Home / Financial Firm (Unknown - Insurer) / Determination 314209

Determination 314209

Refusal of flood-exclusion claim for inundation of home

FirmFinancial Firm (Unknown - Insurer)
Decided2013-12-23
ProductGeneral Insurance · Home building and contents
OutcomeFor the complainant in part
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

The applicants' home was inundated during the January 2011 Queensland storm events and the FSP refused the claim under the flood exclusion. The Panel found the FSP had not established the initial inundation was caused by floodwater, and ordered cover for building and contents loss up to 150mm inside the home, with interest from the claim decline date.

The insurer bears the onus of establishing an exclusion, and the policy does not exclude inundation from stormwater drains, so the initial loss was covered to 150mm given the unreliable and shifting hydrology evidence.

Issues

Subjects and remedies

natural disasterpay claimpay interest

Related

All Financial Firm (Unknown - Insurer) determinations · Find similar determinations

Text of the determination

Case No: 314209 Determination Page 1 of 10 Case number: 314209 General Insurance - Domestic Insurance - Home Building - FSP Decision - Flood - Denial of Claim 13 December 2013 Summary Description: Claim under Home and Contents Policy following inundation of Applicants‟ home in January 2011 after the heavy rainfall in Queensland. Basis of Determination: The information establishes that the home was first inundated by stormwater as defined in the policy prior to the floodwater impacting on the home. Determination: The FSP is liable to cover the claim for damage to the building and contents arising from inundation of the home to a level of 150mm above floor level. Background 1. The Applicants held a home building and contents policy with the Financial Services Provider (FSP). 2. In January 2011, the Applicants‟ home in Narangba was inundated with water following severe weather events in Queensland. 3. The FSP assessed the subsequent claim and after obtaining a hydrology report, refused liability on the basis the loss was caused by flood, which is an exclusion under the policy. 4. The Applicants disputed the decision, saying the loss was caused by local stormwater runoff. Further reports were obtained and the FSP maintained its decision to refuse liability. 5. The Applicants seek a review of the FSP‟s decision. Determination Case No: 314209 Determination Page 2 of 10 Summary of Applicant s’ p osition 6. The Applicants say that the FSP‟s hydrologist has made a number of errors in the reports and this is highlighted by the fact the conclusions across the reports vary significantly. 7. Other insurers that do not cover flood covered their clients in the same locality for the same event. 8. The Product Disclosure Statement (PDS) does not define the term “areas surrounding the site”, so they expect this would include all runoff, including water that may have escaped from Burpengary Creek. 9. A large drain adjacent to Burpengary Creek is a major collection point for the areas‟ drainage system and connects directly to Burpengary Creek. Water surcharges from this drain before Burpengary Creek breaks its banks and given the drain has a „3m by 3m‟ capacity, it could have been the sole cause of the water flow. The original hydrology report did not even mention this drain. 10. Photographs of the drain the day after the event show no evidence of significant water flow between the nearby Burpengary Creek and the drain; however, there was significant mud and debris between the drain and Lookout Place. 11. A number of witness statements from local residents support their submission that the water was not from Burpengary Creek and that water did not backflow up or overflow the open channel on Stony Creek Reserve. 12. The Applicants acknowledge the subsequent hydrology reports more accurately reflect what occurred at the time of the loss, they have concerns with the validity of the reports, given the significant shift in conclusions after they challenged the hydrology reports. For example, the hydrologist now accepts water backs up from the drain at Stony Creek Reserve, which is a complete reversal from the earlier reports. 13. It is absurd for the hydrologist to suggest that a large volume o f water overflowed over a narrow landscaped area from Burpengary Creek and left no evidence of passing. 14. The hydrologist also concedes that stormwater drainage in the area may be “complex” during major flood conditions, which is supported by the inconsistencies across the reports. The hydrological conclusions cannot be relied upon. 15. The explanation that silt only settled on Lookout Place because it is a low point on the flow path is not acceptable. There are other low points that did not have settlement. A more likely explanation is that the mud was in the drainage system from the time of construction and it was forced out of the drain and settled close by. Case No: 314209 Determination Page 3 of 10 16. The Applicants say that the fact stands that there is no evidence of water from the channel but there is ample evidence of water discharging from the drains. Expert opinion and modelling must be tested against physical evidence and in this case, there is far more evidence to indicate the inundation was caused by water from the drainage system. 17. The Applicants say the overwhelming majority of water that caused the insured loss was from drainage infrastructure and on this basis, the policy should respond to the loss. 18. The Internal Disputes Resolution process was faulty as the FSP did not seek further expert opinion from the hydrologist. Their claim and the dispute process of the FSP were discussed at the Queensland Floods Commission of Enquiry. They provide a copy of the relevant transcript. 