Determination 319813

Delay in claim handling

FirmFinancial Firm (Unknown - Insurer)
Decided2014-01-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded$2,794
Non-financial loss$1,000
Amount claimed—
SourceAFCA PDF

Summary

A fire damaged the Applicant's home and he disputed the insurer's repairs, settlement and handling. AFCA ordered an expert inspection and further repairs, a further $2,794 for the evaporative cooling unit, $1,000 for non-financial loss, and statutory interest on any cash settlement.

The FSP must restore the damaged property to an acceptable standard under the policy, and the substandard repairs and prolonged delay justify non-financial loss compensation under clause 9.3 of the Terms of Reference.

Issues

Subjects and remedies

home or building damagepay claimpay interestpay non financial lossrepair or rectify

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 319813 Determination Page 1 of 9 Case number: 319813 General Insurance - Domestic Insurance - Home Building - Service - Delay in claim handling 19 December 2013 Summary Description: A claim under a home building policy for loss following a fire. Basis of Determination: A consideration of the evidence in relation to the repairs that have been completed by the FSP. Determination: The FSP is to attend to further repairs in accordance with the Determination herein. Background 1. The Applicant held a home building insurance policy with the Financial Services Provider (FSP) at the relevant time. The policy provided building cover for $332,016. 2. On or about 18 May 2012, the Applicant’s home was damaged in a fire and he lodged a claim. 3. The FSP accepted the claim and arranged for repairs to be undertaken. The Applicant was unhappy about the standard and extent of these repairs. Whilst some additional work has been attended to by the FSP’s agents, he remains unhappy about the handling of the claim, the overall work comple ted and settlement offered. 4. The dispute was considered by a Case Manager of the Service who issued a Recommendation. In that Recommendation, the Case Manager recommended that the FSP should indemnify the Applicant for certain stated matters but had no obligation for additional matters. 5. The Recommendation was not accepted by the Applicant. Pursuant to clause 8.5(c) of the Terms of Reference of the Service, the Applicant requested that the dispute proceed to determination. Determination Case No: 319813 Determination Page 2 of 9 Summary of Applicant’s position 6. The Applicant says that there are various unresolved issues which require examination, including:  The replacement roller door is of an inferior quality;  The settlement for the air conditioning system was insufficient;  The FSP has failed to adequately attend to the replacement of roof tiles;  He was poorly advised and left disadvantaged through the lack of temporary accommodation offered; and  Other outstanding repair/damage issues remain, including: the plastic air vent, damage to doors and walls, the wall heater, floor tiling, stove top, solar panels and bathroom issues. 7. Subsequent to the Recommendation, the Applicant has lodged a further submission raising a number of issues, some of which have already been dealt with. 8. I propose to consider the issues raised by the Applicant within the further submission at a later stage of this Determination. Summary of FSP’s position 9. The FSP is of the view that the Applicant’s claim has been resolved. 10. It considers that many of the noted issues have been addressed through the repairs already completed and others are not related to the event and/or were caused by other means. 11. The FSP relies on the following policy provisions: Page 8 of the Product Disclosure Statement (PDS) “ When your buildings are protected The specific events that your buildings will be covered for are listed in the table below. This cover is subject to the exclusions outlined on pages 43 – 44. ” Page 10 of the PDS “ When your buildings are protected (continued) Event We will cover We won’t cover ... Fire or explosion Loss or damage as a result of a fire or an explosion. Loss or damage caused by a bushfire or grass fire that occurs within 48 hours of the start date of your Policy Case No: 319813 Determination Page 3 of 9 unless you took out your insurance with us immediately after: i. another insurance policy covering the same buildings expired, without a break in cover, or ii. the risk passed to you as purchaser of your buildings. ...” Page 15 of the PDS “ Additional buildings benefits ... Additional benefits We will cover We won’t cover Alternative temporary accommodation (including for pets) Costs of alternative accommodation for up to 12 months if your buildings suffer loss or damage and you are unable to live in your home as a result. The loss or damage must occur as a result of an event we have agreed to cover. ... We will not cover this, if you do not need to pay for alternative accommodation . ...” Page 43 of the PDS “ Buildings and contents cover exclusions We will not pay for any loss or damage which is caused directly or indirectly by: iii. ... iv. erosion, rust, corrosion, gradual deterioration, depreciation, wear or tear v. ... vi. a defect in an item, structural defects, faulty or poor workmanship or design... ” Page 49 of the PDS “ How we settle a buildings claim ... If we accept your claim, we will decide whether to: Case No: 319813 Determination Page 4 of 9 vii. repair viii. rebuild ix. pay you the cost to repair or rebuild that part of your buildings that suffered damage (cash settlement). ... What happens if we decide to repair your buildings If we decide to repair your building(s), we will: • only repair the part or parts of your buildings that actually sustained damage, including damaged portions of fixed coverings to walls, floors and ceilings, in the rooms, halls or passages where the damage occurred, to a condition as close as possible to when new, but not better • try to match any material used to repair your buildings with the original materials or nearest equivalent available to the original materials...” Page 50 of the PDS “ What happens if we decide to pay you the cost to repair or rebuild your buildings If we decide to pay you the cost to repair or rebuild your building(s) we will: • pay you the cost of repairing your building(s) to a condition as close as possible to when new, but not better • pay you the full building replacement cost of rebuilding your building(s) to a condition as close as possible to when new, but not better, in the event of a total loss • deduct any: - excess - unpaid premium - input tax credit you would have been entitled to under A New Tax System (Goods and Services Tax) Act 1999 if you had paid to repair or rebuild your buildings. ” Issue 12. Whether the FSP has finalised its obligations to the Applicant within the terms of the policy. Reasons for decision 13. I have reviewed all of the material provided by the parties and included within their respective submissions. 