Text of the determination
Case No: 315413 Determination Page 1 of 8
Case number: 315413
General Insurance - Domestic Insurance - Home Building - FSP Decision -
Claim amount
6 February 2014
Summary
Description
Dispute as to liability and quantum following a claim under a Home
Building and Contents Policy for damage following stormwater
inundation in March 2012.
Basis of Determination
The property suffered both internal and external damage due to the
storm water.
On balance, the evidence establishes a 30% to 40% contribution to the
damage to the piers and stumps.
On balance, the internal damage was caused by stormwater.
Determination
The FSP is to cash settle the Applicants’ claim for $43,218.80 plus interest
pursuant to Section 57 of the Insurance Contract Act 1984 (the Act).
The FSP is to pay the make safe repairs and contents claim if it has not
already done so.
Background
1. The Applicants’ home and contents were insured with the Financial Services
Provider (FSP) under a home and contents policy.
2. They claimed for water damage to their property, said to have been caused
by stormwater inundating their home in early March 2012.
3. The FSP partially accepted liability and offered a cash settlement of $22,125,
contending that only 35% of the damage to their home damage may be
attributed to the storm event. It later revised its offer to $23,540.
4. The Applicants maintain they are entitled to full indemnity for the damage to
their property.
Determination
Case No: 315413 Determination Page 2 of 8
Summary of Applicants ’ position
5. Their home sustained damage as a result of two severe storms in two years,
however:
They did not lodge a claim following the first storm as that storm only
caused minor damage.
They decided to lodge a claim after the second storm because it had
caused more visible damage.
6. Whilst their home is about 50 years old, there is no basis for the FSP’s
conclusions that:
Only 35% of the damage to the sub floor area was caused by storm;
and
The remaining 65% of the damage was due to a long standing problem
that has been occurring over a long period of time.
7. Their sons have had to sleep in the lounge as a result of mould and damp
developing from the storm event.
8. The FSP’s assessor “CL” verbally informed them that builder “SWB” had
quoted $79,000 to repair the damage.
Summary of FSP’s position
9. Its building consultant “S” reported:
The majority of the damage is due to wear and tear and building
defects, and has been occurring for an extended period of time.
60% to 70% of the damage was not related to the storm event.
The storm event may have exacerbated “existing maintenance and
defect issues”.
10. The $80,000 quo te referred to by the Applicants “includes maintenance and
defect related items which are not covered by the policy”.
11. It has reassessed the “resultant damage” to $58,850 and offered $23,540,
which is 40% of the assessed loss.
12. In its letter of denial dated 9 January 2013, relied on the following policy
provisions:
“ We will not cover loss or damage caused by:
Wear and tear and lack of maintenance, including rust, corrosion,
deterioration, except in the case of escape of liquid (refer page 21), or
legal liability claims;
Gradual loss or damage of any kind
Erosion or earth movement including shrinkage…”
Case No: 315413 Determination Page 3 of 8
Issues
13. Whether the FSP’s cash settlement offer is fair in all the circumstances, and
sufficient to discharge its obligation under the policy.
14. Whether the Applicants are entitled to compensation for the manner in which
their claim had been handled.
Reasons for decision
15. Due to the nature and complexity of the dispute, it has been referred to the
Panel for Determination in accordance with the Operational Guidelines to the
Financial Ombudsman Service’s (FOS) Terms of Reference.
16. The Panel consists of an Ombudsman and two Panel members with
extensive experience in the insurance industry and consumer claims.
17. The Panel is satisfied that the parties have exchanged the material they rely
upon and have had the opportunity to respond to the issues raised.
Sub-Floor Damage
18. In its 9 January 2013 letter to the Applicants, the FSP indicates 35% of the
sub-floor damage to the Applicants’ property was caused by storm.
19. In the F SP’s submissions to the Service, the FSP submits 30% to 40% of the
total damage to the Applicants’ property (that is not just the sub floor
damage) may be attributable to the storm event. In fact, according to the
FSP, it has reassessed the resultant damage to a total of $58,850 and has
offered $23,540 which represents 40% of the total damage sustained.
20. There is no evidence from the building consultant S that it ever provided an
opinion that only 30% to 40% of the damage to the Applicants’ property
(whether as a whole or with respect to the sub-floor only) could be
attributable to a storm event, let alone an explanation for such a conclusion.
21. The suggestion that 30% to 40% of the damage to the Applicants’ property
could be attributable to a storm event was made by assessor CL. CL
contacted S who apparently advised that 60% to 70% of the damage is
maintenance related.
22. According to S, the property was in good condition for its age. He identified
areas of water ingress and considered that water entering the unde r-floor
space was unable to drain away. It was evident that movement to the
foundation was due to the moisture. Although the movement had occurred
generally over an extended period of time, S considered the movement was
exacerbated by the floods.
23. It is unclear from the report exactly why S considered that the movement had
occurred over an extended period of time. S identified down pipes that were
discharging water directly into the soil and identified that the sub-soil directly
Case No: 315413 Determination Page 4 of 8
beneath the home may have been lower than the ground level soil outside
the home. This of itself does not necessarily establish that the movement
related damage to the Applicants’ home in fact occurred over an extended
period of time.
