Home / Financial Firm (Unknown - Insurer) / Determination 320801
Determination 320801
Cash settlement amount for fire-damaged home
Summary
After a house was destroyed by fire, the applicant sought $280,000 for the building claim while the FSP offered $190,000 cash settlement based on the lowest builder quotation. AFCA found the offer fair, found no unreasonable delay, and ordered interest on the $190,000.
Where the insured elects cash settlement, the insurer may base the settlement on the lowest reasonable quotation for the agreed scope of works.
Issues
- Claim amount dispute primary · not upheld“The FSP is entitled to cash settle the claim for $190,000.”
- Delay secondary · not upheld“The material presented does not indicate that the FSP delayed the claim unreasonably.”
Subjects and remedies
home or building damagepay claimpay interest
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Case No: 320801 Determination Page 1 of 9
Case number: 320801
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim Amount
23 January 2013
Summary
Description :
Claim under a Home Insurance Policy following a fire on 7 November
2012. The FSP has agreed to cash settle the claim but the Applicant
disputes the cash settlement offer.
Basis of Determination
The FSP has offered to repair the home based on the quotation from JL .
The Applicant wants to cash settle the dispute but believes the amount
quoted is too low and that the cash settlement should be based on a
quotation from a builder ―MR‖.
The quotation from JL is based on an agreed Scope of Works. It is fair in
all the circumstances given the FSP has offered to complete the repairs
that it be entitled to cash settle the claim based on the quotation from JL.
Determination
The FSP is entitled to cash settle the claim for $190,000.
Interest is payable pursuant to Section 57 of the Insurance Contracts Act
1984 (the Act) from 30 August 2013.
Background
1. The Applicant held a home insurance policy with the Financial Services
Provider (FSP). The policy provided defined events cover over the building
and contents of the Applicant’s double storey home in Cedar Creek,
Queensland.
2. On 7 November 2012, the home was destroyed by fire and a claim was
lodged with the FSP.
Determination
Case No: 320801 Determination Page 2 of 9
3. After obtaining quotes for the repairs, the FSP offered to either authorise the
repairs or to pay the Applicant an amount equivalent to the lowest quote it
had obtained.
4. The Applicant wants a cash settlement so he can demolish and rebuild the
house, but disagrees with the quantum of the FSP’s settlement offer and
wants a review by the Financial Ombudsman Service (FOS).
Summary of Applican t’s position
5. The Applicant says he had to fight to get the Scope of Works (SOW) for the
repair work amended to include the full scope of the repairs required.
6. He notes that the FSP initially obtained several quotes for the repairs,
ranging between approximately $109,000 up to $230,000. He does not
accept that there can be such variation between the quotations for the same
work.
7. Even though the FSP obtained updated quotes to allow for any further
damage which may be revealed once the work commences, he says that the
FSP’s settlement offer of $190,000 is inadequate. The quotation he has
obtained from a builder (―MR‖) indicates that the cost of the repairs would be
$218,000, plus approximately $59,700 to allow for variations for other
damage which may be revealed or otherwise necessary.
8. The Applicant wants the FSP to pay him $280,000 as settlement for the
building claim, and wants the temporary accommodation payments to
continue until the dispute has been resolved.
Summary of FSP’s position
9. The FSP says that if it were to authorise repairs to restore the Applicant’s
home to its previous condition, it would be responsible for repairing any
further damage which may become apparent once the work commences.
10. The policy provides that it can choose how it will settle a home building claim
but that it agreed to the Applicant’s request for cash settlement.
11. The FSP arranged for building consultant ―B‖ to produce a Scope of Works
for the repairs required to the house. The Applicant provided a quotation
from MR for the repairs, and it obtained two other quotations for the repair
work.
12. After comparing the three quotations, all of which were based on the same
SOW, it offered to pay the Applicant the amount represented by the lowest of
these quotations, rounded up to the nearest $5,000. It says that under the
circumstances, its offer is very fair and reasonable.
Case No: 320801 Determination Page 3 of 9
13. Further, it has paid the Applicant’s temporary accommodation costs, up to
the full 12 month limit provided under the policy.
14. The FSP relies on the following policy provisions:
― Other cover
We may also provide 'other cover' for your home or contents during the policy
period.
...
Temporary accommodation for home owners
...
If a listed event causes loss or damage to your home and we agree you can’t
live in it and you need to move out so it can be repaired or rebuilt.
