Home / Financial Firm (Unknown - Credit) / Determination 320221

Determination 320221

Delayed settlement of home purchase financed by the FSP

FirmFinancial Firm (Unknown - Credit)
Decided2014-03-17
ProductCredit · Home loan
OutcomeFor the complainant in part
Amount awarded$1,500
Non-financial loss—
Amount claimed$2,550
SourceAFCA PDF

Summary

The applicants claimed $2,550 in extra fees and stress after a home purchase settlement was delayed by the FSP's late request for income verification and lost documents. AFCA ordered $1,500 for the extended settlement period plus interest and no non-financial loss, rejecting the balance of the claim.

A firm must compensate the financial loss its delay caused, limited to the period for which it was responsible, and non-financial loss requires an unusual degree of inconvenience.

Issues

Subjects and remedies

pay compensationpay interest

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Case No: 320221 Determination Page 1 of 5 Case number: 320221 Credit - Consumer Credit - Home Loans - Instructions - Delay 4 March 2014 Summary Description  The Applicants seek compensation from the Financial Services Provider (FSP) for delays in the settlement of their home purchase (which was financed by the FSP). Basis of Determination  The FSP did contribute to the delays in settlement and is responsible for the financial losses suffered by the Applicant as a result. Determination  The FSP is to pay the Applicants the amount $1,500 plus interest. Background 1. As advised to the parties, the Financial Ombudsman Service (FOS) has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. The dispute has not been the subject of a Recommendation and has proceeded directly to Determination. 2. On 10 December 2012 the FSP advised the Applicants that they qualified for a home loan and on 12 December 2012 the Applicants entered into a contract of sale for a property. The settlement of that sale was delayed. 3. This dispute is about:  whether the FSP breached its obligations to the Applicants in relation to the delayed settlement of the property, and  if so, did it cause the Applicants a loss for which they should be compensated. Determination Case No: 320221 Determination Page 2 of 5 Reasons for decision Is the FSP responsible for the delayed settlement? 4. Based on the information provided, the following timeline sets out the events relating to the Applicants’ loan application and settlement. Date Event 10 Dec 2012 FSP letter to the Applicants advising that they qualified for a home loan. 12 Dec 2012 The Applicants enter a contract of sale with the settlement date 7 January 2013. 15 Dec 2012 The FSP issues a valuation request for the property. 22 Dec 2012 The contract of sale and the Applicants ’ income details are provided to the FSP. The FSP is informed that settlement is scheduled for 14 January 2013. 24 Dec 2012 FSP internal email seeking a letter from the Applicants’ accountant to verify their income. 25 - 26 Dec 20 12 Christmas Day and Boxing Day 27 Dec 2012 The FSP emails the Applicants requesting a letter from their accountant to verify their income. 1 Jan 2013 New Years Day 4 Jan 2013 The FSP calls the Applicants to follow up the accountant letter. The Applicants advise that their accountant is on leave until 7 January and they are seeking another accountant to provide the verification. The Applicants negotiate an extend ed settlement date to 21 January 2013 at cost of $150 per day. 7 Jan 2013 The Applicants provide the FSP with an accountant’s letter. 8 Jan 2013 The FSP issues the Applicants with loan contracts. 11 Jan 2013 The FSP receives signed loan contracts from the Applicants . 16 Jan 2013 The FSP requests an amendment to the contract of sale to correct a title reference. The Applicants sign the amendment. 18 Jan 2013 The FSP telephones the Applicants to advise them it has lost their documentation and that they should extend the settlement date at the FSP’s cost. Settlement date extended to 24 January 2013 22 Jan 2013 The FSP’s d ocumentation is found and the settlement process proceeds. 24 Jan 2013 The Applicants query with the FSP a $4,517.14 shortfall in settlement funds. The FSP responded that the figures were correct. The Applicants fund the shortfall from their personal funds to ensure settlement proceeds. 24 Jan 20 13 - Settlement completed 5. The Applicants are claiming $2,550 for the additional fees and penalties they incurred for the twice delayed settlement of the property together with compensation for the stress and inconvenience they have suffered. Case No: 320221 Determination Page 3 of 5 6. The FSP says that its usual timing for a settlement is 4-6 weeks and in this instance it met those time frames. The FSP acknowledges it caused a delay to settlement due to the lost documentation and has offered to refund the Applicants $388.20 in compensation. 