Finance contract terms not disclosed and contract price disputed

FirmFinancial Firm (Unknown - Credit)
Decided2015-02-10
ProductCredit · Car loan
OutcomeFor the firm
Amount awarded—
Non-financial loss—
Amount claimed—
SourceAFCA PDF

Summary

A vehicle finance customer said the contract terms were not disclosed to him and the contract price was wrong. AFCA found the price correct and the customer bound by the contract he signed, and it ordered no payment.

A person who signs a document containing contractual terms is bound by them whether or not they read it, absent extenuating circumstances.

Issues

Subjects and remedies

no remedy

Related

All Financial Firm (Unknown - Credit) determinations · Find similar determinations

Text of the determination

Determination Credit - Consumer Credit - Personal Loans – Disclosure – Incorrect product/service information Determination Case No: 314029 Determination Page 1 of 4 Case number: 314029 7 January 201 5 1 Overview 1.1 Dispute The Applicant entered into a Term Purchase Agreement (the Finance Contract) with the Financial Services Provider (FSP) for the purchase of a vehicle. He says:  the Finance Contract terms were not disclosed to him  the purchase price stated in the Finance Contract is incorrect. The Case Manager provided the parties with a Recommendation on the issues in dispute. The Recommendation was in favour of the FSP. A copy of the Recommendation is attached to this Determination. The Applicant disputes the findings in the Recommendation. He maintains that the price stated in the Finance Contract is incorrect, and argues that he did not receive an offer of finance prior to taking possession of the vehicle. 1.2 Issues and Key findings Were the findings of the Recommendation correct? The findings contained in the Recommendation were correct and are adopted in this Determination . The Applicant‟s further submissions have been considered. Is the Contract price correctly stated ? The figure of $65,617.80 stated in the Finance Contract is correct, being the total of all payments agreed to by the Applicant in entering the Finance Contract. Was the Applicant given notice of the Finance Contract terms? The available information establishes that the Applicant was provided with the Finance Contract terms at the time of signing the Finance Contract. If the Applicant took delivery of the vehicle prior to signing the Finance Contract, thi s does not invalidate the Finance Contract. 1.3 Determination This Determination is in favour of the FSP. I agree with the case manager‟s reasons for, and the outcome recommended in, the Recommendation. The Applicant is liable to repay the outstanding debt and should work with the FSP (as set out in section 2.4 below) to agree on a mutually acceptable repayment plan. Case No: 314029 Determination Page 2 of 4 2 Reasons for Determination 2.1 Were the findings in the Recommendation correct? I have decided this case on its merits, having regard to the relevant law, good industry practice, codes of practice and previous FOS decisions. I have taken into account all the material submitted by the parties, both before and after the Recommendation. I am satisfied that the documentation I have relied on has been provided to both parties. I am satisfied that the case manager‟s Recommendation contains an accurate summary of the dispute, the issues to be determined, any applicable paragraphs of the Terms of Reference and any relevant law. 2.2 Is the Finance Contract Price correctly stated? The Applicant agreed to a Contract price of $65,617.80 The Finance Contract is for a fixed term of five years. In entering into the Finance Contract, the Applicant agreed to repay the FSP the vehicle purchase price of $50,500, together with fees of $975.00 and interest charges over the five year term totalling $14,133.80. The Applicant therefore committed himself to a total Contract price of $65,617.80. The Applicant argues that:  no court will uphold an invoice that is not for the correct amount  the invoice is not acceptable for taxation purposes. These complaints refer to the invoice signed by the Applicant on 26 September 2011 for the purchase of the vehicle, rather than the Term Purchase Schedule the subject of this dispute. Nevertheless, as these arguments are based on an assumption that the Finance Contract price is incorrect, they must necessarily fail. However, if the Applicant wishes to contest the Finance Contract in court, it is open for him to do so. Similarly, as the Finance Co ntract price is correctly calculated, the Applicant‟s claim that the FSP has been unjustly enriched must also fail. 2.3 Was the Applicant given notice of the Finance Contract terms prior to entering into the Finance Contract? The Applicant acknowledged receiving the Finance Contract terms When signing the Term Purchase Schedule, the Applicant acknowledged receiving a copy of the Term Purchase Schedule and Conditions Booklet. In the absence of extenuating circumstances, the Applicant is bound by