Covered under Buildings Insurance
costs for temporary accommodation that we agree are reasonable and
appropriate for you, your family and your pets that you normally keep
at your site
any additional living expenses that we agree are appropriate
costs to remove and store your contents and then return them to your
home.
We pay these costs for the reasonable time we agree it should take to repair
or rebuild your home. If you have a:
Home policy, for up to 12 months from when the listed event took
place
...
We pay this on top of the Buildings sum insured .
Conditions
you must have lived in your home permanently before the listed event
took place
we must agree to pay the costs before you make any arrangements
we won’t cover costs caused by unreasonable delays in repairing or
rebuilding your home.
...
What we pay for – Buildings Insurance
If we agree to cover your claim under Buildings Insurance, then we will:
pay the cost to repair or rebuild the part of your home that was
damaged (whichever is lower)
pay for any extra costs we cover under 'other cover' – see below.
...
How we settle your buildings claim
We will choose to settle your claim for loss or damage to your home or 'other
cover' in one of the following ways:
Case No: 320801 Determination Page 4 of 9
1. Arrange for repairers, builders or suppliers to repair or rebuild your
home.
If you agree, we can arrange for our preferred repairers, suppliers or builders
to repair or rebuild your home.
2. Pay you the reasonable cost to repair or rebuild your home.
We can choose to:
pay you
pay your nominated repairer, supplier or builder, or
provide you with store credits from one of our nominated suppliers.
3. Pay you the buildings sum insured
We may do this when we consider your home to be a total loss or when we
choose to do so. ‖
Issues
15. Whether the FSP’s offer for the settlement of the Applicant’s claim for the
damage to the building is fair in all the circumstances.
16. Whether the FSP has met its obligations under the policy to pay the
Applicant’s temporary accommodation costs.
Reasons for decision
17. Due to the nature of the dispute, FOS has considered it appropriate to
expedite the dispute in accordance with the Operational Guidelines to the
FOS Terms of Reference. Thus, this dispute has not been the subject o f a
FOS Recommendation and has proceeded directly to Determination. The
parties have been previously advised that a Determination will be issued in
this case.
18. This decision has been made by a Panel of three decision makers including
an Ombudsman and two decision makers with extensive experience in
insurance and consumer claims.
19. The Panel is satisfied that an exchange of the relevant information has taken
place between the respective parties and that each party has had the
opportunity of addressing any issues raised.
20. There is no dispute that:
The damage to the Applicant’s property was caused by fire, which is an
event covered under the policy;
The FSP has accepted liability for the damage;
The FSP agreed to pay the Applicant’s costs for rental accommodation
under the temporary accommodation benefits of the policy.
Case No: 320801 Determination Page 5 of 9
21. The Panel notes that the Applicant also claimed for fire damage to some of
his home contents and that the FSP settled that portion of the claim.
Accordingly, the Panel will not consider this matter as part of this
Determination.
Building claim – settlement offer by FSP
22. The central issue for the Panel to consider is whether the amount offered by
the FSP with respect to settlement of the claim for the damage to the
building is fair in all the circumstances.
23. The FSP arranged for the SOW for the repairs. After the Applicant identified
various items on the SOW which needed amendment, the FSP arranged for
a revised SOW to be produced.
24. Using the revised SOW, produced by building consultant ―N‖ on 5 February
2013, the FSP proceeded to obtain three builder’s quotations for the repairs.
The three quotations (inclusive of GST) were provided by builder ―A‖ (in the
amount of $120,383.38), builder ―E‖ (in the amount of $160,470) and builder
―AB‖ (in the amount of $ 230,600).
25. In an email dated 20 February 2013, the FSP sought advice from the
Applicant as to whether he wanted the repairs to be performed by A — which
provided the most competitive quotation for the repairs — or preferred cash
settlement for the amount of the quotation by A.
26. The FSP noted that it was aware that there would be further damage
revealed once the repairs were underway. According to the FSP, this
additional damage could not be checked until the upper structure was
demolished for safety reasons. The FSP advised that once the upper
structure had been demolished, it would have a builder scope and cost the
additional damage. However, if the Applicant chose a cash settlement, it
would have him perform the demolition (as per the SOW) and once this was
completed, it would arrange for a builder to assess the additional damage
and scope and cost of these repairs.
27. The Applicant advised the FSP on 28 February 2013 that he was not happy
with what was being offered. He said that he had obtained a quotation for the
repairs from builder MR, in the amount of $218,130, which he believed was a
more realistic quotation, and requested copies of the quotations from A, E
and AB.
