Home / Financial Firm (Unknown - Insurer) / Determination 314985

Determination 314985

Claim denied under faulty design and defect exclusion

FirmFinancial Firm (Unknown - Insurer)
Decided2013-09-27
ProductGeneral Insurance · Strata
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed$18,383
SourceAFCA PDF

Summary

A body corporate's claim for storm-water leak damage to a garage, toilet and boundary wall was denied by the FSP under an exclusion for faulty design. AFCA upheld the denial, found IDR delays, and awarded no compensation.

Damage caused by the faulty design of the stormwater system, or any inherent pipe defect, falls within the policy exclusion regardless of the insured's awareness.

Issues

Subjects and remedies

home or building damageno remedy

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 314985 Determination Page 1 of 9 Case number: 314985 General Insurance - Domestic Insurance - Residential Strata Title - FSP Decision - Denial of claim-Exclusion/ condition 25 September 2013 Background 1. This Determination follow the review of a Recommendation issued on behalf of the Financial Ombudsman Service (FOS) on 16 July 2013. The Recommendation was rejected by the Applicants. 2. The Applicants are representatives of a body corporate which held a residential strata insurance policy with the Financial Services Provider (FSP). The policy was incepted on 8 October 2001 and renewed annually. 3. On 2 July 2012, the Applicants (on behalf of the insured) lodged a claim under the policy for damage to a garage, external toilet and brick boundary wall, caused by a leaking stormwater pipe. 4. The FSP initially declined liability for the claim on the basis that the damage was caused by earth movement and/or normal settling which had been occurring for a considerable period of time. 5. After the Applicants queried the FSP’s denial of th e claim, the FSP reviewed its decision and confirmed its denial, on the basis that the claimed damage was caused by a defect in the stormwater system. 6. The Applicants dispute the FSP’s denial of the claim and seek to have the FSP indemnify the insured for the claimed damage. Summary of Applicants ’ position 7. The Applicants say the damage was caused by a leaking stormwater pipe and therefore falls within the scope of cover under the policy. 8. The Applicants acknowledge that repairs to cracking damage to the building were carried out in 1996. However, they say that there was no evidence of damage between the date the repairs were completed and 2009, when the building was repainted and no damage was visible. 9. The Applicants also say that the FSP failed to manage the insured’s claim diligently. Determination Case No: 314985 Determination Page 2 of 9 10. The Applicants seek to have the FSP indemnify the insured for the cost of repairing the damage to the property (estimated to be $17,723). The Applicants also seek reimbursement of $660, being the fees of the insured’s property manager for managing the claim. Summary of FSP’s position 11. The FSP says that its engineer has confirmed that:  the damage to the property occurred as a result of the storm water drainage system being defective, which caused water to escape into the surrounding soils; and  the stormwater system failed because of the manner in which it was installed. 12. The FSP says that the claimed damage occurred over a lengthy period of time. Photographs t aken by the FSP’s engineer establish that there was movement in the brickwork prior to the building being repainted in 2009. 13. Accordingly, the FSP says that the claimed damage falls within an exclusion under the policy for damage caused by or arising from “the failure of or a defect in any item, faulty workmanship, structural defect or faulty design”. Issues 14. Whether the FSP is entitled to deny the insured’s claim. 15. Whether the insured is entitled to compensation for financial and/or non- financial loss as a r esult of the FSP’s handling of the claim. Reasons for decision 16. I am satisfied that there has been a full exchange of material between the parties and that each party has had an opportunity to respond to the issues raised therein. 17. The Applicants have confir med that the insured’s claim is for damage to the building resulting from the leak in the stormwater pipe and does not relate to the repair or rectification of the stormwater system itself. The FSP has stated that it would consider a claim for “any resulta nt damage”. However, it is clear that in the FSP’s view, this would not include the damage to the building which is the subject of the insured’s claim. Accordingly, it is this damage which is the subject of the current dispute. 