that acknowledgement, whether or not he read the Term Purchase Schedule before signing it. Case No: 314029 Determination Page 3 of 4 The dealership‟s Business Manager has also stated that, as a matter of normal practice, a copy of the terms and conditions booklet is provided to a customer together with the Term Purchase Schedule, Direct Debit Service Agreement and Application form, when these are signed by the customer. The Applicant has provided no information to indicate circumstances which would negate his acknowledgement of receiving the Finance Contract Terms. If the Applicant took possession of the vehicle prior to signing the Finance Contract, this does not invalidate the Finance Contract The Applicant maintains that, after signing the sales contract for the vehicle on 26 September 2011, he left the dealership and drove to Adelaide. He says that the fact that the sales contract states that finance was “TBA” („to be advised‟) establishes that he purchased the vehicle without any agreement for finance being in place. On this basis, he says that received “n o offer or acceptance of the offer for finance .. before he drove off with the truck”. The Applicant‟s claim is misconceived. The sales contract for the vehicle is a separate contract from the Finance Contract entered into with the FSP. The available information establishes that the Finance Contract was signed by the Applicant on 28 September 2011, and that the Term Purchase Schedule and Conditions Booklet was received by him on that date. As the Applicant agreed to the price as stated in the Finance Contact, there is no basis for his claim that he was not given an opportunity to refuse finance. Equally, as there was no error in the Finance Contract price, no right to repudiate the contract, or to avoid the Finance Contract on the ground of mistake, arose. It is not unusual for a sales contract to be finalised on the basis that details of finance are “to be advised”. However, a s noted in the Case Manager‟s Recommendation, it would be highly unusual for a seller to hand over possession of a vehicle before finance had been approved. The Applicant has provided no information in support of his assertion that he took delivery of the vehicle on 26 September 2011. In any event, whether or he took possession of the vehicle before finance had been finalised, this does not invalidate the Finance Contract he entered into on 28 September 2011. 2.4 Liability for outstanding loan balance The Applicant is liable to the FSP for the repayment of the outstanding balance. The Applicant should provide a reasonable payment proposal to the FSP in respect of the outstanding debt (together with information about his financial position) within 30 days of the Applicant accepting this Determination. If the Applicant does so, the FSP should work with him to agree on a repayment arrangement that would see the debt repaid over a reasonable period. If the parties are not able to agree on a repayment arrangement within 14 days after the date the Applicant provides a repayment proposal (or he does not provide a Case No: 314029 Determination Page 4 of 4 repayment proposal within the specified timeframe), then the FSP will be entitled to take recovery action in respect of the outstanding debt. 3 Other information In addition to the grounds addressed in this Determination, in rejecting the case manager‟s Recommendation the Applicant also seeks to rely on a finance contract previously held by him with another financier. The terms on which the Applicant has previously secured finance with a third party lender can have no relevance to liability of the Applicant in this dispute, which must be determined by reference to the Contract and the conduct of the Applicant and the FSP. I have therefore not considered this argument further. Recommendation Credit - Consumer Credit - Personal Loans - Charges - Incorrect interest added Recommendation Case No: 314029 Recommendation Page 1 of 8 Case number : 314029 30 September 2014 1 Overview 1.1 Dispute The Applicant entered into Term Purchase Agreement (the Contract) with the Financial Services Provider (FSP) to purchase a vehicle. The total Contract amount is $65,617.80 which consists of the vehicle purchase price of $50,500, fees of $975 and term (interest) charges of $14,133.80. The Contract requires 60 monthly repayments of $1,098.63. The Applicant claims that the dealership who prepared the Contract did not disclose the Contract terms to the Applicant, and that he signed a blank signing page without any Contract details shown. The Applicant is disputing the total Contract amount and the interest structure of the Contract. 1.2 Issues and key findings What is the Applicant’s liability towards the Contract ? The weight of information indicates that the Applicant was given a printed Term Purchase Schedule which he subsequently signed. There is insufficient information to establish that the Applicant was not provided with a copy of the Contract on or about 28 September 2011. The Applicant was aware he was entering into a legal relationship with the FSP when he signed the Term Purchase Schedule. The Applicant is bound to the Contract. Has the FSP provided the Applicant with account statements? The FSP is not under an obligation to provide the Applicant with periodic statements of account. 