Alleged misrepresentation that the lender would control shed construction, plus dishonoured drawings and hardship assistance
Text of the determination
Determination
Case No: 316289 Determination Page 1 of 3
C ase number : 316289 7 November 2014
1 Overview
1.1 Dispute
The Financial Services Provider (the FSP) has approved various credit facilities to
the Applicants and subsequent variations to their facilities. In July 2010 the FSP
approved finance for the Applicants to refinance an existing loan with another
lender and construct a packing shed. In September 2010 the Applicants obtained
an increase on the facility from $200,000 to $350,000.
The Applicants claim that:
The FSP failed to manage the construction project for the packing shed and
allowed the costs to reach approximately $350,000 against a budget of
$175,000.
The FSP dishonoured drawings on the Company’s account in error .
The FSP failed to comply with its obligations to provide them with financial
difficulty assistance.
The Case Manager provided the parties with a Recommendation on the issues in
dispute. The Recommendation was in favour of the FSP. A copy of the
Recommendation is attached to this Determination.
1.2 Issues and Key findings
Were the findings of the Recommendation correct?
The findings contained in the Recommendation were correct and are adopted in
this Determination . Further submissions provided after the Recommendation have
been considered but did not raise any new issues.
1.3 Determination
This decision is in favour of the FSP.
I agree with the case manager’s reasons for the Recommendation and the
recommended outcome.
There is no compensation payable by the FSP to the Applicants with respect of
the issues raised in this dispute .
Once our file is closed the FSP is entitled to recommence recovery action for the
debt outstanding.
Case No: 316289 Determination Page 2 of 3
2 Reasons for Determination
2.1 Were the findings in the Recommendation correct?
I have decided this case on its merits, having regard to the relevant law, good
industry practice, codes of practice and previous FOS decisions. I have taken into
account all the material submitted by the parties, both before and after the
Recommendation. I am satisfied that the documenta tion I have relied on has been
provided to both parties.
I am satisfied that the case manager’s Recommendation contains an accurate
summary of the dispute, the issues to be determined, any applicable paragraphs
of the Terms of Reference and any relevant law.
The Applicants did not raise any further issues to be considered after the
Recommendation. They disputed the findings in the Recommendation on the
basis that there were irregularities in the documents and that the FSP approved
progress payments from the relevant facility without the requisite authority. On the
available information there is nothing to support this claim. The Applicants
provided authority for the progress payments to complete the construction of the
shed as required.
In addition to the payments being made with the Applicants’ authority, the
payments also had the effect of discharging the Applicants’ liability to the various
suppliers. The Applicants have not suffered a loss as a result of these payments.
2.2 Did the FSP mislead the Applicants that it would take control of
the shed construction?
Documents show that the FSP made progress payments at the request of
the Applicants
I agree with the case manager’s finding that there were some irregularities in the
documents relating to the equipment finance. However, after reviewing all the
available information I am satisfied that the FSP made the progress payments for
the construction of the packing shed in accordance with the facility terms and at
the request of the Applicants. All the suppliers for the construction provided
invoices to the Applicants and they were paid with the Applicants’ knowledge and
authority.
There is no information to show that the FSP misled the Applicants about
taking control of the construction process
Further, the FSP did not represent to the Applicants that it would take control or
manage the construction of the packing shed on behalf of the Applicants. The
loan documents do not state that the FSP was taking control of the construction
and the FSP cannot be responsible for the construction costs escalating. It is the
Applicants’ responsibility to manage the construction including organising the
contracts with the various suppliers. The Applicants’ accountant had prepared
Case No: 316289 Determination Page 3 of 3
detailed financial information to support the request for the increase in the facility
and the increase was appropriately approved by the FSP.
Recommendation
Case No: 316289 Recommendation Page 1 of 8
Case number : 316289 29 July 2014
1 Overview
1.1 Dispute
The Financial Services Provider (FSP) has approved various credit facilities to the
Applicants and subsequent variations to their facilities.