18. The primary issue to be determined is the application of the policy wording, having regard to the cause of the claimed damage. Case No: 314985 Determination Page 3 of 9 Evidence as to cause of damage 19. Following lodgement of the insured’s claim, the FSP appointed an engineer (“F”) to report on the cause of the damage. F’s repo rt dated 2 October 2012 states that:  the building is located on relatively flat land with only a slight fall and has poor drainage;  significant stepped brickwork cracking was observed at the corners of the garage and toilet block, with previous repairs and paintwork evident in some locations. There was also horizontal cracking at the top of the internal wall between the garage and the toilet, and a gap of approximately 2.5 centimetres between the internal wall and the external wall;  there was a relative pattern of localised fall/settlement towards the internal wall of the block and significant settlement and rotation of the infill slab to the toilet. The toilet cistern had cracked due to the movement of the concrete slab;  soil testing carried out by F and hydraulic investigations carried out by a plumber (“AP”) revealed a fracture or leak in the earthernware stormwater drain under the concrete slab which allowed stormwater to escape into the surrounding ground, causing the soils around the slab and footings to become saturated and lose bearing strength; and  the downpipe connecting the roof to the underground stormwater drain via the eave gutters at the south-east corner of the toilet had been incorrectly installed so that it was not connected to the drain in an approved manner, and therefore allowed rainwater discharge to flow into the soils. This had contributed to the saturation of the soils . 20. Based on the damage observed and the results of the tests carried out, F concluded that:  the leaking stormwater had been flowing under the concrete slab for a prolonged period of time and had caused saturation and partial erosion of the poorly compacted fill and sandy soils, resulting in local bearing failure and subsequent downward soil movement which led to cracking of the walls and rotation of the slab;  the damage did not appear to be recent as there was evidence of previous repairs, which suggested that movement had been occurring for many years;  the stormwater system was defective and/or not functioning adequately due to the identified blockage and limited fall in the pipe and the leak under the building. It was likely that stormwater had not been discharging to the intended discharge point over a long period of time. This would have resulted in “back up” in the pip e, causing the contained water in the pipe to be under pressure, and eventually leak at the joints into the soils under the slab; and Case No: 314985 Determination Page 4 of 9  the defective section of the underground stormwater drain needed to be replaced with new PVC drains and the entire stormwater drainage system cleaned with high pressure water jet, following which steps should be undertaken to expand the soil underneath the foundations (in order to replumb the walls) and then reinstate the concrete slab. 21. F subsequently confirmed in an email dated 1 February 2013 that:  it was evident that the brickwork had been painted long after the movement and subsequent cracking damage had developed;  while the Applicants had advised that repairs were carried out in 1996, it was not possible to confirm whether these repairs related to the stormwater leak, due to the lack of information available; and  if the stormwater pipe had been leaking since 1996 and had caused saturation and soil bearing failure, the damage would have been noticeable within a couple of years of the leak commencing. Analysis 22. The courts have determined that a reference in a policy of insurance to damage “caused by” a par ticular event will generally be taken to refer to the proximate cause of the damage. This means the real, predominant or effective cause of the damage. 23. I accept that, as an engineer, F is appropriately qualified to report on the cause of damage. I note that F has relied on the findings of hydraulic investigations carried out by AP, as set out in AP’s report dated 29 September 2012 which is included as an appendix to F’s report. The Applicants have not provided any evidence which contradicts F’s findings as to the cause of the claimed damage. 24. F’s report clearly states that the claimed damage was due to foundation movement resulting from water saturating the surrounding soils. Further, both F and AP concluded that:  the primary cause of water entering the soils was a leak in the underground earthenware stormwater drain; and  a contributing cause was the incorrect manner in which the downpipe had been installed. 25. However, the reports of F and AP are inconsistent in their findings as to what caused the leak in the stormwater drain. 26. F’s report refers to the limited fall of the underground pipe and an identified blockage as contributing to the failure of the stormwater system to function properly. F goes on to state that the failure of the stormwater system to discha rge to the intended discharge point has resulted in “back up” in the pipe (as evidenced by AP’s finding that the pipe was “holding water”) which has caused pressure in the pipe resulting in water leaking through the joint. Case No: 314985 Determination Page 5 of 9 27. By comparison, AP’s report states that the stormwater drain was laid in filled ground under the slab, and subsequently dropped, which caused an opening either through a fracture or a joint in the pipe. However, AP does not provide any evidence to support his conclusion that the leak in the pipe was caused by the settling of filled ground around the stormwater drain. 