1.3 Recommendation This Recommendation is in favour of the FSP. The Applicant is liable to repay the outstanding Contract balance of $41,353.70 (as at 14 September 2014). The Applicant should work with the FSP (as set out in section 3.6 below) to agree a mutually acceptable repayment plan. Case No: 314029 Recommendation Page 2 of 8 2 Reasons for Recommendation 2.1 What is the Applicant’s liability towards the Contract ? The Applicant signed the Term Purchase Schedule on 28 September 2011 The Term Purchase Schedule and the Terms and Conditions comprise the Contract. The following documents relate to the vehicle purchase and the Contract:  The contract for the vehicle purchase was signed by the Applicant on 26 September 2011.  The Term Purchase Schedule was signed by the Applicant and dated 28 September 2011.  The Term Purchase Application Form was signed by the Applicant and dated 28 September 2011.  The Declaration of Purpose for Which Credit Provided (the Declaration) was signed by the Applicant and dated 28 September 2011.  The statements of account show that the facility was funded on 29 September 2011. The Applicant stated that he arrived at the dealership on 21 September 2011, and drove the vehicle back to Sydney on the evening of 21 September 2011. However, the Applicant had also previously stated that he purchased the vehicle on 29 September 2011. It is highly unlikely that the dealership would hand possession of the vehicle to the Applicant unless finance for the vehicle was secured . The above documentation indicates that finance was approved on or about 28 September 2011. The weight of information supports the conclusion that the Applicant signed the Term Purchase Schedule on or about 28 September 2011. The Applicant did not sign a blank Term Purchase Schedule The Applicant does not dispute his signatures shown on the signing page of the Term Purchase Schedule. The Applicant instead claims that the dealership‟s Business Manager provided him with blank signing page which only contained “two or three signature lines numbered in sequence”. The Applicant says that this was the only document that he was given to sign. However, the documents outlined above do not support the Applicant‟s claim that he only signed a blank signing page of the Term Purchase Schedule. In addition to the Schedule, the Applicant‟s signature also appears in the Declaration and Application Form. Examinations of the Applicant‟s signatures contained in the three separate documents shows slight variations. This in dicates that the Applicant‟s signature from the Term Purchase Schedule was not copied over onto the other documents Case No: 314029 Recommendation Page 3 of 8 showing his signature. Rather, they suggest that the Applicant signed three times, contrary to his recollection. The Applicant alleges that the signing page was blank with only two or three signature lines shown. In contrast, the Business Manager states that no blank forms are generally used in the application process. Rather, the customer‟s details are inputted to the computer. Following finance approval, the contracts are always printed and handed to the customers. The Business Manager further states that she goes through the contract to explain the financial terms, discusses the Declaration and subsequently arranges a monthly direct debit. Further, upon examination of the executed signing page, it is unlikely that the dealership would be capable of successfully printing over this document to include the written text now shown, after the Applicant had signed the document. The available information does not support the Applicant‟s claim that he was only provided with an entirely blank signing page, with no Contract details recorded. Instead, the weight of information indicates that on 28 September 2011, the Applicant was provided with the Declaration, the Application Form and the Term Purchase Schedule documents for signing. The Applicant subsequently signed the documents, including the printed signing page Term Purchase Schedule. The Applicant is bound to the Contract If a person signs a document that they know contains contractual terms and which they understand will affect their legal relationship with the financial institution, then the person is legally bound by those terms. It is irrelevant whether or not the person read the document before signing it. The only exception to this is if there are extenuating circumstances, for example if the person was misled into signing the document. The Applicant states that he was asked to sign a “sheet” which the dealership would u se as the Applicant‟s agreement to obtain the finance, which he subsequently signed. The Applicant