The FSP’s records show the following position of the Applicants’ accounts as at 7
February 2013 when the management of the accounts was transferred to another
business unit:
Borrower Facility Limit Balance Arrears
Company Commercial Loan $ 299,333 $ 17,022
Overdraft $ 100,000 $ 712,635 $ 612,635
Director Commercial Bill $ 433,681 $ 433,681
Working account $ 37,995 $ 37,995
Total $ 533,681 $ 1,483,644 $ 667,652
The Applicants claim that:
The FSP failed to manage the construction project to build a packing shed and
allowed the costs to reach approximately $350,000 against a budget of
$175,000
The FSP dishonoured drawings on the Company’s account in error
The FSP failed to comply with its obligation to provide them financial difficulty
assistance
1.2 Issues and key findings
Did the FSP misrepresent to the Applicants that it would take control of the
constru ction project of the packing shed and fail to protect the Applicants’
interests?
The FSP made progress payments at the Applicants’ requests which were
supported by invoices issued by the suppliers to the Applicants. The information
available does not suggest that the FSP misrepresented to the Applicants that it
would take control of the construction project for the packing shed.
Did the FSP dishonour any drawings from the Applicants’ working account
inappropriately or unreasonably?
The relevant account statements show that, when the disputed dishonoured
transactions were presented for payments, the account balance exceeded the
Case No: 316289 Recommendation Page 2 of 8
approved overdraft limit at the time. The FSP was not obliged to honour payments
when the account was over its limit.
Did the FSP breach its obligation to provide the Applicants assistance in
response to their financial difficulty?
In response to the Applicants’ requests for assistance, the FSP granted various
short term overdraft increases and additional credit accommodations to provide
relief for the cash flow shortage the Applicants’ business operation was
experiencing.
The FSP has complied with its obligation to assist the Applicants as customers in
financial difficulty.
There is no obligation on the FSP to provide any further credit accommodation or
extensions of their existing credit facilities which are in default.
What is the appropriate outcome?
The Applicants have not been able to maintain their repayment obligations.
Statement of financial position provided by the Director as at 21 May 2014 shows
that he is not currently earning an income.
The Applicants have attempted to refinance their loans to another lender since
March 2013 without success.
Information available indicates that the only apparent viable source of clearance
of the Applicants’ debt is from the sale of the property held by the FSP as
security.
1.3 Recommendation
This Recommendation is in favour of the FSP.
There is no compensation payable by the FSP to the Applicants with respect of
the issues raised in this dispute.
Within 14 days of the parties accepting this Recommendation, the Applicants are
required to offer the security property for sale and provide a copy of the authority
appointing a real estate agent to the FSP.
The Applicants will need to have sold the property within 90 days after the
appointment of the selling agent and provide the FSP with a copy of the
unconditional contract of sale.
If the Applicants do not provide a signed agent authority the FSP within 14 days of
both parties accepting this Recommendation or if the property remains unsold
within 90 days after the appointment of the selling agent, the Applicants are
required to surrender the property to the FSP for it to sell to repay the debt owed
by them.
Case No: 316289 Recommendation Page 3 of 8
2 Reasons for Recommendation
2.1 Did the FSP misrepresent to the Applicants that it would take
control of the construction project of the packing shed and fail to
protect the Applicants’ interests?
There is no information to show that the FSP represented to the Applicants
that it would take control of the construction project of the packing shed
Documents available show that the FSP approved the following finance for the
Applicants in July 2010:
A bill facility of $700,000 to the Director to refinance his existing loan with
another lender
Equipment finance of $200,000 to the Company to complete construction and
set up of a packing shed
Overdraft $85,000 to the Company for operating cash flow requirements
To support the Applicants’ proposal for finance, their accountant wrote to the FSP
on 3 June 2010 and said that the Applicants required $175,000 to fund to
construction and set up of a packing shed and an overdraft of $75,000 for working
capital.
The Applicants say that out of the $175,000 earmarked for the construction of the
packing shed, $100,000 was to pay for works to be completed by subcontractors.
The balance of $75,000 was for works they intended to complete themselves.
In September 2010, the FSP approved the Applicants’ request to increase the
equipment finance to $350,000. This increase was required because the initial
cost estimates was inaccurate.
The loan documents did not have any information regarding, or making reference
to, the FSP taking control of or otherwise managing the construction project of the
packing shed.
In response to my request to provide any documentary information to support
their claim, the Applicants said that they do not have any additional information to
provide.