28. Having carefully considered the available evidence, I prefer F’s findings as to the cause of the leak in the stormwater drain. In my view, F’s explanation as to the reasons why the stormwater system has failed to function adequately for a long period of time establishes, on the balance of probabilities, that the system was not adequately designed to cope with the drainage requirements of the site on which the insured property was located, having regard to the limited fall and poor natural drainage observed by F. Application of policy 29. The insured’s policy provides cover for accidental damage to the insured building which occurs during the period of insurance. 30. For the purposes of the policy, “accidental” is defined to mean something that is not intended or expected by the insured and would not be expected from the standpoint of a reasonable person in the insured’s position. 31. There is an onus on an insured to establish, on the balance of probabilities, that a claim fits the definition of an insured event. This is known as a prima facie claim. Should this onus be discharged, it is then the responsibility of the insurer to establish, on the balance of probabilities, that it is entitled to reduce or deny liability for the claim. 32. As outlined above, the cover for accidental damage under the policy is broadly defined. I accept that the damage to the insured building was not intended or expected by the insured, and would not be expected by a reasonable person in the insured’s position. 33. Accordingly, I consider that the insured has established a prima facie claim under the policy, and therefore the onus shifts to the FSP to establish a basis on which it is entitled to deny liability. 34. In its Notice of Response, the FSP says that the claimed damage falls within the exclusion under the policy for damage caused by or arising from “the failure of or a defect in any item, faulty workmanship, structural defect or faulty design”. 35. The FSP has previously sought to deny the insured’s claim on the basis that it fell within policy exclusions for damage arising from or caused by:  erosion, collapse or any other earth movement; or  normal settling, seepage, shrinkage, expansion, creeping, heaving or vibration. Case No: 314985 Determination Page 6 of 9 36. Further, in earlier correspondence with the insured, the FSP has claimed that F’s report establishes that the claimed damage occurred many years ago and therefore does not fall within the relevant period of insurance. 37. For the reasons outlined above, I consider that the underlying cause of the claimed damage was the inadequate design of the drainage system at the insured property. Accordingly, the damage falls within the exclusion under the policy for damage caused by “faulty design”. 38. Further, even if I were to accept that the alternative view expressed by AP that the leak in the stormwater drain was caused by the filled ground around the drain dropping, the claimed damage would still be excluded from cover under the policy, due to the exclusions for earth mo vement and normal settling (or possibly, faulty design). 39. Finally, I note that it remains possible that the leak in the stormwater drain arose from an inherent defect in the stormwater pipe, particularly given F’s findings that the damage had been occurring for an extended period of time. 40. As outlined above, the policy excludes damage arising from or caused by “the failure of or a defect in any item, faulty workmanship, structural defect or faulty design”. On its face, this would appear to exclude damage caus ed to the Applicant’s building by any inherent defect in the stormwater pipe. 41. I have considered whether section 9 (“Exploratory Costs”) of the Additional Benefits section of the policy affects this conclusion. Among other things, section 9 provides that, where water leaks from a fixed pipe, the FSP will pay the reasonable costs of repairing and replacing the defective part from where the liquid escaped, but only where the cause of the leaking is not otherwise excluded under the policy. It has been suggested that the operation of the exclusion in relation to “the failure of or a defect in any item” (as referred to above) makes this element of the cover provided by section 9 illusory. However, I do not agree that this is the case. There are a number of potential circumstances in which the leak of water from a pipe would be subject to cover because the defective part of the pipe is not the underlying cause of the leak, but would nevertheless require replacement (thereby giving effect to section 9) – for example, as a result of an earthquake, explosion or damage by tree roots. 42. Accordingly, I consider that the claimed damage is excluded from cover under the policy, regardless of whether the underlying cause of the leak in the stormwater pipe was:  the faulty design of the stormwater system (as identified by F);  the settling of the filled ground around the stormwater pipe (as identified by AP); or  an inherent defect in the stormwater pipe. 43. In his report, F also identified issues with the downpipe connecting the roof to the underground stormwater drain as being a secondary contributor to the claimed damage. F concluded that this downpipe had been incorrectly Case No: 314985 Determination Page 7 of 9 installed. Accordingly, to the extent the claimed damage arose as a result of this downpipe discharging rainwater directly into the soils, the exclusion for damage caused by faulty workmanship would apply. 