Determination 319717

Lender's progress payments to builder and alleged duty to ensure construction quality

FirmFinancial Firm (Unknown - Credit)
Decided2015-02-19
ProductCredit · Home loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicant claimed the lender should have prevented or stopped progress payments to the builder for defective slab work on her home and should compensate her. AFCA found the lender owed no duty to ensure construction quality and had acted on her instructions, so the determination was in favour of the lender.

A lender acting as a business counterparty rather than an advisor or supervisor is not obliged to inspect construction or protect the borrower's interests, and must follow the borrower's payment instructions.

Issues

Subjects and remedies

financial hardshipno remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Consumer Credit - Construction Loans - FSP Decision - Denial of claim- Exclusion/ condition Credit - Consumer Credit - Construction Loans – Financial difficulty – Decline of Financial Difficulty Request Determination Case No: 319717 Determination Page 1 of 6 Case number : 319717 1 9 February 2015 1 Overview 1.1 Dispute The Applicant obtained a loan from the Financial Services Provider (FSP) to pay for the construction of her home. The loan was funded by a series of progress payments to the builder at set stages of construction. This dispute is about whether the FSP breached a duty or obligation to the Applicant in making the progress payments to the builder, and whether the FSP was required to ensure the home was constructed correctly. The Case Manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination. The Applicant rejects the Recommendation because:  The FSP, and not her, authorised the builder to commence construction. The Applicant says the FSP should have obtained a copy of the building permit and building insurance certificate before giving the builder authority to commence construction.  The FSP had a duty to protect her interests and ensure her home was constructed correctly.  The FSP has not disclosed all the information it holds about the issues in dispute to avoid incriminating itself. She has not received copies of all of the information the FSP provided to FOS, in particular the FSP‟s internal policies.  The Recommendation may have been influenced by employees, officers and agents from the finance industry. Therefore the Recommendation is not an independent decision.  The FSP refuses to release the final progress payment to her and in doing so has not complied with its obligations to assist her overcome her financial difficulty. 1.2 Issues and Key findings Were the findings of the Recommendation correct? The findings contained in the Recommendation were correct and are adopted in this Determination . Further submissions provided after the Recommendation have Case No: 319717 Determination Page 2 of 6 been considered but do not establish the FSP owed the Applicant a duty to ensure her home was constructed correctly. 1.3 Determination This Determination is in favour of the FSP. I agree with the case manager‟s reasons for the Recommendation and the recommended outcome.  The Applicant is not entitled to compensation.  The FSP may decline the Applicant‟s request for further funds to overcome her financial difficulty. Case No: 319717 Determination Page 3 of 6 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case manager‟s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. My view on the Applicant‟s reasons for rejecting the Recommendation are outlined below. The importance of when the FSP obtained a copy of the building permit has been overstated The Applicant says everything turns on the FSP signing an “Authority to Commence Construction” document before obtaining a copy of the building permit. However in relation to determining the FSP‟s liability to the Applicant, it does not matter when the FSP obtained a copy of the building permit. This is because the FSP was no t the Applicant‟s advisor. It was simply the lender providing funds to the Applicant so she could pay the builder. The responsibility to ensure things such as the building permit and insurance were in place before construction commenced (and it turns out that they were in place before construction commenced) rests with the Applicant as owner, not the FSP as lender. The FSP did not authorise the builder to commence construction The Applicant suggests that the FSP authorised construction of her home to commence when it signed an “Authority to Commence Construction” form. The “Authority to Commence Construction” form the FSP signed was a document giving the builder comfort that the Applicant‟s finance was in place and that progress payments would be made upon the FSP receiving a payment instruction from the Applicant. It did not authorise the builder to commence construction because only the Applicant as owner of the land could do this. To the extent that the builder commenced construction without the Appl icant‟s authority, that is a matter between the Applicant and builder. The FSP was not required to protect the Applicant In rejecting the Recommendation and making her claim for compensation against the FSP, the Applicant essentially says that the FSP had an obligation to ensure