Determination 315930

Denial of roof water damage claim under faulty work exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2013-12-12
ProductGeneral Insurance · Business / commercial
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$6,000
SourceAFCA PDF

Summary

A business owner's premises leaked through the roof after a 2012 storm, and the FSP denied the claim as caused by faulty construction and repairs. AFCA found the faulty work exclusion applied, and any defects in the repairs by the applicant's chosen repairer were an issue between the applicant and that repairer.

After the insured established a prima facie storm claim, the FSP proved the faulty workmanship and design exclusion through the building consultant's evidence of construction defects.

Issues

Subjects and remedies

home or building damagenatural disasterno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 315930 Determination Page 1 of 8 Case number: 315930 General Insurance - Small Business/Farm Insurance - Commercial Property - FSP Decision - Denial of Claim 11 December 2013 Summary Description: A claim under a business policy for damage to business buildings. Basis of Determination: A consideration of the evidence presented for an earlier claim arising from Cyclone Yasi as compared to the evidence available in respect to the more recent claim. Together with a consideration of whether the repairer for the original claim was engaged by the Applicant or the FSP. Determination: The evidence supports the fact that the original repairer was engaged by the Applicant and therefore any failed repairs are not the concern of the FSP. The evidence also supports that many of the ongoing problems are related to initial construction and therefore are excluded from coverage under the terms of the policy. Background 1. The Applicant operates a business which sells boats and boating accessories. The business is insured with the Financial Services Provider (FSP). The Applicant had previously lodged a claim under the policy as a result of damage sustained to the business premises during cyclone Yasi in February 2011. 2. The FSP assessed the damage, noting there were signs of pre-existing damage and/or building defects and settled the claim in November 2011, for the amount of $25,249.60. 3. As a result of a storm on 20 March 2012, the Applicant notified the FSP that his business premises had once again suffered damage. The FSP assessed the damage and concluded it was due to defects present at the time the building was constructed. 4. The FSP further concluded there were defective repairs carried out by the Applicant‟s chosen repairer in the wake of cyclone Yasi. The FSP therefore denied the claim on both grounds. Determination Case No: 315930 Determination Page 2 of 8 5. The Applicant is seeking repairs to the business premises‟ roof as water had entered the premises during both weather events. Summary of Applicant’s position 6. The Applicant wants the claim approved by the FSP which would mean the roof capping is replaced as originally proposed. The Applicant says the difference between the quote he had obtained and the FSP‟s quote is $6,000. 7. The Applicant says there are many we t seasons in their region and there has never been an issue with the roof prior to cyclone Yasi. The Applicant also says there have been issues with the roof since the repairs were carried out by the FSP‟s repairer in the wake of the cyclone. The Applicant says he did not employ the repairer. 8. The business premises is a commercial building which was professionally built and fully inspected and approved by the local council. As such, the Applicant rejects the FSP‟s comments. Summary of FSP’s position 9. The FSP says that it had noted pre-existing damage to the premises while inspecting the premises after the Applicant lodged a claim for property damage due to cyclone Yasi in February 2011. The FSP only settled for the cyclone related damage. 10. The FSP says the Applicant subsequently lodged a claim on 20 March 2012, for further water damage. An inspection of the premises by the FSP found there was faulty construction work and some faulty repair work. The FSP denied the claim on those two grounds. 11. The FSP relies on the following policy provisions: “ Business Property Cover Section … What you are not covered for under this Section … (d) faulty work including: (i) errors in, omissions from or wrong design; (ii) faulty materials or faulty workmanship. ” 12. The FSP also says it cash settled the claim resulting from the cyclone and therefore it was the Applicant who had arranged the repairer to carry out the rectification work. As such, any defective repairs, is an issue between the Applicant and the repairer. Case No: 315930 Determination Page 3 of 8 Issue 13. Whether the FSP was entitled to deny the claim. Reasons for decision 14. Due to the nature of the dispute, the FOS has considered it appropriate to expedite the dispute in accordance with the Operational Guidelines to the FOS Terms of Reference. Thus, this dispute has not been the subject of a FOS Recommendation and has proceeded directly to Determination. The parties have been previously advised that a Determination will be issued in this case. 15. I am satisfied there has been a full exchange of information between the parties and the respective parties to the dispute have had the opportunity to comment on the other‟s submissions. 