19. The Applicants seek cover under the policy on the basis the loss was caused by a storm event. Summary of FSP’s position 20. The FSP has provided a number of submissions and five reports from its hydrologist the latest on 11 October 2013. The FSP says the expert opinion establishes the loss was caused by flood and as the policy excludes flood, the claim is not covered under the terms and conditions of the policy. 21. The hydrologist has addressed the issues raised by the Applicants and concludes the water that entered the home was a mix of stormwater runoff and floodwater from Burpengary Creek. 22. If the water from Burpengary Creek inundated the home at the same time as stormwater runoff then the Wayne Tank principle applies to defeat the claim. 23. The Applicants have acknowledged that overland flow from Burpengary Creek was a cause of the loss. 24. The FSP relies on the following policy provisions contained in the PDS: “ What we cover - insured events This section describes under the heading: Yes - the insured events you are covered for, No - the conditions and exclusions that specifically apply to particular insured events. … Yes Storm and rainwater including stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or su rface. Case No: 314209 Determination Page 4 of 10 Storm means violent wind (including a cyclone or tornado), thunderstorm or a heavy fall of rain, snow or hail. … No Damage or loss caused by flood . Flood means the inundation or covering of normally dry land by water which: escapes or overflows from , or cannot enter, because it is full or has overflowed, or is prevented from entering, because other water has already escaped or been released from it, the normal confines of any watercourse or lake, including any that may have been modified by human intervention, or reservoir, canal, dam or stormwater channel. Flood does not mean stormwater runoff from areas surrounding the site, or water escaping from any water main, drain, pipe, street gutter, guttering or surface. … What we do not cover - general exclusions You are not covered under any section of the policy for damage, loss, cost or liability caused by or arising from or involving: … flood,” Issues 25. Whether the loss was caused by stormwater runoff or flood? 26. Whether the FSP is entitled to refuse liability under the terms and conditions of the policy? Reasons for decision 27. As advised to the parties, the Financial Ombudsman Service has considered it appropriate to elevate the dispute in accordance with the Operational Guidelines to the Terms of Reference. This is because of the potential amount of the claim and the issues to be considered. This dispute has not been the subject of a Recommendation and has p roceeded directly to Determination. 28. The decision has been made by a Panel of three decision makers, including an Ombudsman and decision makers with experience in the insurance industry and consumer rights. Case No: 314209 Determination Page 5 of 10 The policy 29. While not a specific issue in dispute, the Panel has reviewed the terms and conditions of the Product Disclosure Statements containing the details of cover for the building and contents. 30. The Panel is satisfied the policy covers loss due to the storm but specifically excludes loss caused by flood, defined as water escaping a watercourse, lake or stormwater channel. The policy however does not exclude inundation from water escaping from, mains, drains, pipes, street gutters, guttering or surface. Whether the loss was caused by stormwater runoff or flood? 31. The Applicants say that the inundation was caused by stormwater runoff discharging from the drainage system and therefore the policy responds to the loss. 32. The FSP says the loss was caused by flood as defined by the policy as water from Burpengary Creek mixed with the runoff before the property was inundated above floor level. 33. The Panel notes that there have been extensive exchanges between the Applicants, the FSP and the hydrologist, „W‟. A total of five hydrologist reports have been provided. The Panel does not propose reciting all the reports in detail in this determination as they have been exchanged between the parties but notes the first two reports from “W” dated 7 March 2011 and 15 April 2013 concluded as follows: ” Based on the available information we remain of the opinion that the initial and maximum above floor inundation of the subject property was caused by floodwater from Burpengary Creek. Stormwater runoff from the local catchment could not have inundated the house on the subject property above floor level during the event. ” 34. “…Following further concerns raised by the Applicant, W prepared another report of some length, dated 7 August 2013, which relevantly states: “… … 5 CONCLUSIONS The additional information provided by [male Applicant] and Moreton Bay Regional Council, as well as detailed hydraulic modelling, have shown that the maximum depth of stormwater runoff from the local catchment in the vicinity of the subject property is likely to have reached a higher level than indicated in our previous reports, but it is unlikely to have reached the floor level of the house. Our further investigations have shown that the dynamics of the local stormwater pipe network are complex. During major flood events in Burpengary Creek which prevent stormwater outflow from the pipe network at Lookout Place, there is the potential for stormwater from an additional catchment area of 13 ha located to the south of Lookout Place to be diverted down M Street. We estimate that this would have increased the rate of Case No: 314209 Determination Page 6 of 10 surface flow down M Street to 4.36 m3/s and resulted in a water level close to the house floor level. To reach the observed peak flood level of 0.21 m above the house floor level, we estimate a peak discharge of 12.86 m3/s down M Street. A flow of this magnitude could not have been generated by the local stormwater catchment (including the diverted catchment located to the south of Lookout Place). Our opinion is that the additional flow was caused by floodwater overflowing from Burpengary Creek at Lookout Place. Hence, the peak flood level at the subject