her house was built in accordance with local council and government requirements, and to Australian building standards. Case No: 319717 Determination Page 4 of 6 However the FSP was not required to do so because it was not acting in an advisory or supervisory role in its dealings with the Applicant. That is, it was not obliged to protect the Applicant‟s interests . The parties relationship was a business one The relationship between the FSP and Applicant was a purely business one – the loan representing a standard and relatively simple business transaction in which the Applicant wanted to obtain funds to build her home and the FSP wanted to provide those funds and obtain an interest in the property (as registered mortgagee) to secure the Applicant‟s obligation to pay. Whether or not the FSP or Applicant engaged experts such as engineers, building inspectors and the like either before, during or after construction of the home was a choice for each party to make. It appears that the FSP was comfortable proceeding with the loan without engaging such experts other than a valuer to inspect the home during construction but that was its choice. Likewise it was the Applicant‟s choice whether she engaged experts. The FSP also provided the Applicant with a step by step guide to requesting progress payments. Step 1 is requesting a payment and contains the following note: Important note: when requesting a progress payment please ensure that you‟re satisfied with the construction, and that the work has been completed to the stage as agreed in your building contract schedule. While the Applicant says she advised the FSP of defects in the work performed by the builder, even if she did so it was still open for the FSP to make a progress payment that was authorised by the Applicant without inspecting the property. The FSP, like the Applicant, ran a risk of the house not being constructed correctly if it was not inspected but that was a risk each party could take without breaching an obligation owed to the other. To hold the FSP responsible for the loss the Applicant claims to have incurred as a result of her home not being constructed correctly would be placing the FSP in a fiduciary-type role, which is not the role the FSP played in this particular case. The FSP complied with its progress inspection policy The relevant part of the FSP‟s policy dealing with progress inspections says: When the To Be Erected (TBE) valuation indicates that the end LVR will be: >=0% LVR = progress inspections at frame and at practical completion will be required. <80% LVR = progress inspection at practical completion is required. The FSP obtained a valuation showing the completed valuation of the property was $328,000. The loan amount was $262,000 meaning the Loan to Value Ratio (LVR) was less than 80%. Case No: 319717 Determination Page 5 of 6 As the LVR was less than 80%, a progress inspection was only required by the FSP at practical completion of the Applicant‟s house . While the builder has made a request for final payment, the Applicant disputes the builder has completed her home and has instructed the FSP not to make the final progress payment. If or when the Applicant authorises the final payment to the builder, the FSP should inspect the property in accordance with its policy. However the FSP is not required to do so beforehand. As at the date of this Determination, the FSP has complied with its policy on progress inspections. The FSP was entitled to make the progress payments to the builder once instructed to do so by the Applicant The Applicant says that she only authorised the progress payments because the FSP told her to and that “My hands were tied, an d I was forced into a financial sinkhole on the FSP advice and scare tactics.” It is evident the Applicant had concerns early on in the construction of her home about the design of house slab, the quality of the builder‟s workmanship and whether each met the applicable Australian standards. There is also no doubt that the Applicant was in a difficult position when it came to authorising the progress payments to the builder. On the one hand the Applicant had concerns about the standard of building taking place. On the other a decision to not pay the builder would result in work stopping, and action to recover payment for the work it had performed to that date. A statement from the FSP, if given, that she risked being sued by the builder for non-payment was an accurate summary of the situation and not inappropriate. While the Applicant may have felt she had very little choice but to pay the builder upon receiving its progress payment demands, the choice to pay, despite being made in difficult circumstances, was still hers to make and was one she made freely. Once the decision to pay the builder was made by the Applicant, the FSP was obliged to make the payments in accordance with those instructions (which it did in this case). The FSP was not required to release money from the loan to assist the Applicant pay her legal fees The Applicant suggests that the FSP should have given her money from the loan to help pay her legal fees. However the FSP was entitled to decline this request because the loan contract provided the funds were to be used to pay the builder. The FSP‟s decision to decline