16. The Applicant has the onus of establishing that he has a prima facie claim under the policy. Once he has achieved this, the onus then shifts to the FSP to establish the application of a policy exclusion. 17. The Applicant lodged a claim on 20 March 2012, after heavy rain had once again resulted in water seeping through the roof. The policy provides cover in relation to storm damage, amongst other events and therefore, the Applicant has established a prima facie claim. Accordingly, the FSP now has the onus of establishing the application of a policy exclusion. Previous claim 18. There was a previous property damage claim arising from cyclone Yasi in February 2011. The FSP settled that claim by paying the sum of $25,249.60, which was net of GST and the $5,000 policy excess. This amount covered building repair costs and signage, which the FSP had assessed as storm related damage. 19. In arriving at that amount, the FSP had arranged for “C” to act as claim administrator in relation to the Applicant‟s claim for property damage. C provided a number of reports during the processing of the claim. C appointed a building consultant (“SJ”) from a specialist tech nical company to attend the Applicant‟s business premises and report on the damage. 20. SJ carried out an inspection of the premises on 26 May 2011, in the presence of the Applicant. He noted the premises consisted of a show room on the lower level and offices on the first floor, with a work shop to one side. SJ made a number of observations and concluded that: “Much of the damage observed is due to cyclonic winds and water ingress into the building during tropical cyclone Yasi (viz. First Floor light fittings, First Floor ceiling tile, Ground Floor Office door, Ground Floor Office wall stains and external fascia sign and signage on three sides of the building).” Case No: 315930 Determination Page 4 of 8 21. SJ recommended the remedial work , listed under “ Specific Recommendations” , should be carried out as soon as possible, including: “Properly repair seating and fixing to roof mounted air conditioning unit complete with all required flashings and accessories. Water test on completion. Properly repair and/or replace flashings and roof sheeting at the junction of the split in roof levels. Water test on completion.” 22. However, SJ concluded that some of the damage he observed was due to maintenance issues. These included the first floor office, store ceilings and ground floor office ceiling. SJ provided photographs in support and estimated the cyclone related repairs would cost approximately $25,000. 23. The Applicant had previously asked a construction company (“RC”) to supply a quote to carry out repairs. RC‟s quote was for $16,236, while a quote from a signage comp any was for $13,139.30. As a result of SJ‟s report, C asked RC to review their quote based on SJ‟s repair recommendations. However, RC was not willing to do so. 24. C indicated in its report dated 12 August 2011, that it appointed another builder, however, C s tated the Applicant “did not want him to attend the site”. C stated the Applicant‟s insurance broker “subsequently requested a copy of the repair recommendation so that they may obtain their own quotation”. 25. C said the quote obtained by the Applicant‟s broker “failed to include some repairs and included others not listed” in SJ‟s report. C also stated the quote was too expensive. C therefore appointed another builder (“W”) to attend the premises and provide a quote, which he did. 26. C recommended the FSP pay the insured $25,249.60, being a combination of the signage costs and the building repair costs. C subsequently wrote to the insured on 24 November 2011, outlining the amount it would pay upon receipt of a signed deed of release, which was enclosed with the letter. 27. The deed of release indicated the payment was “in final satisfaction and discharge of all claims under [the] Policy … arising from the loss or damage which occurred at [the insured premises] on or about 3 February 2011”. The Applicant signed the deed of release on 24 November 2011, on the insured‟s behalf and returned the document to C. 20 March 2012 claim 28. The Applicant lodged another claim as a result of a severe high wind storm event on 20 March 2012. He said water had once again entered the business premises through the roof, stating this was due to defective repairs from the earlier claim. Case No: 315930 Determination Page 5 of 8 Building Consultant’s report dated 25 May 2012 29. C arranged for a building consultant (“BH”) from a building and engineering consultancy company to attend the A pplicant‟s premises and provide a report on the cause of water entry through the roof, including a revision of the cyclone damage repairs undertaken. In addition to inspecting the premises, BH viewed SJ‟s earlier report. 