged. It arranged quotations from builders for the repairs
required.
4. As the tiles on the Applicant’s roof were no longer available, the repair work
required the use of tiles that were the nearest match to the existing tiles.
5. The Applicant does not agree with the FSP’s proposed solution and wants
the FSP to replace his entire roof with the same type of tile.
Summary of Applicant’s position
6. The Applicant says that he does not accept the FSP’s position regarding
replacing damaged roof tiles with non-matching tiles.
7. He has issues with the difference between the FSP’s offer of settlement and
the cost to reinstate his roof and with the delays in the resolution of the
matter. He believes that the solution proposed by the FSP would devalue his
home.
8. He wants the FSP to reinstate his home to its pre-loss condition.
9. His preferred builder quoted $49,780 for the repairs, including the
replacement of the roof and the Applicant seeks this amount as settlement of
the claim.
Determination
Case No: 321113 Determination Page 2 of 6
Summary of FSP’s position
10. The FSP says that, consistent with the policy, it offered to pay the cost of
repairing the damaged portion of the Applicant’s roof to the same condition
as when it was new.
11. It says it was not able to source tiles that were the same as those that were
damaged, due to the age of the existing tiles on the Applicant’s roof.
12. It proposed using a row of tiles from an undamaged section of the roof at the
rear of the home to replace the damaged tiles. It wo uld then use the closest
equivalent tiles available to replace those removed from the rear section of
roof.
13. The FSP relies on the following policy provisions:
― How we pay a claim for your buildings
When loss or damage occurs to your buildings, we will pay the cost of
rebuilding your buildings or repairing the damaged portions to the same
condition as when they were new.
...
We will pay for the damaged portions of fixed coverings to walls, floors and
ceilings only in the room, hall or passage where the damage occurred.
We will try to match any material used to repair your buildings with the original
materials. If we cannot, we will use the nearest equivalent available to the
original materials. We will not pay any costs for replacing undamaged
property.‖
Issue
14. Whether the FSP’s proposal for repairing the damage to the Applicant’s roof
is in accordance with the terms and conditions of the policy.
Reasons for decision
15. Due to the nature of the dispute, the Financial Ombudsman Service (FOS)
has considered it appropriate to expedite the dispute in accordance with the
Operational Guidelines to the FOS Terms of Reference. This dispute has not
been the subject of a FOS Recommendation and has proceeded directly to
Determination. The parties have been previously advised that a
Determination will be issued in this case.
16. There has been an exchange of information between the parties and I am
satisfied that each party has had the opportunity to address any issues
raised by the other.
17. There is no dispute that the Applicant’s home was damaged in a hail storm
on 25 December 2011 or that the policy provides cover for the damage.
Case No: 321113 Determination Page 3 of 6
18. The FSP states in its submission that its assessor advised that the damage
to the Applicant’s home was consistent with hail impact and water ingress as
a result of gutters being blocked with hail.
19. It says that immediately after the storm, the Applicant engaged a roofer to
repair some of the roof and it was at this point that it was found that
replacement tiles were no longer available. The roofer removed tiles from the
down pitch of the roof of the alfresco at the rear of the house and used these
tile to replace the damaged tiles.
20. The Applicant provided a quotation in the amount of $44,000 from builder
―M‖ for the repairs to his home. Builder ―C‖ quoted th e FSP $23,590.78 for
the repairs.
21. C’s quote included the following repairs to the roof:
―1.11.1 Remove and replace four broken roof tile for the second storey with
undamaged tiles from lower roof.
1.11.2 Realign all dislodged roof tiles on both first and second storey roofs
back to correct positioning
1.11.3 Carefully remove the entire row of bottom tiles from the rear lower
roof, reinstate back onto the row above to fill in void and leave the
remainder tiles onsite as spare tiles for the insured.
1.11.4 Supply, deliver and install 200 new tiles to match with pre existing as
close as possible in colour and profile if available to infill the exposed
entire lower row.‖ (sic)
22. The FSP engaged roofing plumber ―TP‖ to inspect the Applicant’s roof. TP’s
report confirmed that only four roof tiles had been damaged.
23. Building firm ―AHG‖ provided a further quote to the Applicant. This quotation
for $49,780 dated 18 February 2013 includes a note from its author as
follows:
― * Please note: It is my opinion that you cannot patch roof tiles as they are no
longer in production with profiles and colours not the same therefore they will
need to be completely replaced. To attempt patching would be a piece meal
finish with disastrous affect not only in appearance (being a different profile)
but with gaps and unevenness between tiles due to baking process.
Such a job will always leak with heavy rain; therefore in my opinion as
previously stated the entire roof must be replaced .‖
24. The Applicant says that the FSP’s proposed settlement will not reinstate his
house to the condition it was in before the hail storm and will devalue this
home.
25. He also says that the roof of his home is one item — a roof — and he does
not consider this item to be a collection of materials as it was built as one
item.
Case No: 321113 Determination Page 4 of 6
26. The FSP says that the roof is made up of many parts, each with a different
role and made of different materials. Further, it says that a tile can be
purchased individually and not as a set.
27. The Applicant’s broker referred to another claim where the FSP paid to
replace all the tiles of a tiled floor, saying that this supports the Applicant’s
claim for the entire roof replacement. The FSP noted that there is a specific
provision in the policy for fixed floor coverings, but no equivalent provision
for roof tiles.
