Text of the determination
Case No: 319190 Determination Page 1 of 11
Case number: 319190
General Insurance - Domestic Insurance - Home Building - Service - Delay in
Claim Handling - Dispute Over Extent of Damage - Quality of Repairs
14 March 2014
Summary
Description
A claim under a Home and Contents policy for water damage sustained as
a result of a burst water pipe in July 2012.
A dispute has arisen as to the extent of the repairs conducted by the FSP.
Basis of Determination
The Applicant’s property suffered water damage as a result of a burst
water pipe, blocked storm water drain and also possibly as a result of a
storm event.
The FSP has engaged the services of an independent engineer to inspect
and evaluate the nature of the ongoing damage claimed by the Applicant
and adequacy of repairs conducted.
The engineering report is detailed and identifies the majority of the
ongoing damage claimed by the Applicant is not related to the claim but
also identifies further areas to be completed by the FSP.
The FSP has offered to have further assessors attend the property and
arrange for a further inspection of the property.
Whilst there has been some delays in this dispute, there is no evidence
that the FSP has not acted appropriately to try and resolve the issues with
the Applicant’s claim.
Determination
The FSP is to attend to further works identified in the body of this
Determination and to cover potential additional accommodation costs
incurred.
The FSP has otherwise met its liability in accordance with the terms of the
policy.
Determination
Case No: 319190 Determination Page 2 of 11
Background
1. The Applicant held a home and contents insurance policy with the Financial
Services Provider (FSP) at the relevant time.
2. On 25 July 2012, the Applicant lodged a claim for damage to her home that
was subsequently found to have occurred as a result of a burst water pipe
and a subsequently blocked stormwater drain.
3. The FSP accepted the claim and determined that the repairs required meant
that the Applicant would have to move out of the home for a short period.
The Applicant did this but the repair process ultimately took the FSP
significantly longer than expected.
4. The Applicant remains dissatisfied with the quality of work done by the FSP’s
contractors, the extent of the repairs undertaken, the time taken to attend to
it and ongoing problems she has at the property.
Summary of Applicant’s position
5. The Applicant says that the FSP told her that she would need to move out
for a few weeks and it was ultimately about 12 months before she was able
to move back home. She and her daughter had to stay with other family
members and were seriously inconvenienced during this time.
6. The two events caused extensive damage to the property, not all of which
the FSP has repaired.
7. Of the repairs that were done, many of these repairs were not to an
acceptable standard and the Applicant believes that the FSP should be
responsible for attending to this.
8. She has suffered from ongoing respiratory problems since moving back into
the home and attributes this to the acknowledged bacterial problem that
arose as a result of moisture intrusion into the home.
Summary of FSP’s position
9. The FSP says that it has provided indemnity to the Applicant for her loss.
There may be some issues that remain but these matters require ongoing
assessment which the FSP is prepared to do.
10. Whilst there may be issues cited by the Applicant with the property itself,
there is no evidence that most of these issues are in any way related to the
insured events.
11. To properly evaluate the merits of the Applicant’s dissatisfaction, an
engineering expert visited the property and confirmed that the repairs were
Case No: 319190 Determination Page 3 of 11
(in the main) satisfactorily completed and that the issues that remained were
generally not related to the insured events.
12. The FSP otherwise relies on the general provisions and policy conditions
outlined in its Product Disclosure Statement (PDS).
Issues
13. Whether the FSP has adequately attended to the damage at the Applicant’s
home, incurred as a result of the burst water pipe/drain blockage.
14. Whether any of the remaining issues at the property are claim related.
15. Whether the FSP handled the matter appropriately and whether
compensation is appropriate.
Reasons for decision
16. I am satisfied that a full exchange of the relevant information has taken place
between the respective parties and that each party has had the opportunity
of addressing any issues raised.
17. The parties have raised numerous issues in their submissions to the Service.
For the purpose of this Recommendation, I will restrict my commentary to
only those issues I consider relevant to the outcome.
18. The Applicant’s home was damaged through the combined effects of burst
water pipe that was left untended for about two weeks whilst she was on
holiday and a blocked stormwater drain. Little evidence has been submitted
by the parties in relation to the origin, detection or original repairs, although it
is conceded that the Applicant had a valid claim under the policy.