28. The Applicant subsequently advised that after analysing the quotations
provided by the FSP, he was of the view that he would not be properly
indemnified for the damage to his building if he settled on either of the A
quotation or the E quotation.
29. He believes the A quotation was based on the incorrect version of the SOW,
which explains why this quotation was so much lower than the others. He
wanted this quotation to be disregarded.
Case No: 320801 Determination Page 6 of 9
30. The Applicant believes E had not provided a detailed or accurate quotation,
making it difficult to assess whether E had taken into consideration all
aspects of the work required.
31. He also questioned E’s competency as it was E who produced the original
SOW which missed many items, making it necessary for N to become
involved in the production of the SOW. Further, he had witnessed more than
one incident on the site which indicated that E did not seem concerned about
safety.
32. The Applicant believed AB appeared to be the only builder of the three who
considered the order of events, the labour required and the specific trades
needed, and that the matter would not be resolved until an i ndependent
quantity surveyor quantified the repairs required.
33. The FSP subsequently arranged for building consultant ―B‖ to attend and
remove the top section of the building structure (to allow for a safe working
area from which to accurately sight and scope any additional damage) and
produce a new SOW. Three quotations for the repairs, based on this new
SOW, were obtained by the FSP, as follows:
Builder AB — $234,373.
Builder JL — $186,030.
Builder MR - $218,130 (+$59,700 for additional damage).
34. An amount of $190,000 was offered to the Applicant as cash settlement for
the building claim, based on the JL quotation and rounded up to the nearest
$5,000.
35. The Applicant remains dissatisfied with the settlement offer made by the
FSP. In an email dated 26 August 2013 he stated:
―When I met with [RD] form [JL] he explain a few things. Prior to receiving the
new scope of works from [B] they were asked to quote on the old scope. The
only reason that I can think of, for [FSP] to do this as to ensure that [JL] are
quoting low enough for them. They quoted this in at $126K. Also [JL] weren’t
told the quote they were being asked to do wasn’t for an actual repairs but just
for price reference of a cash settlement. He also told me that some builders
quote low to get the job and to keep their employees with work. As you know
[JL] came back with a quote of $186K ($60K more than original scope)...‖ [sic]
36. The Applicant advised AB did not come out to the property to re -check the
work required for the new scope, and was critical of the revised quotation of
$234,373, stating that:
―This is only a ridiculous $5K more for all the extra work which [JL] quoted to
be $60K.‖ [sic]
37. The Applicant arranged for MR to amend its quotation to take into
consideration the new SOW produced by B. MR’s n ew quotation included an
amount of $59,700 for additions to the earlier SOW.
Case No: 320801 Determination Page 7 of 9
38. The Panel has reviewed the submissions from the parties, including the
SOW by B, as well as the quotations by AB, MR and JL.
39. The Panel accepts that in circumstances where an insurer authorises repairs
to damage for which it has accepted liability, it is entitled to select a builder
which has provided the lowest quotation for the work to be performed. In
these situations, the insurer is responsible for any new issues that arise and
for the repair of any damage which was previously unforeseen.
40. Where despite the offer to repair the premises, a claimant seeks a cash
settlement, the Panel also accepts that the FSP should be entitled to base its
settlement offer on the lowest builder’s qu otation obtained (providing that the
quotation is reasonable and based on the agreed SOW). In these situations,
the responsibility for any damage which becomes apparent subsequent to
settlement typically rests with the claimant, as does the responsibility for the
quality of any repairs the claimant may subsequently commission.
41. There is no dispute between the parties that the SOW produced by B is an
accurate reflection of the repairs required to the Applicant’s building.
42. All three quotations are considerably detailed although the latest quotation
by AB is the only one which lists prime costs and provision sums (PC/PS
items).
43. The Applicant has provided an account of a conversation he says he had
with ―RD‖ from building firm JL. According to the Applicant, dur ing this
conversation RD says that he arrived at a figure of about $126,000 for the
repairs based on the original SOW. However, the Applicant has not provided
a statement from RD (or from JL) or any other evidence to support his
account of the conversation.
44. Even if the Panel were to accept the Applicant’s account of the conversation
which he says took place, and accept that JL produced a quotation based on
the original SOW in the amount of $126,000, this does not invalidate the
quotation of JL’s as based on the new SOW.
45. Part of the Applicant’s concern appears to stem from a $60,000 difference
between the amount of JL’s former and latter quotation. The Panel notes that
the two quotations from MR (one based on the original SOW, and the other
based on the new SOW) also vary by approximately $60,000 and accepts
the variation is reasonable given the new Scope of Works.