30. BH stated in his report, dated 25 May 2012, that a visual inspection of the roof identified a number of issues where water will potentially leak:  Stepped apex roof flashing: BH said the flashing should ideally have been installed as one piece. BH said the poor flashing detail is a result of the initial construction of the building and not related to cyclone Yasi or the 20 March 2012 storm or from the Yasi repairs.  Stepped apex roof flashing fixings: BH identified four loose screws that secure the joining of this flashing. BH said these have come loose due to wind damage sustained from either Yasi or the storm of 20 March 2012.  Flue penetrations: BH noted that the two penetrations have only had sealant applied around them. BH said that specific collar type flashings should be installed to prevent water ingress at those locations. BH said this appears to be a poor detail carried out at the time of the initial construction and not related to Yasi or the 20 March 2012 storm or the Yasi repairs.  Apron flashing: BH said the work appears recent and he believed it was likely to have been carried out by the contractor who performed the Yasi damage repairs. BH concluded the repair work was carried out in an attempt to correct poor building detail from the initial construction of the building.  Block wall capping – roof penetration: BH subsequently amended his comments on this matter after meeting with the builder who had carried out the repairs. Only the fixings had been replaced and BH concluded these were not likely to have been fit for the purpose. He concluded the damage in this instance was due to initial defective building work and was not sustained by a weather related event.  Apron flashing workshop area: BH said this was poor building work from the initial construction and from the building work of the later extension. He believed that water was still likely to penetrate through this roof area in heavy rain. 31. BH made a number of conclusions based on his examination of the premises. He said he had “identified several areas of poor building work” which he concluded had occurred at the time of initial construction. He indicated that the Applicant should: “… engage a competent roof plumber to replace the flashings on the roof that have been poorly designed, poorly installed and those that are missing/never been installed.” Case No: 315930 Determination Page 6 of 8 32. BH concluded the building will remain highly susceptible to continued water ingress until repairs are carried out. BH identified four loose roof screws to the stepped flashings at the apex of the roof. He said these were likely loosened as a result of either Yasi or the 20 March 2012 storm. 33. BH said this flashing was poorly designed and should be replaced or an over-flashing should be installed to ensure water is not able to penetrate. BH believes this flashing “is most likely allowing water to penetrate int o the building”. BH concluded the flashing had been installed in a defective manner at the time of initial construction. 34. BH indicated that SJ‟s report did not include any photographic evi dence of damage to the roof and as such, he was not able to ascertain what flashings and/or roofing had suffered damage as a result of Yasi. However, he stated: “We can only assume, from this heavy application of the water proof membrane, that this flashing had sustained cyclone damage, as such we believe it should have been replaced and not had a temporary repair to it. We concede that this one flashing only, as described in item 5.15, would therefore appear to not have been repaired in an appropriate manner, in relation to the insurance rectifications following TC Yasi.” R epairer builder’s comments 35. During June and July 2013, C obtained comment from the builder (“W”) who had carried out the repairs in the wake of cyclone Yasi. C provided W with a copy of BH‟s report and asked W for confirmation: “…that cyclone repairs were f inalised to the roof. That involved removal of old plastic fixings and re-fixing of flashings and then waterproofing any joins. Extra waterproofing was later placed over some susceptible area, where there had been defective flashings, not associated with c yclone damage.” 