the Applicant‟s request did not breach its duties to assist the Applicant overcome her financial difficulty. The FSP‟s financial difficulty obligations apply to debts the Applicant owes the FSP, not a debt the Applicant owes her solicitor or others. Case No: 319717 Determination Page 6 of 6 The FSP may decline the Applicant’s request for further funds As the FSP has already agreed to interest only payments during the construction period (and is entitled to decline the Applicant‟s request for the final loan amount to be paid directly to her), there is no further variation that FOS can direct the FSP make to the loan to assist the Applicant overcome her financial difficulty. A repayment holiday where the Applicant is allowed to miss one or more payments and direct those funds to pay her other debts would not change the Applicant‟s o verall debt position. The Applicant‟s l oan would simply increase by the redirected interest payment, and the amount available to pay the final progress payment to the builder would decrease. An indulgence by the FSP to waive or reduce interest would obviously assist the Applicant but such a decision is a commercial decision by the FSP that FOS is unable to review. FOS is independent The Applicant has expressed a concern that FOS may have been influenced by employees, officers and agents from the finance industry. The Banking Specialist that provided advice in this dispute is employed directly by FOS, not a financial service provider. While a Banking Specialist is seconded to FOS from financial services providers from time to time, he or she does not provide advice on matters involving their ultimate employer. In addition, an Ombudsman is not bound to accept the advice they provide. The decisions of the FOS Ombudsman are independent of any interference from all parties, including the FOS Board. Further, to ensure its independence, FOS:  i s governed by an independent board of equal members of consumer and financial services industry representatives , with an independent chair  d oes not act for the person or entity lodging the dispute or the financia l services provider it concerns  Ombudsmen are not employed by the financial services providers or consumer groups. Recommendation Credit - Consumer Credit - Construction Loans - FSP Decision - Denial of claim- Exclusion/ condition Recommendation Case No: 319717 Recommendation Page 1 of 6 Case number : 319717 29 October 2014 1 Overview 1.1 Dispute The Applicant has a construction loan with the Financial Services Provider (the FSP). This dispute is about whether the FSP should have made progress payments to the Builder engaged by the Applicant to complete the construction. 1.2 Issues and key findings Did the FSP improperly approve the start of construction? The Applicant consented to construction starting. The building permit and construction insurance were issued before construction started, although the FSP had not yet obtained a copy. Was the FSP obliged to obtain progress inspections? Would such inspections have uncovered the alleged slab defect? The FSP was not obliged by the loan contract or good industry practice to obtain progress inspections before making progress payments. Progress inspections by a valuer were unlikely to have uncovered the alleged slab defect. Should the FSP have agreed to make progress repayments? Even if the FSP was aware of the building dispute, the FSP was not responsible for resolving a dispute about engineering standards. The Applicant authorised the progress payments and the FSP was entitled to act on the Applic ant‟s instruction. Did the FSP comply with its obligations to the Applicant as a customer in financial difficulty? The Applicant‟s financial difficulty was prolonged and caused by the building dispute. The Applicant did not request short term assistance. 1.3 Recommendation This Recommendation is in favour of the FSP. The FSP is not required to pay compensation to the Applicant. 2 Reasons for Recommendation Case No: 319717 Recommendation Page 2 of 6 2.1 Did the FSP improperly approve the start of construction? The Applicant consented to construction commencing The Applicant says that the FSP gave consent for construction to commence, and that it did so without obtaining a copy of the building permit and the construction insurance. In early February 2010, the Builder asked the Applicant to have the FSP complete an „Authority to commence construction‟ form. Emails show that the Applicant asked the FSP to complete the form. On 25 February 2010, the Builder emailed the Applicant and told her construction was booked to commence on 1 March 2010. The Applicant thanked the Builder for this information by return email. By her actions the Applicant consented, at least impliedly, to the commencement of construction. The building permit and construction insurance were issued before construction commenced The Appl icant says that the FSP should not have completed the „Authority to commence construction‟ without first obtaining the building permit and building insurance certificate. The FSP‟s policy would have required it to obtain these documents. However, nothing turns on this as the building warranty insurance was issued on 11 February 2010, and the building permit issued on 16 February 2010. Therefore, the relevant documents were issued before construction commenced in early March 2010. If the FSP had asked for these documents it would have received them and construction would have started in any event. The FSP obtained a copy of these documents before it allowed the first progress payment on 27 April 2010. 