24. The Panel notes the comments by the assessor CL following inspection of
the property on 2 April 2012 as follows:
“From our own inspection of the premises we can confirm there is evidence of
the floors in the areas described above having settled. As that settling is more
felt than seen, it was not possible to provide visual representation in the way
of photographs”
25. The Applicants however, despite the limited evidence presented by the FSP
have not provided any evidence of their own, to dispute these findings. In
these circumstances, the Panel must be guided by the expert opinion as
presented by the FSP. The only expert opinion is that provided by CL and S.
26. On balance, the reports establish that most likely there would have been pre -
existing movement to the floor but this has been exacerbated as a result of
the floods.
Evidence in respect of roof construction defects and faulty construction
27. S noted:
“I observed that the installation of the sheets and cappings generally is poor. I
observed capping junctions that would allow water ingress and also sheets
with nail holes and nails in down corrugations along the eastern roof plane
directly above the boys (sic) bedroom. Water ingress is also likely to have
occurred at these locations.
I observed an air-conditioning unit above the lounge room area where water
staining has occurred. I also observed that the roof sheets over this area have
limited screws . As a result there are loose sheet laps where wind driven rain
could enter. I also observed a patch over an old roof penetration with silicone
that appeared deteriorated.
I am on the opinion that the water ingress to the ceilings of the residence has
been the result of incorrect screw fixings in accordance with the Building Code
of Australia – Volume Two. Hole left in the sheets and nails to down
corrugations is not an acceptable practice and is likely to allow water ingress.”
[Panel emphasis]
28. However, photographs provided in support of S’s report show:
There is only one area with a poorly finished capping joint.
There is only one roof sheet with an exposed nail hole.
There is only one roof sheet where a nail has been driven into the
“down corrugation”.
29. The suggestion that an area of the roof had “limited screws” is also vague
and in the Panel’s view, does not establish that that section of the roof was
Case No: 315413 Determination Page 5 of 8
defectively installed. Ultimately, no evidence has been provided to
demonstrate:
How many screws the relevant section of the roof actually required as a
minimum (by reference to either, the manufacturer’s installation
requirements or whatever building standard that may have been
applicable at the time of installation); and
That the number screws which were actually used on that section of the
roof were in fact less than such requirement or standard.
30. Further:
No evidence has been led to demonstrate that water (or at least a
substantial portion of it) had in fact entered the home through the areas
S claimed to have been defectively installed or constructed.
There is nothing in S’s report to suggest that the alleged leaking areas
were ever water tested. In the absence of such evidence, it appears
plain to the Panel that S was merely speculating on these matters.
Apart from a bare reference to the Australian Building Code, neither the
FSP nor S provided any information relating to the building codes that
were allegedly breached, nor demonstrated that they were in fact
breached.
Whilst the Panel accepts there is no flashing at the meeting point
between the verandah roof and the weatherboard wall, no evidence
has been provided to demonstrate that this was in fact a construction or
installation defect by reference to any building standard in force or in
practice at the time of the roof’s construction.
In this respect, the Panel notes that the relevant area is actually
covered by another roof. Therefore, in the absence of evidence
demonstrating that it was a building requirement or practice for the area
to be flashed (at the time of the roof’s construction), the Panel is not in
a position to assume that the area required flashing.
31. Accordingly, whilst S seemed to have provided a fairly extensive report, the
report has in effect offered little to substantiate the conclusions insofar as it
relates to the internal damage.
32. Further, the Panel notes the assessor CL identified rainfall ingress into the
roof cavity as a source of the internal damage.
33. In the circumstances, the Panel is not satisfied the evidence is sufficient to
establish the internal damage was due to construction or roof defects.
Scope of Works
34. There are a number of items in the Scope of Works identified by S that are
clearly not storm related. These items include items 1.1, 1.2, 1.3, 1.4. These
items relate to external damage not related to the storm. The Panel also
Case No: 315413 Determination Page 6 of 8
accepts item 2.1 is not storm related as it deals with the replacement of
kitchen drawer units not damaged by the storm.
35. Insofar as the balance of the damage identified, that is the damage to the
“Boys Bedroom”, “Lounge Room” and General, the Panel accepts this is
storm related and covered under the policy.
36. The Scope of Works does not extend to cover all damage identified by the
assessor CL. It does not cover damage identified to the ceilings of the
lounge room, kitchen bedroom 2, bedroom 3 or replacement of the vinyl on
the kitchen floor. CL identified rainfall ingress into the roof cavity as a source
of damage. The Panel accepts in the absence of any evidence to the
contrary that it is reasonable to accept that this damage should be included
in any Scope of Works.
Quantum
37. The Panel has considered quotations from TKM building contractors who
provided a quotation to the assessor in the sum of $82,234.24 with respect
to the external damage, damage to the kitchen drawer units, boys bedroom
and lounge room. The quotation has an additional amount for maintenance
repairs for the dining room, master bedroom and replacement of the kitchen
flooring totalling $13,160.40. Based on this, for the full repair of the property,
the quotation is $95,394.64.