14. The Recommendation of the Case Manager has not been accepted by the Applicant and as such, this matter will proceed to determination in accordance with the Terms of Reference of the Service. Case No: 319813 Determination Page 5 of 9 “8.5 Dispute is resolved on the basis of the Recommendation. c) If, within 30 days of receiving the Recommendation, either: The Financial Services Provider does not accept the Recommendation in relation to the Dispute; or Either party requests FOS to proceed from a Recommendation to a Determination FOS will proceed to a Determination by either an Ombudsman or by a FOS Panel (as the Chief Ombudsman or his or her delegate decides is appropriate). Before the Determination is made, the parties will be given a reasonable opportunity to make submissions, and provide any further information, in response to the Recommendation.” 15. Subsequent to the Case Manager’s Recommend ation, the Applicant by way of an email of 18 November 2013, has provided a further detailed submission raising a number of matters in relation to the dispute. 16. The FSP has elected not to provide any further submissions in this matter and I presume relies upon the material previously presented for the purposes of the Recommendation. 17. I have considered all of the material as part of this Determination. 18. The first issue raised by the Applicant within his further submission and considered by the Case Manager within the Recommendation relates to the roller shutter. 19. Within his further submission, the Applicant has said that he accepts the Case Manager’s Recommendation insofar as the roller shutter is concerned. 20. The FSP has not responded to the Recommendation but given the evidence that has been presented, together with the relevant policy provision, I am satisfied that the FSP is required to match the original materials if at all possible and if the FSP is not able to source the item on a like-for-like basis, only then may the FSP rely upon an alternative. 21. The Applicant’s concerns regarding the quality of the replacement are highlighted in the report from AC. 22. Given the evidence, it is appropriate that the FSP ensure that the roller shutter replacement is of the same original materials as used in other areas of the home, should this type of unit be available. If that unit is not available, then I am satisfied the FSP may rely upon the replacement used but in any event the FSP is still required to ensure that it is worki ng properly. 23. In the circumstances, I am satisfied that it is appropriate for the FSP to arrange for an inspection of the premises to verify the quality and suitability of the replacement material and to ensure it is working properly. Case No: 319813 Determination Page 6 of 9 24. The second matter rais ed within the Case Manager’s Recommendation is in relation to an evaporative cooling system and for the reasons detailed within the Recommendation, the Case Manager was of the view that the FSP should pay an additional $2,794 with respect to the evaporative cooling system. 25. Having considered the evidence presented, I agree with the additional allowance for GST. 26. In essence, the Applicant has agreed with this calculation save for the question of removal of the damaged unit. 27. As detailed earlier, the FSP has not responded to the Recommendation and in the circumstances I agree that it is appropriate that the FSP pay the additional sum of $2,794 with respect to the evaporative cooling unit. 28. As stated, the Applicant now says that the damaged unit was not removed as part of the demolition works. However, I do note that the Applicant elected to take a cash settlement in respect to the evaporative cooling system. 29. Given that the Applicant elected to and the FSP agreed to, cash settle this aspect of the claim, I am not satisfied that it is appropriate that the FSP make any further payments. In my view the FSP is entitled to assume that that aspect of the claim is finalised on the payment of a cash settlement. 30. I note that the Applicant raises a further issue with regard to the removal of the kitchen cabinetry and the storage of the old kitchen cabinetry. 31. The Applicant says he was forced to remove the old damaged kitchen himself but he has not presented any evidence of any expense incurred in respect to that matter and in the absence of that evidence I am not disposed to require the FSP to make any payment for the claimed expenses. 32. The Applicant says the scope of works states “remove and dispose of kitchen cabinetry including overheads and replace with similar”. 33. Unless the Applicant has been cash settled for the kitchen works, in my view the FSP should arrange for the removal of the cabinetry from the Applicant’s garage. 34. The next issue raised by the Applicant is in respect to roof tiles. 35. The Applicant says that he will be getting an independent expert to access the roof tiles for damage caused by the fire. However, the Applicant has not provided an independent expert and on the basis of the material already presented, I am satisfied that the FSP should only be liable to replace those tiles that were damaged in the fire incident. I am not satisfied that there is any evidence to support that the tiles were made more brittle or damaged as a result of the fire and I am not satisfied that the FSP is liable to pressure clean or recolour the remaining tiles. 