claims that he was not shown a written contract or any Terms and Conditions by the dealership. As detailed previously, the weight of information indicates that the Applicant was provided with a printed (non-blank) signature page of the Term Purchase Schedule. The “ RECEIPT OF DOCUMENTS ” section of the signature page states that both parties acknowledge the Applicant has received a copy of the Term Purchase Schedule and Terms and Conditions Booklet. The Applicant signed this section with the date 28 September 2011 recorded, which indicates that the Applicant received the Contract documents. Further to this, the dealership‟s Business Manager states that it is her normal practice to provide printed Contracts to customers. Specifically, the Business Manager states that a copy of the Term Purchase Schedule, Terms and Case No: 314029 Recommendation Page 4 of 8 Conditions booklet, Direct Debit Service Agreement and Application Form are provided to customers in a while folder with the FSP‟s label. There are no contemporaneous documents showing that the Contract was not provided to the Applicant. There is insufficient information to support the App licant‟s claim that he was not provided with a copy of the Term Purchase Schedule and Terms and Conditions Booklet on or about 28 September 2011 when he signed the Term Purchase Schedule. The available information does not indicate that the Applicant was misled to enter into the Contract. The Applicant was aware that by signing the Term Purchase Schedule, he was entering into a financial arrangement with the FSP. This is supported by his statement that “I know that I should have been more careful, I should never have signed a blank three signature page...” The Applicant has received the benefit and use of the vehicle obtained through the Contract. The Applicant is bound to the Contract. The Applicant has an obligation towards the outstanding Contract debt The Applicant states that he only borrowed $50,500 (plus fees) and not $65,617.80. The Applicant asserts that the interest charges for the Contract term should not be included in the total Contract amount. Consequently, the opening balance should be $50,500 and not $65,617.80. The total Contract amount is $65,617.80 which consists of the vehicle purchase price of $50,500, fees of $975 and interest charges of $14,133.80 for the Contract term. For hire purchase loan products, it is usual for the term‟s inte rest charges to be included in the total Contract amount. The FSP has not breached any obligation owed to the Applicant by including the interest charges for the term in the total Contract amount. The Applicant stated that he only wanted a loan for the purchase price of $50,500 with interest payable on this amount. However, the structure of the Contract is not dissimilar to loan product the Applicant was seeking. The Contract amount of $65,617.80 consists of the principal amount of $50,500 plus fees and charges (financed amount) and the accrued interest for the term of the Contract. Interest for the financed amount was calculated based on the fixed rate of 9.99% p.a. and the term of five years. Consequently, the rent payments of $1,093.63 encompass the principal and interest components of the Contract. In the event the Applicant decides to terminate the Contract prior to the end of the five year term, the Applicant receives a rebate on the lump sum interest included in the Contract amount. The rebate is 75% of the un-accrued interest as outlined in Clause 1.1 of the Terms and Conditions. Case No: 314029 Recommendation Page 5 of 8 The FSP is entitled to include term interest charges in the total Contract amount. The Applicant is liable to repay the outstanding balance of the Contract which is $41,353.70 as at 14 September 2014. 2.2 Has the FSP provided the Applicant with account statements? No obligation for the FSP to provide the Applicant with periodic account statements The available information indicates that the FSP did not provide the Applicant with any other statements prior to 15 January 2013. Section 33 of the National Credit Code (NCC) outlines the requirements for credit providers to provide statements of account to debtor s. However, the Applicant‟s Contract is not regulated by the NCC and the requirements under the NCC do not apply to the Contract. This is because the credit provided was wholly or predominantly for business purposes. In any case, section 33 states that periodic statements of account need not be provided for a credit contract where the annual percentage rate is fixed for the whole term of the contract, and there is no provision to vary the rate. The Contract between the Applicant and the FSP is for a term of five years and interest was calculated on a fixed rate of 9.99% p.a . for the term. There is also no provision in the Contract that allows for a variation of the fixed annual percentage rate. If the Contract was regulated by the NCC, the FSP has no obligation to provide the Applicant with periodic statements of account. The FSP did not breach any obligation owed to the Applicant by not providing any statements of account prior to 15 January 2013. 