38. A second quotation has been obtained from S P in the sum of $63,500. This
quotation is not itemised and simply refers to the repair of flood damage as
per the Scope of Works. It is clear that this quotation does not include
quotation for the repair of the dining room, master bedroom or kitchen.
39. The Panel accepts that the majority of the costs associated with the external
damage are not related to the actual flood, but that the balance of the
internal damage is in the absence of alternative information related to the
storm damage due to rain water entering the property.
40. The Panel accepts that this dispute has been ongoing for some time and
despite efforts made by the FSP and the Applicants to reach a compromise
of the dispute, the parties have been unable to do so. The Panel is also
mindful of the fact that due to the location of the Applicants’ property, there
are difficulties in arranging for the repairs of the property.
41. Given these circumstances the Panel considers it would be preferable for
this matter to be cash settled. In assessing an appropriate cash settlement
figure, the Panel considers the itemised quotation from TKM to be more
reliable, in particular given the FSP’s comments as to the reluctance of
builders attending the property to quote given its remoteness and the limits
on the availability of tradesmen.
42. TKM provided the following quotation:
External:
Supply install new roof
Case No: 315413 Determination Page 7 of 8
Supply install new flashing
Stormwater drains, connect downpipes
Prepare and pack existing pier supports to sub-floor - $21,876.
The Panel considers the FSP should only be liable for the preparation and
packing of the pier supports. In the absence of a precise breakdown of this
cost, the Panel believes $5,000 to be fair and reasonable in the
circumstances.
Complete removal and reinstatement of floor to allow access to sub floor -
$44,000.
The Panel accepts the assessment by S that of a 30% to 40% contribution
by the storm to this damage and determines that it would be fair and
reasonable to allocate a 40% allowance. Accordingly, the Panel considers
$17,790 to be fair and reasonable.
Repairs to the bedrooms, kitchen (less kitchen drawers) lounge room and
dining room - $20,428.80.
The Panel accepts the FSP is liable for these repairs and considers an
allowance in the full amount of $20,428.80.
43. Based on the above calculations, the Panel determines the appropriate cash
settlement in this dispute at $43,218.80.
Make safe repairs and contents claim
44. The Panel notes from the material exchanged the recommendation of the
loss adjustor for payment of the sum of $1,044.50 to P building with respect
to the make safe repairs. It is unclear whether the FSP has actually attended
to payment of this although this issue has not been raised by the Applicants.
In the event that the FSP has not made payment of this amount, then the
Panel determines that the FSP should make payment of this amount without
delay.
45. The Panel also notes comment from the assessor with respect to the
contents claim. Instructions were sought from the FSP with respect to
whether the contents claim is to be decli ned. It is unclear from the
information exchanged whether the FSP has now accepted the Applicants’
contents claim.
46. According to the assessor the damage caused by the roof leak, required the
replacement of carpets to the lounge room and living room and replacement
of the Acer computer. Damage caused by stormwater runoff require the
replacement of the Frigidaire Custom Deluxe Cyclamatic 2 door refrigerator,
replacement of the Hoover 370 Cyclic Defrost 2 door refrigerator and
replacement of the spoiled food in the fridge and freezer.
47. In the absence of any information from the FSP to dispute liability with
respect to the Ap plicants’ claim for the damage to the contents, the Panel
Case No: 315413 Determination Page 8 of 8
determines in the event that the FSP has not already done so, that the FSP
meet its liability with respect to the contents claim and damage as identified
by the FSP’s loss adjustor CL in their repor t of 22 December 2012 to the
FSP.
Compensation
48. In view of the nature of this dispute, the Panel has considered whether or not
compensation is payable to the Applicants given the delay.
49. Paragraph 9.3 of the Terms of Reference provides that compensation may
be awarded by the Service where an Applicant suffers an unusual degree of
inconvenience in the resolution of the claim. The Applicants have indicated
that they have been inconvenienced in particular because of the mould that
has developed in the house and the impact on their two sons.
50. The Panel accepts that this would be quite distressing for the family however
the Panel notes that the FSP has at all times acted on the basis of available
information. The FSP’s loss adjustors have responded quickly and the F SP
has attempted to settle the Applicants’ claim.
51. In the circumstances and given the determination that has been reached in
this matter, the Panel considers it would be inappropriate to make an order
of compensation.
52. In determining not to award compensation, the Panel acknowledges the
delays that have existed in this claim but as interest is payable, considers an
award of compensation would be unnecessary.
Determination
53. Accordingly, the Panel determines that the FSP cash settle the Applicants’
claim for the sum of $43,218.80 in accordance with the terms of the policy.
54. The FSP is to attend to the payment of the Applicants’ make safe repairs
and contents claim without further delay if it has not already resolved these
claims.
55. As the dispute is to be cash settled, the Panel determines the FSP is to pay
interest in accordance with Section 57 of the Insurance Contracts Act 1984
(the Act) from 9 January 2013 being the date of the FSP’s decision in this
dispute to date of payment of the claim.
Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.