7. Based on the above timeline, the Applicants must have informed the FSP of their purchase of the property on or before 15 December 2012, being the date that the FSP requested the property valuation. However, it was not until 22 December 2013, a week later, that the Applicants provided the FSP with the contract of sale and their income details. 8. The 22 December 2012 was a Saturday. The next b usiness day was 24 December 2012. It would appear that despite the FSP’s internal email dated 24 December requesting an accountant’s income verification, the FSP’s staff member did not convey that request to the Applicants until the next business day, being 27 December 2012. 9. It is important to note that the FSP’s loan qualification dated 10 December 2012 was subject to the FSP receiving confirmation of the Applicants’ income. It is therefore reasonable for the FSP to seek independent verification of the Applicants’ income, especially as one Applicant was self employed. 10. Upon receiving the Applicants ’ income details on 22 December, the FSP acted promptly by requesting the accountant verification the next business day. However, the one business day delay in communicating that request to the Applicants is significant given the time of year and the high propensity for people to take holidays during the Christmas – New Year period. 11. In my view, in light of the time of year and the absence of their own accountant, it was reasonable for the Applicants to extend the settlement date to 21 January 2013 when they received the verification request. The need to do so could have been avoided if the Applicants were informed of the verification request on 24 December, prior to the holiday season. For that reason, I consider it appropriate that the FSP compensate the Applicants for the extended settlement until 21 January 2013. 12. It follows that the FSP also compensate the Applicants for the subsequent delay from 21 January 2013 to 24 January 2013, responsibility for which the FSP has accepted. What should the Applicants be compensated? Financial loss 13. Based on the above findings, I am satisfied that the FSP should compensate the Applicants for the loss they incurred in extending the settlement date and that loss is represented by the $150 per day the Applicants had to pay the vendor. Case No: 320221 Determination Page 4 of 5 14. The Applicants have claimed loss for extending the settlement date from 7 January 2013. I do not support that claim for two reasons: a. the FSP was advised on 22 December 2012 that settlement was to occur on 14 January 2013, and b. given that the contract of sale and income details were only provided to the FSP on 22 December 2012, a settlement date of 7 January 2013 was unreasonable particularly given the Christmas – New Year holiday period. 15. I therefore consider it appropriate that the FSP compensate the Applicants an amount of $1,500, being $150 per day for the 10 days that settlement was delayed from 14 January 2013 to 24 January 2013. Non-financial loss 16. Non-financial loss claims include claims for stress or inconvenience cause by an error of the FSP. FOS will only award compensation for non-financial loss where there has been an unusual degree or extent of inconvenience. Applicants are expected to be moderately robust in dealing with unexpected problems. 17. In the current dispute, I accept that the FSP’s failure to provide prompt ( that is, same day) notice to the Applicants of the n eed for an accountant’s verification letter created additional pressure for the Applicants. However, I also consider that the Applicants need to accept some responsibility for that pressure because they did not provide the relevant income documentation to the FSP until 22 December 2012. 18. On balance , considering both parties’ contribution to the delays I consider that the Applicants are appropriately compensated with an award of financial loss and that no non-financial loss should be payable. Ombudsman’s Determination 19. I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. 20. I have taken into account all the material submitted by the parties. I am satisfied that the documentation I have relied on has been provided to both parties. Case No: 320221 Determination Page 5 of 5 21. On the basis of the available information I determine in favour of the Applicants and find as follows. 22. Should the Applicants accept this Determination within 30 days of its date of issue, within a further 14 days of that acceptance the FSP must pay to the Applicants a. an amount of $1,500 plus b. interest on that $1,500 amount, calculated at the FSP’s annual variable interest rate commencing from the 24 January 2013 to the date of payment by the FSP under this Determination.