19. Repairs were attended to at the Applicant’s home and it is not in dispute that
these took longer than intended or that the Applicant was upset with the
delays and the subsequent quality of the work done.
20. In her submissions to the Service, the Applicant suggests that the damage to
her home that remains in dispute includes (but is not necessarily limited to):
The need to replace blinds in the home;
Inferior “two - tone” paint job inside the home;
Poor quality general repair work completed;
Cracks in the plaster and corners of the home;
Separation and incomplete finishing of the skirting boards;
Cracks in the archway, plaster walls, bookcase and ceiling;
Case No: 319190 Determination Page 4 of 11
A hook was removed from behind one of the doors, with a poor patch
job attempted;
Damaged and/or removed light fittings;
Bowed ceiling;
Misaligned doors in the home and sliding door rear entrance;
Uneven settling of the concrete pathways outside, cracks in the surface
from heavy vehicle/equipment use and uneven colouring and staining ;
Cracks to the slab under the outdoor shed;
Bowing of the roof line for the home, with cracks in the mortar and
some tiles;
Inconsistent application of the render used for the brickwork, rising
damp from lingering moisture or a failure to properly dry out the area;
Rust on downpipes;
Unevenness in the backyard which needs compaction/backfilling.
21. The Applicant has supplied videos and photographs of the damage apparent
at her home indicating the areas of damage and areas of concern.
22. The Applicant attributes the damage to the water damage claim and the
work of the FSP’s contractors in repairing this damage.
23. In order to fully evaluate and consider the issues highlighted by the
Applicant, the parties agreed to the appointment of an engineer to inspect
and report on the extent and possible causes of the damage sustained to the
property.
24. BS was appointed by the FSP to provide an independent expert report. The
report focused on four main areas apparently suggested by the Applicant,
including the concrete under the patio, the front window, the ramp leading
into the home and the internal damage to the walls and ceilings.
25. To assist in the inspection, BS engaged the assistance of a builder (“DC”) to
provide a secondary opinion and input into the report. The Applicant and her
daughter were also present to show the experts the affected areas and to
provide their views as to the possible causes. The report detailed a timeline
of relevant events for the home, including:
That it was constructed in or around 1976/77 and an extension was
added to the western side of the property in 1992;
In or around 2005/06, the Applicant reported that there had been a “lot
of water lying in the area” and the loca l council responded by placing
chip bark in the reserve situated behind the property;
In 2012, the water pipe under the home leaked for about two weeks
whilst the Applicant was on holiday. The stormwater drains became
Case No: 319190 Determination Page 5 of 11
blocked and water subsequently drained under the home. Heating
ducts at the property were infused with water and this was blown into
the home, causing mould and bacteria to generate;
After the lodgement of the claim, the FSP’s repairer “PR” conducted a
“major rehabilitation program” at the home, which required the
Applicant to move out for a period whilst this work was completed. PR
attended to renovating the home and the:
“...replacement of heating ducts and drying out of the sub -floor area.
Cupboards, vanity units and troughs were replaced. All existing floor
coverings were removed and a floating floor installed. Vinyl flooring was
supplied to the bathroom and laundry. The western extension concrete floor
was ground down and sealed.
Water pipes were tested to be ok and stormwater drains located and cleaned.
Part of the driveway was replaced to drain away from the western side of the
house.
Other minor works were carried out. During the works program a steel
container was placed on the front driveway and a large part of the backyard
was excavated.”
26. On to the inspection of the interior BS, under the guidance of the Applicant
and her daughter, noted that there were numerous ongoing or unresolved
issues with the home, including:
The plaster to the rear wall was loose in the first bedroom, with
diagonal cracks emanating from the four corners of the window;
There was a significant sag over the window to the second bedroom
but no cracks;
A hairline crack was present at the door head to the third bedroom,
which also affects the hallway;
Mould was present in the ceiling and near the light fitting of the ensuite;
Hairline cracks were visible in the first living room, hall and third
bedroom;
There were “slight cracks” in the plaster join of the ceiling plaster over
the kitchen;
The lounge had cracks in the plaster of the lintel over the doorway and
slight cracks along the wall and cornice at the north west corner;
In the study there also was small cracks in the lintel plaster over the
doorway;
The second living room had only a ceiling crack at the south east
corner and there were no concerns in the spare room.