On the basis of available information, the FSP did not represent to the Applicants
that it would take control or manage the construction of the packing shed on their
behalves.
Documents show that the FSP made progress payments for the shed
constructions at the request of the Applicants
I have listed the details of the Progress Payment Notices requesting the FSP to
release funds from the equipment finance facility in paragraph 3.1.
Each of these Progress Payment Notices had been signed by the Director.
Case No: 316289 Recommendation Page 4 of 8
Documents relating to the equipment finance contain irregularities
There are irregularities in the FSP ’s documentation in relation to the drawings of
the equipment finance as follows:
The FSP did not obtain an amended Progress Payment Commercial Loan
Agreement after the facility was increased from $200,000 to $350,000.
The Commercial Loan Agreement for the $350,000 equipment finance was
originally dated 14 April 2011 which was the date of the first scheduled
repayment. The agreement date was subsequently changed to 17 August
2010, which was before the facility approval date.
There was no tax invoice for the final drawing requested by the Applicants on
11 April 2011, although the FSP has provided a copy of an email dated 31
March 2011 with which the account manager requested confirmation for
approval to draw the balance of the facility in full without production of an
invoice.
However, all the payments were made in accordance with the Applicants’
requests and the invoices provided were issued by the suppliers to the Company.
The information available does not support that the FSP was controlling or
managing the construction of the packing shed. Nor did it pay the suppliers
without the Applicants’ knowledge or authorisation.
2.2 Did the FSP dishonour any drawings from the Applicants’
working account inappropriately or unreasonably?
Account statements show that the account balance exceeded the approved
limit when the disputed dishonoured drawings were presented
Details of the transactions which the FSP dishonoured that the Applicants
complained as inappropriate or unreasonable are listed in a table under
paragraph 3.2.
At the time each of the dishonoured drawings was presented, the account did not
have sufficient funds to allow payment. The FSP was not obliged to hour any
payments when there were not sufficient funds in the Applicants’ account. The
Applicants’ claim w ith respect of the dishonoured drawings has not been
established.
Case No: 316289 Recommendation Page 5 of 8
2.3 Did the FSP breach its obligation to provide the Applicants
assistance in response to their financial difficulty?
The FSP has obligation to assist the Applicants as customers in financial
difficulty
Being a subscribing member of the Code of Banking Practice (CBP), the FSP has
an obligation to give genuine consideration to a customer’s request for
assistance, where the customer is in financial difficulty.
We also expect a customer to be willing to work with their financial services
provider, and to propose a realistic repayment plan that will result in the
repayment of the debt within a reasonable timeframe.
The FSP has complied with its obligation to assist the Applicants by
approving various variations to their credit facilities
In the period from 2 September 2010 to 14 September 2012, the FSP provided
the Applicants the following temporary overdraft increases in response to their
requests for assistance to overcome the cash flow shortage their business was
experiencing:
Date Amount Increase Repayment
2/09/2010 $ 165,000 $ 80,000 Revert to $85,000 on 15/10/2010
21/10/2010 $ 185,000 $ 100,000 Revert to $85,000 by 22/11/2010
6/04/2011 $ 135,000 $ 50,000 Revert to $85,000 on 06/05/2011
21/04/2011 $ 235,000 $ 150,000 Revert to $85,000 on 01/05/2011
27/04/2011 $ 350,000 $ 265,000 Reduce to $230,000 by 01/07/2011 &
to $85,000 by 01/09/2011
20/07/2011 $ 420,000 $ 70,000 Repayment of $220,000 by
02/09/2011 and revert to $85,000 by
02/11/2011
6/09/2011 $ 350,000 $ 265,000 Revert to $85,000 on 10/10/2011
3/11/2011 $ 200,000 $ 85,000 Revert to $85,000 on 16/12/2011
9/02/2012 $ 720,000 $ 635,000 Seasonal monthly limit from January
to September 2012 , peaking at
$720,000 in June 2012 & reverting to
$85,000 in October 2012.
17/08/2012 $ 717,000 $ 297,000 to reduce to $420,000 on 31/08/2012
14/09/2012 $ 820,000 $ 400,000 Reduce by $250,000 on 31/10/2012,
$300,000 on 30/11/2012 & $170,000
on 31/12/2012
The FSP has complied with its obligation to assist the Applicants as customers in
financial difficulty.
