Determination 314083
Roof batten damage claim refused under gradual deterioration exclusion
Summary
The applicants claimed for roof batten damage from Cyclone Yasi after the insurer's $2,670 cash offer excluded it. AFCA found the batten damage was caused by the cyclone and ordered the insurer to repair the roof and other covered damage.
The insurer had to establish the gradual deterioration exclusion, and the weight of expert evidence showed wind-related batten lift rather than shrinkage.
Issues
- Claim denial primary · upheld“Panel satisfied on balance that batten damage was caused by Cyclone Yasi batten lift; FSP liable despite gradual deterioration exclusion.”
- Claim amount dispute secondary · upheld“FSP cash settlement of $2,670 did not cover all Cyclone Yasi damage; other building damage ordered covered.”
- Repairs or contractors secondary · unclear“Evidence of poor workmanship by the FSP's repairer may have caused the damage; Panel did not decide it.”
Subjects and remedies
home or building damagenatural disasterrepair or rectify
Related
All Financial Firm (Unknown - Insurer) determinations · Find similar determinations
Text of the determination
Case No: 314083 Determination Page 1 of 7
Case number: 314083
General Insurance - Domestic Insurance - Home Building - Storm - Cyclone
Yasi - FSP Decision - Claim Amount - Exclusion/Condition - Gradual
Deterioration
27 February 2014
Summary
Description
Claim under a home contents policy for damage sustained during
Cyclone Yasi in February 2011 and poor workmanship. While accepting
the claim, dispute arises as to the extent of the damage.
Basis of Determination
There is no dispute the property was damaged during Cyclone Yasi.
Four experts including the FSP’s experts identify roof damage due to
the Cyclone Yasi.
On balance, the damage including batten lift is due to Cyclone Yasi.
There is evidence of poor workmanship by the FSP’s repairer that may
have caused the damage.
Determination
The FSP is liable to meet the cost of repair to the roof and other
Cyclone Yasi related damage.
Background
1. The Applicants held a home and contents insurance policy with the Financial
Services Provider (FSP) which was current at the time of the loss. The policy
provided accidental damage cover.
2. The Applicants lodged a claim on 8 February 2011 for damage to their
property following the Cyclone Yasi event. The FSP accepted the claim and
authorised repairs to the property.
3. On 4 June 2012, the Applicants lodged a claim for damage due to a leaking
roof. The Applicants believed the damage was due to either previously
Determination
Case No: 314083 Determination Page 2 of 7
unidentified Cyclone Yasi damage or poor workmanship in the repairs
performed by the FSP.
4. The FSP reassessed the claim, accepted there was previously overlooked
Cyclone Yasi related damage and offered the Applicants a cash settlement
of $2,670.
5. The Applicants disagree with this offer as it does not include cover for the
cost to repair the roof battens.
Summary of Applicants ’ position
6. The FSP’s authorised builder (J) repaired the roof after Cyclone Yasi. In April
2012, the Applicants found mildew on the ceiling due to water coming
through one of the roof valleys.
7. During reassessment of the damage, it was identified there was damage to
the roof structure due to batten lift caused by winds during Cyclone Yasi.
8. It says the batten damage cannot be due to shrinkage as the faults are
confined to the peak area of the roof and are not across the entire roof.
9. It argues if a batten screw is partially lifted but not removed, the part
remaining in the wood would still be secure. It contends the lever test
performed by the FSP’s experts may not have revealed any movement but
this does not mean there was no batten lift.
10. The batten lift was caused by Cyclone Yasi. The FSP should be accountable
for the repairs of this and all other damage missed in the previous repairs.
11. The Applicants provided a quotation of $71,254 from builder CC to cover the
repairs.
Summary of FSP’s position
12. After inspecting the damage, the building consultant (S) appointed by the
FSP reported there was cyclone-related damage including batten lift. The
FSP agreed to cover part of the damage as cyclone-related but disagreed
the event had any impact on the roof battens.
13. The FS P relies on structural engineer (KA’s) opinion to argue the spacing in
the battens was due to the manner in which the building was originally built
and batten shrinkage contributed to the spacing.
14. Further, it says according to Australian standards the gaps identified in the
battens are well within the range of timber shrinkage allowance.
Case No: 314083 Determination Page 3 of 7
15. It argues the battens have not sustained any damage or in the alternative,
batten shrinkage occurred over a period of time which is considered gradual
deterioration and/or wear and tear and is thus excluded under the policy.
16. The FSP accepts there was some damage overlooked and offered to cash
settle the Applicants’ claim for $2,670. Otherwise, the FSP declines liability
for the loss.
