Home / Financial Firm (Unknown - Insurer) / Determination 316235

Determination 316235

Legal costs reimbursement

FirmFinancial Firm (Unknown - Insurer)
Decided2014-08-29
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant
Amount awarded$3,000
Non-financial loss—
Amount claimed$3,815
SourceAFCA PDF

Summary

After the FSP's contractor damaged and mis-rebuilt a boundary wall during fire repairs, the applicant sought legal costs of $3,814.80 to challenge a building notice. AFCA found the contractor's errors caused the dispute and ordered the FSP to pay $3,000, the usual cap.

An insurer is generally liable for its contractors' errors, and reasonable legal costs incurred to resolve a dispute the insurer's contractor caused may be compensated up to the usual $3,000 cap.

Issues

Subjects and remedies

home or building damagepay compensation

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Determination General Insurance - Domestic Insurance - Home Building - FSP Decision - Denial of Claim - No Policy or Contract Determination Case No: 316235 Determination Page 1 of 6 Case number : 316235 26 August 2014 1 Overview 1.1 Dispute In June 2008, the Applicant lodged a claim under his home building insurance policy with the Financial Services Provider (FSP) after his property was damaged in a fire. The FSP accepted the Applicant’s claim and authorised its builder to carry out extensive repair works, which were finally completed in or around June 2012. During the repair works, the FSP’s builder damaged a brick wall on the boundary of the Applicant’s property. The builder accepted liability and rebuilt the wall in its original location. However, following a complaint by the Applicant’s neighbour some two years later, it became apparent that the replacement wall was located partly on the neighbour’s property. The FSP’s builder proposed to rectify the issue at its own expense by demolishing the wall and rebuilding it entirely on the Applicant’s property. However , the Applicant did not agree to these works as he did not believe that the wall needed to be demolished . The FSP’s builder the n appointed a building surveyor, who issued the Applicant with a building notice requiring him to show cause as to why the proposed works should not proceed. The Applicant incurred costs of $3,814.80 in seeking legal advice following the issue of the building notice. He seeks reimbursement of these costs from the FSP. 1.2 Issues and key findings Is the Applicant entitled to reimbursement of his legal costs? The dispute which caused the Applicant to seek legal advice arose as a result of errors by the FSP and its contractors. Due to the nature and circumstances of the dispute, it was reasonable for the Applicant to seek legal advice to protect his interests. The assistance provided by the Applicant’s solicitors contributed to the dispute being resolved in his favour. Accordingly, he is entitled to reimbursement of his legal costs (subject to a cap of $3,000). 1.3 Determination This Determination is substantially in favour of the Applicant. The FSP is to pay the Applicant the amount of $3,000 as a contribution to his legal costs. Case No: 316235 Determination Page 2 of 6 2 Reasons for Determination 2.1 Is the Applicant entitled to reimbursement of his legal costs ? Policy does not provide cover for legal costs The Applicant acknowledges that his policy does not provide cover for legal costs. Under the terms of the policy, cover for legal costs is only provided where the insured has home contents cover as well as home building cover. As the Applicant has home building cover only, the policy does not entitle him to reimbursement of his legal costs. FSP is generally responsible for the actions of its contractors Where an insurer settles a claim by authorising its contractors to undertake repairs, FOS generally considers that the insurer will be responsible to the insured for the actions of its contractors and therefore will be liable for any additional loss or damage caused. This is particularly appropriate in circumstances where the insurer has selected the relevant contractors and managed the repair process. While an insurer may seek to recover from its contractors for any additional loss or damage caused, this does not alter its overriding liability to the insured for such loss or damage. Errors by FSP’s contractors led to disputed building notice The FSP’s builder has acknowledged that it was liable for replacing the single skin brick boundary wall, which was not damaged by the fire but was inadvertently demolished during the course of the repairs. The builder rebuilt the wall at its own cost using the existing foundations and the first three rows of the original bricks, which remained intact after the collapse. The builder also installed a second skin wall on the Applicant’s property, which it attached to an adjoining wall located at right angles to the replacement wall. However, the rebuilding