2.2 Was the FSP obliged to obtain progress inspections? Would such an inspection have uncovered the alleged slab defect? The loan contract did not oblige the FSP to obtain progress inspections The Applicant says that:  The slab was not engineered and was unsuitable for the soil type.  The FSP was obliged to complete progress inspections, and that these inspections would have uncovered the alleged slab defect. The Applicant has noted the following provisions of the standard loan terms and conditions: 1. The FSP needs to be satisfied that the security property is acceptable, and may arrange an inspection or valuation before the borrower draws their loan [Clause 1(a) and 1(b)]. Case No: 319717 Recommendation Page 3 of 6 2. Before the borrower can draw progress payments, the borrower will need to provide a progress inspection by a licensed valuer. However, this is only i f the FSP requires the inspection [Clause 4(b)]. The contract clauses set out at number 1 above are under the heading „Before you can draw your loan‟. These clauses disclose possible conditions the FSP might place on the first draw down. The FSP obtained a valuation on 6 November 2009 . Based on the valuer‟s opinion, the FSP was satisfied that the property would be acceptable security once construction was complete. The contract clause at number 2 above gives the FSP the discretion to require a progress inspection before a borrower can draw a progress payment. The FSP is not contractually obliged to order inspections. Further, the above contract clauses do not act as a warranty from the FSP to a borrower that the FSP will ensure the security property is of sufficient security value. The FSP did not owe a duty of care as claimed by the Applicant The Applicant says that:  The FSP had a duty of care to ensure that the completed construction was of sufficient value to provide adequate security for the loan.  By not obtaining inspection reports, the FSP breached its duty of care. The FSP‟s obligations to the Applicant are based in the contract between the parties, and its role is to be the lender. A lender does not generally have a higher duty of care, or a fiduci ary duty, to act in the borrower‟s interests. The FSP did not owe the Applicant a duty of care to ensure the property was of sufficient security value. The FSP did not breach good industry practice by deciding not to obtain progress inspections The Applicant says that the FSP was obliged by usual industry practice, and its own usual procedures, to obtain progress inspections and compliance certificates. The FSP‟s conduct of the construction loan has been reviewed by a FOS Banking Specialist. The Banking Specialist has had extensive experience in the banking and financial services industry. Prior to construction commencing, the FSP decided that it would not require a progress inspection until construction was completed. This is recorded in a file note dated 2 1 November 2009. The Banking Specialist‟s view is that it is not unusual, in relation to construction projects of this smaller size, for a lender not to require progress inspections. A lender may decide not to obtain progress inspections because:  Progress inspections incur extra costs for the borrower.  If the builder was of good standing and reputation, as in this case, the lender could generally expect construction to be completed in accordance with relevant regulations and good workmanship. Case No: 319717 Recommendation Page 4 of 6 Therefore, the FSP has not breached good industry practice. However, the FSP has not provided a copy of its own policy about progress inspections. Therefore, it has not been established whether the FSP complied with its own policy when it decided not to seek progress inspections. A progress inspection ordered by the FSP would not have uncovered the alleged structural issue Even if the FSP had an obligation to order progress inspections, it was unlikely that such an inspection would have uncovered the alleged slab defect. A progress inspection is performed by a licensed valuer. The valuer will perform a surface inspection and form a view about whether the work completed is consistent with the progress payment request. The valuer performs the inspection on the lender‟s be half, and the progress inspection is not a substitute for the borrower‟s own building or engineering inspections. The valuer is not typically an engineer or have the task of auditing compliance with building codes and regulations. 2.3 Should the FSP have agreed to make progress repayments? It has not been established that the FSP was aware of the building dispute before it made progress payments to the Builder I have reviewed:  The FSP‟s file notes showing contact between the FSP and the Applicants in relation to the construction loan.  