17. The FSP relies on the following policy provisions within the Product
Disclosure Statement:
“ Exclusions to your cover
Any cover we provide is subject to the following exclusions.
Accidental
Damage cover,
Additional
cover and
Strata Title
Mortgagee
Protection
exclusions
We will NOT COVER any loss o r damage as a result of, or
caused by
…
erosion, rust, corrosion, gradual deterioration,
depreciation, wear or tear …”
Issue
18. Whether the FSP is entitled to deny the claim for the alleged damage to the
roof battens according to the terms and conditions of the policy.
Reasons for decision
19. As advised to the parties, due to the nature of the dispute, the Financial
Ombudsman Service (FOS) has considered it appropriate to expedite the
dispute to Determination in accordance with the Operational Guidelines to
the FOS Terms of Reference.
20. This decision has been made by a Panel consisting of an Ombudsman and
two Panel members with extensive experience in insurance industry matters
and consumer claims.
21. The Panel is satisfied a full exchange of the relevant information has taken
place between the parties and each party has had the opportunity to address
the issues raised.
22. The Panel notes there is no dispute the property has cyclone-related
damage which was not previously identified and the FSP has offered a cash
settlement for part of this.
23. In a telephone conversation of 28 January 2014, the male Applicant
confirmed to FOS that the central point of dispute with the FSP refers to the
damage to the roof battens. The central issue is whether the cause of
Case No: 314083 Determination Page 4 of 7
damage to the roof battens is batten lift or shrinkage and thus whether the
FSP is liable for their repair.
24. The relevant evidence supporting the Applicants’ position is as follows:
A report by the Applicants’ builder (CO) which says “ all roof batton
spacings top and bottom are not to Australian Standards some
spacings are 1200 from nearest batton to ridge” [sic].
Two reports by the FSP’s building consultant S which say damage in
the form of loose roof sheets and “uplift” of the roof framing is a direct
result of the strong wind experienced during Cyclone Yasi and one can
see batten lift at various locations over the entire roof cavity.
A report by the Applicants’ consulting engineer (CM) which says the
roof battens have lifted in the high pressure areas at the apex of the
roof and at the eaves/heel areas. It also says the observations do not
indicate batten shrinkage.
CM’s second report which says:
i. Shrinkage is not concentrated in a particular section of a roof,
whereas batten separation as in this case is predominantly at the
ridge which is the highest pressure area.
ii. In other houses failed batten fixings will not “spring back” into
position while walking on the batten.
iii. It is incorrect to use a screw driver or pinch bar to assess the
structural integrity of the roof fixings to resist future cyclonic loading.
iv. The failure of the batten fixings is progressive due to the fluctuating
loads and complexity of the screw fixing.
v. The degree of damage to roof battens is dependent not only on the
velocity of the winds but also on the travel speed of the cyclone.
vi. The current battens have load-carrying capacity but it has been
diminished by the wind damage.
A report by the Applicants’ consulting engineer (CA) which says:
i. While many battens have not visibly lifted, gaps measured under
affected ones were of 3-5mm.
ii. Due to the allowance for shrinkage having been exceeded, lift of
more than 1.5mm cannot be considered timber shrinkage.
iii. Timber shrinkage will typically result in battens shrinking down onto
the frame, not in defying gravity and lifting the battens off the roof
frame.
iv. A lifted batten screw would tend to jam up until it may fail
completely if the loading is applied long enough.
25. The relevant evidence supporting the FSP’s position is as follows:
A report by consulting engineering company (IC) in which building
consultant (BH) says:
Case No: 314083 Determination Page 5 of 7
i. The roof batten to truss tie down connections are compliant with the
current Australian Standard AS1684.3.
ii. Gaps of around 2mm are present in various locations along the
entire length of individual battens, save for one roof batten
connection which has a gap of 6mm.
iii. Where gapping was evident, BH tested the tie down strength using
an 800mm prise bar to try separating the batten off the truss. At no
point did the connections separate. If failure or batten lift had
occurred, battens should be able to be separated.
iv. There is no batten lift or failure of the roof batten to roof truss
connections. The roof batten with the 6mm gap was likely not
screwed down tight onto the roof frame at the time of initial
construction.
IC’s second report in which structural engineer KA agrees with BH and
adds:
i. Some of the gaps to the battens appear to be of 2.78mm or larger.