The Applicants’ financial difficulty was a long term issue, caused by the business
not performing to the level projected by the Applicants. It is likely that a number of
uncertainties, such as unseasonal weather, that a farming operation is inherently
exposed to, have played a role in the business not performing to the Applicants’
expectations.
Case No: 316289 Recommendation Page 6 of 8
The FSP was not obliged to provide further assistance, in particular the
Applicants’ request for further finance, in circumstances when they are not
meeting their current obligations.
2.4 What is the appropriate outcome?
The Director’s property will need t o be sold.
Within 14 days of the parties accepting this Recommendation, the Applicants are
required to offer the security property for sale and provide a copy of the authority
appointing a real estate agent to the FSP.
The Applicants will need to have sold the property within 90 days after the
appointment of the selling agent and provide the FSP with a copy of the
unconditional contract of sale.
If the Applicants do not provide a signed agent authority the FSP within 14 days of
both parties accepting this Recommendation or if the property remains unsold
within 90 days after the appointment of the selling agent, the Applicants are
required to surrender the property to the FSP for it to sell to repay the debt owed
by them.
Case No: 316289 Recommendation Page 7 of 8
3 Supporting information
3.1 List of equipment finance Progress Payment Notices
Date Amount of
payment Invoice amount
29/07/2010 $ 73,570.20 $ 62,700.00
$ 10,870.20
17/08/2010 $ 28,200.53 $ 12,098.92
$ 14,867.50
$ 246.34
$ 198.55
$ 391.56
$ 131.41
$ 266.25
17/08/2010 $ 42,828.58 $ 27,500.00
$ 859.38
$ 14,469.20
30/08/2010 $ 20,121.26 $ 20,121.26
22/09/2010 $ 21,747.18 $ 10,000.00
$ 11,747.18
1/10/2010 $ 75,504.32 $ 75,504.32
18/10/2010 $ 43,134.70 $ 13,593.63
$ 29,541.07
28/10/2010 $ 31,897.05 $ 31,897.05
11/04/2011 $ 12,996.18 No invoice provided
Total $ 350,000.00 $ 337,003.82
Case No: 316289 Recommendation Page 8 of 8
3.2 List of dishonoured drawings
Date Direct debit/
Cheque no. Amount Account
Balance
Approved
limit
1/08/2012 Direct debit $ 189.28 $ 724,115.76 $ 420,000
15/08/2012 Direct debit $ 5,626.05 $ 717,237.94 $ 420,000
15/08/2012 400677 $ 20,000.00 $ 715,237.94 $ 420,000
28/08/2012 Direct debit $ 674.00 $ 722,359.95 $ 717,000
28/08/2012 Direct debit $ 189.28 $ 722,359.95 $ 717,000
5/09/2012 400674 $ 1,000.00 $ 697,850.58 $ 717,000
11/09/2012 Direct debit $ 674.00 $ 697,850.58 $ 717,000
11/09/2012 Direct debit $ 189.28 $ 697,850.58 $ 717,000
2/11/2012 400686 $ 164.32 $ 788,069.02 $ 570,000
2/11/2012 400690 $ 178.20 $ 787,890.82 $ 570,000
2/11/2012 400699 $ 667.00 $ 787,223.82 $ 570,000
6/11/2012 Direct debit $ 674.00 $ 787,252.07 $ 570,000
6/11/2012 Direct debit $ 189.28 $ 787,252.07 $ 570,000
7/11/2012 400689 $ 90.20 $ 787,400.07 $ 570,000
7/11/2012 400708 $ 130.00 $ 787,270.07 $ 570,000
13/11/2012 Direct debit $ 674.00 $ 749,540.99 $ 570,000
13/11/2012 Direct debit $ 189.28 $ 749,540.99 $ 570,000
15/11/2012 Direct debit $ 5,626.05 $ 749,549.99 $ 570,000
20/11/2012 Direct debit $ 674.00 $ 728,076.86 $ 570,000
20/11/2012 Direct debit $ 189.28 $ 728,076.86 $ 570,000
22/11/2012 Direct debit $ 13,811.47 $ 728,094.86 $ 570,000
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.