property was caused by a combination of local stormwater runoff and overflow of floodwater from Burpengary Creek. ” [sic] 35. Again further issues were raised by the Applicant and W prepared a further report, dated 3 September 2013, which relevantly states: “… 5 CONCLUSIONS The configuration of the drainage system in the vicinity of Lookout Place indicates that overflow down M Street could not occur until Burpengary Creek had broken its banks at Lookout Place. In addition, the stormwater pipe network connecting the drainage system in Lookout Place to Burpengary Creek is too small to convey the flow of water required to inundate the subject property to the observed peak depth of inundation. Once the floodwater reached sufficient height to begin overflowing into M Street from Moorhen Court the head differential between water levels within and outside the Burpengary Creek bank would have been minimal resulting in a much lower pipe flow rate. This information indicates that Burpengary Creek overflowed its banks in the vicinity of Lookout Place and contributed to the inundation of the subject property. The observed minimal disturbance at the Burpengary Creek overflow location upstream of the subject property was due to the significantly lower flow velocities compared to Stony Creek Reserve. Hydraulic modelling showed that inundation of the subject property above floor level required significant additional inflows from the catchment area to the south of Moorhen Court. When water overflowed from Lookout Place and Moorhen Court there was a direct overland connection to Burpengary Creek. For these reasons it is our opinion that the subject property could not have been inundated above floor level prior to Burpengary Creek overtopping its banks. ” 36. After further exchanges, W provided its fina l report, dated 11 October 2013, which relevantly, states: “… 4 CONCLUSIONS [male Applicant] has estimated the elevations of the embankment crest prior to the council modifications based on recent observations and photographs obtained from Google Street View. The resultant cross-section is [male Applicant‟s] best guess at how the embankment looked prior to the modifications and is not an accurate representation of the embankment. The aerial survey data used in our report provides an accurate representation of the embankment elevations during the January 2011 flood event as it was captured in 2009 prior to the council modifications. Therefore, we maintain Case No: 314209 Determination Page 7 of 10 that the cross-sectional area (6.42 m2) and flow velocity (1.3 m/s) calculated in our previous report (Report No. 0768-02-245C) is a more accurate estimate of the flow characteristics at this location during the event. When water overflowed from Lookout Place and Moorhen Court (into M Street) there was a direct overland connection to Burpengary Creek. Therefore, our opinion remains that the subject property could not have been inundated above floor level prior to Burpengary Creek overtopping its banks. Minimal flow in the low point of Lookout Place after the peak of the flood event allowed sufficient time for the observed silt to deposit on the road. ” 37. The Applicant has provided a number of witness statements from locals in Narangba. The statements provide the following relevant information:  „JA‟ says that on 11 January 2011, he went for a walk to a friend‟s new home on Koel Drive to check the water level. He checked the water level in Burpengary Creek and noted it was 4-5m from breaking its banks. He returned home 40 minutes later to find he had been inundated to a depth of 600mm. He claimed through his insurer and was informed it was not a flood event because the creek did not break its banks.  „ST‟ says the open channel did not overflow its banks.  „EE‟ says her property on Koel Drive (near B urpengary Creek) was not inundated with water and the creek did not overtop it banks.  „ET‟ says she owns a small business and makes house calls and is knowledgeable of local events. She says the hydrologist‟s flood map is wrong and she knows 10 people whose homes are noted as flooding that did not. No houses were inundated on the side of the open channel.  „RE‟ says he investigated the area to establish the reason for the inundation and found there was no evidence Burpengary Creek broke its banks as there was no debris and damage to any vegetation or landscaping. The only evidence of debris was around the stormwater drains.  „KC‟ says there was heavier rain from 11:00am on 11 January 2011 and water was rising in the area. In the days after the event, he took his camera and discovered the source of the water was the stormwater drain at Lookout Place. He attended a community meeting and those who were present all reported that the water came out of the large stormwater drain and no water came over the embankment between the stormwater drain and Burpengary Creek. KC says the loose rocks in the channel between the drain and Burpengary Creek appeared to be undisturbed. Case No: 314209 Determination Page 8 of 10 Discussion 38. At law, the onus to establish a loss has occurred to which an insurance policy responds rests with the insured. This is known as establishing a prima facie claim. If an insured is able to establish a prima facie claim and the insurer seeks to refuse the claim on the basis of an exclusion in an insurance policy, then the onus shifts to the insurer to establish the exclusion applies to the circumstances of the claim. 39. As it applies to this claim, the Applicants say the loss was caused by the discharge of water from the drainage system which falls within insured event of storm. The FSP says the excluded event of flood from a watercourse was the cause on the basis that Burpengary Creek overtopped its banks and mixed with the stormwater runoff. It must be remembered in determining this dispute that inundation caused by water, regardless of its source, escaping from any water main, drain, pipe, street gutter, guttering or surface is covered under the terms of the policy. With this in mind the Panel has reviewed the various reports and submissions of the parties. 