of the wall by th e FSP’s builder ultimately led to a d ispute between the Applicant, the FSP’s builder and a building surve yor (appointed by the builder) when:  the body corporate for the neighbouring property complained that the wall encroached onto its property by 40 millimetres and exceeded the height permitted under the building permit;  despite putting forward a number of proposals over several months for rectification works to resolve the issue, the FSP’s builder was unable to identify a solution which was acceptable to both neighbours; and  in a final effort to resolve the dispute, the builder appointed a building surveyor who issued a notice under the Building Act 1993 (Vic) (the building notice), requiring the Applicant to show cause as to why the boundary wall should not be demolished and rebuilt solely on the Applicant’s property. Following the issue of the building notice, the Applicant lodged a dispute with FOS and sought legal advice about his ability to challenge the building notice. While Case No: 316235 Determination Page 3 of 6 the Applicant accepted that the height of the wall (and an associated roof) needed to be reduced in order to comply with applicable requirements, he was concerned that the rebuilding of the wall solely on his land would result in the loss of usable space (in circumstances where he considered that the manner in which the wall had been rebuilt had already encroached further into his property). It appears that the original wall straddled the boundary of the two properties when it was constructed some forty years earlier. The FSP’s builder has acknowledged that in hindsight it might have been preferable to carry out a boundary survey before the replacement wall was constructed. I agree that this would have been helpful to identify the respective rights and obligations of the Applicant and his neighbour in relation to the boundary wall, so that any relevant issues could be addressed (and appropriate consents obtained) prior to commencing construction. In the circumstances, I am satisfied that it was the actions of the FSP’s builder (including by damaging the original wall and then failing to obtain a boundary survey before building the replacement wall) which led to the issue of the building notice and the resulting dispute. Further, I consider that it was reasonably foreseeable that a failure to confirm the specific requirements which applied to the rebuilding of the boundary wall (and constructing the wall in a manner which breached applicable requirements) could lead to a dispute of this nature (given the prevalence of boundary disputes between neighbours). The FSP has suggested that the disagreement between the Applicant and the neighbouring body corporate in relation to the boundary wall was part of a pre- existing dispute which had been ongoing for some years. However, the Applicant has denied this and the FSP has not provided any independent information in support of its position (for example, evidence of previous complaints). In any event, I am satisfied that the collapse and rebuilding of the boundary wall gave rise to new and discrete issues (and triggered the issue of the building notice), which would not have occurred had the wall not been inadvertently demolished. FOS may award compensation for legal costs Under clause 9.4 of FOS’s Terms of Reference, FOS may require a financial services provider to contribute to the legal or other professional costs incurred by an applicant in the course of their dispute. However, an applicant will generally only be entitled to reimbursement of their legal costs where the nature of the dispute justifies the obtaini ng of legal advice (for example, where a dispute raises complex legal issues). Further, unless exceptional circumstances apply, FOS will generally not require the financial services provider to contribute more than $3,000 to the applicant’s legal costs. Applicant acted reasonably in seeking legal advice The Applicant lodged his dispute with FOS after it became apparent that the building surveyor was intending to issue the building notice (which in fact occurred several days later). The Applicant requested that the FSP pay for an independent review of the situation to determine whether the building surveyor was correct in Case No: 316235 Determination Page 4 of 6 requiring that the boundary wall be demolished and rebuilt on his property. This would have removed the need for the Applicant to seek his own legal advice. When the FSP rejected the Applicant’s request, he engaged a firm of solicitors who specialised in building and construction law to advise him on his right to challenge the building notice. The solicitors provided the Applicant with preliminary and final letters of advice. They also drafted a letter to the building surveyor setting out the reasons why the boundary wall should not be demolished and proposing an alternative solution. Given the nature of the dispute, I