36. W responded by saying he did not believe the flashings were the problem. He „suspected‟ there is a problem with the sealing of the screws or the flashing that needs resealing/refixing to the „right hand side‟ of the building. He did not believe the waterproofing was a temporary measure as the supplier had indicated it was “uv stable”. W indicated there were signs of a leak within the suspended ceiling to the showroom, however, he added: “All flashing to wall was refixed and resealed with sil icon and should have been sufficient to fix the leak without the waterproofing” (sic) 37. W had also arranged for a plumber to examine the roof and said: “There seems to be numerous maintenance issues up on the roof that the plumber pointed out to me, like the replacement / resealing of screws to flashing where the roof drops down, but they are not leaking at the moment and don‟t seem to be the cause of the major leaks. I asked the plumber his opinion on the repaired flashing and he believes that replacing the flashing would probably not fix the problem as the water could be tracking from another location. I feel that if the screws are replaced and the maintenance issues are fixed then there should be no water leak problems.” Case No: 315930 Determination Page 7 of 8 38. W‟s comments do not advance the ma tter any further, given that he is uncertain as to the likely cause of the water intrusion. However, he does refer to the plumber‟s comments about the existence of „maintenance issues‟ for the roof. It would have been of greater assistance to FOS if C had obtained comments in writing from the plumber. Nevertheless, BH‟s report still remains persuasive with respect to the likely cause of water intrusion into the building. Applicant’s comments 39. The Applicant reiterated that his dispute concerns inadequate repair work in the wake of cyclone Yasi, although he has not indicated what these are nor has he obtained any comment from a relevant tradesperson on these matters. He contends he never appointed W to undertake the cyclone Yasi repair work. Instead, he said it was the FSP who had appointed the repairer. 40. The FSP denied that it appointed W and authorised the repair work to be carried out. C did obtain a quote from W upon which C relied in calculating the amount the FSP should pay to settle the building damage claim. The policy provides for settlement by the FPS paying the cost of rebuilding, replacing or repairing any damaged part of the business property. The FSP then paid its insured upon receipt of the deed of release, which the Applicant signed on behalf of the insured. 41. The FSP provided a note which indicates W acted on the Applicant‟s instructions to undertake the cyclone related repair work. Given the FSP settled the cyclone related claim by the payment of cash to its insured, it is highly unlikely the FSP would then retain an interest in overseeing the repair work. 42. In this respect, any issue concerning possible defective repair work will therefore be between the Applicant and W. However, the reports provided to FOS identify a number of defects which were present at the date of construction or the date when the extension was built. The defects relating to repair work after Yasi are minimal. 43. An insurance broker, acting for the insured, stated in an email to FOS, dated 1 May 2013, the Applicant is disputing that his building has never suffered any ingress of water prior to cyclone Yasi. As such, the broker is questioning why it is now seen as a problem. However, the broker has provided nothing in support of this contention. 44. The broker said the amount in dispute is $1,349, although the Applicant subsequently provided a quote (dated 14 June 2013) for $3,960 from a plumber for roofing repairs. It is uncertain whether this amount represents the full amount in dispute. 45. The Applicant also referred to BH‟s report and cont ended that certain parts of the report related to areas of the building for which he had not claimed. However, his claim following cyclone Yasi, concerned the resulting damage to the business premises. Case No: 315930 Determination Page 8 of 8 46. The FSP arranged for the property to be assessed following the lodging of the Applicant‟s claim and as a result, SJ provided a report on the extent of damage due to the cyclone. The FSP was required to verify the extent of damage and SJ did exactly that. SJ identified those matters which resulted from the cyclone and those which were considered to be construction defects. 47. BH provided a comprehensive report following the Applicant‟s second claim of 20 March 2012. This report also identified a number of construction related defects and W confirmed during a discussion with C that a plumber had identified a number of maintenance issues (although the plumber‟s comments have not been corroborated). 48. W‟s comments on their own are insufficient to negate the findings in BH‟s report, which overwhelmingly concludes there are a number of construction related defects which were likely to have led to water intrusion. It is apparent from BH‟s report that there are minimal items which could be categorised as defects due to W‟s repair work. In any event, such items would be an i ssue between the Applicant and W. 49. Accordingly, I am therefore satisfied on the balance of probabilities, the FSP has established the application of a policy exclusion, namely, “faulty work including: errors in, omissions from or wrong design; faulty materials or faulty workmanship”. Determination 50. On the basis of the available information I determine the FSP was entitled to deny liability in relation to the Applicant‟s claim.