Case No: 319190 Determination Page 6 of 11
27. Inspection of the exterior of the home identified issues including:
Outside the study window, the brickwork was in good condition but the
timber frame for the home had shrunk and the window had not been
fitted properly. BS considered that these issues were not claim related;
The access ramp at the entrance to the property was in good condition
with “one small chip” , although no view was expressed as to whether
this was claim related;
The driveway was old and had aged cracks present. There were also
scuff marks from the use of a container used by the contractors;
The backyard had been excavated and roughly replaced;
Some areas of damp were present in the brickwork and scoria. The hot
water service had a faulty valve and was constantly dripping.
28. BS considered the home was generally “in very good condition”, though
there were a number of cracks present inside and outside the home that
were “typical of houses of this age in both plaster and brickwork”.
29. In relation to the specific areas identified as concerns by the Applicant, BS
noted:
The concrete under the patio was in a “good condition”;
The front window had been “poorly installed” and the damage present
was not related to the insured event;
The access ramp to the front of the property was in “sound condition”;
Of the internal cracking and damage to the walls and ceilings, some
were recent and some were long term. All of the walls and ceilings
should have been fully cleaned and repainted as part of the repairs
undertaken by PR. T his was “carried out in some areas but not all”. The
first bedroom required the plaster replaced and repainted, as should
the ceiling lining in the ensuite. Where small cracks were present in
painted rooms, it was likely that this should be considered “fair wear
and tear”, although in rooms which have not been repainted, this
should be attended to “for hygienic reasons”.
The cracks to the concrete driveway were not caused by heavy
machinery, though the area could be pressure cleaned to clear the
scuff marks present. He attributed these marks to the use of a heavy
storage container, probably used for rubbish removal.
The grassed area in the backyard was in a less than ideal state,
however the work required to be undertaken by the FSP had not been
completed to this area at the time of inspection.
The moisture patches in the scoria along the sideway were not claim
related.
Case No: 319190 Determination Page 7 of 11
Noting that there is drainage into the property from the council reserve,
the Applicant should consider the installation of agricultural drains at
the property. BS also suggested that fans might be considered for
under the home to ensure that this area remained properly ventilated,
although this was not cited as damage relevant to the insured events.
30. The Applicant has not responded to the issues raised in the engineering
report despite having the opportunity to do so.
31. As a result of the report the FSP agreed to arrange for a new assessor to re-
inspect the home and to review the damage to the internal walls in
accordance with the recommendation of BS. Since that undertaking was
made, the Service has received no update in relation to the matter.
32. It is clear that there remain unresolved issues with the repair of the
Applicant’s home.
33. In the absence of any alternative expert evidence, I am satisfied that the
report from BS can be relied upon. BS has left open the possibility that some
of the cracking and some of the ongoing issues may be related to the
damage sustained to the house and the work conducted by the FSP.
34. Certainly, I am satisfied that the FSP has some work left to attend to. Based
on the recommendations provided by BS in the engineering report, I accept
that:
A secondary and complete bacterial treatment of the home should take
place;
Repainting (or painting from scratch) of the identified problem areas
suggested by BS and to be verified by the FSP should be attended to.
It is my recommendation that the FSP should use a different contractor
for this;
A proper inspection of the insulation should be done to ascertain if it is
suitable for retention, noting the bacterial problems acknowledged to
have occurred at the home. Should there be any issues in this regard,
the insulation should be replaced at the FSP’s expense;
The first bedroom is to have the plaster replaced and the ceiling lining
must also be replaced in the ensuite;
The backyard has not been levelled properly and I consider this to be a
reasonable expectation for the Applicant. The FSP must retain an
appropriately qualified person to compact and re-level this area and lay
new turf if required.