am satisfied that it was reasonable for the Applicant to seek specialist legal advice. In this regard, I note that:  the dispute involved technical areas of law – for example, one of the arguments put forward by the Applicant was that the boundary wall was governed by the Fences Act 1968 (Vic) (on the basis that it was properly characterised as a “dividing fence”) rather than by the Building Act 1993 (Vic) and therefore could not be the subject of a building notice;  prior to seeking legal advice, the Applicant (through his daughter) had approached the FSP, the local council, the Building Commission and the Building Appeals Board, but had been unable to achieve a satisfactory outcome; and  the Applicant had a limited period of time (30 days) to challenge the building notice and was concerned about the possibility of being fined if he failed to do so. Given that FOS has no power to prevent the building regulatory process proceeding, it was not practical for the Applicant to hold off on taking any action until after his FOS dispute had been resolved. Legal advice assisted in resolving dispute about building notice In their final letter of advice dated 11 April 2013, the Applicant’s solicitors advised that the replacement boundary wall (and associated roof) did not comply with applicable building requirements, and therefore the building surveyor was acting in accordance with his statutory duty when he issued the building notice. The solicitors canvassed several possible arguments which could be raised with the building surveyor as to why the wall should not be required to be demolished and rebuilt on the Applicant’s property, but could instead be altered so as to comply with applicable building requirements. However, the solicitors concluded that these arguments were “not strong” and tha t they would have difficulties in convincing the building surveyor not to require the demolition and rebuilding of the wall. Nevertheless, it appears that, after the solicitors sent a letter to the building surveyor and following further discussions between the relevant parties, it was agreed that the issues with the wall would be rectified by detaching the second skin wall built on the Applicant’s property from the perpendicular wall to which it had been attached (and lowering the non-structural section of the wall and the associated roof). This was the Applicant’s preferred outcome (as compared to demolishing and rebuilding the wall). Case No: 316235 Determination Page 5 of 6 It is not clear from the available information exactly why the building surveyor (and presumably the neighbouring body corporate) agreed to this outcome, which had previously been rejected. However, in the circumstances it is reasonable to assume that the representations made by the Applicant’s solicitor on his behalf contributed to this outcome in no small way. FSP should contribute to Applicant’s legal costs For the reasons outlined above, I am satisfied that it was reasonable for the Applicant to seek specialist legal advice to challenge the building notice and that the advice he obtained contributed to the dispute about the rectification of the wall being resolved in his favour. I have reviewed the solicitors’ accounts and am satisfied that their fees were not unreasonable in the circumstances, although they significantly exceeded the initial estimate provided (which the Applicant had in turn passed on to the FSP). The FSP’s builder has suggested that the Applicant should not be entitled to full reimbursement of their legal costs on the basis that he contributed to the initial delay in resolving the dispute about the rectification works, which ultimately resulted in the issue of the building notice “as a last resort”. I accept that the FSP’s builder used his best endeavours to try and resolve the dispute about the rectification works and that the Applicant’s actions contri buted to some of the delays which occurred during this process. However, the key factor which prevented the resolution of the dispute was the different outcomes sought by the Applicant and the neighbouring body corporate. In all of the circumstances, and i n particular having regard to how the dispute arose, I consider that it is fair that the FSP be required to compensate the Applicant in the amount of $3,000 for his legal costs. However, I do not consider that the circumstances of this dispute are so exceptional as to justify the award of compensation in excess of $3,000. Case No: 316235 Determination Page 6 of 6 3 Supporting information 3.1 Terms of policy Subject Terms Legal costs Legal defence costs (Applicable only when you have contents cover) If you live at the risk address, we will pay up to a maximum of $5,000 during any one period of insurance for legal fees, costs and expenses that you reasonably incur with our consent in defending legal proceedings brought against you by a third party in Australian during the period of insurance.