Statements of recollection from the Applicant and the FSP branch officers. The Applicant says that she first made the FSP aware of the building dispute in April 2010. She says she informed two FSP officers at her local branch a nd also the FSP‟s lending area in another capital city. FSP officer PN recalls only that the Applicant advised the FSP of the building dispute within 12 months of the FSP funding the construction loan. FSP officer GT‟s recollection is based entirely on th e file notes. The FSP‟s file notes first record mention of the building dispute in May 2011. There is no documentary information which objectively establishes that the FSP was aware of the building dispute before it made progress payments. On 15 and 16 June 2010 the FSP funded the frame, lock up and fixing instalments of the building contract. No further stage payments have been funded. The FSP was not responsible for resolving a dispute about whether the slab was defective Case No: 319717 Recommendation Page 5 of 6 The Applicant says that if the FSP was aware of the building dispute, then it was obliged to cease progress payments until the Builder rectified their defects. However, at the time progress payments were requested, it had not been independently determined that the slab was defective. The Builder was satisfied that the slab was suitable and apparently had engineering reports and compliance certificates including:  On 20 January 2010, a foundation investigation report was prepared by an Engineer.  On 29 March 2010 an „Engineering Certificate of Compliance –Design‟ was issued. The Applicant‟s father (also an engineer) had a different view. The Applicant‟s father‟s view that the slab was unsuitable for the soil type has subsequently been supported by expert advisers engaged by the Applicant. A financial services provider is not responsible for adjudicating a dispute over engineering standards. As it was, the building dispute later proceeded to the relevant tribunal. The Builder continued to submit that it had complied with relevant codes and standards, and the Engineer was added to the dispute. The parties eventually reached terms of settlement in October 2013. The Applicant authorised progress payments while aware of the building dispute The Applicant had concerns about the suitability of the slab from February 2010. On 7 April 2010, the Applicant sent an email authorising the Builder to continue construction, but advising the Builder that she would hold the Builder responsible for any defects that later emerged. By early June 2010, t he construction had been completed to „fixing‟ stage. In mid - June 2010, the Applicant provided the FSP with a signed authority form and then verbally authorised the outstanding progress payments. The Applicant was aware of potential issues with the slab at the time she authorised the payments. It has not been established that the FSP gave the Applicant incorrect advice about whether to authorise progress payments The Applicant says that she only authorised the payments because the FSP told her:  If she did not authorise the progress payments she would be in breach of her contract with both the FSP and the Builder.  Both the FSP and the Builder would fine her for breach of contract. There is no objective documentary information to show that the FSP made these statements. Apart from the loan contract documents, the only other relevant document we have is a progress payments fact sheet the FSP provided to the Applicant. This fact sheet states: Case No: 319717 Recommendation Page 6 of 6 “ Important note : when requesting a progress payment please ensure tha t you‟re satisfied with the construction, and that work has been completed to the stage as agreed in your building contract schedule.” If the FSP told the Applicant that the Builder might pursue her for breach of contract, that information was not necessarily incorrect. By June 2010, the Builder had almost completed construction and had only been paid the „base‟ stage payment. If the Applicant did not authorise progress payments owing to the Builder, it is possible that the Builder would have taken recovery action against the Applicant. In June 2010, the Applicant had to decide whether to authorise payments or engage in proceedings against the Builder about the alleged building defects. The FSP was entitled to act on the Applicants instructions. 2.4 Did the FSP comply with its obligations to the Applicant as a customer in financial difficulty? The Applicant says that:  The FSP will not “close off” the construction loan and transfer her to a loan with a lower interest rate.  Because of the FSP‟s actions, she is una ble to refinance her loan to another lender. The FSP says that the Applicant would not have been in any better position if the progress draws had been completed. There was no option to transfer to a lower interest rate. The Applicant could have formally applied for interest only repayments, but the loan has interest only repayments in any event while it is still open for progress draws. If the Applicant cannot refinance because the security property is yet to be issued with a certificate of occupancy, then this has not been caused by the FSP. There has been no suggestion that the Applicant has requested other forms of short term assistance. Construction loan repayments are up to date and there is no information to show that the Applicant has sought other financial difficulty assistance.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.