35. Beyond the extra work detailed above, I am satisfied that there is no
persuasive evidence to link the cracking in the concrete areas in the
driveway to the use of heavy machinery or the water events. In all likelihood,
I consider that this damage is attributable to normal wear and tear.
Case No: 319190 Determination Page 8 of 11
36. There is no persuasive evidence to link the moisture in the sideway area of
the home to the insured events and BS suggested that these were more
likely influenced by the run-off problems from the council land, the faulty
valve on the hot water service and the lack of adequate ventilation under the
home after the extension was added. I am satisfied that the FSP is not
responsible for this damage.
37. I accept BS ’s conclusions in relation to the concrete under the patio, the front
window and the access ramp. I see no issues arising from the insured
events which require attention.
38. The Applicant suggested that the drying out of the property in the original
repair attempt was not adequately completed and that the blowers used to
dry in side the home had to run for approximately two months and not “a
couple of weeks” as was done.
39. No evidence was supplied in support of this contention. I accept that another
bacterial examination and treatment is necessary, although in the absence of
expert evidence on this issue, I am not persuaded that further drying work is
required.
Other issues with the home
40. The report from BS has limited commentary regarding the quality of the work
completed by the FSP’s contractors and any other possible problems
created by the alleged inadequacies of these efforts. It focuses primarily on
the condition of the home and attempts to evaluate if the damage is claim
related or not.
41. The Applicant noted a hook that had been removed from the rear of a door
inside the home and this would not appear to be relevant to damage caused
by the insured events, although it is alleged that this damage was inflicted by
the FSP’s contractors whilst they occupied the property. The FSP has not
disputed this and I am of the view that this work should be repaired as part of
the FSP’s ongoing obligations to ensure that the property is properly
attended to.
42. Whilst I am satisfied that the driveway (and the concrete slabs at the
property in general) were not damaged as a direct result of the event, BS
identified that scuffing was present on the driveway from the use of a storage
container or something similar by the contractors . BS suggested that the
resultant marking of the driveway could be pressure cleaned and restored
and I am satisfied that the FSP should attend to this.
43. The Applicant reported that there was “two tone” paint work showing around
areas of the home, including the skirting boards and windows. Noting that
repainting is required of the FSP, I expect that these issues should be
resolved as part of this process.
Case No: 319190 Determination Page 9 of 11
44. A smoke detector was allegedly damaged whilst the home was in the
possession of the FSP’s contractors and the FSP has not disputed this, I am
satisfied that this should be replaced.
45. The photographs and videos supplied from the Applicant demonstrate that
some of the fixed skirting applied during repair work was of an extremely
poor standard and this should be rectified by the FSP.
46. Whilst photos also show that there appears to be a bow through the roof of
the home (which the Applicant believes has also caused issues with the
ceiling), there is no evidence that this has resulted from the insured events. I
note that BS considered that the home was overall in pretty good condition
(presumably for its age), and I see no issue with this which requires the
FSP’s involvement.
47. The Applicant suggests that the rear sliding door was out of alignment,
although there is no evidence to link this to repair work or other issues
arising from the insured event. The same applies for the allegedly misaligned
floor boards, the concrete slab for the shed, the damage to the blinds, the
rusting downpipes, the garage floor and the brick wall at the rear of the
home. There is no evidence to link the alleged damage or problems with any
of these areas to the insured events.
48. It is further alleged by the Applicant that one of the laundry taps was
unnecessarily replaced by one of the FSP’s contractors and that the
replacement tap is of inferior quality. The FSP has not challenged this
statement or offered any commentary on this. I am satisfied that the original
tap should be returned to the Applicant and if this is not available, then the
FSP should arrange for a commensurate replacement.
Accommodation
49. As a result of the repair process, the Applicant and her daughter lived with a
relative. The Applicant’s policy provides for temporary accommodation costs
and the FSP offered to meet the nominal accommodation costs of $200 per
week for the period 20 May 2013 to 12 July 2013 being the date the
Applicant moved back into the property.
50. The Applicant does not dispute that she has received payment for the
accommodation costs for this period but is of the view that $200 per week is
not an accurate reflection of the true costs or inconvenience suffered.