Gaps of 3mm would still be most likely due to shrinkage of timber.
ii. No movement resulted from using a long screwdriver to attempt
levering the roof battens from the trusses.
iii. The battens are screw-fixed. When screws pull out, their thread
strips the timber internal fibres along the full length of the thread,
creating a total loss of effectiveness. It is not possible for half a
screw to pull out and the rest to remain in place.
iv. No batten lift or failure of roof battens has occurred.
Two emails where KA provides comments to CM’s reports as follows:
i. If there was batten lift, the threaded screw pulling out would tear the
timber and thus when applying pressure, there would be movement.
ii. If battens had lifted, walking on the roof would have applied
pressure and pushed the battens back down. There was no
indication of this occurring.
iii. The relevant Australian Standards say shrinkage can happen
between 2% and 10% and the Australian Hardwood Network
suggests 4-14% is possible.
iv. The battens are 38mm deep, so it is conceivable that shrinkage of
3.8-5.3mm has occurred. As the gaps previously identified are
between 2-3mm, they are consistent with shrinkage.
v. Had there been sufficient uplift to lift and break batten connections
across the entire roof, it would be expected that areas at the ridge
and eaves would be greatly affected. There was no evidence of this
occurring.
vi. CM did no testing and said gaps are only present in selected areas
around the ridge but the gaps were present across the full area of
the roof, which corresponds with the effects of timber shrinkage.
Case No: 314083 Determination Page 6 of 7
vii. Further, the wind experienced during Cyclone Yasi in the area
where the property is built would have been insufficient to cause
major structural damage.
26. S, IC and CM have also provided photographs of the roof cavity which
clearly show separation between some of the roof battens and trusses.
These images however do not assist in identifying whether the damage is
localised or not.
27. Based on the experts’ explanation, the Panel c onsiders both positions are
plausible. However, the Panel notes the majority of experts including an FSP
appointed building consultant agree that the likely cause of damage was
batten lift.
28. Further, following CA’s opinion, the Panel considers it reasonable to say
shrinkage would usually result in battens shrinking down onto the frame. CA
also notes that lifted batten screws tend to jam up when lifted, which
provides a reasonable explanation as to why BH and KA found no
movement.
29. Although KA has explained there has to be batten movement in order to
establish batten failure, it seems he has not considered the possibility of the
screws jamming up. No counterargument by a qualified expert has been
provided to CA’s reasoning.
30. Having considered the evidence as a whole, the Panel is satisfied, on the
balance of probabilities, that the damage was caused due to batten lift as a
result of high wind pressures during the Cyclone Yasi event.
31. In the alternative, even if it were accepted that damage was due to
shrinkage, all reports coincide in that uncompleted repairs and/or
unidentified damage has allowed additional moisture to enter the roof cavity.
32. The period between the damage by Cyclone Yasi (February 2011) and the
roof cavity inspections (between June 2012 and October 2013) was
prolonged. The Panel is persuaded any potential shrinkage would have been
caused by unusual exposure to the elements due to the uncompleted repairs
or previously unidentified damage.
33. In that case, the proximate cause of shrinkage would still be Cyclone Yasi or
J’s workmanship. In any case, it is the Panel’s view the FSP should provide
cover for this damage.
Other issues
34. The Applicants raised other issues related to J’s workmanship and Cyclone
Yasi related damage. The FSP accepted there was at least previously
unidentified Cyclone Yasi damage and offered a cash settlement of $2,670.
35. Following IC’s first report, this would cover only part of the previously
unidentified Cyclone Yasi damage.
Case No: 314083 Determination Page 7 of 7
36. The Panel notes that IC’s second report contains the most de tail regarding
other damage to the building.
37. KA’s report is not challenged in these aspects by any other expert opinion.
Therefore, the Panel is of the view that KA’s report should be relied upon to
establish which damage to the building should be covered as previously
unidentified Cyclone Yasi damage or rectification works to the first repairs.
38. Following KA’s report, other damage in the property that should be covered
is: overtightened roof screws, hip and ridge capping damage, water ingress
above the laundry and insulation on top of the laundry ceiling, cornice
cracking and ceiling damage to one bedroom.
39. On the evidence presented, it appears that the roof is capable of repair and
would not require replacement, unless demonstrated to the contrary during
repair work.
Determination
40. On the basis of the available information, the Panel determines the FSP is
liable for the repair of the roof battens.
41. Within 30 days of being notified of the Applicants’ acceptance of this
decision, the FSP is to organise a quote for the repair of the roof battens and
other building damage as described in paragraph 38 of this Determination.
42. Within 45 days of being notified of the Applicants’ acceptance of this
decision, the FSP is to organise for a builder of its choice to start repairs to
the property based on the quotation previously obtained.