44. The Applicants have stated that the claimed damage should not be excluded from cover as the leak in the pipe was not apparent to the insured or the property manager. However, the terms of the exclusion do not depend on whether the insured was aware of the issue which caused the damage. 45. Section 46 of the Insurance Contracts Act 1984 (Cth) prevents an insurer denying a claim as a result of a defect in a thing before the contract was entered into. However, section 46 has no application in the current circumstances as judicial authority has confirmed that this section does not apply where the exclusion relied on does not refer to the time at which the defect arose. 46. Accordingly, for the reasons outlined above, I consider that the FSP is entitled to deny the insured’s claim. Compensation for financial loss 47. The Applicants say that the insured should be able to recover the amount of $660 paid to its property manager for services provided in managing the claim. 48. As I am satisfied that the FSP was entitled to decline the claim, it follows that it should not be responsible for the insured’s costs in managing the claim process. Compensation for non-financial loss 49. The Applicants are dissatisfied with the manner in which the FSP has handled the insured’s claim. In particular, the Applicants say that the FSP has unnecessarily delayed referring the claim for review by its internal dispute resolution (IDR) department and making a final decision in relation to the claim. 50. Under paragraph 9.3(b)(i) of FOS’s Terms of Reference, compensation for non-financial loss (capped at $3,000) may be awarded where there has been an unusual degree or extent of physical inconvenience, time taken to resolve the situation or interference with an insured’s expectation of enjoyment or peace of mind. However, compensation for non-financial loss will not be provided where the policy expressly excludes such liability. 51. I note that some of the delays complained of by the Applicants have arisen because the dispute was handled through the insured’s broker – accordingly, in some instances the Applicants have communicated directly with the broker and there has been a lag in the relevant communication reaching the FSP. Additionally, the Applicants have not always been privy to all correspondence between the FSP and the broker. Case No: 314985 Determination Page 8 of 9 52. However, it is also clear that there were delays in the FSP’s handling of the claim. The evidence provided by the parties indicates that:  the FSP initially declined the claim on 26 October 2012 by a letter to the insured’s broker, which the broker forwarded to the Applicants on 30 October 2012;  after the broker forwarded the Applicants’ objections to the denial to the FSP, the FSP wrote to the broker on 13 November 2012, seeking further information;  on the Applicants’ instructions, the broker emailed the FSP on 3 December 2012 requesting that the claim be either settled on the basis of the evidence provided or referred for IDR review;  the FSP confirmed its denial of the claim by way of a letter dated 17 December 2012. The FSP ’s cover email attaching the letter indicated that this was “the first step in the IDR process”;  the Applicants instructed the broker to formally ask the FSP for an IDR review, which the broker did on 24 December 2012;  on 22 January 2013, the FSP advised that a “level 1” review had been carried out on 16 January 2013 and a copy of the file sent to the IDR department;  on 1 February 2013, the FSP’s engineer appears to have responde d to a request from the FSP’s IDR department for further information; and  the FSP’s final decision was issued on 12 February 2013. 53. Accordingly, there were approximately 50 days between the insured’s formal request for an IDR review on 24 December 2012 and the issue of the FSP’s final decision on 12 February 2013. This incorporates the FSP’s “level 1” review which appears to be an additional internal review step undertaken prior to the formal IDR review. Further, if 3 December 2012 is taken as the date on which the IDR review was first requested, then the delay is approximately 70 days. 54. I note that part of this period includes the Christmas holiday period. It also appears that further information was requested from the FSP’s engineer as part of the review (although not until a significant amount of time had already passed). However, these factors do not explain the extent of the delay before the FSP’s final decision was issued, or the failure by the FSP to keep the insured informed as to the progress of the review. 55. However, I do not consider the delay in processing the insured’s claim to be so unusual as to warrant the payment of compensation under clause 9.3(b)(i) of the Terms of Reference, in circumstances where the FSP had already advised the insured that it had denied the claim, and I have determined that the FSP was entitled to do so. Case No: 314985 Determination Page 9 of 9 Determination 56. On the basis of the available information I determine that:  the FSP was entitled to deny the insured’s claim; and  the insured is not entitled to compensation for financial and/or non- financial loss as a result of the FSP’s handling of the claim.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.