40. The hydrological conclusions of W have changed significantly since the first report. The third report dated 7 August 2013 states “the dynamics of the local storm water pipe network are complex” , and that while the peak inundation was deemed to be a combination of stormwater runoff and floodwater from Burpengary Creek, the report indicates that stormwater runoff could have been “close to the floor level” under certain circumstances. 41. This is a marked difference to W‟s first report which stated stormwater runoff could only have reached a depth of around 36mm. 42. W‟s later reports state that the Applicants‟ home could not have been inundated above floor level by stormwater runoff alone. 43. However, the various statements provided by the Applicants from locals in the area, are consistent in their view that Burpengary Creek did not overtop its banks. 44. Further, RE and KC state that there was no evidence Burpengary Creek broke its bank in the location of the drain at Lookout Place, with KC stating there was little evidence the channel between Burpengary Creek and the drain had been disturbed, while there was ample debris around the drain. 45. The Applicants have provided photographs of the channel between Burpengary Creek and the drain, taken the day after the event. The Panel has reviewed these photographs and accepts there is little evidence of debris in the channel. 46. Bearing in mind W‟s statement that under certain circumstances stormwater runoff could have come close to the floor level of the home, and the fact W has changed his conclusions significantly across various reports, the Panel accepts the Applicants‟ submission that limited reliance can be placed on W‟s conclusions. Case No: 314209 Determination Page 9 of 10 47. It is always concerning when a technical expert provides a report and then is forced to amend conclusions because certain aspects of the initial report have been drawn into question. This has occurred on a number of occasions in this dispute. The evidence of the eye witnesses has not been disputed and in the circumstances should not be easily discarded. 48. Referring back to the legal onus on the parties, the Panel is satisfied that a severe storm event occurred in January 2011 and the Applicants‟ home was inundated with water. The FSP has refused the claim on the basis the loss was caused by the excluded event of flood and therefore bears the onus to establish the exclusion of flood applies to the claim. 49. In the Panel‟s view, the FSP has failed to sufficiently establish that the cause of the initial loss was floodwater. 50. The Panel accepts the peak inundation was likely caused by a mix stormwater runoff and floodwater from Burpengary Creek, which would invoke the Wayne Tank principle; however, the Panel is not persuaded the FSP has established the initial inundation was necessarily caused by floodwater. 51. Further, that the Applicants concede some water may have overtopped Burpengary Creek is a secondary consideration to the FSP‟s onus to establish the exclusion. The Panel is not persuaded the male Applicant‟s limited concession is overly relevant in this instance. 52. Given W has changed conclusions significantly between reports, locals in the Narangba have provided statements which indicate Burpengary Creek did not break its banks and there is some question as to whether the channel between Burpengary Creek and the drain was affected by floodwater, the Panel determines that the initial inundation of the home above floor level was most likely due to an insured event of storm and rainwater. The Panel accepts the evidence that the peak level of inundation would have been due to a combination of stormwater runoff and flood. 53. The evidence does not allow for an accurate assessment of the height of the initial inundation however given the time that has elapsed since the inundation, the Panel considers it would be fair in the circumstances to determine the initial inundation to a height of 100 to 150mm. The FSP is liable to meet the cost of repair and contents loss sustained as a result of inundation to this height. 54. The Case Manager at the Financial Ombudsman Service spoke with the male Applicant on 21 November 2013 and he indicated that he had undertaken most of the repair work himself and he had a number of receipts for materials etc. 55. In the circumstances, the Panel determines that the Applicants are to provide receipts and details of the work done to the FSP and the FSP is to obtain a scope of works and quotation to cover the repairs and provide these to the Applicants. The parties are asked to work cooperatively to agree on a Case No: 314209 Determination Page 10 of 10 reasonable settlement of any building damage and contents loss sustained as a result of inundation up to 150mm inside the home, including an allowance for Applicants‟ labour in undertaking repairs. 56. If there is any unrepaired damage that should be covered up to 150mm in the home, then the FSP is to allow for this or undertake the further repair itself, at its option. 57. For the sake of clarity, the FSP is not liable for damage over 150mm inside the home. The Panel notes the latest hydrology identifies the maximum inundation to be 210mm. Determination 58. On the basis of the available information the Panel determines the FSP is to cover building damage and any contents loss up to 150mm inside the home, including a reasonable allowance for the Applicants‟ labour given most repairs have reportedly been completed. 59. Further, the FSP is to pay interest on any settlement at the statutory rate from 11 March 2011, being the date the claim was initially declined. 60. The Panel trusts that the parties will co-operate in good faith in reaching a resolution, although the matter can be referred back to the Panel if the parties cannot agree on the settlement amount.

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.