3 Supporting information 3.1 The Applicant’s previous loan facility The Applicant has referred to his previous loan facility with another financial institution, but the Applicant has not provided a copy of the credit contract. Rather, the Applicant provided printouts of information on this financial institution‟s website as at 29 March 2014. It is unclear what the structure of the Applicant‟s previous facility was and how familiar the Applicant was with credit contracts associated with vehicle purchases. 3.2 Clause 1 of the Contract’s Terms and Conditions “ 1.1 Definitions and interpretation .... Case No: 314029 Recommendation Page 6 of 8 Termination Amount means, on a day for an item of Goods, the amount calculated for that item by the Owner which, on that day, equals that part of each rent payment which the Owner determines relates to that item and is due for payment under this agreement after that day, discounted to a present value on that day by applying a discount rate equal to 75% of the implicit interest rate used by the Owner to calculate the principal and interest component of the rent payable under this agreement. ...” 3.3 Section 33 of the National Credit Code “33 Statements of account (1) A credit provider that provides credit must give to the debtor , or arrange for the debtor to be given , periodic statements of account in accordance with this Division. ... (3) A statement of account need not be given if: (a) the credit is provided under a credit contract for which the annual percentage rate is fixed for the whole term of the contract and under which there is no provision for varying the rate; or ....” 3.4 Early Termination Fee The Applicant also disputes the ability of the FSP to charge an early termination amount and suggests the amount is excessive. Under Clauses 7.1 and 11.1 of the Contract‟s Terms and Conditions, the Applicant is required to make all repayments and has no right to terminate the Contract early. If the Applicant decides to terminate the Contract he will be in breach of Clause 11.1 and is required to pay the termination amount. The termination amount, as defined in Clause 1.1 of the Terms and Conditions, is 25% of the un-accrued interest 3.5 Clause 11 of the Contract’s Terms and Conditions “ 11.1 Your fundamental obligations under this agreement (a) In addition to clause 2.1, your fundamental obligations under this agreement are that you must: Case No: 314029 Recommendation Page 7 of 8 (i) pay each amount which you owe under this agreement on time and as required by this agreement; .... (b) If you do not comply with one of your fundamental obligations under this agreement then you will be taken to have repudiated this agreement. Despite anything else which you and the Owner may have agreed, you will also be taken to have repudiated every other agreement between you and the Owner relating to the lease, hire, finance or maintenance of goods. The Owner may then accept any of your repudiations by giving you a notice terminating any relevant agreement. 11.2 Your obligations following repudiation If the Owner gives you a notice under clause 11.1(b) your must immediately do all of the following things: ... (d) pay to the Owner, as liquidated damages for loss of bargain, the Termination Amount; and (e) pay to the Owner any other amount which you still owe under this agreement, including any amount which you owe under clause 8. .... ” However I note the Applicant has not paid out the Contract. The termination amount varies time to time. As the Applicant has not paid out the Contract, no termination amount has yet arisen under the Contract. Accordingly, I cannot consider this issue at the time. 3.6 Liability for outstanding loan balance As at 14 September 2014, the outstanding balance is $41,353.70. The Applicant is liable to the FSP for the repayment of the outstanding balance. However, the Applicant has not made a repayment since 18 October 2013, and it appears the Applicant may be in financial hardship. If this is the case, then the Applicant should provide a reasonable payment proposal to the FSP in respect of the outstanding debt (together with information about his financial position) within 30 days of the Applicant accepting this Recommendation. If the Applicant does so, the FSP should work with him to agree on a repayment arrangement that would see the debt repaid over a reasonable period. If the parties are not able to agree on a repayment arrangement within 14 days after the date the Applicant provides a repayment proposal (or he does not provide a repayment proposal within the specified timeframe), then the FSP will be entitled to take recovery action in respect of the outstanding debt. Case No: 314029 Recommendation Page 8 of 8

Coded fields were extracted from the text by a language model and may contain errors. The published PDF is the authoritative record.