51. The policy provides that the FSP meet the reasonable costs of
accommodation. The FSP identified that similar accommodation to the
Applicant’s home in the area was approximately $225 per week . As the
accommodation was with a relative and no actual charge made, I accept that
the FSP has acted reasonably in settling the accommodation costs at the
sum of $200 per week. Arguably, it could have elected to obtain evidence
from the Applicant of the actual costs incurred which has not been provided.
Case No: 319190 Determination Page 10 of 11
52. In addition to providing accommodation costs, the FSP agreed to indemnify
the Applicant for water and electricity costs incurred over at least part of the
period during which the Applicant was unable to occupy the home and the
contractors were using these facilities. I am satisfied that the FSP’s decision
in this regard was appropriate and made in the interests of genuinely
compensating the Applicant for the inconvenience she experienced .
53. It is possible that the Applicant will be required to relocate to enable the FSP
to attend to any additional work that I have identified. I accept that this does
cause inconvenience and that the FSP should either provide suitable
accommodation with wheel chair access and appropriate amenities to cater
for the Applicant’s daughter or again subsidise the Applicant at $200 per
week if she prefers to stay with a relative.
54. The payment for these costs should cover the period the Applicant is absent
from the home whilst the FSP completes the relevant repairs.
Compensation for non-financial loss
55. The Applicant has also sought compensation for non-financial loss
associated with the delays and stress involved in the handling of this dispute.
56. Paragraph 9.3 of the Terms of Reference provide that such compensation to
a maximum of $3,000 may be awarded by FOS in circumstances where an
Applicant experiences an unusual degree or extent of physical
inconvenience, time taken to resolve the situation or interference with an
Applicant’s expectation of enjoyment or peace of mind.
57. There is no doubt in examining this dispute that there have been errors
made and delays encountered with the repair process. Despite this, the FSP
has genuinely attempted to cater for the Applicant’s concerns and to repair
the home to a satisfactory standard.
58. The nature of the damage caused and loss inflicted was unusual and difficult
to isolate from the normal wear and tear issues that might affect a home of
this age. Whilst there were shortcomings in the FSP’s approach in some
aspects and in the extent and quality of some of the repairs done, the FSP
appears to have responded to the Applicant’s request in a reasonable
manner.
59. Given the FSP’s prepare dness to undertake some work which would appear
not to be directly related to the incidents, I am satisfied in these
circumstances that it would not be appropriate to award compensation
pursuant to paragraph 9.3 of the Terms of Reference.
Determination
60. On the basis of the available information, I determine that the FSP needs to
attend to further work at the insured premises, including:
Case No: 319190 Determination Page 11 of 11
A secondary and complete bacterial treatment of the home;
Repainting (or painting from scratch) of the identified problem areas
suggested by BS and to be verified by the FSP. I consider that the FSP
should use a different contractor for this;
A proper inspection of the insulation must be done to ascertain if it is
suitable for retention, noting the bacterial problems acknowledged to
have occurred at the home. Should there be any issues in this regard,
the insulation should be replaced at the FSP’s expense;
The first bedroom is to have the plaster replaced and the ceiling lining
must also be replaced in the ensuite;
The backyard must be compacted and re-levelled, with new turf laid if
required.
61. In addition to this, I determine that the FSP should repair the door where the
hook had been removed, arrange for the cleaning of the concrete driveway
to remove scuff marks, eradicate the “two tone” problem paint areas and
other painting issues where appropriate, replace the missing smoke
detector, repair and re-attach the skirting boards (where necessary) and
return the tap from the laundry or source a commensurate quality
replacement to match.
62. To the extent that further repairs at the home require the removal of the
Applicant and her daughter for a period, I determine that the FSP must
provide the Applicant the option of either:
Suitable accommodation with wheelchair access and appropriate
amenities for the Applicant and her daughter throughout the duration of
the necessary rectification works; or
Again subsidise the Applicant for $200 per week if she prefers to stay
with relatives or otherwise does not incur actual costs for the relevant
period.
63. To the extent that any payments are required to be made to the Applicant for
this matter, I am satisfied that the FSP must include interest calculated at the
statutory rate from 15 September 2013 until the date of settlement.