28. The policy clearly states that the FSP will not pay any costs for replacing
undamaged property. As the damage to the Applicant’s roof was limited to
four t iles, the remainder of the roof is ―undamaged property‖ and the FSP is
therefore not required to pay for the costs of repairing or replacing this
portion of the roof.
29. The policy also contemplates situations where it is unable to match
remaining material and provides that the FSP will use the nearest equivalent
materials available.
30. The report from AHG stated that the roof tiles could not be ―patched‖, due to
the ―disastrous‖ appearance and the gaps between tiles. The FSP’s
assessor has indicated that, by using tiles from the rear of the house, the
difference in the tiles would be less noticeable and the roof can be made
watertight.
31. I am satisfied that, providing the repairs render the roof water-tight, the
solution proposed by the FSP is consistent with the policy and fair in all the
circumstances. The FSP would, of course, be responsible for any leaks that
resulted from a failure to render the roof watertight and would be required to
rectify any such issues.
32. The FSP is not required, under the terms of the policy, to obtain an exact
colour match. The FSP’s efforts to minimise the effects of any colour
mismatch are reasonable.
33. Accordingly, I find that the FSP’s proposal for repairing the damage to the
Applicant’s roof is in accordance with the terms of the pol icy.
Other roof damage
34. TP also reported that there was some other damage to the roof, including
cracking to the hip and ridge capping and the valley tray cement, which was
not related to the storm event but was as a result of wear and tear.
35. The FSP’s builder agreed to repair this additional damage to the Applicant’s
roof at no extra cost.
36. Accordingly, it would appear that the issue of the FSP’s liability in this regard
is not in dispute.
Case No: 321113 Determination Page 5 of 6
Tiles to porch
37. The Applicant has stated in his initial submission that he has a similar issue
with ―the front porch reinstatement of damaged porch steps with non
matching tiles‖.
38. With respect to this aspect of the dispute, there has been limited information
provided by the parties.
39. The quotation by AHG included the following items:
― - Remove and replace 45 sq meters of terracotta tiles to Porch area due
to damaged tiles that cannot be matched.
- Remove and replace 15 lineal meters of terracotta step-nose tiles to
Porch area due to damaged tile that cannot be matched.‖
40. The author of the AHG report stated that in his opinion, (all) the terracotta
tiles to the porch area needed to be replaced with new tiles as they too
would be impossible to match.
41. The quotation by C dated 22 June 2012 included the following items:
―1 -10 Front Garden – 150.00m 2
1-10-1 Strip and replace none bullnose cappings and six risers to the
staircase leading up to the front steps attempting to match with pre-existing
terracotta as close as possible if available.
1-10-2 Strip, supply and install 16 new terracotta tiles for the surface of the
brick pillars at the front of the property to match with pre-existing as close as
possible if available‖
42. The tiles which are affixed to the front steps and brick pillars at the front of
the home constitute part of the building.
43. The policy provides that the FSP will pay for the damaged portions of fixed
coverings to walls, floors and ceilings only in the room, hall or passage
where the damage occurred.
44. The front porch and front garden are not a room, a hall or a passage.
Therefore the policy provision outlined in paragraph 43 is not applicable to
this portion of the claim and the FSP is only required to repair or replace the
damaged tiles on the front porch and in the front garden area.
45. If the original tiles in this area cannot be matched, the FSP is only required
to use the nearest equivalent tile available and is not required to replace any
undamaged tiles to achieve a completely consistent appearance.
Time taken to resolve claim
46. The Applicant, in his initial submission to FOS, indicated that he has an
issue with the delay in the resolution of the disputed aspects of the claim.
Case No: 321113 Determination Page 6 of 6
47. The FOS Terms of Reference at paragraph 9.3 allows for the awarding of
compensation for non-financial loss, but only in circumstances where an
unusual degree or extent of physical inconvenience, time taken to resolve
the situation or interference with the Applicant’s expectation of enjoyment or
peace of mind has occurred
48. The claim was lodged on 8 March 2012, several months after the hail storm
event.
49. The FSP has stated that it advised the Applicant to obtain a report detailing
the damage and if the cost of the repairs was under $5,000, he was to go
ahead with the repairs and submit the invoices for reimbursement. However,
according to the FSP’s submission, no further response was received until
29 May 2012, several months after the claim lodgement.
50. The FSP’s assessor first attended at the Applicant’s home on 31 May 2012.
The FSP has provided interim assessment reports dated 26 June 2012, 2
August 2012, 22 August 2012, 24 October 2012 and 4 December 2012.
51. Having reviewed the timeline for the processing of the claim, I am satisfied
the FSP’s handling of the cla im was reasonable.
52. The FSP’s refusal to replace all the tiles on the Applicant’s roof delayed
settlement of the claim. However, as I have found that the FSP’s position
was fair in all the circumstances there are insufficient grounds for an award
of compensation for non-financial loss.
Determination
53. On the basis of the available information I determine that:
The FSP’s proposal for repairing the damage to the Applicant’s roof is
in accordance with the terms of the policy and that the FSP is not
required to r eplace all the tiles on the Applicant’s roof.
The FSP is only required to replace terracotta tiles on the front porch
and in the front garden that have been damaged by the hail storm. If
the original tiles in this area cannot be sourced, the FSP is only
required to use the nearest equivalent tile available.
There are insufficient grounds for the award of any compensation to the
Applicant for non-financial loss.