46. The FSP has maintained its position that it was prepared to authorise JL to
perform the repairs to the Applicant’s building, based on its quotatio n and the
SOW from B, should the Applicant alter his preferred method of settlement.
47. The Applicant has not identified anything in the latest quotation from JL that
is inconsistent with the latest Scope of Works. In these circumstances, given
it is the Applicant who seeks to cash settle the claim, the Panel is satisfied
the offer of $190,000 based on the quotation by JL and rounded up by
almost $3,970, is fair in all the circumstances.
Case No: 320801 Determination Page 8 of 9
Temporary accommodation
48. The FSP agreed to pay the Applicant’s costs with respect to rental
accommodation, given that his home was uninhabitable due to the fire
damage. This is despite the fact the Applicant was not living in the insured
building immediately prior to the fire, and it is a condition of the temporary
accommodation benefit that the insured is living in the home at the time of
the event which causes the damage.
49. The policy benefit for temporary accommodation is limited to 12 months from
the date upon which the fire occurred.
50. Given the fire occurred on 7 November 2012, according to the terms and
conditions of the policy, the FSP would only be required to pay temporary
accommodation until 6 November 2013.
51. The FSP has in fact agreed to pay the temporary accommodation benefit
until 7 January 2014.
52. The Applicant says that the FSP indicated in its Notice of Response dated 4
June 2013 that it would ―continue to pay the rental costs until the settlement
has been decided ”. The FSP subsequently advised that this was an error as
in its final decision letter to the Applicant it refers to the policy provision
which allows a period of 12 months for temporary accommodation.
53. The FSP further refers to an email dated 30 August 2013 which was sent to
the Applicant advising the full 12 months policy limit for temporary
accommodation had been paid by the FSP.
54. A copy of that 30 August 2013 email has been provided to FOS. The Panel
notes that the FSP invited the Applicant to show any areas in which it had
unfairly delayed the claim. The FSP has indicated that the Applicant has not
provided any such evidence.
55. The Panel has considered the submissions on this matter and notes that the
FSP’s 30 August 2013 advice to the Applicant that it had paid the full 12
months policy limit for the temporary accommodation benefit post-dated its
Notice of Response by almost 3 months.
56. The Applicant wants the FSP to honour the commitment it made in its Notice
of Response with respect to temporary accommodation benefit, but has not
indicated that he has suffered any preju dice pursuant to the FSP’s Notice of
Response statement.
57. As outlined earlier in this Determination, the Panel finds that the FSP’s offer
of settlement for the building claim was fair in all the circumstances.
58. Although the Applicant disagreed with the FSP’s position with respect to the
offer of settlement, and it is clear that he became frustrated that the FSP
held this position despite his disagreement, in the Panel’s view the material
presented does not indicate that the FSP delayed the claim unreasonably.
Case No: 320801 Determination Page 9 of 9
59. Accordingly, and noting that the FSP has agreed to pay the Applicant’s
rental costs up to 7 January 2014, two months past the 12 month limit
imposed by the policy, the Panel finds that the FSP has met its obligations
under the policy for payment of temporary accommodation benefit.
Compensation for non-financial loss
60. The Applicant has indicated that the claim process was protracted that as a
result, he and his family have struggled financially and have suffered from
stress and depression.
61. Under paragraph 9.3 of its Terms of Reference, FOS can give consideration
to an award of compensation for non-financial loss, but only in
circumstances where an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with the
Applicant’s expectation of enjoyment or peace of mind has occurred .
62. The Panel notes that the FSP has maintained its position from the outset
that it was prepared to authorise the repairs to the damage to the Applicant’s
home. It pointed out on more than o ne occasion that if the Applicant chose
this option, the FSP would be responsible for any issues that might arise and
that the repairs would be covered by a lifetime warranty.
63. Based on the material presented, and in light of its findings that the FSP’s
settlement offer is fair in all the circumstances, the Panel finds that there are
insufficient grounds for an award of compensation for non-financial loss.
Determination
64. On the basis of the available information the Panel determines that:
The FSP’s cash settlement offer of $190,000 for the Applicant’s
building claim is fair in all the circumstances.
The FSP has fulfilled its obligations under the policy for the payment of
temporary accommodation allowance.
There are insufficient grounds for the award of compensation for non-
financial loss.
The FSP should pay interest pursuant to Section 57 of the Act from 30
August 2013 being the date of offer of settlement to date of payment of
the claim.