36. Accordingly, I am of the view that this aspect of the claim has been resolved. Case No: 319813 Determination Page 7 of 9 37. Within the further submission, the Applicant says that the scope of works in respect to the solar panels includes a requirement to supply and install a new electrical power circuit to the solar panel array, including inverter and connection to the existing electrical metre box and provide a certificate of compliance on completion. 38. The Applicant says that this has not occurred so that he has not been able to use the solar panels. 39. In my view, in the event that this aspect of the claim has not been cash settled, the FSP should be required to ensure that the solar panels have been repaired in accordance with the scope of work and the FSP’s obligations to the Applicant are not finalised until such time as the scope of works has been completed. 40. The Applicant has raised the question of the heater in the lounge room but concludes by saying that he is not asking anything in respect to this matter and as such I do not propose to address that question further within this Determination. 41. The Applicant says that the scope of works requires the cleaning, preparation and painting of the eave lining but this has not been completed. The Applicant says that the eaves were not cleaned but just painted. 42. My commentary in relation to this matter is the same as my commentary in relation to the solar panels and it is incumbent upon the FSP to ensure that the scope of works is complied with. 43. In addition, the Applicant has pointed to a number of other issues and has advised of correspondence between the parties wherein he says that the representative of the FSP has said that they are currently in the process of arranging the repairs and expect these repairs to be completed by mid next week (which I take to be the first week of December 2012). 44. The Applicant says that the item should have been finished by 5 or 6 December 2012, which was obviously not the case. The Applicant says further that in any event it is still a breach of contract by the FSP and their representatives and the Applicant says that now over 12 months have gone by and there is still no end in sight. 45. Given all the circumstances of this matter, I am of the view that it is appropriate that a suitably qualified expert attend at the property and evaluate the issues identified by the Applicant, in accordance with the terms of the policy and this Determination, with a view to rectification or repair, where necessary. 46. I am satisfied that the onus in relation to establishing that these issues are claim related and outstanding, remains with the Applicant. 47. The final matter raised by the Applicant is the question of temporary accommodation and lack of compensation. Case No: 319813 Determination Page 8 of 9 48. The Applicant points to the policy provision that provides for the cost of alternative accommodation of up to 12 months, if the Applicant’s building is unable to be lived in. 49. The Applicant recognises that the policy does say “we will not cover this, if you do not need to pay for alternative accommodation” but the Applicant says the fact is that he did need to pay for it but could not afford to pay for it and was fortunate enough to be able to obtain accommodation with his parents. 50. There is no evidence that the Applicant has had to pay any amount of money in respect to this accommodation. 51. I am satisfied that the commercial intent of the policy is clear, in that an amount for alternative accommodation is payable when an expense is incurred by the Applicant for the alternate accommodation. 52. In the absence of payment by the Applicant for the alternate accommodation, I am not satisfied that the FSP is required to make any payment for that specific item. 53. However, I note the terms of clause 9.3 from the Terms of Reference provides that the Service may decide that the FSP compensate the Applicant for non-financial loss where there has been an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with the Applicant’s expectation of enjoyment or peace of mind. 54. I agree with the Case Manager’s commentary in relation to the delay. It is quite apparent from the evidence that the original repair work was not of an acceptable standard and that this was confirmed in the report from AC and unfortunately was still not perfected when the home was later inspected by RC. 55. The length of time taken to resolve this matter has in my view put the Applicant to serious inconvenience and the inconvenience arose as a result of the standard of the initial repairs and the delays that have resulted. 56. In the circumstances, I am of the view that the FSP should pay the Applicant compensation in the sum of $1,000. 57. The Applicant has raised a number of other issues which I have not specifically addressed above but were addressed within the Case Manager’s Recommendation. 58. In my view and consistent with paragraph 45 above, the FSP should arrange for an independent expert to visit the home and view these further highlighted issues. 59. In addition to the issues of the solar panels and painting of the eaves, the expert should also provide a report in relation to the issues relating to the bathroom including the cleaning and re-grouting of the glass bricks, together with a consideration of the alleged damage to the air vent and the causing of Case No: 319813 Determination Page 9 of 9 plaster holes and the defective repairs alleged to be related to the door and floor tiles. 60. As with the earlier matters, the onus remains with the Applicant to establish that this additional damage is covered under the terms of the policy. 61. Upon receipt of the expert’s report, the FSP is to attend to rectification, repair and/or payment based upon the conclusions of the expert within their report. Determination 62. I determine that the FSP is to meet its obligations in accordance with the Determination herein. 63. If the FSP is to cash settle any part of the Applicant’s claim (save for the payment of compensation), then a cash settlement is to include interest at the statutory rate from 28 November 2012, being the date of the CS report, until the date of settlement.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.